s Appendix A NOTICE OF VD LATION Union Electric C3mpany Docket No. 50-483 3ased on the findings of :he NRC inves:igation conducted on Dece=ber 13-14, 15-22, 1977, and January 3-6, 1978, i appears that cer:ain of your a:tivities were not conducted in full com-pliance with NRC require =ents as noted below.

Ite=s I and 2 are inf ractions and ite _ 3 is a deficiency.

1.

Conersry to 10 CFR 50, Appendix 3, Criterion V; the SNUPPS PSAA, Chapter 17, Paragraph 17.1.5; and the SNUPPS Standard Quality Assurance Manual, Section 3-3, Paragraph 3.2; it was de: ermined that the cadweld inspection criteria found in QCP-118, Section 4.4 did not re flec t the require =ent in the cadweld production procedure WP-118, which, in Section 3.9 requires th a t a cadweld be identified wi:h a die stamp. The inspection

/

showed that action had been taken to correct the identified

( _

reply to this noncompliance is required and we have no further noncr=pliance, and to prevent recurrence. Consequently, no ques: ions regarding this matter at this time.

2.

Contrary to 10 CFR 50, Appendix 3, Criterion IV; the SNUPPS PSAR, Chapter 17, Paragrapn 17.1.15; the SNUPPS Standard Quality Assurance Manual, Section 3-9, Paragraph 9.2.1; and D&niel International procedure AP-VII-02 entitled " Control of Noncon-formances," i: was deter =ined that overlength shear ties were identified as being in the reinforcement for :he third lif t of the reactor containment vall, but were no: documented and disposi:ioned as nonconforming items.

3.

Contrary :o 10 CFR 50, Appendix 3, Cri:erion IV; :he SNUPPS PSAR Chapter 17, Paragraph 17.1.15; the SNUPPS Standard Quality Assurance Manual, See: ion 3-9, Paragraph 9.2.1; and Daniel Interna:icnal procedure AP-VII-02 entitled " Control of Noncon-for=ances," i: was determined : hat, at one location on the reae:or containment vall, the reinforcement har spacing exceeded applicable placing tolerances, and had not been identified as a nonconformance.