Results
Other: ML18193A697, ML18232A438, ML18232A439, ML18289A379, ML18299A124, ML18304A200, ML18346A675, ML18354B066, ML19007A282, ML19007A326, ML19010A383, ML19023A227, ML19290D440, ML19290D506, ML19308A006, ML19311C545, ML20054A175
|
MONTHYEARRS-17-149, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the2017-12-15015 December 2017 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Project stage: Supplement RS-18-033, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-15015 March 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request RS-18-043, Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-28028 March 2018 Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request ML18193A6972018-07-10010 July 2018 Cover Letter Submitting Subsequent License Renewal Application Project stage: Other RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from .2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from . Project stage: Response to RAI ML18232A4392018-09-0404 September 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18232A4382018-09-10010 September 2018 Letter - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18275A3712018-09-25025 September 2018 Subsequent License Renewal Environmental Scoping Meeting 9-25-18 Project stage: Meeting ML18288A4382018-09-25025 September 2018 Transcript from Peach Bottom SLR Envr Scoping Meeting 2018-09-25 Project stage: Request ML18299A1242018-10-0101 October 2018 Pennsylvania State Historic Preservation Office Scoping Comments Concerning Peach Bottom Atomic Power Station, Units 2 & 3 Subsequent License Renewal Application Project stage: Other NRC-2016-0078, Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 32018-10-0303 October 2018 Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 3 Project stage: Request ML18299A2132018-10-0909 October 2018 Comment (3) of Cheryl T. Seager on Behalf of Us Environmental Protection Agency (Epa)On the Draft Environmental Impact Statement (NUREG-1437,Supplement 59) for the License Renewal of Waterford Steam Electric Station Unit 3 ML18282A1692018-10-0909 October 2018 Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Request ML18289A5092018-10-18018 October 2018 Summary of Meeting for Environmental Review of Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Meeting ML18289A3792018-10-25025 October 2018 License Renewal Environmental Site Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18288A1942018-10-25025 October 2018 Summary of the Site Visit Related to the Review of the Subsequent License Renewal Application for the Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Approval ML18304A2002018-11-0606 November 2018 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18323A7492018-11-19019 November 2018 Beyond Nuclear Hearing Request and Petition to Intervene Project stage: Request ML18330A1572018-11-23023 November 2018 Subsequent License Renewal Environmental Requests for Additional Information Project stage: RAI ML18323A1032018-11-30030 November 2018 NUREG-1437, Suppl. 59, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford Steam Electric Station, Unit 3 - Final Report Project stage: Acceptance Review ML19007A2822018-12-0404 December 2018 Fws to NRC, Peach Bottom Subsequent License Renewal Ipac Trust Resources List of Endangered Species, Migratory Birds, and Wetlands Project stage: Other ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review Project stage: Other ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: RAI ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details Project stage: Other ML18354B0612018-12-20020 December 2018 Response to NRC Request for Additional Information, Dated November 23, 2018, Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application, Environmental Requests for Additional Information Project stage: Response to RAI ML19007A3352019-01-0707 January 2019 Map of Conowingo Pond Showing Location of Stations in Trawl Zones 405, 406 and 408 - Figures Project stage: Request ML19007A3302019-01-0707 January 2019 Final Report PBAPS Thermal Study Project stage: Request ML19007A3262019-01-0707 January 2019 Response to Request Dated December 7, 2018 for Docketing of Additional Documents to Support NRCs Environmental Review of the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML19023A0152019-01-23023 January 2019 Supplement No. 2 - Changes to the Subsequent License Renewal Application Project stage: Supplement ML19028A2802019-01-28028 January 2019 Response to NRC Request for Additional Information, Dated December 13, 2018, Regarding Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: Response to RAI ML18346A6752019-01-31031 January 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Other ML19023A2272019-02-0505 February 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19042A1312019-02-11011 February 2019 Supplement No. 3 - Changes to the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Supplement ML19037A3482019-07-25025 July 2019 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Application Project stage: Approval ML19210D4532019-07-31031 July 2019 NUREG-1437, Supplement 10, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 10, Second Renewal for Peach Bottom, Units 2 and 3 Project stage: Acceptance Review ML19210C5712019-07-31031 July 2019 Schedule Revision for the Review of the Peach Bottom Atomic Power Station Units 2 & 3 Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0012/L-2018-RNW-0013) Project stage: Approval ML19199A1142019-08-0101 August 2019 Notice of Availability of Draft Supplement 10, Second Renewal to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Draft Other ML19199A1152019-08-0101 August 2019 Federal Register Notice - Peach Bottom Atomic Power Station Notice of Availability of the Draft Plant-Specific Draft Supplement 10 Second Renewal to the Generic Environmental Impact Statement for SLR Project stage: Draft Other ML19260F9652019-08-0101 August 2019, 12 September 2019, 23 September 2019, 2 October 2019 Nuclear Regulatory Commission'S Public Meeting on the Draft Supplemental Environmental Impact Statment for Subsequent License Renewal of Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Request ML19256E3522019-09-12012 September 2019 Slides - Peach Bottom SLRA Dseis Public Meeting - Sep 12 2019 Project stage: Request ML19310D2042019-09-12012 September 2019 TMI Alerts Testimony NUREG-1437 Supplement 10 Second Renewal GEIS for License Renewal of Nuclear Plants Supplement 10 Second Renewal Peach Bottom SLRA Project stage: Supplement ML19308A0062019-09-16016 September 2019 Jennifer Shang Comments on Pb Dseis Project stage: Other ML19266A0102019-09-23023 September 2019 Comments on the Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 10 Second Renewal Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 ML19269E9372019-09-23023 September 2019 Barbara Rudnick, NEPA Program Coordinator, Office of Communities, Tribes and Environmental Assessment, Region III, U.S. EPA to David Drucker, NRC, EPA Comments on NUREG-1437, Supplement 10, Second Renewal Draft SEIS Peach Bottom SLR Project stage: Request ML19273B9692019-10-0202 October 2019 September 12, 2019 - Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic EIS for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station Units 2 and 3 SLRA (EPID: L-201-RNW-0013) ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs Project stage: RAI ML19303D1432019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- Email Project stage: RAI ML19290D5062020-01-27027 January 2020 FRN for Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19290D4402020-01-27027 January 2020 Notification of the Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19311C5452020-01-27027 January 2020 Notice of Availability of the Final Plant-Specific Supplement 10, Second Renewal, to the GEIS Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 (EPID L 2018 Lne 0013) (Docket Nos.: 50-277 and 50 277) - EPA - Letter Project stage: Other 2018-08-28
[Table View] |
Text
U.S. Nuclear Regulatory Commission Public Meeting Summary October 18, 2018
Title:
Public Scoping Meeting for Environmental Review of Peach Bottom Atomic Power Station, Units 2 and 3 Subsequent License Renewal Application (EPID NO. L-2018-RWL-0013)
Meeting Identifier: 20180960 Date of Meeting: Tuesday, September 25, 2018 Location: Peach Bottom Inn, 6085 Delta Road, Delta, PA 17314 Type of Meeting: Category 3 Purpose of the Meeting(s):
To describe the license renewal process and to allow members of the public the opportunity to provide comments regarding environmental issues that the U.S. Nuclear Regulatory Commission (NRC) should consider during its environmental review of the Peach Bottom SLRA.
General Information:
The NRC held a public scoping meeting as part of the Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom) Subsequent License Renewal Application (SLRA) environmental review. The meeting started at 6:00 p.m. local time. The meeting was preceded by an informal open house beginning 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> prior to the meeting where members of the public were provided the opportunity to meet with NRC staff. The meeting ended at 7:05 p.m. There were 12 NRC staff members present. The meeting was facilitated by Brett Klukan, an NRC in-house facilitator. The meeting began with a review of meeting ground rules and an introduction of NRC staff, followed by a presentation on the license renewal safety review process by Bennett Brady and the license renewal environmental review process by Lauren Gibson. The presentations emphasized that comments were welcome to help focus the environmental review. Next, there was a question and answer period on the NRC staff presentations. Finally, there was the comment portion of the meeting.
There were 34 people in attendance at the meeting, including NRC staff. Their names and affiliations are listed in Table 1.
Table 1: Attendees Name Affiliation Albert Wong NRC Angela Wu NRC Benjamin Beasley NRC Bennett Brady NRC Brett Klukan NRC David Drucker NRC Eric Oesterle NRC Jenny Tobin NRC Joe Donoghue NRC Kevin Folk NRC Lauren K Gibson NRC Neil Sheehan NRC Albert Phia Exelon Denise Ingoe Exelon Donald Ferraro Exelon Liz Williamson Exelon Michael Griffin Exelon Mike Gallagher Exelon Nancy Ranek Exelon Pat Nauin Exelon Sam Hansell Exelon Sam Rice Exelon Paul Gunter Beyond Nuclear Zach Barthel Maryland Department of Environment Shawn Seaman MD Power Plant Research Program Brad Fuller Pennsylvania Department of Environmental Protection Dave Allard Pennsylvania Department of Environmental Protection Rich Janati Pennsylvania Nuclear Safety David Lewis Pillsbury Jyuji D. Hewitt public Susan Hewitt public Ernest Eric Guyll public-local resident Todd Eaby Susquehanna River Basin Commission Bruce L. Clark TMC Summary of Presentation:
The Atomic Energy Act of 1954 authorizes the NRC to grant licenses for commercial power reactors to operate for up to 40 years and allows these licenses to be renewed for up to another 20 years. A renewed license may be subsequently renewed. The NRC has established a license renewal process that has two separate, but parallel review tracks; a safety review and an environmental review.
