MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 ML18102A7361997-01-0707 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Eighteen Month Surveillance Performed to Measure RCS Total Flow Rate to Account for Necessary Plant Conditions for Performing Test in Mode 1 & Current Extended Plant Outages 1999-08-25
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML18107A4991999-08-25025 August 1999 Application for Amends to Licenses DPR-70 & DPR-75,proposing to Authorize Licensee to Perform Single Cell Charging of Connected Cells in Operable Class 1E Batteries ML18107A5141999-08-25025 August 1999 Suppl to 971114 Application for Amends to Licenses DPR-70 & DPR-75,deleting Footnotes Added as one-time Changes & Proposing Change Identified Subsequent to 971114 Submittal That Corrects Error Issued in Amend 69 for Unit 2 ML18107A4631999-07-29029 July 1999 Application for Amends to Licenses DPR-70 & DPR-75,replacing Surveillance 4.6.1.1a with Appropriate NUREG-1431 Requirements ML18107A4581999-07-23023 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Change TS Surveillance Requirement 4.8.1.1.2 D 7 by Removing Restriction to Perform Test Every 18 Months During Shutdown ML18107A4221999-07-0202 July 1999 Application for Amends to Licenses DPR-70 & DPR-75 to Relocate TS 3/4.3.4 Lco,Surveillance Requirements & Bases from TS to Ufsar,Iaw GL 95-10 ML18107A3771999-06-10010 June 1999 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.6.1, Containment Integrity, by Clarifying When Verification of Primary Containment Integrity May Be Performed by Administrative Means ML18107A3571999-06-0404 June 1999 Application for Amends to Licenses DPR-70,DPR-75 & NPF-57 Re Transfer of PSEG Ownership Interests & Licensed Operating Authorities to New,Affiliated Nuclear Generating Company, PSEG Nuclear Llc.Proprietary Encls Withheld ML18107A2081999-04-14014 April 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.9.12, Fhvas, to Ensure Consistency Between TS Requirements for Fhavs & Sys Design Basis,Per NUREG-1431. Page 4 of 4 in Attachment 2 of Incoming Submittal Omitted ML18106B1571999-03-31031 March 1999 Suppl to 990115 Application for Amend to License DPR-70, Allowing Plant Operation to Continue to Thirteenth Refueling Outage (1R13),currently Scheduled to Begin on 990918 ML18106B0621999-02-0808 February 1999 Application for Amends to Licenses DPR-70 & DPR-75, Respectively.Proposed Amend Modifies ECCS Subsystems Surveillance Requirement 4.5.3.2.b by Adding Option of Providing Necessary Isolation Function When Testing ML18106B0501999-02-0202 February 1999 Application for Amends to Licenses DPR-70 & DPR-75,revising Max Permissible Enrichment of Stored New Fuel Described in TS Section 5.6.1.1.Rept Entitled, Criticality Analysis of Salem Units 1 & 2 Fresh Fuel Racks, Encl ML18106B0221999-01-15015 January 1999 Application for Amend to License DPR-70,proposing one-time Changes to Certain Unit 1 TS Surveillance Requirements for Fuel Cycle 13,currently Scheduled to Begin on 990918 ML18106A9161998-10-12012 October 1998 Application for Amend to License DPR-75,requesting one-time Changes to Certain Unit 2 TS SR for Fuel Cycle 10.Basis for Requested Changes,Analysis Supporting No Significant Hazards Determination & Marked Up TS Pages,Encl ML18106A8921998-09-29029 September 1998 Application for Amends to Licenses DPR-72 & DPR-75,modifying TS 3/4.9.4 to Permit Use of Equivalent Methods to Obtain Containment Closure During Refueling Operations for Containment Equipment Hatch ML18106A8761998-09-17017 September 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TSs 3/4.8.2.2,3/4.8.2.4 & 3/4.8.2.6 to Address Movement of Irradiated Fuel & Deleting LCO Re Requirement to Establish Containment Integrity ML18106A8351998-08-12012 August 1998 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS for Containment Air Locks for Salem Units 1 & 2 ML18106A7911998-07-30030 July 1998 Application for Amends to Licenses DPR-70 & DPR-75,revising Acceptance Criteria for CR Emergency Air Conditioning Sys from Maintaining CR at 1/8-inch Positive Pressure W/Respect to Adjacent Areas to