MONTHYEARML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C 2024-09-03
[Table view] |
Text
Vogtle PEmails From: Patel, Chandu Sent: Wednesday, January 24, 2018 10:22 AM To: 'Chamberlain, Amy Christine'; 'Sparkman, Wesley A.' (WASPARKM@southernco.com)
Cc: Vogtle PEmails; Drzewiecki, Timothy; Palmrose, Donald
Subject:
Audit Plan for Vogtle Units 3 and 4, LAR 17-027 Attachments: LAR 17-027 Audit Plan.docx Hi, Please see the attached audit plan for Vogtle Unit 3 and 4, license amendment request 17-027. This plan is entered in to the official record via this e-mail. Please let me know if you have any questions.
Sincerely, Chandu Patel 1
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 208 Mail Envelope Properties (BN6PR09MB2259A9E66CDCF7AAFA94D49582E20)
Subject:
Audit Plan for Vogtle Units 3 and 4, LAR 17-027 Sent Date: 1/24/2018 10:21:33 AM Received Date: 1/24/2018 10:21:38 AM From: Patel, Chandu Created By: Chandu.Patel@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None "Drzewiecki, Timothy" <Timothy.Drzewiecki@nrc.gov>
Tracking Status: None "Palmrose, Donald" <Donald.Palmrose@nrc.gov>
Tracking Status: None
"'Chamberlain, Amy Christine'" <ACCHAMBE@southernco.com>
Tracking Status: None
"'Sparkman, Wesley A.' (WASPARKM@southernco.com)" <WASPARKM@southernco.com>
Tracking Status: None Post Office: BN6PR09MB2259.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 257 1/24/2018 10:21:38 AM LAR 17-027 Audit Plan.docx 23253 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Southern Nuclear Operating Company Audit Plan for Vogtle Electric Generating Plant Units 3 and 4 Docket Nos.52-025 and 52-026 License Amendment Request 17-027 Reactor Coolant System Vacuum Fill and ITAAC for Containment Floodup A. Background By letter dated September 27, 2017 Southern Nuclear Operating Company (SNC) submitted license amendment request (LAR)17-027 requesting changes to technical specifications to allow reactor coolant system (RCS) vacuum fill operations in cold shutdown conditions (Reference 1). As described in LAR-17-027, the proposed change is supported by safety analyses. The purpose of this audit is to review the calculations and analyses to verify the information and conclusions in LAR 17-04.
B. Regulatory Audit Bases 10 CFR 52.98(f) requires NRC approval for any modification to, addition to, or deletion from the terms and conditions of a Combined License (COL). This activity involves a departure from COL Appendix C information and corresponding plant-specific Tier 1 information; therefore, this activity requires an amendment to the COL. Accordingly, NRC approval is required prior to making the plant specific changes in this license amendment request.
10 CFR 52, Appendix D, Section VIII.B.5.a allows an applicant or licensee who references this appendix to depart from Tier 2 information, without prior NRC approval, unless the proposed departure involves a change to or departure from Tier 1 information, Tier 2* information, or the Technical Specifications, or requires a license amendment under paragraphs B.5.b or B.5.c of the section. The proposed change to UFSAR (Tier 2) design information involves changes to plant-specific Tier 1 (and corresponding changes to COL Appendix C) information, and thus requires NRC approval for the Tier 2 and involved Tier 1 departures.
10 CFR Part 52, Appendix D, Section VIII.A.4 and 10 CFR 52.63(b)(1) govern the issuance of exemptions from elements of the certified design information for AP1000 nuclear power plants.
10 CFR 52, Appendix D, VIII.A.4 requires a Tier 1 change shall not result in a significant decrease in the level of safety otherwise provided by the design.
This regulatory audit will include the following area:
- COL, Appendix C (and Plant -Specific Tier 1) Section 3.3
- COL, Appendix A, Technical Specifications, Specification 3.4.12 C. Regulatory Audit Scope or Methodology
The audit team will examine the inputs, methodology and results of the calculations supporting LAR-17-027.
D. Information and Other Material Necessary for Audit NRC staff requests the following calculations be made available:
- The analysis demonstrating that adequacy of the revised containment floodup volume for a loss of coolant accident (i.e., supporting the change to COL, Appendix C (and Plant-Specific Tier 1) Section 3.3.
- The analysis supporting the following statement in LAR-17-027:
For TS 3.4.12 with the reactor subcritical for 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />, the proposed ADS stage 1, 2, and 3 valves (two required to be ADS stage 2 or 3) and three ADS stage 4 valves have a smaller total flow area than the currently required nine ADS flow paths. This is acceptable based on the evaluation for reactor subcritical for 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />, which results in less decay heat and therefore less venting flow area required.
E. Team Assignments The audit team includes:
Donald Palmrose, Senior Reactor Systems Engineer Timothy Drzewiecki, Reactor Systems Engineer Chandu Patel, Senior Project Manager F. Logistics Depending on the availability of the licensees documentation, the audit is planned to be conducted between January 22, 2018, and February 28, 2018. The audit is intended to be conducted from the NRC Headquarters via the licensees electronic reading room; however, the audit may be performed at a local office of the licensee, if the technical information is only retained in hard copy.
Location: NRC Headquarters Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 Alternatively, Location: Westinghouse Electric Company, LLC Washington Operations 11333 Woodglen Drive, Suite 203 Rockville, MD 20852 Telephone: 301-881-7040/7042
The NRC staff acknowledges the proprietary nature of the information requested. It will be handled appropriately throughout the audit. While the NRC staff will take notes that will be marked as proprietary and will not remove hard copies or copy electronic files.
G. Special Requests N/A H. Deliverables In accordance with NRO Office Instruction, NRO-REG-108, the audit team will issue an audit summary within 90 days of audit completion.
I. References
- 1. Vogtle Electric Generating Plant, Units 3 and 4 - Request for License Amendment and Exemption Regarding Technical Specifications for Reactor Coolant System Vacuum Fill and Inspections, Tests, Analyses, and Acceptance Criteria for Containment Floodup (LAR-17-027), September 25, 2017 (ADAMS Accession Number ML17268A188).