NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Delete Decommissioning Trust License Conditions
ML19261A226
Person / Time
Site: Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle  Constellation icon.png
Issue date: 09/18/2019
From: Blake Purnell
Plant Licensing Branch III
To: Torres-Cruz L
Exelon Generation Co
References
L-2019-LLA-0185
Download: ML19261A226 (3)


Text

NRR-DRMAPEm Resource From: Purnell, Blake Sent: Wednesday, September 18, 2019 8:09 AM To: Linda.TorresCruz@exeloncorp.com Cc: Simpson, Patrick R.:(GenCo-Nuc); Regner, Lisa

Subject:

Exelon Generation Company, LLC - Acceptance of License Amendment Request to Delete Decommissioning Trust License Conditions (EPID L-2019-LLA-0185)

Mrs. Palutsis, By application dated August 28, 2019 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML19240B609), Exelon Generation Company, LLC (the licensee) submitted a license amendment request for Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2; Clinton Power Station, Unit No. 1; Dresden Nuclear Power Station, Units 1, 2, and 3; James A. FitzPatrick Nuclear Power Plant; LaSalle County Station, Units 1 and 2; Limerick Generating Station, Units 1 and 2; Nine Mile Point Nuclear Station, Units 1 and 2; Peach Bottom Atomic Power Station, Units 1, 2, and 3; Quad Cities Nuclear Power Station, Units 1 and 2; and R. E. Ginna Nuclear Power Plant. The proposed amendments would delete certain license conditions that specify requirements for decommissioning trust agreements for these facilities.

The amendments would also delete some obsolete license conditions associated with completed license transfers for these facilities. The decommissioning trust fund requirements in 10 CFR 50.75(h) would become applicable to these facilities if the amendments are approved.

The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that the review of this licensing request will take approximately 175 hours7.292 days <br />1.042 weeks <br />0.24 months <br /> to complete. The NRC staff expects to complete this review by September 30, 2020. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and 1

review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-1380.

Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461,50-010. 50-237, 50-249, 50-333, 50-373, 50-374, 50-352, 50-353, 50-220, 50-410, 50-171, 50-277, 50-278, 50-254, 50-265, and 50-244 2

Hearing Identifier: NRR_DRMA Email Number: 205 Mail Envelope Properties (MWHPR09MB15332E3F58C846ACC32E8057E68E0)

Subject:

Exelon Generation Company, LLC - Acceptance of License Amendment Request to Delete Decommissioning Trust License Conditions (EPID L-2019-LLA-0185)

Sent Date: 9/18/2019 8:09:20 AM Received Date: 9/18/2019 8:09:00 AM From: Purnell, Blake Created By: Blake.Purnell@nrc.gov Recipients:

"Simpson, Patrick R.:(GenCo-Nuc)" <patrick.simpson@exeloncorp.com>

Tracking Status: None "Regner, Lisa" <Lisa.Regner@nrc.gov>

Tracking Status: None "Linda.TorresCruz@exeloncorp.com" <Linda.TorresCruz@exeloncorp.com>

Tracking Status: None Post Office: MWHPR09MB1533.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 4386 9/18/2019 8:09:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: