Letter Sequence ' |
|---|
EPID:L-2018-RNW-0013, Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement
Results
Other: ML18193A697, ML18232A438, ML18232A439, ML18289A379, ML18299A124, ML18304A200, ML18346A675, ML18354B066, ML19007A282, ML19007A326, ML19010A383, ML19023A227, ML19290D440, ML19290D506, ML19308A006, ML19311C545, ML20054A175
|
MONTHYEARRS-17-149, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the2017-12-15015 December 2017 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Project stage: Supplement RS-18-033, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-15015 March 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request RS-18-043, Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-28028 March 2018 Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request ML18193A6972018-07-10010 July 2018 Cover Letter Submitting Subsequent License Renewal Application Project stage: Other RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from .2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from . Project stage: Response to RAI ML18232A4392018-09-0404 September 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18232A4382018-09-10010 September 2018 Letter - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18275A3712018-09-25025 September 2018 Subsequent License Renewal Environmental Scoping Meeting 9-25-18 Project stage: Meeting ML18288A4382018-09-25025 September 2018 Transcript from Peach Bottom SLR Envr Scoping Meeting 2018-09-25 Project stage: Request ML18299A1242018-10-0101 October 2018 Pennsylvania State Historic Preservation Office Scoping Comments Concerning Peach Bottom Atomic Power Station, Units 2 & 3 Subsequent License Renewal Application Project stage: Other NRC-2016-0078, Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 32018-10-0303 October 2018 Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 3 Project stage: Request ML18299A2132018-10-0909 October 2018 Comment (3) of Cheryl T. Seager on Behalf of Us Environmental Protection Agency (Epa)On the Draft Environmental Impact Statement (NUREG-1437,Supplement 59) for the License Renewal of Waterford Steam Electric Station Unit 3 ML18282A1692018-10-0909 October 2018 Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Request ML18289A5092018-10-18018 October 2018 Summary of Meeting for Environmental Review of Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Meeting ML18289A3792018-10-25025 October 2018 License Renewal Environmental Site Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18288A1942018-10-25025 October 2018 Summary of the Site Visit Related to the Review of the Subsequent License Renewal Application for the Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Approval ML18304A2002018-11-0606 November 2018 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18323A7492018-11-19019 November 2018 Beyond Nuclear Hearing Request and Petition to Intervene Project stage: Request ML18330A1572018-11-23023 November 2018 Subsequent License Renewal Environmental Requests for Additional Information Project stage: RAI ML18323A1032018-11-30030 November 2018 NUREG-1437, Suppl. 59, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford Steam Electric Station, Unit 3 - Final Report Project stage: Acceptance Review ML19007A2822018-12-0404 December 2018 Fws to NRC, Peach Bottom Subsequent License Renewal Ipac Trust Resources List of Endangered Species, Migratory Birds, and Wetlands Project stage: Other ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review Project stage: Other ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: RAI ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details Project stage: Other ML18354B0612018-12-20020 December 2018 Response to NRC Request for Additional Information, Dated November 23, 2018, Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application, Environmental Requests for Additional Information Project stage: Response to RAI ML19007A3352019-01-0707 January 2019 Map of Conowingo Pond Showing Location of Stations in Trawl Zones 405, 406 and 408 - Figures Project stage: Request ML19007A3302019-01-0707 January 2019 Final Report PBAPS Thermal Study Project stage: Request ML19007A3262019-01-0707 January 2019 Response to Request Dated December 7, 2018 for Docketing of Additional Documents to Support NRCs Environmental Review of the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML19023A0152019-01-23023 January 2019 Supplement No. 2 - Changes to the Subsequent License Renewal Application Project stage: Supplement ML19028A2802019-01-28028 January 2019 Response to NRC Request for Additional Information, Dated December 13, 2018, Regarding Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: Response to RAI ML18346A6752019-01-31031 January 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Other ML19023A2272019-02-0505 February 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19042A1312019-02-11011 February 2019 Supplement No. 3 - Changes to the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Supplement ML19037A3482019-07-25025 July 2019 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Application Project stage: Approval ML19210D4532019-07-31031 July 2019 NUREG-1437, Supplement 10, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 10, Second Renewal for Peach Bottom, Units 2 and 3 Project stage: Acceptance Review ML19210C5712019-07-31031 July 2019 Schedule Revision for the Review of the Peach Bottom Atomic Power Station Units 2 & 3 Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0012/L-2018-RNW-0013) Project stage: Approval ML19199A1142019-08-0101 August 2019 Notice of Availability of Draft Supplement 10, Second Renewal to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Draft Other ML19199A1152019-08-0101 August 2019 Federal Register Notice - Peach Bottom Atomic Power Station Notice of Availability of the Draft Plant-Specific Draft Supplement 10 Second Renewal to the Generic Environmental Impact Statement for SLR Project stage: Draft Other ML19260F9652019-08-0101 August 2019, 12 September 2019, 23 September 2019, 2 October 2019 Nuclear Regulatory Commission'S Public Meeting on the Draft Supplemental Environmental Impact Statment for Subsequent License Renewal of Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Request ML19256E3522019-09-12012 September 