Following Phrase ML18106A4271998-03-26026 March 1998 Application for Amend to License DPR-70,changing Applicability Statement from Mode 3 to Modes 1 & 2 ML18106A4221998-03-26026 March 1998 Application for Amends to Licenses DPR-70 & DPR-75, Respectively,Incorporating Note at Bottom of Salem Unit 2 T3/4.8.2 Into Salem 1 TS & Adding Asterisks to Word Inverters. ML18106A2521998-01-0808 January 1998 Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page ML18106A2111997-12-15015 December 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS to Adopt Option B of 10CFR50,App J,For Type B & C Testing & Modifying Existing TS Wording for Previous Adoption of Option B on Type a Testing ML18106A1941997-12-11011 December 1997 Application for Amend to License DPR-70,requesting one-time Exemption to Allow Containment Purging in Modes 3 & 4 ML18102B6771997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing TS Surveillance Requirements to Codify Existing Procedural Commitments for SW Accumulator Vessels ML18102B6731997-11-14014 November 1997 Application for Amends to Licenses DPR-70 & DPR-75, Correcting Editorial & Administrative Errors in Ts,Which Existed Since Initial Issuance ML18102B6611997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.8.1 Re EDG & Deleting SR 4.8.1.1.2.d.1,calling for Diesels to Be Subjected to Insp Based on Vendor Recommendations ML18102B6571997-11-0404 November 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Surveillance Requirement 4.6.2.1.b to Verify That on Recirculation Flow,Containment Spray Pumps Develop Differential Pressure of Greater than or Equal to 204 Psid ML18102B6371997-10-29029 October 1997 Application for Amend to License DPR-75,revising TS 3/4.4.6, Steam Generators, Making One Time Change to Unit 2 SG Insp Schedule to Require Next Insp within 24 Months of Mode 2 for Unit 2 Fuel Cycle 10 ML18102B6411997-10-29029 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.8.1.1.2.d.2 Proposed in Util 960925 Submittal Re EDG Testing ML18102B6471997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying TS 3/4.7.7, Auxiliary Building Exhaust Air Filtration Sys & Bases ML18102B6441997-10-24024 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of TS 4.6.4.1 ML18102B6291997-10-21021 October 1997 Application for Amends to Licenses DPR-70 & DPR-75,extending Applicability of Power Range Neutron Flux TS Trip to Require Operability & Surveillance Testing in Mode 3,when Reactor Trip Sys Breakers in Closed Position ML18102B6181997-10-14014 October 1997 Application for Amend to License DPR-70,modifying Pressure Isolation Valve Lco,Lco Action Statement,Surveillance Requirement & Table 4.4-4 to Be Consistent W/Salem Unit 2 ML18102B6061997-10-0606 October 1997 Application for Amend to License DPR-70,changing TS for LCOs 3.1.3.1, Movable Control Assemblies & 3.1.3.2.1, Position Indication Sys. ML18102B5551997-08-27027 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,providing Revised TS Bases Pages for TS 3.7.3, CCW Sys, to State That CCW Pumps Required to Be Operable to Meet LCO ML18102B5281997-08-19019 August 1997 Application for Amend to License DPR-75,providing Addl Operational Flexibility to Allow Orderly Resumption of Startup & Preclude Unwarranted Power Transients at Plant Unit 2 ML18102B5321997-08-18018 August 1997 Application for Amend to License DPR-75,incorporating Plant Computer (P-250) Into TS Bases for Movable Control Assemblies ML18102B4871997-08-0101 August 1997 Application for Amends to Licenses DPR-70 & DPR-75,rewording TS Section 4.2.1 to State That Util Will Adhere to Section 7 Incidental Take Statement Approved by Natl Marine Fisheries Svc ML20148K0841997-06-0404 June 1997 Amends 194 & 177 to Licenses DPR-70 & DPR-75,respectively, Changing TSs 3.4.3 & 3.4.5, Relief Valves, to Ensure That Automatic Capability of PORVs to Relieve Pressure Is Maintained When Valves Are Isolated ML18102B3041997-05-14014 May 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising SR 4.7.6.1.d.1 to Indicate That Specified Acceptable Filter Dp Is to Be Measured Across Filter Housing & to Reflecting Filter Dp