University of Texas at Austin - Extension to Revised Schedule for the Completion of the Reactor Analyses Renewal of Facility Operating License No. R 129 for the University of Texas at Austin Research Reactor
ML19340A017
Person / Time
Site: University of Texas at Austin
Issue date: 12/19/2019
From: Geoffrey Wertz
NRC/NRR/DANU/UNPL
To: Charlton W
University of Texas at Austin
Wertz G, NRR/DANU/UNPL, 301-415-0893
References
EPID L-2017-RNW-0032
Download: ML19340A017 (4)


Text

December 19, 2019 Dr. William Charlton, Director Nuclear Engineering Teaching Laboratory The University of Texas at Austin Pickle Research Campus, Building 159 10100 Burnet Road Austin, TX 78758

SUBJECT:

UNIVERSITY OF TEXAS AT AUSTIN - EXTENSION TO REVISED SCHEDULE FOR THE COMPLETION OF THE REACTOR ANALYSES RE: RENEWAL OF FACILITY OPERATING LICENSE NO. R-129 FOR THE UNIVERSITY OF TEXAS AT AUSTIN RESEARCH REACTOR (EPID NO. L-2017-RNW-0032)

Dear Dr. Charlton:

The U.S. Nuclear Regulatory Commission (NRC) staff is continuing its review of the University of Texas at Austin (UTA) application for renewal of Facility Operating License No. R-129, for the Nuclear Engineering Teaching Laboratory nuclear research reactor, dated December 12, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12156A097), as supplemented by letter dated February 21, 2012 (ADAMS Accession No. ML12061A009). The NRC staff requested a schedule for completion of the reactor analyses, by letter dated October 18, 2018 (ADAMS Accession No. ML18262A182).

By letter dated November 25, 2019 (ADAMS Accession No. ML19337A435), the UTA staff provided a detailed status as to the work done in support of the development of the neutronics model needed to support the UTA license renewal application. Further, by telephone conference conducted on December 5, 2019, UTA staff provided additional insights into the remaining work needed to complete the nuetronics model. Additionally, after discussion with the NRC staff, the UTA staff requested an extension to March 31, 2020, to complete and submit the UTA nuetronics and thermal hydraulics analyses. Based on the information described above, the NRC staff finds the March 31, 2020, date to be acceptable.

Finally, the NRC staff discussed plans to conduct an audit of the UTA reactor analyses following the March 31, 2020, submittal. The audit plan details will be provided by letter at a later date.

If you have any questions, contact me at (301) 415-0893 or by electronic mail at Geoffrey.Wertz@nrc.gov.

Sincerely,

/RA by Greg A. Gasto for/

Geoffrey A. Wertz, Project Manager Non-Power Production and Utilization Facility Licensing Branch Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No. 50-602 License No. R-129 cc: See next page

University of Texas Docket No. 50-602 cc:

Bureau of Radiation Control State of Texas 1100 West 49th Street Austin, TX 78756 Dr. Gregory L. Fenves The University of Texas at Austin Office of the President 110 Inner Campus Drive, G3400 Austin, TX 78712-3400 Maurie McInnis Executive Vice President and Provost The University of Texas at Austin 1 University Station, G1000 Austin, TX 78712 DeAnn Walker, Director Office of the Governor Office of Budget and Policy P.O. Box 12428 Austin, TX 78711 Paul Whaley, Associate Director Nuclear Engineering Teaching Laboratory The University of Texas at Austin 10100 Burnet Road, Building 159 Austin, TX 78758 Larry Hall, Reactor Supervisor Nuclear Engineering Teaching Laboratory The University of Texas at Austin 10100 Burnet Road, Building 159 Austin, TX 78758 Test, Research and Training Reactor Newsletter Attention: Ms. Amber Johnson Dept of Materials Science and Engineering University of Maryland 4418 Stadium Drive College Park, MD 20742-2115 John G Ekerdt, PhD The University of Texas at Austin Chemical Engineering 200 East Dean Keeton Street, Stop C0400 Austin, TX 78712-1589 Dr. Richard Neptune, Dept. Chair Walker Department of Mechanical Engineering 204 East Dean Keeton Street, ETC 5.200 (C2200)

Austin, TX 78712-1591 Dean Sharon Wood The Cockrell School of Engineering 301 East Dean Keeton Street, ECJ 10th Floor (C2100)

Austin, TX 78712-2100

ML19340A017

  • concurrence via email OFFICE NRR/DANU/UNPL/PM*

NRR/DANU/UNPL/LA*

NRR/DANU/UNPL/BC NRR/DANU/UNPL/PM NAME GWertz NParker GCasto GWertz (GCasto for)

DATE 12/9/19 12/9/19 12/9/19 12/19/19