Information Notice 2019-09, Spent Fuel Cask Movement Issues
ML19043A734 | |
Person / Time | |
---|---|
Issue date: | 10/30/2019 |
From: | Mark Lintz NRC/NRR/DRO/IOEB |
To: | |
Lintz M | |
References | |
IN 2019-09 | |
Download: ML19043A734 (7) | |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, DC 20555-0001 October 30, 2019 NRC INFORMATION NOTICE 2019-09: SPENT FUEL CASK MOVEMENT ISSUES
ADDRESSEES
All holders of an operating license or construction permit for a nuclear power reactor issued
under Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of
Production and Utilization Facilities, including those that have permanently ceased operations
and have spent fuel in storage in spent fuel pools (SFPs).
All holders of and applicants for a power reactor combined license, standard design approval, or
manufacturing license under 10 CFR Part 52, Licenses, Certifications, and Approvals for
Nuclear Power Plants. All applicants for a standard design certification, including such
applicants after initial issuance of a design certification rule.
All holders of and applicants for an independent spent fuel storage installation (ISFSI) license
under 10 CFR Part 72, Licensing Requirements for the Independent Storage of Spent Nuclear
Fuel, High-Level Radioactive Waste, and Reactor-Related Greater Than Class C Waste.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform
addressees of recent issues related to spent fuel cask movement issues. The NRC expects
recipients to review the information for applicability to their facilities and consider actions, as
appropriate, to avoid similar problems. However, suggestions contained in this IN are not NRC
requirements; therefore, no specific action or written response is required.
DESCRIPTION OF CIRCUMSTANCES
Spent Fuel Cask Load Drop Analysis/Single-Failure-Proof Handling System
San Onofre Nuclear Generating Station
On August 3, 2018, licensee personnel failed to notice that a loaded spent fuel canister was
misaligned during a lowering evolution into the vault. The licensee and its contractor continued
to lower the vertical cask transporter lift beam until the contractors staff believed that the
canister had been fully lowered to the bottom of the vault. A radiation protection technician
identified radiation readings that were not consistent with a fully lowered canister. The licensee
then identified that the loaded spent fuel canister was resting on a shield ring near the top of the
vault, preventing it from being lowered, and that the rigging and lifting slings were slack and no
longer bearing the load of the canister.
ML19043A734 With the slings slack, the lifting equipment was no longer capable of performing its important to
safety function of holding and controlling the loaded canister. The canister could have
experienced an approximately 17-18 foot drop into the storage vault if the canister had slipped
off the shield ring. This condition placed the cannister in an unanalyzed condition because the
postulated load drop of a cannister is not a condition analyzed in the dry fuel storage systems
Final Safety Analysis Report. The licensee implemented corrective actions that include fuel
loading procedural revisions, training of fuel loading personnel and evaluation of any deviations
based on cannister contact with vault components for canister integrity.
Additional information appears in NRC Special Inspection Report 050-00206/2018-005,
050-00361/2018-005, 050-00362/2018-005, 072-00041/2018-001 and Notice of Violation dated
November 28, 2018 (Agencywide Documents and Management System (ADAMS) Accession
No. ML18332A357).
Kewaunee Power Station
During an inspection, NRC inspectors reviewed the design qualification of the Secure Lift
Yoke/Chain Hoist Assembly used to lift the spent fuel cask. The Updated Safety Analysis
Report (USAR) describes the auxiliary building crane as single-failure-proof in accordance with
NRC guidance and the cask drop analysis is not part of the licensing basis. The inspectors
identified, however, that the Secure Lift Yoke/Chain Hoist Assembly only was qualified as a
non-single-failure-proof lifting device to handle a cask containing spent fuel. The
non-single-failure-proof lifting device was inconsistent with the licensing basis and created the
possibility of dropping a cask, an accident of a different type than described in the USAR, which
would require a license amendment pursuant to 10 CFR 50.59. Licensee corrective actions
include a license amendment request to use a non-single-failure-proof Secure Lift Yoke/Chain
Hoist Assembly as part of cask handling operations within the auxiliary building.
Additional information appears in NRC Inspection Report No. 050-00305/2015-004(DNMS);
072-00064/2015-002(DNMS) - Kewaunee Power Station, dated August 19, 2016 (ADAMS
Accession No. ML16235A301).
Pilgrim Nuclear Power Station
During an inspection at the Pilgrim Nuclear Power Station, the inspectors reviewed the
10 CFR 50.59 regulatory evaluation that removed an energy-absorbing pad from the SFP. This
pad was credited for mitigating a postulated spent fuel cask load drop accident. The pad was
part of the Technical Specification (TS) requirements since the crane used to lift spent fuel
casks was non-single-failure-proof. The licensee installed a single-failure-proof crane, which
removed the need for the energy-absorbing pad. Also, the licensee had installed a
cask-leveling pad designed to provide protection for the SFP floor liner during cask handling
with a single-failure-proof crane, prior to beginning dry storage cask-handling activities.