Acceptance Value of Greater than 2.70 Wg ML18102B2611997-05-0101 May 1997 Suppl Info to Util 970211 Application for Amends to Licenses DPR-70 & DPR-75,revising TS for Chilled Water Sys - Auxiliary Bldg Subsystem.Ref to Radiation Monitoring Signal Removed from Bases Section ML18102B2581997-05-0101 May 1997 Application for Amend to License DPR-75,revising TS Section 3/4.7.7 to Reflect Extended Allowed Outage Times & Creating New TS Section 3/4.7.11 to Address Importance of Switchgear & Penetration Area Ventilation Sys ML18102B0071997-04-30030 April 1997 Application for Amends to Licenses DPR-40,DPR-56,DPR-70 & DPR-75,requesting Consent of NRC for Indirect Transfer of Control of Interest in Plants That Will Occur Under Proposed Merger ML18102B2511997-04-28028 April 1997 Submits Suppl to 970131 & 0314 Applications for Amends to Licenses DPR-70 & DPR-75,revising TS on Pressurizer Power Operated Relief Valves.Suppl Issued to State That Conclusion of NSHC Remains Valid ML18102B0221997-04-25025 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Eliminating Flow Path from RHR Sys to RCS Hot Legs as Specified in LCO 3.5.2.c.2 ML18102A9791997-04-11011 April 1997 Application for Amends to Licenses DPR-70 & DPR-75, Increasing Cw Flow to 2550 Gpm for 31 Day Surveillance Fans Started & Operated in Low Speed ML18102A8951997-03-0404 March 1997 Application for Amends to Licenses DPR-70 & DPR-75,modifying ECCS Surveillance Test Acceptance Criteria for Centrifugal Charging & SI Pumps ML18102A8491997-02-11011 February 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Addition of New TS 3/4.7.10, Chilled Water Sys ML18102A8361997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75,revising TS 3/4.4.3 to Ensure That Automatic Capability of Power Operated Relief Valve to Relieve Pressure Is Maintained When Valves Are Isolated by Closure of Block Valves ML18102A8021997-01-31031 January 1997 Application for Amends to Licenses DPR-70 & DPR-75, Requesting Rev to TS Re Containment Systems Air Temp to Ensure Representative Average Air Temp Is Measured ML18102A7861997-01-23023 January 1997 Application for Amend to License DPR-75,revising TS Bases 3/4.3.3.1 Re Radiation Monitoring Instrumentation Channel 2R41 1999-08-25
[Table view] |
Text
.:*
Public Service Electric and Gas Company Louis F. Storz Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-5700 Senior Vice President - Nuclear Operations I.
LR-N980358 LCR S95-34 SEP17 1998 United States Nuclear Regulatory Commission
REQUEST FOR AMENDMENT ELECTRICAL POWER SYSTEMS - SHUTDOWN SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 in accordance with the requirements of 10CFR50.90, Public Service Electric & Gas Company (PSE&G) hereby transmits a request for amendment to Facility Operating Licenses DPR-70 and DPR-75 for Salem Generating Station Unit Nos. *1 and 2 respectively. Pursuant to the requirements of 10CFR50.91 (b)(1 ), a copy of this request for amendment has been sent to the State of New Jersey.
The proposed amendment modifies Electrical Power Sources specifications 3/4.8.2.2, AC_Qlstribution - Shutdown, 314-8.2.4, 125-Volt D.C. Distribution Shutdown, and 3/4.8.2.6, 28-Volt D.C. Distribution - Shutdown. The Applicability is being revised to address movement of irradiated fuel and the Action requirements for failure to meet the Limiting Condition For Operation are being modified to delete the requirement to establish Containment Integrity. The proposed changes are consistent with NUREG-1431, Standard Technical Specifications - Westinghm,ise Plants, Revision 1, dated April 1995.
The proposed change has been evaluated in accordance with 10CFR50.91(a)(1), using the criteria in 10CFR50.92(c), and it. has been determined that this request involves no significant hazards considerations.
A description of the requested amendment, the reason for the changes and the justification for the changes are provided as Attachment 1. The basis for no significant hazards consideration determination are provided in Attachment 2. The Technical Specification pages affected by the proposed changes are provided in Attachment 3.
