ML18190A181
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/26/2018
From: Dent J
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-13-109, NLS2018020
Download: ML18190A181 (8)


Text

H Nebraska Public Power District Always there when you need us NLS2018020 June 26, 2018 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Nebraska Public Power District's Eighth Six-Month Status Report in Response to June 6, 2013, Commission Ord,er Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)

Cooper Nuclear Station, Docket No. 50-298, DPR-46

References:

1. NRC Order Number EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened ContainmentVents Capable of Operation Under Severe Accident Conditions," dated June 6, 2013
2. NPPD letter to NRC, "Nebraska Public Power District's Phase 1 Overall Integrated Plan in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109),"

dated June 30, 2014 (NLS2014057)

3. NPPD letter to NRC, "Nebraska Public Power District's First Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated December 19, 2014 (NLS2014101)
4. NPPD letter to NRC, "Nebraska Public Power District's Phase 1 and Phase 2 Overall Integrated Plan in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated December 21, 2015 (NLS2015137)
5. NPPD letter to NRC, "Nebraska Public Power District's Fifth Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated December 28, 2016 COOPER NUCLEAR STATION P.O. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 www.nppd.com

NLS2018020 Page 2 of2 On June 6, 2013, the Nuclear Regulatory Commission (NRC) issued Order EA-13-109 (Reference

1) to Nebraska Public Power District (NPPD). Reference 1 was immediately effective and directs NPPD to take certain actions to ensure that Cooper Nuclear Station (CNS) has a Hardened Containment Vent System to remove decay heat from the containment, and maintain control of containment pressure within acceptable limits following events that result in loss of active containment heat removal capability while maintaining the capability to operate under severe accident conditions resulting from an Extended Loss of AC Power. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of a Phase 1 overall integrated plan (OIP) pursuant to Section IV, Condition D, and status reports at six-month intervals thereafter. NPPD submitted an initial OIP for CNS by letter dated June 30, 2014 (Reference 2), Revision 1 to the OIP by letter dated December 19, 2014 (Reference 3), and Revision 2 which provided a combined Phase 1 and Phase 2 OIP (Reference 4). In Reference 5, NPPD reported that CNS had completed implementation of Phase 1 Order requirements.

The purpose of this letter is to provide the eighth six-month update pursuant to Section IV, Condition D.3, of Reference 1.

I This letter contains no new regulatory commitments. Should you have any questions concerning the content of this letter, please contact Jim Shaw, Licensing Manager, at (402) 825-2788.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on: &/2b / 1Y

--=-+,--+,---'--"'-----

Dent, Jr.

ice President - Nuclear and Chief Nuclear Officer

/bk

Attachment:

Nebraska Public Power District's Eighth Six-Month Status Report for the Implementation of Order EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" cc: Regional Administrator, w/attachment Senior Resident Inspector, w/attachment USNRC - Region IV USNRC-CNS Director, w/attachment NPG Distribution, w/o attachment USNRC - Office of Nuclear Reactor Regulation CNS Records, w/attachment Cooper Project Manager, w/attachment USNRC - NRR Plant Licensing Branch IV

NLS2018020 Attachment Page 1 of 6 Attachment Nebraska Public Power District's Eighth Six-Month Status Report for the Implem~:ntation of Order EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" Introduction Nebraska Public Power District (NPPD) developed an Overall Integrated Plan (OIP) for Cooper Nuclear Station (CNS) (Reference 1), documenting the installation of a Hardened Containment Vent System (HCVS) that provides a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris, in response to Reference 2. Updates of milestone accomplishments are based on the combined Phase 1 and 2 OIP (Reference 4).

NPPD developed Reference 4 in accordance with the guidance contained in Reference 3, documenting:

1. The installation of a HCVS that provides a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris, in response to Reference 2.
2. An alternative venting strategy that makes it unlikely that a drywell vent is needed to protect the containment from overpressure related failure under severe accident conditions, including those that involve a breach of the reactor vessel by molten core debris, in response to Reference 2.

This attachment provides an update of milestone accomplishments since submittal of the December 2017 status report (Reference 10) including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

Milestone Accomplishments None completed since the December 2017 status report.

Milestone Schedule Status The following tables provide an update to Attachment 2 of Reference 4. They provide the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

NLS2018020 Attachment Page 2 of 6 Phase 1 and 2 HCVS Milestone Table Milestone Target Completion Date Activity Status Submit Phase 1 OIP June 2014 Complete Submit Six-Month Updates: -- --

Update 1 December 2014 Complete Update 2 June 2015 Complete Update 3 with Phase 2 OIP December 2015 Complete Update 4 June 2016 Complete Update 5 December 2016 Complete Update 6 June 2017 Complete Update 7 December 2017 Complete Update 8 June 2018 Complete with this submittal Phase 1 Specific Milestones Milestone Activity Status Hold preliminary/conceptual design meeting Complete Design Engineering On-site/Complete Complete Operations Procedure Changes Developed Complete Site Specific Maintenance Procedure Developed Complete Training Complete Complete Procedure Changes Active Complete Walk Through Demonstration/Functional Test Complete Phase 2 Specific Milestones Activity Comments/Date I

Milestone Target I Completion Date Status Changes Hold preliminary/conceptual design December 2015 Complete meeting Design Engineering On-site/Complete October 2017 Complete Operations Procedure Changes September 2018 May2018 In Progress Developed Site Specific Maintenance Procedure September 2018 May2018 In Progress Developed Training Complete June 2018 In Progress October 2018 Implementation Outage October 2018 Not Started Walk Through Demonstration/Functional October 2018 Not Started Test Procedure Changes Active October 2018 Not Started Submit Completion Report (60 days after January 2019 Not Started full site compliance)

NLS2018020 Attachment Page 3 of 6 Changes to Compliance Method There are no changes to the compliance method as documented in the combined Phase 1 and 2 OIP.

