EPID:L-2018-RNW-0013, Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement
Results
Other: ML18193A697, ML18232A438, ML18232A439, ML18289A379, ML18299A124, ML18304A200, ML18346A675, ML18354B066, ML19007A282, ML19007A326, ML19010A383, ML19023A227, ML19290D440, ML19290D506, ML19308A006, ML19311C545, ML20054A175
|
MONTHYEARRS-17-149, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the2017-12-15015 December 2017 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Project stage: Supplement RS-18-033, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-15015 March 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request RS-18-043, Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-28028 March 2018 Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request ML18193A6972018-07-10010 July 2018 Cover Letter Submitting Subsequent License Renewal Application Project stage: Other RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from .2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from . Project stage: Response to RAI ML18232A4392018-09-0404 September 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18232A4382018-09-10010 September 2018 Letter - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18275A3712018-09-25025 September 2018 Subsequent License Renewal Environmental Scoping Meeting 9-25-18 Project stage: Meeting ML18288A4382018-09-25025 September 2018 Transcript from Peach Bottom SLR Envr Scoping Meeting 2018-09-25 Project stage: Request ML18299A1242018-10-0101 October 2018 Pennsylvania State Historic Preservation Office Scoping Comments Concerning Peach Bottom Atomic Power Station, Units 2 & 3 Subsequent License Renewal Application Project stage: Other NRC-2016-0078, Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 32018-10-0303 October 2018 Comment (1) of Alan Harris on Behalf of Entergy Louisiana, LLC and Entergy Operations, Inc. on Entergy Operations, Inc; Waterford Steam Electric Station, Unit 3 Project stage: Request ML18299A2132018-10-0909 October 2018 Comment (3) of Cheryl T. Seager on Behalf of Us Environmental Protection Agency (Epa)On the Draft Environmental Impact Statement (NUREG-1437,Supplement 59) for the License Renewal of Waterford Steam Electric Station Unit 3 ML18282A1692018-10-0909 October 2018 Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Request ML18289A5092018-10-18018 October 2018 Summary of Meeting for Environmental Review of Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Meeting ML18289A3792018-10-25025 October 2018 License Renewal Environmental Site Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18288A1942018-10-25025 October 2018 Summary of the Site Visit Related to the Review of the Subsequent License Renewal Application for the Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Approval ML18304A2002018-11-0606 November 2018 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18323A7492018-11-19019 November 2018 Beyond Nuclear Hearing Request and Petition to Intervene Project stage: Request ML18330A1572018-11-23023 November 2018 Subsequent License Renewal Environmental Requests for Additional Information Project stage: RAI ML18323A1032018-11-30030 November 2018 NUREG-1437, Suppl. 59, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Waterford Steam Electric Station, Unit 3 - Final Report Project stage: Acceptance Review ML19007A2822018-12-0404 December 2018 Fws to NRC, Peach Bottom Subsequent License Renewal Ipac Trust Resources List of Endangered Species, Migratory Birds, and Wetlands Project stage: Other ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review Project stage: Other ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: RAI ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details Project stage: Other ML18354B0612018-12-20020 December 2018 Response to NRC Request for Additional Information, Dated November 23, 2018, Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application, Environmental Requests for Additional Information Project stage: Response to RAI ML19007A3352019-01-0707 January 2019 Map of Conowingo Pond Showing Location of Stations in Trawl Zones 405, 406 and 408 - Figures Project stage: Request ML19007A3302019-01-0707 January 2019 Final Report PBAPS Thermal Study Project stage: Request ML19007A3262019-01-0707 January 2019 Response to Request Dated December 7, 2018 for Docketing of Additional Documents to Support NRCs Environmental Review of the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML19023A0152019-01-23023 January 2019 Supplement No. 2 - Changes to the Subsequent License Renewal Application Project stage: Supplement ML19028A2802019-01-28028 January 2019 Response to NRC Request for Additional Information, Dated December 13, 2018, Regarding Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: Response to RAI ML18346A6752019-01-31031 January 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Other ML19023A2272019-02-0505 February 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19042A1312019-02-11011 February 2019 Supplement No. 3 - Changes to the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Supplement ML19037A3482019-07-25025 July 2019 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Application Project stage: Approval ML19210D4532019-07-31031 July 2019 NUREG-1437, Supplement 10, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 10, Second Renewal for Peach Bottom, Units 2 and 3 Project stage: Acceptance Review ML19210C5712019-07-31031 July 2019 Schedule Revision for the Review of the Peach Bottom Atomic Power Station Units 2 & 3 Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0012/L-2018-RNW-0013) Project stage: Approval ML19199A1142019-08-0101 August 2019 Notice of Availability of Draft Supplement 10, Second Renewal to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Draft Other ML19199A1152019-08-0101 August 2019 Federal Register Notice - Peach Bottom Atomic Power Station Notice of Availability of the Draft Plant-Specific Draft Supplement 10 Second Renewal to the Generic Environmental Impact Statement for SLR Project stage: Draft Other ML19260F9652019-08-0101 August 2019, 12 September 2019, 23 September 2019, 2 October 2019 Nuclear Regulatory Commission'S Public