9809240301 980917 PDR ADOCK 05000272 P PDR
. . *J .t.-
1~ .....i \' ._,
@. Printed on
~ Recycled Paper
.. SEP 171998 Document Control Desk LR!.N980358 By letters dated June 21, 1991 and February 7, 1994, similar amendments were approved for Baltimore Gas and Electric Company's Calvert Cliffs Nuclear Power Plant (Docket Nos. 50-317 and 50-318) and Duquesne Light Company's Beaver Valley Power Station (Docket Nos. 50-334 and 50-412) respectively.
PSE&G requests a 60 day implementation period after amendment approval. Approval of this change is requested sy January 8, -1999 to permit implementation prior to the next scheduled Salem refueling outage.
Should you have any questions regarding this request, please contact Brooke Knieriem, Salem Licensing, at (609) 339-1782.
Sincerely,
/rbk Affidavit Attachments (2)
C Mr. H.J. Miller, Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. P Milano, Licensing Project Manager - Salem U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr. S. Morris (X24)
USNRC Senior Resident Inspector Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering 33 Arctic Parkway CN 415 Trenton, NJ 08625 95-4933
REF: LR-N980358 LCR S95-34 STATE OF NEW JERSEY)
) SS.
COUNTY OF SALEM )
L. F. Storz, being duly sworn according to law deposes and says:
J am Senior Vice President - Nuclear Operations for the Public Service Electric & Gas Company, and as such, I find the matters set forth in the above referenced letter, concerning the Salem Generating Station, Units Nos. 1 and 2, are true to the best of my knowledge, information and belief.
Subscribed and Swo~~efore me this L3 ,e,d day of£ J(J / : , 1998
~Jil~j)~~
Not?~ryP,:;jblic of New Jersey
Attachment 1
~ LR-N980358 ELECTRICAL POWER SYSTEMS - SHUTDOWN I. DESCRIPTION OF THE PROPOSED CHANGES The proposed changes will revise the Applicability and Actions for the below listed specifications as indicated:
- a. Specification 3.8.2.2 is being revised to state:
Applicability:
MODES 5 and 6.
During movement of irradiated fuel assemblies.
Actions:
With less than the above complement of A. C. busses and inverters OPERABLE and energized, immediately suspend all operations involving CORE ALTERATIONS, positive reactivity changes, and movement of irradiated fuel assemblies until the minimum required A. C. electrical power sources are restored to OPERABLE status.
- b. Specification 3.8.2.4 is being revised to state:
Applicability:
MODES 5 and 6.
During movement of irradiated fuel assemblies.
Actions:
With less than the above complement of D.C. equipment and busses OPERABLE, immediately suspend all operations involving CORE ALTERATIONS, positive reactivity changes, and movement of irradiated fuel assemblies until the minimum required 125-Volt D.C. electrical power sources are restored to OPERABLE status.
- c. Specification 3.8.2.6 is being revised to state:
Applicability:
MODES 5 and 6.
During movement of irradiated fuel assemblies.
Attachment 1 LR-N980358 Actions:
With less than the above complement of D.C. equipment and busses OPERABLE, immediately suspend all operations involving CORE ALTERATIONS, positive reactivity changes, and movement of irradiated fuel assemblies until the minimum required 28-Volt D.C. electrical power sources are restored to OPERABLE status.
- d. The Bases for specifications 3/4.8.1 and 3/4.8.2 is being revised to state:
The Applicability of specifications 3.8.2.2, 3.8.2.4, and 3.8.2.6 includes the movement of irradiated fuel assemblies. This will ensure that adequate electrical power is available for proper operation of the Fuel Handling Area Ventilation system during movement of irradiated fuel in the spent fuel pool.
II. REASON FOR THE CHANGES Salem Technical Specifications for AC and DC Distribution, Shutdown (MODES 5 and 6), require that with less than the minimum complement of AC or DC sources available, containment integrity must be established within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Under the same conditions, NUREG-1431, Standard Technical Specifications -
Westinghouse Plants, requires that immediate action be taken to suspend core alterations, to suspend movement of irradiated fuel assemblies, and to suspend operations involving positive reactivity additions.
