MONTHYEARML19276G3132019-10-0202 October 2019 Draft Exigent License Amendment Request - One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source Project stage: Draft Request ML19277G0852019-10-0404 October 2019 Emergency License Amendment Request: One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source Project stage: Request ML19280A0362019-10-0404 October 2019 NRR E-mail Capture - FitzPatrick Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days Project stage: RAI ML19280A0052019-10-0404 October 2019 NRR E-mail Capture - (External_Sender) FitzPatrick Emergency Amendment Public Conference Call Discussion Points - 4 Project stage: Request ML19277D5522019-10-0404 October 2019 Draft James A. FitzPatrick Nuclear Power Plant - Emergency License Amendment Request - One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source Project stage: Draft Request ML19280A0392019-10-0505 October 2019 NRR E-mail Capture - FitzPatrick Additional Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days Project stage: RAI ML19280A0372019-10-0505 October 2019 NRR E-mail Capture - FitzPatrick Revised Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days Project stage: RAI ML19279A0012019-10-0606 October 2019 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to the TS 3.8.1 Action . Project stage: Response to RAI ML19281A9962019-10-0808 October 2019 Withdrawal of Emergency License Amendment Request for One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source Project stage: Withdrawal ML19282A4502019-10-10010 October 2019 Withdrawal of Emergency License Amendment Request Project stage: Withdrawal ML19291A0022019-11-0101 November 2019 10/03-10/08/2019 Summary of Meetings with Exelon Generation Company, LLC, on Emergency Amendment Request Regarding One-Time Extension to Technical Specifications 3.8.1 Action A.3 Completion Time for Inoperable Offsite Source (EPID L-2019-LL Project stage: Meeting 2019-10-05
[Table View] |
Text
October 10, 2019 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT WITHDRAWAL OF EMERGENCY LICENSE AMENDMENT REQUEST (EPID L-2019-LLA-0214)
Dear Mr. Hanson:
By letter dated October 4, 2019, as supplemented by letter dated October 6, 2019, Exelon Generation Company, LLC (Exelon) submitted to the U.S. Nuclear Regulatory Commission an emergency license amendment request for the James A. Fitzpatrick Nuclear Power Plant, Renewed Facility Operating License No. DPR-59. The amendment request was for a one-time change to modify the completion time for Technical Specification 3.8.1, AC [Alternating Current]
Sources -Operating, Action A.3, Restore offsite circuit to OPERABLE status from 7 days to 21 days. Subsequently, by letter dated October 8, 2019 (Agencywide Documents Access and Management System Accession No. ML19281A996), Exelon withdrew the amendment request.
The purpose of this letter is to advise that the above-cited application is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.
Sincerely,
/RA/
Samson S. Lee, Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-333 cc: Listserv