MONTHYEARML18031A7302018-02-12012 February 2018 Honeywell International, Inc., 2018 Lr - Request for Additional Information Concerning License Renewal Application in the Areas of Integrated Safety Analysis Summary and Management Measures Project stage: RAI ML18031A7262018-02-12012 February 2018 Request for Additional Information Concerning License Renewal Application in the Areas of Integrated Safety Analysis Summary and Management Measures, Honeywell Metropolis Works (Cost Activity Code 000224/04003392/L-2017-RNW-0002) Project stage: Request ML18031A9712018-02-12012 February 2018 Honeywell International Inc., Request for Additional Information Integrated Safety Analysis Summary and Management Measures Renewal of Source Materials License No. SUB-526 Project stage: RAI ML18037B0472018-02-28028 February 2018 Telecon Summary-Honeywell LRA D-RAI Revised ISA and Mm Review 1-2018 Enclosure 2 Project stage: RAI ML18037B0322018-02-28028 February 2018 January 31, 2018 Conference Call to Clarify Draft Request for Additional Information in the Areas of Integrated Safety Analysis Summary and Management Measures, Honeywell Metropolis Works (CAC 000224/04003392/L-2017-RNW-0002) and Enclosures Project stage: Request ML18037B0422018-02-28028 February 2018 Telecon Summary-Honeywell LRA D-RAI Revised on ISA and Mm Review 1-31-2018 List of Participants Enclosure 1 Project stage: RAI ML18037B0372018-02-28028 February 2018 Telecon Summary-Honeywell LRA D-RAI Revised on ISA and Mm Review 1-31-2018 Project stage: RAI ML18113A0722018-04-12012 April 2018 Enclosure 2: Form Honeywell Meeting Summary-ISA and Mm Draft RAI Response April 12, 2018 Project stage: Draft RAI ML18113A0742018-05-15015 May 2018 Meeting Summary - Honeywell-LRA Draft RAI Response on ISA and Mm April 12, 2018 with Enclosure 1 Project stage: Draft RAI ML18187A2202018-06-29029 June 2018 Acknowledgement of Receipt of Centrus Final Status Survey Report for the American Centrifuge Lead Cascade Facility Decommissioning Project Project stage: Other ML18292A5202018-10-25025 October 2018 Acceptance Review of Louisiana Energy Services, LLC, Doing Business as Urenco USA License Amendment Request 18-01 Allowance to Feed UF6 Greater than O.72 WT % 235Urainium, But Less than 1 WT % 235Urainium Project stage: Acceptance Review L-2019-005, License Amendment Request 266, Clarify Requirements When One Unit Is Outside the Applicability of Certain Technical Specifications2019-02-14014 February 2019 License Amendment Request 266, Clarify Requirements When One Unit Is Outside the Applicability of Certain Technical Specifications Project stage: Request ML19079A3562019-03-20020 March 2019 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Acceptance of License Amendment Request to Clarify TS Requirements When One Unit Is Shutdown Project stage: Acceptance Review ML19184A1002019-07-0303 July 2019 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 266 Project stage: RAI L-2019-135, Response to Request for Additional Information Regarding License Amendment Request 266, Clarify Requirements When One Unit Is Outside the Applicability of Certain Technical Specifications2019-07-22022 July 2019 Response to Request for Additional Information Regarding License Amendment Request 266, Clarify Requirements When One Unit Is Outside the Applicability of Certain Technical Specifications Project stage: Response to RAI ML19263E2962019-09-20020 September 2019 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Florida Regarding Turkey Point License Amendments - Defueled Condition Project stage: Other ML19269B7742019-09-23023 September 2019 Us Dept. of Commerce, National Institute of Standards and Technology - NIST Decommissioning Funding Plan, September 2019 Project stage: Request ML19309E6662019-11-20020 November 2019 Acceptance of Passport Systems Inc.S Request to Terminate SNM-960 Project stage: Acceptance Review ML19317E5702019-11-20020 November 2019 Acceptance Review-2019 Decommissioning Funding Plan Submittal, SNM 362, Docket 07000398 Project stage: Acceptance Review ML19266A5852019-12-17017 December 2019 Issuance of Amendment Nos. 289 and 283 Technical Specification Applicability to Equipment Shared Between