Salem Technical Specifications define containment integrity and require that containment integrity be established during normal plant operation in Modes 1 through 4. Containment integrity is necessary in Modes 1 through 4 to mitigate the consequences of a Design Basis Accident in those modes. The Salem Technical Specifications also require the establishment of containment closure during refueling operations (Mode 6). This action is necessary to mitigate the consequences of a Fuel Handling Accident. A specific technical specification requirement for containment integrity or for containment closure in Mode 5 does not exist. When required by Technical Specification 3.8.2, 3.8.4, and 3.8.6 actions, Salem must establish containment integrity, as defined, for Modes 1 through 4.
The requested Technical Specification changes are based upon the impracticality of establishing containment integrity, as defined for Modes 1 through 4, in Mode 5 and during refueling operations in Mode 6. In Modes 5 and 6, .conditions could .
exist when the equipment necessary to establish containment integrity has been removed from service for required maintenance and the minimum AC or DC power systems required by specifications 3.8.2.2, 3.8.2.4, and 3.8.2.6 are not available.
Attachment 1 LR-N980358 The proposed changes will also extend the Applicability of the Technical Specifications 3.8.2.2, 3.8.2.4, and 3.8.2.6 to include the movement of irradiated fuel. For the Salem units, the Spent Fuel Pool is located outside of the containment, in the Fuel Handling Building. The present Salem Technical Specifications do not contain requirements for electrical power during movement of fuel in the Spent Fuel Pool. The Applicability of specifications 3.8.2.2, 3.8.2.4, and 3.8.2.6 is being changed to ensure that adequate electrical power is available for proper operation of the Fuel Handling Area Ventilation system during movement of irradiated fuel in the Spent Fuel Pool.
Ill. JUSTIFICATION FOR CHANGES The minimum Power Distribution System trains required to be OPERABLE in Modes 5 and 6 are necessary to provide sufficient power to ensure that:
- 1. The unit can be maintained in the shutdown or refueling condition for extended periods, and
- 2. Sufficient instrumentation and control capability is available for monitoring and maintaining the unit status, and
- 3. Adequate electrical power is available to mitigate events postulated during shutdown, such as a fuel handling accident.
The proposed change will eliminate the requirement imposed by Technical Specifications 3.8.2.2, 3.8.2.4, and 3.8.2.6 to establish containment integrity in Modes 5 and 6 if the minimum number of AC or DC power sources are not available. The requirement to establish containment integrity will be replaced by a requirement to immediately suspend all operations involving core alterations, positive reactivity changes, and movement of irradiated fuel assemblies until the minimum required electrical power sources are restored to an operable status.
The elimination of the requirement to establish containment integrity is justified based upon the nature of the consequences of the postulated shutdown events, the Technical Specification requirements already in place to mitigate the consequences of those events, and the proposed Technical Specification actions.
During operation in Modes 1 through 4, a Design Basis Accident would pressurize containment and result in the release of radioactive material into the containment.
Prevention against the release of this radioactive material to the environment is accomplished by Technical Specification 3.6.1, Primary Containment, Containment Integrity. This Technical Specification requires that containment integrity be maintained in Modes 1 through 4.
Attachment 1 LR-N980358 In Modes 5 and 6 the probability and consequences of a Design Basis Accident are lower because of the reduced Reactor Coolant system temperature and pressure. In these modes, a minimum complement of electrical power sources is maintained to assure adequate power for systems required for mitigation of a fuel handling accident.
For a fuel handling accident in Mode 6, establishment of containment integrity to prevent the release of radioactive material to the environment is unnecessary because of the lack of containment pressurization potential and the reduced radiological source term associated with that accident. The spread of radioactive material to the environment from a fuel handling accident is mitigated by the requirements of Technical Specification 3.9.4, Refueling Operations, Containment Building Penetrations. Technical Specification 3.9.4 is applicable in Mode 6 and establishes containment closure during refueling operations (core alterations and movement of irradiated fuel within containment). For Mode 6, the proposed Technical Specification Action will also require that all operations involving core alterations, positive reactivity changes, and movement of irradiated fuel within the containment be suspended unless the minimum A.G. and D.C. power sources are available. This requirement will ensure that adequate power is available for systems and components necessary to mitigate a postulated event during refueling operations.
