EPID:L-2019-LLA-0214
From kanterella
Jump to navigation
Jump to search
EPID - L-2019-LLA-0214, Emergency License Amendment Request: One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source (Withdrawn, Closed) 2 October 2019 - 1 November 2019 | |
|---|---|
Request for: - License Amendment Withdrawn, Closed | |
| |
| From: | |
MONTHYEARML19276G3132019-10-0202 October 2019
[table view]Title: Draft Exigent License Amendment Request - One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source ML19277G0852019-10-0404 October 2019 Title: Emergency License Amendment Request: One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source ML19280A0362019-10-0404 October 2019 Title: NRR E-mail Capture - FitzPatrick Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days ML19280A0052019-10-0404 October 2019 Title: NRR E-mail Capture - (External_Sender) FitzPatrick Emergency Amendment Public Conference Call Discussion Points - 4 ML19277D5522019-10-0404 October 2019 Title: Draft James A. FitzPatrick Nuclear Power Plant - Emergency License Amendment Request - One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source ML19280A0392019-10-0505 October 2019 Title: NRR E-mail Capture - FitzPatrick Additional Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days ML19280A0372019-10-0505 October 2019 Title: NRR E-mail Capture - FitzPatrick Revised Request for Additional Information: Emergency Amendment to Extend Completion Time of Transformer to 21 Days ML19279A0012019-10-0606 October 2019 Title: Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to the TS 3.8.1 Action . ML19281A9962019-10-0808 October 2019 Title: Withdrawal of Emergency License Amendment Request for One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source ML19282A4502019-10-10010 October 2019 Title: Withdrawal of Emergency License Amendment Request ML19291A0022019-11-0101 November 2019 Title: 10/03-10/08/2019 Summary of Meetings with Exelon Generation Company, LLC, on Emergency Amendment Request Regarding One-Time Extension to Technical Specifications 3.8.1 Action A.3 Completion Time for Inoperable Offsite Source (EPID L-2019-LL 2019-10-05 | |