Need for Relief/Relaxation and Basis for the Relief/Relaxation NPPD completed implementation of Phase 1 Order requirements prior to CNS entering Mode 2 (Startup) on November 6, 2016.

NPPD expects to comply with the Phase 2 Order implementation date and no relief/relaxation is required at this time.

Open Items from Combined Phase 1 and 2 Overall Integrated Plan and Interim Staff Evaluation The following tables provide a summary of the open items documented in the combined Phase 1 and 2 OIP, the Interim Staff Evaluations (ISE) for Phase 1 and Phase 2 (References 5 and 7), and the status of each item.

Combined Phase 1 and 2 OIP Open Items Phase 1 Open Items OIP Open Item # Status/Comment 1 Closed. Response provided in Reference 6.

2 Closed. Response provided in Reference 6.

3 Closed. Response provided in Reference 6.

4 Closed. Response provided in Reference 6.

5 Closed. Response provided in Reference 6.

6 Closed. Response provided in Reference 6.

7 Closed. Response provided in Reference 6.

8 Closed. Response provided in Reference 6.

9 Closed. Response provided in Reference 6.

10 Closed. Response provided in Reference 6.

11 Closed. Response provided in Reference 6.

12 Closed. Response provided in Reference 8.

Phase 2 Open Items None.

NLS2018020 Attachment Page 4 of 6 Phase 1 Interim Staff Evaluation Open Items ISE Open Status Item#

1 Response provided in Reference 6 and open item closed by NRC per Reference 11.

2 Response provided in Reference 6 and open item closed by NRC per Reference 11.

3 Response provided in Reference 6 and open item closed by NRC per Reference 11.

4 Response provided in Reference 6 and open item closed by NRC per Reference 11.

5 Response provided in Reference 8 and open item closed by NRC per Reference 11.

6 Response provided in Reference 8 and open item closed by NRC per Reference 11.

7 Response provided in Reference 6 and open item closed by NRC per Reference 11.

8 Response provided in Reference 6 and open item closed by NRC per Reference 11.

9 Response provided in Reference 6 and open item closed by NRC per Reference 11.

10 Response provided in Reference 6 and open item closed by NRC per Reference 11.

11 Response provided in Reference 6 and open item closed by NRC per Reference 11.

Phase 2 Interim Staff Evaluation Open Items ISE Open Status Item#

1 Response provided in Reference 8 and open item closed by NRC per Reference 11.

2 Response provided in Reference 8 and open item closed by NRC per Reference 11.

ISE Open Action / ISE Section Reference Status Item#

Licensee to demonstrate the SAWM flow Initial response to this ISE open item instrumentation qualification for the was provided in Reference 9. As a expected environmental conditions. result of audit discussions with the Section 3.3.3.4 NRC on July 13, 2017, additional discussion on flow instrumentation accuracy was requested and is provided in the update below. This information was reviewed as part of continuing audit discussions on March 8, 2018, 3

and was closed by the NRC per Reference 11.

June 2018 Update - The vendor has provided a Certificate of Conformance and Calibration for the flow meter stating that operating it at a temperature of minus 5 degrees Fahrenheit will not impact accuracy of the instrument.

NLS2018020 Attachment Page 5 of6 Interim Staff Evaluation Impacts There are no potential impacts to the ISE identified at this time.

References

1. NPPD letter to NRC, "Nebraska Public Power District's Phase 1 Overall Integrated Plan in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated June 30, 2014
2. NRC Order Number EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" dated June 6, 2013
3. NEI 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109: BWR Mark I and II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 1, dated April 2015
4. Nebraska Public Power District's Phase 1 and Phase 2 Overall Integrated Plan in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated December 21, 2015
5. NRC letter to NPPD, "Cooper Nuclear Station - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 1 of Order EA-13-109 (Severe Accident Capable Hardened Vents) (TAC NO. MF4384)," dated February 11, 2015
6. NPPD letter to NRC, "Nebraska Public Power District's Fourth Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated June 30, 2016
7. NRC letter to NPPD, "Cooper Nuclear Station - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Vents) (TAC NO. MF4384)," dated September 29, 2016
8. NPPD letter to NRC, "Nebraska Public Power District's Fifth Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated December 28, 2016
9. NPPD letter to NRC, "Nebraska Public Power District's Sixth Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated June 19, 2017

NLS2018020 Attachment Page 6 of 6

10. NPPD letter to NRC, "Nebraska Public Power District's Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated December 21, 2017
11. NRC letter to NPPD, "Cooper Nuclear Station - Report for the Audit of Licensee Responses to Interim Staff Evaluations Open Items Related to NRC Order EA-13-109 to Modify Licenses With Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (CAC NO. MF4384; EPID L-2014-JLD-0046), "dated March 29, 2018