LR-N970810, Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page

From kanterella
(Redirected from ML18106A252)
Jump to navigation Jump to search
Supplemental Application for Amends to Licenses DPR-70 & DPR-75,respectively Adding Asterisk to Word Operable in LCO & Associated Note at Bottom of Page
ML18106A252
Person / Time
Site: Salem  
Issue date: 01/08/1998
From: Storz L
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML18106A253 List:
References
LCR-S95-44, LR-N970810, NUDOCS 9801220315
Download: ML18106A252 (7)


Text

...

Public Service Electric and Gas Company Louis F. Storz Public SeNice Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-5700 Senior Vice President - Nuclear Operations United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 SUPPLEMENTAL INFORMATION FOR REQUEST FOR LICENSE AMENDMENT AUXILIARY BUILDING VENTILATION LR-N970810 LCR S95-44 JAN 0 8 1998 SALEM GENERATING STATION UNITS 1 AND 2 FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 Gentlemen:

By "LR-N970603, Application for Amends to Licenses DPR-70 & DPR-75,revising Containment Hydrogen Analyzer SRs of [[TS" contains a listed "[" character as part of the property label and has therefore been classified as invalid..1|letter dated October 24, 1997]] (our Ref: LR-N97488; NRC ref: M99875/6), Public Service Electric and Gas Company (PSE&G) submitted a request to revise the Technical Specifications (TS) for Salem Generating Station Units 1 and 2. In this submittal, PSE&G requested that all Auxiliary Building Ventilation Fans (two supplies and three exhausts) be included in the Limiting Condition for Operation (LCO).

Although, PSE&G. identified in the Technical Specifications Bases of the original submittal (LR-N97 488) that the supply fan with the autostart removed under administrative controls was operable, PSE&G did not identify this requirement in the Limiting Condition for Operation. This supplemental letter requests addition of 1) an asterisk(*) to the word OPERABLE in the LCO, and 2) its associated note at the bottom of the page. to this letter provides this additional explanation. Attachment 2 contains revised Inserts A and E, and the new marked up pages for the Limiting Condition for Operation. PSE&G has reviewed the original no significant hazards evaluation submitted in support of LR-N97 488, and determined that it remains valid.

PSE&G requests that this submittal be reviewed on an expedited basis. Although this license change request is not required for compliance, it will eliminate 1) discrepancies between the actual system operations and the UFSAR description, and 2) questions concerning operability.

9801220315 980108 PDR ADOCK 05000272 P

PDR

'1:1\\. Printed on W

Recycled Paper I 1\\1111 \\Ill\\ \\Ill\\ \\\\Ill \\111111111\\ Ill 1\\11

r-

'*I Document Control Desk LR-N9708~0

  • JAN*o S 1998

. Should you have any questions regarding this request, we will be pleased to discuss them with you.

Affidavit Attachments (1)

C Mr. H. Miller, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road

  • King of Prussia, PA 19406 Sincerely, Mr. P. Milano, Licensing Project Manager~* Saiem U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Ms. M. Evans (X24)

USNRC Senior Resident Inspector - Salem Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering PO Box415 Trenton, NJ 08625 95-4933

REF: LR-N970810 LCR S95-44 STATE OF NEW JERSEY)

) SS.

COUNTY OF SALEM

)

L. F. Storz, being duly sworn according to law deposes and says:

I am Senior Vice President - Nuclear Operations of Public Service Electric and Gas Company, and as such, I find the matters set forth in the above referenced letter, concerning Salem Generating Station, Units 1 and 2, are true to the best of my knowledge, information and belief.

Subscribed and Sworn to before me this a day of3o-r..u._µ~'{r.1998

~)'""

!Jok A. Q j)-aweff Notary Public of New Jersey BARBARA A. POWELL NOTARY PUBLIC OF NEW JERSEY My Commission Expires Dec. 2, 1998 My Commission expires on ______

m_H_2_1s_o3_23 ____

~ocument Control Desk*

LR-N970810 LCR S95-44 SALEM GENERATING STATION UNITS 1 AND 2 FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 AUXILIARY BUILDING VENTILATION SYSTEM (ABVS)

I.