2019 Slides - Peach Bottom SLRA Dseis Public Meeting - Sep 12 2019 Project stage: Request ML19310D2042019-09-12012 September 2019 TMI Alerts Testimony NUREG-1437 Supplement 10 Second Renewal GEIS for License Renewal of Nuclear Plants Supplement 10 Second Renewal Peach Bottom SLRA Project stage: Supplement ML19308A0062019-09-16016 September 2019 Jennifer Shang Comments on Pb Dseis Project stage: Other ML19266A0102019-09-23023 September 2019 Comments on the Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 10 Second Renewal Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 ML19269E9372019-09-23023 September 2019 Barbara Rudnick, NEPA Program Coordinator, Office of Communities, Tribes and Environmental Assessment, Region III, U.S. EPA to David Drucker, NRC, EPA Comments on NUREG-1437, Supplement 10, Second Renewal Draft SEIS Peach Bottom SLR Project stage: Request ML19273B9692019-10-0202 October 2019 September 12, 2019 - Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic EIS for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station Units 2 and 3 SLRA (EPID: L-201-RNW-0013) ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs Project stage: RAI ML19303D1432019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- Email Project stage: RAI ML19290D5062020-01-27027 January 2020 FRN for Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19290D4402020-01-27027 January 2020 Notification of the Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19311C5452020-01-27027 January 2020 Notice of Availability of the Final Plant-Specific Supplement 10, Second Renewal, to the GEIS Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 (EPID L 2018 Lne 0013) (Docket Nos.: 50-277 and 50 277) - EPA - Letter Project stage: Other 2018-08-28
[Table View] |
"Draft Meeting" is not in the list (Request, Draft Request, Supplement, Acceptance Review, Meeting, Withholding Request, Withholding Request Acceptance, RAI, Draft RAI, Draft Response to RAI, ...) of allowed values for the "Project stage" property.
Text
October 2, 2019 U.S. Nuclear Regulatory Commission Public Meeting Summary
Title:
Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom) Subsequent License Renewal Application (SLRA) (EPID L-2018-RNW-0013)
Meeting Identifier: 20190828 Date of Meeting: Thursday, September 12, 2019 Location: Peach Bottom Inn, 6085 Delta Road, Delta, PA 17314 Type of Meeting: Category 3 Purpose of the Meeting(s):
To discuss the preliminary findings of, and receive public comments on, the draft supplemental environmental impact statement (SEIS) regarding the proposed subsequent renewal of the operating licenses for Peach Bottom SLRA.
General Details:
The NRC held a public meeting as part of the Peach Bottom SLRA environmental review.
The meeting started at 6:00 p.m. local time. The meeting was preceded by an informal open house beginning one hour prior to the meeting where members of the public were provided the opportunity to meet with NRC staff. The meeting ended at 7:40 p.m. The meeting was facilitated by Brett Klukan, an NRC in-house facilitator who opened the meeting with a review of meeting ground rules and an introduction of NRC staff. Next, Caroline Hsu, NRC, discussed the license renewal environmental review process and the preliminary findings of the draft supplemental environmental impact statement (SEIS) regarding the proposed subsequent renewal of the operating licenses for Peach Bottom Units 2 and 3. The presentation emphasized that comments were welcome to improve the draft SEIS. Next, there was a question and answer period on the NRC staff presentations.
Finally, there was the comment portion of the meeting.
Twenty-seven people (this number includes nine NRC staff members) attended the meeting.
In addition to four members of the public, meeting attendees included Paul Gunter of Beyond Nuclear, Inc., representatives from Three Mile Island Alert, a representative from the Pennsylvania Department of Environmental Protection, members of the press and the applicant.
Summary of Presentation:
Exelon submitted its subsequent license renewal application for Peach Bottom Units 2 and 3 in July of 2018. If renewed for a second time, the licenses for Units 2 and 3 would expire on August 8, 2053 and July 2, 2054. As a part of the environmental review, the NRC staff published the draft site-specific environmental impact statement containing preliminary findings and recommendation on July 30, 2019 ADAMS Accession No. (ML19210D453).
The NRC staff addresses environmental resource areas by analyzing in detail the impacts that operation of the power plant may have on the resource area. The staff then characterizes these impacts as SMALL, MODERATE, or LARGE. The following resource areas would experience SMALL impacts from subsequent license renewal: land use/visual resources, air quality/noise, geologic environment, surface water resources, groundwater resources, terrestrial resources, socioeconomics, transportation, human health, and waste management. For aquatic resources, the impacts would be SMALL to MODERATE, because subsequent license renewal may noticeably alter the resource but not destabilize the key attributes of the resource. For some environmental resource areas, the characterization of impacts is dictated by statutes or executive orders and not the NRCs SMALL, MODERATE and LARGE determinations. The following table provides the NRC staffs preliminary findings for those resource areas:
Special Status Species and Habitats May affect, but is not likely to adversely affect Northern long-eared bat and Indiana bat May affect Chesapeake logperch No adverse effects on Essential Fish Habitat Historic and Cultural Resources Would not adversely affect known historic properties or historic and cultural resources Environmental Justice No disproportionate high and adverse human health and environmental effects In addition, the NRC staff analyzed cumulative impacts (the impacts of the continued operation of Peach Bottom Units 2 and 3) in combination with other past, present, and reasonably foreseeable future actions in the area) and reasonable alternatives to subsequent license renewal including new nuclear, supercritical pulverized coal, natural gas combined-cycle, a combination of natural gas, wind, solar, and purchased power, and a no-action alternative.