Meeting on the Draft Supplemental Environmental Impact Statment for Subsequent License Renewal of Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Request ML19256E3522019-09-12012 September 2019 Slides - Peach Bottom SLRA Dseis Public Meeting - Sep 12 2019 Project stage: Request ML19310D2042019-09-12012 September 2019 TMI Alerts Testimony NUREG-1437 Supplement 10 Second Renewal GEIS for License Renewal of Nuclear Plants Supplement 10 Second Renewal Peach Bottom SLRA Project stage: Supplement ML19308A0062019-09-16016 September 2019 Jennifer Shang Comments on Pb Dseis Project stage: Other ML19266A0102019-09-23023 September 2019 Comments on the Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 10 Second Renewal Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 ML19269E9372019-09-23023 September 2019 Barbara Rudnick, NEPA Program Coordinator, Office of Communities, Tribes and Environmental Assessment, Region III, U.S. EPA to David Drucker, NRC, EPA Comments on NUREG-1437, Supplement 10, Second Renewal Draft SEIS Peach Bottom SLR Project stage: Request ML19273B9692019-10-0202 October 2019 September 12, 2019 - Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic EIS for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station Units 2 and 3 SLRA (EPID: L-201-RNW-0013) ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs Project stage: RAI ML19303D1432019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- Email Project stage: RAI ML19290D5062020-01-27027 January 2020 FRN for Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19290D4402020-01-27027 January 2020 Notification of the Availability of the Final Plant-Specific Supplement 10, Second Renewal to the GEIS for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 Project stage: Other ML19311C5452020-01-27027 January 2020 Notice of Availability of the Final Plant-Specific Supplement 10, Second Renewal, to the GEIS Regarding Subsequent License Renewal for Peach Bottom Units 2 and 3 (EPID L 2018 Lne 0013) (Docket Nos.: 50-277 and 50 277) - EPA - Letter Project stage: Other 2018-08-28
[Table View] |
Text
Exelon Generation July 10, 2018 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 200 Exelon Way Kennett Square, PA 19348 www.exeloncorp.com Peach Bottom Atomic Power Station, Units 2 and 3
Subject:
Renewed Facility Operating License Nos. DPR-44 and DPR-56 N RC Docket Nos. 50-277 and 50-278 Application for Subsequent Renewed Operating Licenses 10 CFR 50 10 CFR 51 10 CFR 54 Pursuant to the Code of Federal Regulations, Title 1 O, Parts 50, 51, and 54, Exelon Generation Company, LLC (Exelon) hereby applies for the renewal of the Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, Renewed Facility Operating Licenses, Nos. DPR-44 and DPR-56, respectively.
The existing PBAPS renewed facility operating licenses are currently set to expire as follows:
- At midnight on August 8, 2033 for Unit 2 (Facility Operating License No. DPR-44)
- At midnight on July 2, 2034 for Unit 3 (Facility Operating License No. DPR-56)
Exelon seeks to extend the respective operating terms by 20 years beyond the current renewed license expiration dates.
The enclosed Subsequent License Renewal Application (SLRA) contains the information required by the License Renewal regulations set forth in 1 O CFR Parts 54 and 51, and meets the submittal timeliness requirements of 10 CFR 54.17(c) and 10 CFR 2.109(b).
As required by 1 O CFR 54.21 (b), current licensing basis changes which have a material effect on the content of this application will be identified annually while the application is under NRC review, and at least three months prior to the scheduled completion of the NRC review.
Appendix A, Section A.5, of the enclosed PBAPS SLRA provides a list of commitments made in this application. This list will be updated as required throughout the SLRA review process.
U.S. Nuclear Regulatory Commission
- Subsequent Renewed Operating Licenses Docket Nos. 50-277 and 50-278 July 1 O, 2018 Page 2 In accordance with 1 O CFR Part 50, Appendix H, and NUREG-2192, "Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants," an update to the PBAPS reactor surveillance capsule withdrawal schedule addressing the subsequent (i.e.,
second) period of extended operation is included within this submittal, for NRC approval. The capsule withdrawal schedule is provided in Enhancement 1 of the Reactor Vessel Material Surveillance program, as shown in SLRA Sections A.2.1.20, A.5 (Commitment 20), and 8.2.1.20.
The enclosed SLRA is being submitted electronically. A total of one (1) CD-ROM is included in this electronic submission. The CD-ROM labeled "PB_SLRA" contains the following six (6) files:
001 _PB_SLRA.pdf 8,881,000 bytes, publicly available 002 _PB_ERMain.pdf 89,563,000 bytes, publicly available 003 _PB_ER_AppA_B.pdf 31,183,000 bytes, publicly available 004 _PB_ER_AppC1_Part_ 1_of_2_;pdf 75,043,000 bytes, publicly available 005 _PB_ER_AppC1 _Part_2_of_2_.pdf 96,107,000 bytes, publicly available 006 _PB_ER_AppC2_C3_D_E.pdf 20,633,000 bytes, publicly available Exelon has reviewed all information contained in the above files and verified that none of the information is marked as proprietary.
If you have any questions, please contact:
Name Mailing Address E-Mail Address Phone Number John Hilditch 200 Exelon Way Kennett Square, PA 19348 john.hilditch@exeloncorp.com 61 0-765-5373 I declare under penalty of perjury that the foregoing is true and correct.
Executed on _tJ_7_-_l._"_-_'2ol g Respectfully, rt!:ltt://~ -
Vice President - License Renewal and Decommissioning Exelon Generation Company, LLC
U.S. Nuclear Regulatory Commission Subsequent Renewed Operating Licenses Docket Nos. 50-277 and 50-278 July 10, 2018 Page 3
Enclosure:
CD-ROM labeled "PB_SLRA" cc:
without Enclosure Regional Administrator - NRC Region I NRC Project Manager (Safety Review), NRR-DMLR NRC Project Manager (Environmental Review), NRR-DMLR NRC Project Manager, NRR-DORL - Peach Bottom Atomic Power Station NRC Senior Resident Inspector, Peach Bottom Atomic Power Station R.R. Janati, Manager, BRP Nuclear Safety Program, Pennsylvania Department of Environmental Protection S.T. Gray, Deputy Division Director PPAD, Maryland Department of Natural Resources