CLARIFICATION TO ORIGINAL REQUEST On October 24, 1997, (our ref: LR-N97488), PSE&G submitted a request to revise the Technical Specifications (TS) for Salem Generating Station Units 1 and 2. One of the proposed changes was to require both supply fans and all three exhaust fans to be operable and included in the Limiting Condition for Operation (LCO). PSE&G also stated that the supply fan start circuits would be administratively controlled to prevent more than one supply fan from operating at any time, avoiding pressurization of the Auxiliary Building. These administrative controls are contained in the Auxiliary Building Ventilation System Operation procedure, and include in part, the opening of the 125 Vdc control power to one of the supply fans. The procedure provides the operator with specific guidance on how to remove/restore the appropriate supply fan to service.

Although, in the original submittal(LR-N97 488), PSE&G included statements concerning the supply fan with the autostart remov~d under administrative controls in the Technical Specifications Bases;, PSE&G'did not clearly identify in the LCO that the supply fan (with its capability to autostart removed under administrative controls) was considered operable. This supplemental letter requests addition of 1) an asterisk (*) to the word OPERABLE in the LCO, and 2) its associated note at the bottom of the page.

This submittal proposes amending Inserts A and E of LR-N97 488, as follows:

Insert A / Insert E Three Auxiliary Building exhaust air HEPA filter trains, one carbon adsorber bank, two supply fans, and three exhaust fans, shall be OPERABLE(*).

Auxiliary Building pressure shall be negative with respect to atmospheric pressure.

Where (*) is defined at the bottom of the page as follows:

(*)One of the Supply Fans may be considered OPERABLE with its start circuit administratively controlled (removed from service) to prevent more than one supply fan from operating at any time.

. ~ocument Control Desk*

II:

PURPOSE LR-N970810 LCR S95-44 The purpose of this submittal is to clearly identify within the LCO that the supply fan with its capability to autostart removed under administrative controls is considered OPERABLE.

Note that allowing a piece of equipment to be considered OPERABLE under administrative controls is already used in the Salem Technical Specifications. (see***

notation of Table 3.4-3 for both Salem Units)

Ill.

JUSTIFICATION The justification provided in LR-N97 488 remains valid and applicable to this submittal.

However, the following supplemental information is provided in support of this letter.

As stated in our original submittal, the current ABVS TS LCO does not provide sufficient control for ABVS configurations such that the postulated post-accident response of the ABVS, assuming a single failure (vital bus failure) of the fans, is in accordance with the ABV performance as described in the UFSAR. Without Technical Specification limitations for these components, single failure criteria would require that the system must be able to perform its safety function in the presence of a single failure. Applying the single failure criterion to ABVS, without having all fans in the Technical Specifications, can result in a configuration where supply fan capacity exceeds exhaust fan capability or post-LOCA temperatures can not be maintained.

The proposed change, both original and supplemented by this letter, provides explicit requirements for the ABVS to be OPERABLE such that a single failure can be accommodated (or continued operation conservatively restricted via Technical Specification Action Statements when failures can not be tolerated) and assures that negative Auxiliary Building pressure and equipment cooling are maintained.

Administratively controlling the autostart capability of one of the supply fans, while considering the fan operable, does not adversely affect the ability of the ABV system to perform its safety function, specifically maintaining the required negative pressure in the building.

Each of the Salem Units have three vital buses (emergency AC power provided by diesel generators). There are two 100% capacity supply fans per Unit and three 50%

capacity exhaust fans per Unit. The supply fans are powered by A and B vital buses, and the exhaust fans are powered by A, B, and C vital buses. Because of this electrical arrangement, there are no electrical single-failures that can render the system unable to perform its safety function. Failure of the system to perform its safety function could result in 1) Auxiliary Building pressure greater than ambient atmospheric, which could result in the uncontrolled release of radioactive material during LOCA conditions; or 2)

Document Control Desk*

LR-N970810 LCR 895-44 overheating of ESF equipment required to mitigate the consequences of design basis accidents.

CONCLUSIONS PSE&G review has determined that the original 10CFR50.92 evaluation of LR-N97488 remains unaffected by this letter. This letter provides additional information to clarify the statement made in our original submittal regarding administrative controls, and footnotes the word OPERABLE by adding the asterisk and its associated note.

~ocument Control Desk*

Revised Insert A LR-N970810 LCR 895-44 Three Auxiliary Building exhaust air HEPA filter trains, one carbon adsorber bank, two supply fans, and three exhaust fans, shall be OPERABLE(*).

Auxiliary Building pressure shall be negative with respect to atmospheric pressure.

Revised Insert E Three Auxiliary Building exhaust air HEPA filter trains, one carbon adsorber bank, two supply fans, and three exhaust fans, shall be OPERABLE(*).

Auxiliary Building pressure shall be negative with respect to atmospheric pressure.