Based on its evaluation of the environmental impacts of operating Peach Bottom Units 2 and 3 for an additional 20 years, the NRC staffs preliminary recommendation is that any adverse environmental impacts of renewing the Peach Bottom licenses are not so great that preserving the option of license renewal for energy-planning decisionmakers would be unreasonable.
The closing date for submitting scoping comments is September 23, 2019. In addition to providing comments at the meeting, comments can be: (1) mailed to Program Management, Announcements and Editing Staff, Office of Administration, Mailstop: TWFN-7A6OM, U.S.
Nuclear Regulatory Commission, Washington, D.C. 20555-0001; (2) submitted online using the Federal Rulemaking website at regulations.gov (keyword: NRC-2018-0130); or emailed to david.drucker@nrc.gov.
Public Participation Themes: There were four commenters at the meeting. The first commenter was Mr. Ernest Eric Guyll, a member of the public. His comments primarily focused on requesting enhanced radiation monitoring around Peach Bottom. The second commenter was Mr. Paul Gunter, Beyond Nuclear, Inc. His comments focused on the concerns identified in the petitions Beyond Nuclear, Inc. submitted to the NRC on September 3, 2019, as an intervenor on the Peach Bottom SLRA review, i.e., requesting harvesting of items from recently shut down nuclear plants to inform the NRCs subsequent license renewal reviews and industry operating experience. The third commenter was Mr. Scott Portzline, former Three Mile Island Alert Security Consultant. His comments focused on critiquing the NRCs estimate of the risk and method used to determine the risk associated with severe accidents. The fourth commenter was Mr. Eric Epstein, Three Mile Island Alert. His comments focused on the difficulties of evacuating people, especially children, from the Peach Bottom area in the event of a radiological disaster.
The verbal comments provided at this public meeting can be found in the meeting transcript which is available in the NRCs ADAMS public electronic reading room (http://www.nrc.gov/reading-rm/adams.html) at the accession number listed below. The written statements provided at this meeting will be addressed in the final SEIS.
Action Items/Next Steps: The NRC staff will address the comments provided during this meeting in the final SEIS, expected to be published in January 2020.
Enclosure:
List of Meeting Attendees cc: Listserv Attachments:
o Meeting description and agenda - ML19213A054 o NRC staff presentation - ML19256E352 o Meeting transcript - ML19268B351 o Meeting summary - ML19273B969
TITLE:
Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom) Subsequent License Renewal Application (SLRA) (EPID L-2018-RNW-0013) Dated October 2, 2019 DISTRIBUTION:
E-MAIL PUBLIC RidsNrrDmlr Resource RidsNrrPMPeachBottom Resource Ben Beasley Bennett Brady Joe Donoghue David Drucker Rob Elliot Kayla Gamin Lauren Gibson Justin Heinly Caroline Hsu Lois James Eric Oesterle Mitzi Young ADAMS Accession Nos:
Meeting Package: ML19260F965 Meeting Agenda/Notice: ML19213A054 Meeting Slides: ML19256E352 Meeting Transcript: ML19268B351 Meeting Summary: ML19273B969
- via email OFFICE PM:MRPB:DMLR LA:MRPB:DMLR BC:MRPB:DMLR PM:MRPB:DMLR*
NAME DDrucker YEdmonds EOesterle DDrucker DATE 9/25/19 9/26/19 9/26/19 10/2/19 OFFICE RECORD COPY
Enclosure Peach Bottom Atomic Station Units 2 and 3 DSEIS Public Meeting List of Meeting Attendees September 12, 2019 Name Affiliation David Drucker U.S.Nuclear Regulatory Commission (NRC)
Ben Beasley NRC Peter Boguszewski NRC Scott Burnell NRC Rob Elliot NRC Justin Heinly NRC Caroline Hsu NRC Brett Klukan NRC Eric Oesterle NRC Eric Epstein Three Mile Island Alert (TMIA)
Scott Portzline TMIA, former security consultant Brad Fuller Pennsylvania Department of Environmental Protection Paul Gunter Beyond Nuclear, Inc Ernest Eric Guyll Member of public David Lewis Pillsbury Law Maren Machles Scripps News Service Rebecca Moss Spotlight PA Michael Gallagher Exelon Generation Company (Exelon)
Don Ferraro Exelon Samuel Hansell Exelon Denise Ingoe Exelon Megan Lewatowski Exelon Patrick Navin Exelon Albert Piha Exelon Nancy Ranek Exelon Samantha Rice Exelon