However, the site did not perform an adequate 10 CFR 50.59 regulatory evaluation, which
would have concluded that a license amendment was required prior to taking actions that
altered the plant from the stated TS condition. Licensee corrective actions included a license
amendment request submittal to remove the energy-absorbing pad language from the TS
requirement and an extent of condition review on previous engineering changes. Additional information appears in Pilgrim Nuclear Power Station NRC Integrated Inspection
Report 050-00293/2014-005 and Independent Spent Fuel Storage Installation (ISFSI) Report
072-01044/2014-003, dated February 4, 2015 (ADAMS Accession No. ML15037A163).
Failure to Follow Boundary Conditions stipulated in ASME NOG-1 2004
Fort Calhoun Station
During an inspection at Fort Calhoun Station, NRC inspectors reviewed a design calculation for
the auxiliary building crane, which is classified as seismic Category I. The licensees Updated
Safety Analysis Report (USAR) specifies the auxiliary building crane meets the requirements of
American Society of Mechanical Engineers (ASME) NOG-1-2004, Rules for Construction of
Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder), as a single-failure-proof
system. ASME NOG-1-2004, Section 4153, stipulates the boundary condition requirements for
the crane seismic analysis, which delineates full seismic loading at the crane rail/wheel
interface. The licensees calculation, however, showed that sliding would occur at the crane
rail/wheel interface, thus limiting the applied seismic loads to only frictional forces. The
inspectors found that the non-linear sliding effects were incorporated in the seismic analysis in a
manner inconsistent with the linear elastic analysis methodology. Licensee corrective actions
include revising calculations and installing field modifications.
Additional information appears in Fort Calhoun - NRC Component Design Basis Inspection
Report 050-00285/2015-007, dated April 16, 2015 (ADAMS Accession No. ML15106A891).
Loading on Crane Rail Clip not considered
Clinton Power Station
During an inspection at Clinton Power Station, NRC inspectors reviewed a design calculation for
the fuel handling building crane and crane support structure (crane rail clip, rail clip bolts, etc.),
which are seismic Category I. The licensees USAR specifies the acceptance criteria for
Seismic Category I structural steel are based on linear elastic methods and no permanent
deformation is allowed. The licensee calculation, however, used the plastic section modulus for
the rail clip. The licensees USAR specified that Seismic Category I structural steel is designed
to the American Institute of Steel Construction specifications. Also, the licensee calculation
used friction, bolt preload, and clamping force which resulted in the loading on the rail clip being
incorrectly determined and resulted in overestimation of the structural capacity of the rail clip.
Licensee corrective actions include calculation revisions and installation of field modifications.
Additional information appears in NRC Inspection Report Nos. 050-00461/2016-010(DNMS);
072-01046/2016-001(DNMS) - Clinton Power Station, dated March 3, 2016 (ADAMS
Accession No. ML16064A200). Fort Calhoun Station
During an inspection at the Fort Calhoun Station, NRC inspectors reviewed a design calculation
for the auxiliary building crane rail clip. The licensees USAR specifies that acceptance criteria
for safety-related structural steel are based on linear elastic methods and no permanent
deformation is allowed. The licensee, however, incorrectly designed the crane runway rail clips
to inelastic acceptance limits. ASME NOG-1-2004, Section 4153, stipulates that crane seismic
analysis be linear elastic. Instead, the licensee used an allowable bending stress in the
calculation consistent with permanent deformation of the rail clip. This assumption resulted in
overestimation of the structural capacity of the rail clip. Licensee corrective actions include
revising calculations and initiating modifications.
Additional information appears in Fort Calhoun - NRC Component Design Bases Inspection
Report 050-00285/2015-007, dated April 16, 2015 (ADAMS Accession No. ML15106A891).
Inadequate Design of Spent Fuel Cask Laydown Areas
Palisades Nuclear Plant
During an inspection at the Palisades Nuclear Plant, NRC inspectors reviewed design
calculations for the stack-up configuration on the auxiliary building trackway slab and identified
several issues. First, the inspectors identified that a procedure did not require installation of
physical torsional restraints as was assumed in the computer model representing the stack-up
configuration. Second, the inspectors identified the interfacing coefficient of friction used in the
calculation was based on steel surfaces with an oxide layer consistent with Regulatory Issue
Summary (RIS) 2015-13, Seismic Stability Analysis Methodologies for Spent Fuel Dry Cask
Loading Stack-Up Configuration dated November 12, 2015 (ADAMS Accession
No. ML15132A122) guidance. However, the inspectors identified that the installed steel floor
plate surface was painted, which could non-conservatively change the interfacing coefficient of
friction compared to the evaluated unpainted steel surface. Third, the inspectors identified that, in the field, there was a gap between the components in the stack-up configuration and the
analysis did not consider a gap. Lastly, the inspectors identified that the computer analysis
results for the truncated low-profile cask transport (used to tow the spent fuel cask) structure
with the derived torsional restraint was equivalent to computer analysis results where the entire
low-profile cask transport structure was modeled. Therefore, the inspectors determined that the
computer results for the analyzed stack-up model with a truncated low-profile cask transport
structure were non-conservative. Licensee corrective actions included revising the stack-up
seismic analysis to address the identified issues; and translated the analyzed stack-up design
configuration into stack-up installation procedures prior to performing stack-up operations with
spent nuclear fuel in the multi-purpose canister.