Units and Exception to Technical Specification 4.0.4 Project stage: Approval ML20030A6592020-02-0404 February 2020 Request for Additional Information - 2019 Decommissioning Funding Plan Submittal, SNM 362 Project stage: Request ML20030A6812020-02-0404 February 2020 Enclosure 1 NIST 2019 DFP RAI Project stage: Other ML20030A6792020-02-0404 February 2020 Request for Additional Information - 2019 Decommissioning Funding Plan Submittal, Special Nuclear Material License, SNM-362, Docket 07000398 (Cac/Epid 000224/07000398/L-2019-DFA-0008) Project stage: RAI ML20066J9772020-03-0606 March 2020 Updated GEH Vallecitos Nuclear Center Decommissioning Funding Plan (DFP) Project stage: Request ML20085G2152020-04-0303 April 2020 Transmittal, Approval of NIST 2019 Triennial Update to Decommissioning Funding Plan Project stage: Other ML20085G2162020-04-0303 April 2020 Enclosure, Technical Evaluation Report, NIST 2019 Decommissioning Cost Estimate Project stage: Other ML20009E8072020-05-0404 May 2020 NRC Final Response on Passport Systems Inc. License Termination Project stage: Other ML20154K6502020-06-0202 June 2020 GEH Vallecitos Decommissioning Funding Plan Supplemental Information Project stage: Request ML20209A0672020-10-0909 October 2020 Request for Additional Information Letter: Updated DFP for Vallecitos Nuclear Center (Vnc) Project stage: RAI ML20310A2742020-11-0505 November 2020 GE-Hitachi Nuclear Energy Americas, LLC, Response to Nrg Request for Additional Information - Vallecitos Nuclear Center Decommissioning Funding Plan Project stage: Request ML21078A0442021-03-12012 March 2021 Us Dept. of Commerce, National Institute of Standards & Technology, License Amendment Application Project stage: Other ML21126A1142021-05-20020 May 2021 Transmittal, Response to License Amendment Request Project stage: Other ML21126A1152021-05-20020 May 2021 Enclosure 1 - SEP G150 Relocation Project stage: Other ML21126A1162021-05-20020 May 2021 Enclosure 2 - SNM-362 License (Publicly Available) Project stage: Other ML21336A3182021-12-14014 December 2021 Cover Letter - Forward Second Request for Additional Information Re Updated Decommissioning Funding Plan Project stage: RAI ML22012A1482022-01-12012 January 2022 GEH Response to NRC Second Request for Additional Information - Vallecitos Nuclear Center Decommissioning Funding Plan (Enterprise Project Number 000224/07000754/L-2020-DFA-0002) Project stage: Request ML22024A3132022-01-24024 January 2022 GE-Hitachi Nuclear Energy Americas, LLC - Response to NRC Request for Vallecitos Nuclear Center CA-0017-01 Decommissioning Funding Plan Project stage: Request 2019-09-20
[Table View] |
Text
November 20, 2019 Mr. Paul H. Johnson Vice President Contracts and Administration Passport Systems, Inc.
70 Treble Cove Road North Billerica, MA 01862
SUBJECT:
ACCEPTANCE OF REQUEST TO TERMINATE SPECIAL NUCLEAR MATERIAL LICENSE NUMBER 2016 FOR PASSPORT SYSTEMS INC. - COST ACTIVITY CODE/ENTERPRISE PROJECT IDENTIFIER 000224/07007022/L-2019-LLA-0024
Dear Mr. Johnson:
The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal dated October 16, 2019 (Agencywide Documents Access and Management System (ADAMS)
Accession Number ML19290E196), requesting the U.S. Nuclear Regulatory Commission (NRC) to terminate Special Nuclear Material License Number 2016 for Passport Systems, Inc.
We have completed our acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification (EPID)
Number L-2019-LLA-0024. Please reference this EPID number and Docket Number 70-7022.
in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by January 31, 2020. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 40 staff hours which corresponds to about $11,120.00 ($278.00/hr).
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
P. Johnson 2
If you have any questions regarding this communication, please contact me at (301) 415-7827, or via e-mail at Osiris.Siurano-Perez@nrc.gov.
Sincerely,
/RA/
Osiris Siurano-Pérez, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-7022 License No. SNM-2016
ML19309E666 OFFICE: NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/DFM/FFLB NAME:
OSiurano ELee JZimmerman OSiurano DATE:
11/19/2019 11/19/2019 11/19/2019 11/20/2019