In Mode 5, fuel handling is limited to placement of new fuel prior to core off load or movement of irradiated fuel within the spent fuel pool. Because the Spent Fuel Pool is not located within containment, establishment of either containment integrity or containment closure would not help to mitigate the consequences of a fuel handling accident in that area. Mitigation of a fuel handling accident in the Spent Fuel Pool is accomplished through Technical Specification 3.9.12, Refueling Operations, Fuel Handling Area Ventilation System, which requires that the Fuel Handling Area Ventilation system be operable whenever irradiated fuel is present in the storage pool. This ensures that all radioactive material released from the rupture of an irradiated fuel assembly would be filtered through filtration equipment prior to discharge to the atmosphere. For Mode 5, the proposed Technical Specification Action will require that movement of irradiated fuel assemblies be suspended if the minimum AC or DC power sources are not available. This requirement will ensure that the Fuel Handling Area Ventilation system is available to mitigate the consequences of an accident associated with the movement of irradiated fuel in the Spent Fuel Pool.
The proposed changes are consistent with the content of NUREG-1431, Standard Technical Specifications Westinghouse Plants.
LR-N980358
- ATTACHMENT 2 IV. DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION Pursuant to 10CFR50.92, PSE&G reviewed the proposed amendment to determine whether our request involves a significant hazards consideration.
PSE&G has determined that operation of Salem Generating Station, Unit Nos. 1 and 2, in accordance with the proposed changes:
- 1. Will not involve a significant increase in the probability or consequences of an accident previously evaluated.
In Modes 1 through 4, a Design Basis Accident would cause the release of radioactive material into the containment. Release of that radioactive material to the environment is prevented during operation in Modes 1 through 4 by maintaining containment integrity. In Modes 5 and 6 the probability and consequences of this event are lower because of the reduced reactor coolant pressure and temperature limitations of these modes.
A minimum complement of electrical power sources and distribution systems is established in Modes 5 and 6 to assure that adequate electrical power is available to mitigate the consequences of a fuel handling accident. Because of the lack of containment pressurization potential during a fuel handling accident, less stringent .
requirements are needed to isolate containment from the outside atmosphere.
These requirements are applied during refueling operations by Technical Specification 3.9.4, Refueling Operations, Containment Building Penetrations.
Technical Specification 3.9.4 is applicable in Mode 6 and establishes containment closure vice containment integrity during refueling operations (core alterations and movement of irradiated fuel within containment).
In Mode 5, fuel handling is generally limited to placement of new fuel prior to*.core off load or movement of irradiated fuel within the spent fuel pool. Because the Spent Fuel Pool is not located within containment, establishment of either containment integrity or containment closure would not help to mitigate the consequences of a fuel handling accident in that area. Mitigation of a fuel handling accident is accomplished through Technical Specification 3.9.12, Refueling Operations, Fuel Handling Area Ventilation System, which requires that the Fuel Handling Area Ventilation system be operable whenever irradiated fuel is present in the storage pool. This insu*res that all radioactive material released from the rupture of an irradiated fuel assembly would be filtered through filtration equipment prior to discharge to the atmosphere.
With the number of energized A.C. or D.C. power distribution systems less than the required, sufficient power may not be available to recover from a fuel handling accident. Consequently, the Action statements require immediate suspension of
- all operations involving core alterations, positive reactivity changes, and
LR-N980358
- ATTACHMENT 2 movement of irradiated fuel assemblies. This precludes the possibility of a fuel h~ndling accident and the need for containment integrity.
Based upon the above, the proposed change will not increase the probability or consequences of an accident previously analyzed.
- 2. Will not create the possibility of a new or different kind of accident from any previously evaluated.
The proposed changes do not require any change in the configuration or operation of the -plant. Specifically, no new hardware is being added to the _plant as part of the proposed change, no existing equipment is being modified, and no significant changes in operations are being introduced. Therefore, these changes will not create the possibility of a new or different kind of accident from any accident previously evaluated.
- 3. Will not involve a significant reduction in a margin of safety.
The proposed change will not alter any assumptions, initial conditions, or results of any accident analyses. The proposed additional Applicability will ensure proper operation of the Fuel Handling Area Ventilation system during movement of irradiated fuel in the spent fuel pool. The proposed ACTIONS, to be taken in the event that the LCO is not met, will preclude the conditions that would lead to the need for establishing containment integrity. The change will, therefore, not involve a significant reduction in a margin of safety.
V. CONCLUSIONS Based on the above, Public Service Electric & Gas has determined that the proposed changes do not involve a significant hazards consideration.