Information Notice 2019-08, Flow-Accelerated Corrosion Events

From kanterella
(Redirected from ML19065A123)
Jump to navigation Jump to search
Flow-Accelerated Corrosion Events
ML19065A123
Person / Time
Issue date: 10/08/2019
From: Anna Bradford, Chris Miller
NRC/NRO/DLSE, NRC/NRR/DIRS/IRGB
To:
Lintz M, 415-4051, NRR/DIRS
References
IN-19-008
Download: ML19065A123 (4)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS

WASHINGTON, DC 20555-0001 October 8, 2019 NRC INFORMATION NOTICE 2019-08: FLOW-ACCELERATED CORROSION EVENTS

ADDRESSEES

All holders of an operating license or construction permit for a nuclear power reactor under

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of

Production and Utilization Facilities, except those that have permanently ceased operations

and have certified that fuel has been permanently removed from the reactor vessel.

All holders of and applicants for a power reactor combined license, standard design approval, or

manufacturing license under 10 CFR Part 52, Licenses, Certifications, and Approvals for

Nuclear Power Plants. All applicants for a standard design certification, including such

applicants after initial issuance of a design certification rule.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform

addressees of recent operating experience in which flow-accelerated corrosion (FAC) events

resulted in reactor trips. The NRC expects that recipients will review the information for

applicability to their facilities and consider actions, as appropriate, to avoid similar problems.

INs may not impose new requirements, and nothing in this IN should be interpreted to require

specific action.

DESCRIPTION OF CIRCUMSTANCES

Indian Point Energy Center, Unit 3

On September 18, 2018, while in Mode 1 at 100 percent reactor power, operators at Indian

Point Unit 3 manually tripped the reactor and closed all main steam isolation valves in response

to a steam leak on a 6-inch elbow located upstream of the 36C feedwater heater. The direct

cause of the steam leak was FAC. The root cause was attributed to the program engineers not

using the replacement history to identify susceptibility to FAC, as components on this line had

been replaced in 2007 because of previous failures. Contributing causes included weaknesses

in the setup of the FAC program software model and inadequate procedure guidance for scope

expansion from the 2007 failure. Corrective actions included replacing the failed component, revising the model to split the reheater drain branches into three separate runs with one run per

heater, and revising procedures on scope expansion and system replacement history.

Additional information appears in Indian Point - Integrated Inspection Report 05000247/2018004 and 05000286/2018004, dated February 7, 2019, on the NRCs public

website in the Agencywide Documents Access and Management System (ADAMS) Accession

No. ML19038A398, Indian Point - Integrated Inspection Report 05000247/2019002 and

ML19065A123 05000286/2019002, dated August 13, 2019 (ADAMS Accession No. ML19225C606), and

Indian Point Licensee Event Report 50-286/2018-003-00, dated November 19, 2018 (ADAMS

Accession No. ML18341A122).

Davis-Besse Nuclear Power Station

On May 9, 2015, while in Mode 1 at 100 percent reactor power, field operators at Davis-Besse

reported a steam leak on a 4-inch pipe in the moisture separator reheater system. After

initiating a rapid shutdown, the operators manually tripped the reactor from approximately

30 percent power. The direct cause of the steam leak was FAC. An incorrect data input

caused the FAC software model to underestimate the predicted wear rate, so inspections had

not been performed to identify the wall thinning before failure. Additionally, corrective action

from a comparable event in 2006 did not include a validation of all critical data inputs.

Corrective actions from the more recent event included improvements in the fidelity of the data

in the FAC software model and improvements in the corrective action program with respect to

root cause evaluations.

Additional information appears in Davis-BesseNRC Integrated Inspection Report 05000346/2015003, dated October 21, 2015 (ADAMS Accession No. ML15295A107), and

Davis-Besse Licensee Event Report 50-346/2015-002, dated July 8, 2015 (ADAMS Accession

No. ML15194A013).

BACKGROUND

Related NRC Generic Communications

NRC Bulletin 87-01, Thinning of Pipe Walls in Nuclear Power Plants, dated July 9, 1987, requested addressees to submit information on their programs for monitoring the thickness of

pipe walls in high-energy single-phase and two-phase carbon steel piping systems.

NRC Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning, dated May 2, 1989, required addressees to provide assurances that they have implemented a program consisting of

systematic measures to ensure that erosion/corrosion does not lead to degradation of

single-phase and two-phase high-energy carbon steel systems.

DISCUSSION

These events demonstrate the importance of adequately implementing a FAC program, as both

events resulted in reactor trips. While neither of these events caused personnel injury, workers

have been seriously injured or killed in previous events because of failures resulting from FAC.

In 1986, four workers died at Surry Power Station after a catastrophic failure of a pipe because

of FAC. This event prompted the NRC to issue Bulletin 87-01, which requested the

implementation of a program for monitoring the wall thickness of piping at each site.

It is important to apply appropriate engineering judgement and not to place overreliance on the

FAC program software model. Correctly inputting data into the model ensures accurate

modeling and consequential accurate wear rate prediction. Different inputs include, but are not

limited to, diameter, geometry, chemistry, thermodynamic properties, and material content. For

example, if an incorrect diameter is used, or if the presence of trace chromium is inputted when

it is not present, then nonconservative wear rates may be predicted. As such, addressees may

consider performing periodic verifications and validations of the model, in accordance with an approved QC/QC program, and of the assumptions made to the initial setup and updates to the

model.

CONTACT

S

Please direct any questions about this matter to the technical contacts listed below.

/RA/ /RA/

Christopher G. Miller, Director Anna H. Bradford, Deputy Director

Division of Inspection and Regional Support Division of Licensing, Siting, Office of Nuclear Reactor Regulation and Environmental Analysis

Office of New Reactors

Technical Contacts: Catherine Nolan, NSIR James Gavula, NRR

301-415-1535 630-829-9755 Catherine.Nolan@nrc.gov James.Gavula@nrc.gov

ML19065A123 *concurred via email

OFFICE TECH EDITOR NSIR/DPR/OB NRR/DNLR/MCCB NRR/DIRS/IRGB/LA NRR/DIRS/IOEB/BC

NAME KAzariah-Kribbs* CNolan* JGavula* IBetts RElliott*

DATE 9/23/19 9/24/19 9/24/19 09/20/19 9/25/19 OFFICE NRR/DIRS/IRGB/PM NRR/DIRS/IRGB/BC NRO/DLSE/DD NRR/DIRS/D

NAME BBenney PMcKenna ABradford CMiller

DATE 9/26/19 9/26/19 10/1/19 10/10/19