Additional information appears in Palisades Nuclear Plant - NRC Integrated Inspection Report
050-00255/2016-004; 050-00255/2016-501; 072-00007/2015-001; and 072-00007/2016-001, dated February 14, 2017 (ADAMS Accession No. ML17045A709).
BACKGROUND
Related NRC Generic Communications
IN 2014-12, Crane and Heavy Lift Issues Identified during NRC Inspection, dated
November 14, 2014 (ADAMS Accession No. ML14149A145). This IN informed addressees of
issues identified by NRC inspectors during crane and heavy lift inspections conducted in
accordance with guidance from Operating Experience Smart Sample, fiscal year 2007-03, Rev. 2, Crane and Heavy Lift Inspection, Supplemental Guidance for IP-71111.20, dated
September 12, 2008 (ADAMS Accession No. ML13316C040).
RIS 2005-25, Clarification of NRC Guidelines for Control of Heavy Loads, dated
October 31, 2005 (ADAMS Accession No. ML052340485). This RIS alerted addressees and
clarified guidance related to the control of heavy loads as a result of recommendations
developed through Generic Issue 186, Potential Risk and Consequences of Heavy Load Drops
in Nuclear Power Plants.
Supplement 1 to RIS 2005-25, Clarification of NRC Guidelines for Control of Heavy Loads, dated May 29, 2007 (ADAMS Accession No. ML071210434). This supplement alerted
addressees to the availability of guidance on handling systems, single-failure-proof cranes, and
calculational methods for heavy load analyses, as well as communicated regulatory
expectations associated with 10 CFR 50.59, Changes, Tests, and Experiments, and
10 CFR 50.71(e), as these requirements relate to the safe handling of heavy loads and load
drop analyses.
RIS 2005-25 discusses General Design Criterion (GDC) 2, Design Bases for Protection against
Natural Phenomena, of Appendix A, General Design Criteria for Nuclear Power Plants, to
10 CFR, Part 50. The RIS specifies, in part, that structures, systems, and components
important to safety shall be designed to withstand the effects of natural phenomena, such as
earthquakes. GDC 4, Environmental and Dynamic Effects Design Bases, specifies, in part, that structures, systems, and components important to safety be appropriately protected against
dynamic effects, including the effects of missiles that may result from equipment failures.
DISCUSSION
The events above provide examples of issues related to heavy load spent fuel movements.
These issues highlight non-compliances with NUREGs, codes, and standards that are part of
the plant-specific design and licensing basis.
Although there is no specific requirement to do so, licensees can prevent issues such as those
described in this IN by verifying that calculations for load-handling systems and structures
designated to support spent fuel casks are consistent with the plant-specific design and
licensing bases; and that procedures, training and oversight of spent fuel movement are
adequate.
CONTACT
This IN requires no specific action or written response. Please direct any questions about this
matter to the technical contacts listed below or the appropriate Office of Nuclear Reactor
Regulation project manager.
/RA/ /RA/
Christopher G. Miller, Director Anna H. Bradford, Deputy Director
Division of Inspection and Regional Support Division of Licensing, Siting, and
Office of Nuclear Reactor Regulation Environmental Analysis
Office of New Reactors
/RA/
Michael C. Layton, Director
Division of Spent Fuel Management
Office of Nuclear Material Safety and Safeguards
Technical Contacts: John V. Bozga, Region III Rhex Edwards, Region III
630-829-9613 630-829-9722 e-mail: john.bozga@nrc.gov e-mail: rhex.edwards@nrc.gov
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under NRC Library.
ML19043A734 *concurred via email
OFFICE Tech Editor RIII/DRS/EB1 RIII/DRS/EB1/BC NRR/DMLR/MCCB/BC
NAME JDougherty* JBozga* REdwards* SBloom*
DATE 02/19/19 06/12/19 06/17/19 08/06/19 OFFICE NRR/DMLR/D NRR/DE/ESEB NRR/DE/ESEB/BC NRR/DE/D
NAME JDonoghue* SCuadradodeJesus* GThomas* BWittick*
DATE 08/08/19 08/09/19 08/12/19 09/11/19 OFFICE NRR/DIRS/IOEB NRR/DIRS/IOEB/BC NRO/DLSE/DD NRR/DSS/SCPB/BC
NAME AIssa* RElliott* ABradford SJones*
OFFICE 08/21/19 09/11/19 08/20/19 OFFICE NRR/DSS/D NMSS/DSFM/IOB/BC NMSS/DSFM/D NRR/DIRS/IRGB/LA
NAME MWaters* for JMarshall CAraguas* MLayton IBetts*
OFFICE 09/18/19 07/16/19 06/17/19 OFFICE NRR/DIRS/IRGB /PM NRR/DIRS/IRGB/BC NRR/DIRS/D
NAME MLintz* PMcKenna* CJA for CMiller
OFFICE 08/01/19 10/02/19 10/30/19