Forwards Request for Addl Info About Containment Purge & Vent Sys Re Util Plans for Unlimited Purging
ML19260B988
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 11/06/1979
From: Lainas G
Office of Nuclear Reactor Regulation
To: Ippolito T
Office of Nuclear Reactor Regulation
References
TAC-42603, TAC-42604, TAC-51948, TAC-51984, TAC-51985, NUDOCS 7912180083
Download: ML19260B988 (3)


Text

/s /_

/'/)/

,(pa arco, UNITED STATES y ) ",.,, j NUCLEAR REGULATORY COMMISSION E

WASHINGTO N, D. C. 20555

%..'.'./!

NOV 6 1979 MEMORANDUM FOR:

T. Ippolito, Chief Operating Reactors Branch #3 Division of Operating Reactors FROM:

G. Lainas, Chief Plant Systems Branch Division of Operating Reactors

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION - CONTAINMENT PURGE SYSTEM - ECWIN I. HATCH NUCLEAR PLANT, UNITS 1 & 2 (TACS 10178,10177)

REFERENCES :

1.

Letter to Director of Nuclear Reactor Regulation frcm C. Whitmer, " Containment Purging Curing Normal Plant Operation," dated January 9,1979 2.

Letter to Director of Nuclear Reactor Regulation from R. Kelly, " Containment Purging During Normal Plant Operation," dated August 29, 1979 Plant Name: Ecwin I. Hatch Nuclear Plant, Units 1 & 2 Docket Nos. : 50-321,50-36o Project Manager:

D. Verrelli Review Status : Awaiting Information With regard to the containment purge and vent system at Edwin I.

Haten Nuclear Plant, Units 1 & 2, the licensee plans to justify unlimited purging (Reference 2). The Plant Systems Branch, Section B, after naving reviewed the documents (References 1 and

2) filed by the licensee, has prepared the enclosed request for additional information.

The PSB, Section A (EI&C), is currently reviewing the licensee's infor r.ation provided at their October 14, 1979 meeting.

/

/

Q l(Qw

/ G. Lainas, Chief

/ Plant Systems Branch Division of Operating Reactors Enclosure :

As stated O

16&f 147 7 912180 OD

T. Ippolito NOV 6 1979

Contact:

D. Shum, X27058 cc w/ enclosure:

D. Eisenhut W. Gamill L. Nichols G. Lainas E. Reeves E. Adensam D. Verrelli D. Tondi D. Shum J. Xerrigan G. Knighton V. Noonan F. Witt J. Zudans R. Scnoll

\\\\

16])q7 148

ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION FOR CONTAINMENT PURGE SYSTEM AND CONTAINMENT VENTING SYSTEM FOR HATCH NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-321/366 1.

'fith regard to the containment purge and venting system, provide the following infornation:

a.

Discuss the provisions made to. ensure that isolation valve closure will not be prevented by debris which could poten-tially become entrained in the escaping air and steam, b.

Discuss the provisions made for testing the availability of the isolation function and the leakage rate of the isolation valves, individually, during reactor operation.

c.

Specify the amount of containment atmosphere released through the purge and vent isolation valves for a spectrum of break sizes during the maximum closure time allowed in your Technical Specifications.

d.

Provide an analysis to demonstrate the acceptability of the provisions made to protect structures and safety-related equipment, e.g., fans, filters, and ductwork, located beyond the purge system isolation valves against loss of function from the environment created by the escaping air and steam.

e.

For the containment purge isolation valves, specify the differential pressure across the valve for which the maximum leak rate occurs. Provide test results (e.g., from vendor tests of leakage rate versus valve differential pressure) which support your conclusion.

O 16M 149