Clarifies Scheduled Completion of Tasks Identified in Suppl 1 to NUREG-0737,per 830502 Meeting
ML20024D109
Person / Time
Site: Beaver Valley
Issue date: 07/25/1983
From: Carey J
DUQUESNE LIGHT CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-33, TAC-44282, TAC-51141, NUDOCS 8308030170
Download: ML20024D109 (2)


Text

i j

o

'Af USSne @

1,.paea. aia 4se=00 EEYo',4*'

snippingpon. PA 15077 @ 04 Director of Nuclear Reactor Regulation Unite.d States Nuclear Regulatory Commission Attn: Mr. Darrell G. Eisenhut, Director Division of Licensing Washington, DC 20555

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Supplement 1 to NUREG-0737 Gentlemen:

This submittal is being provided as clarification for the scheduled completion of the tasks identified in Supplement 1 to NUREG-0737.

Our submittal of April 15, 1983 provided the information requested in Generic Letter 82-33.

On May 2,1983, a meeting was held at this site as a follow-up to that submittal to negotiate the schedule in accordance with the direction provided in the Generic Letter. At this meeting and in sub-sequent telephone conversations, senral dates for completion of certain tasks and for the submittal of additional infonnation were established.

The information below represents the most recent conversation between our NRC I'roject Manager and members of my staff with regard to the SPDS, CRDR, Regulatory Guide 1.97 and E0Ps.

SPDS 1

Full implementation of the SPDS will be accomplished follow-ing the fifth refueling outage tentatively scheduled for July of 1986.

CRDR 1.

The Program Plan will be submitted in September 1983.

2.

The Summary Report will be submitted in November 1985.

R(g. Guide 1.97 1.

This work activity and development of the final report will be accomplished concurrent with the CRDR.

The final report will be submitted in November 1985.

I o6 nl l

l 8308030170 830725

(

PDR ADOCK 05000334 F

PDR

f

~

B:: aver Valley Power Station, Unit flo.1 Docket tio. 50-334, License No. DPR-66 Supplement 1 to NUREG-0737 Page 2 2.

The schedule for full implementation of R.G.1.97 will be provided in the final report. This is consistent with the request of Supplement 1 to NUREG-0737 of pro-viding a schedule for plant modifications, if any, in the final report.

.EOPs 1.

Full implementation of the E0Ps will be accomplished following the fifth refueling outage tentatively scheduled for July of 1986.

Should you have any questions regarding this submittal, please contact myself or members of my staff.

Very trul you rs,

3

. Carey Vice President, Nuclear cc: Dr. Thomas E. Murley, Regional Administrator U. S. Nuclear Regulatory Commission Office of Inspection & Enforcement Region I 631 Park Avenue King of Prussia, PA 19406 Mr. Steven A. Varga, Chief U. S. Nuclear Regulatory Commission Operating Reactors Branch No.1 Division of Licensing Washington, DC 20555 l

Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, PA 15077 l

U. S. Nuclear Regulatory Commission c/o Document Management Branch Washington, DC 20555