The focus of the safety review stems from the NRCs obligation under the Atomic Energy Act of 1954, and is performed under the regulations of Title 10 of the Code of Federal Regulations (10 CFR), Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plant. The purpose of this review is to verify that each applicant has fully analyzed the management of aging effects in sufficient detail to conclude that the plant can be operated safely during the period of extended operation. The NRCs safety review is documented in the final safety evaluation report.
Under the NRCs environmental protection regulations in 10 CFR Part 51which implement the National Environmental Policy Act (NEPA)issuance of a new nuclear power plant operating license requires the preparation of an environmental impact statement (EIS). The NRC performs plant-specific reviews of environmental impacts of operating life extension in accordance with NEPA and the requirements of 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions. As part of the environmental review, the staff consults with local, State, Federal, and Tribal officials.
The environmental review begins with a scoping process, which is an assessment of specific environmental impacts associated with renewing the Peach Bottom operating licenses.
Some environmental impacts are similar, if not identical, at all nuclear power plants, so, to improve efficiency, the NRC staff developed a generic environmental impact statement, NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, that addresses a number of impacts common to all nuclear power plants. The NRC staff supplements the generic EIS with a plant-specific EIS (SEIS), in which all issues that are specific to Peach Bottom will be addressed. The staff also re-examines the conclusions reached in the generic EIS to determine if there is any new and significant information that would change those conclusions. The NRC staff will make a recommendation on whether or not the environmental impacts are so great that they preclude maintaining the option of license renewal for energy-planning decision makers.
The closing date for submitting scoping comments is October 10, 2018. In addition to providing comments at the meetings, comments can be: (1) mailed to May Ma, Director, Program Management, Announcements and Editing Branch, Office of Administration, Mailstop: TWFN-7A6OM, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; (2) submitted online using the Federal Rulemaking website at regulations.gov (keyword: NRC-2018-0130); or emailed to david.drucker@nrc.gov. Comments will not be edited to remove any identifying or contact information. Do not include any information in comments that you do not want publicly disclosed.
Public Participation Themes:
There were several commenters during the public meeting. Themes included wanting more public participation in the safety review, the possibility of examining materials and age-related degradation from reactors that shut down, and the degree of independence of the NRC review. Commenters also discussed dry cask storage; seismic, flooding, and radiation hazards; and the policy outlook for nuclear power as an energy option in general.
A complete accounting of the comments provided can be found in the meeting transcript which is available in the NRCs Agencywide Documents Access and Management System (ADAMS) public electronic reading room under the accession numbers listed below, http://www.nrc.gov/reading-rm/adams.html.
Action Items/Next Steps:
The NRC staff will address the comments provided during this meeting as part of the SLRA review process for Peach Bottom. A record of how each comment was addressed will be included in the Scoping Summary Report or draft SEIS.
Attachments:
o Meeting description and agenda - ADAMS Accession No. ML18242A021 o NRC staff presentation - ADAMS Accession No. ML18275A371 o Meeting transcript - ADAMS Accession No. ML18288A438
SUBJECT:
PUBLIC SCOPING MEETING
SUMMARY
FOR ENVIRONMENTAL REVIEW OF PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NO. L-2018-RWL-0013) DATED OCTOBER 18, 2018.
DISTRIBUTION:
PUBLIC RidsNrrDmlr Resource RidsNrrDmlrMrpb Resource RidsNrrDmlrMenb Resource RidsNrrDmlrMphb Resource RidsNrrDmlrMccb Resource RidsNrrPMPeachBottom Resource Lauren.gibson@nrc.gov; NRR/DMLR David.drucker@nrc.gov, NRR/DMLR Bennett.Brady@nrc.gov, NRR/DMLR eric.oesterle@nrc.gov; NRR/DMLR george.wilson@nrc.gov; NRR/DMLR joseph.donoghue@nrc.gov; NRR/DMLR mitzi.young@nrc.gov; OGC scott.burnell@nrc.gov; HQ/OPA neil.sheehan@nrc.gov; RI/OPA diane.screnci@nrc.gov; RI/OPA jenny.weil@nrc.gov; OCA douglas.tifft@nrc.gov; RI/ORA jonathan.greives@nrc.gov; RI/DRP justin.heinly@nrc.gov; RI/DRP larry.burkhardt@nrc.gov Nancy.Ranek@exeloncorp.com ADAMS Accession No.: ML18289A509 OFFICE PM:MRPB:DMLR LA:MRPB:DMLR BC:MRPB:DMLR PM:MRPB:DMLR NAME LKGibson SLent EOesterle LKGibson DATE 10/15/18 10/17/18 10/18/18 10/18/18 OFFICE RECORD COPY