COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical TestsML24039A112 |
Person / Time |
---|
Site: |
Vogtle |
---|
Issue date: |
02/08/2024 |
---|
From: |
NRC |
---|
To: |
NRC/NRR/DNRL |
---|
References |
---|
Download: ML24039A112 (4) |
|
|
---|
Category:E-Mail
MONTHYEARML24311A2242024-11-0606 November 2024 NRR E-mail Capture - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) 2024-09-03
[Table view] |
Text
From:
Mike King Sent:
Thursday, February 8, 2024 12:47 PM To:
Billy Gleaves; Lynnea Wilkins (She/Her); Scott Burnell; Dave Gasperson; David Roth OGC; Michael Spencer; Andrea Veil; Laura Dudes; John Lubinski; Mirela Gavrilas; Raymond Lorson; Jack Giessner (He/Him); Robert Lewis; Jason Eargle; Brian Griman; JP Parent; Cayetano Santos; Bradley Davis; Nicole Coovert; John Lamb; Michael Markley; Andrea Johnson; Todd Keene; John Tappert; Scott Morris Cc:
NRR_VPO Distribution; Vogtle PEmails; Michelle Hayes; Brian Smith - NRR; Lauren Nist (She)
Subject:
RE: FYI - SNC Notification Received of Vogtle Unit 4 "Completion of Pre-Critical Tests" Thanks Billy!
Mike King Deputy Director for Reactor Safety Programs & Mission Support Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission
+1 678-506-0178 From: Billy Gleaves <Bill.Gleaves@nrc.gov>
Sent: Thursday, February 8, 2024 10:48 AM To: Lynnea Wilkins (She/Her) <Lynnea.Wilkins@nrc.gov>; Scott Burnell <Scott.Burnell@nrc.gov>; Dave Gasperson <David.Gasperson@nrc.gov>; David Roth OGC <David.Roth@nrc.gov>; Michael Spencer
<Michael.Spencer@nrc.gov>; Mike King <Michael.King2@nrc.gov>; Andrea Veil <andrea.veil@nrc.gov>;
Laura Dudes <Laura.Dudes@nrc.gov>; John Lubinski <John.Lubinski@nrc.gov>; Mirela Gavrilas
<Mirela.Gavrilas@nrc.gov>; Raymond Lorson <Raymond.Lorson@nrc.gov>; Jack Giessner (He/Him)
<John.Giessner@nrc.gov>; Robert Lewis <Robert.Lewis@nrc.gov>; Jason Eargle
<Jason.Eargle@nrc.gov>; Brian Griman <Brian.Griman@nrc.gov>; JP Parent <Jason.Parent@nrc.gov>;
Cayetano Santos <Cayetano.Santos@nrc.gov>; Bradley Davis <Bradley.Davis@nrc.gov>; Nicole Coovert
<Nicole.Coovert@nrc.gov>; John Lamb <John.Lamb@nrc.gov>; Michael Markley
<Michael.Markley@nrc.gov>; Andrea Johnson <Andrea.Johnson@nrc.gov>; Todd Keene
<Todd.Keene@nrc.gov>; John Tappert <John.Tappert@nrc.gov>; Scott Morris <Scott.Morris@nrc.gov>
Cc: NRR_VPO Distribution <NRR_VPODistribution@nrc.gov>; Vogtle PEmails
<Vogtle.PEmails@usnrc.onmicrosoft.com>; Michelle Hayes <Michelle.Hayes@nrc.gov>; Brian Smith -
NRR <Brian.Smith@nrc.gov>; Lauren Nist (She) <lauren.nist@nrc.gov>
Subject:
FYI - SNC Notification Received of Vogtle Unit 4 "Completion of Pre-Critical Tests" Hi all, On February 8, 2024, (attached & ML24039A055) SNC notified NRR of the successful completion of the pre-critical tests for Vogtle Unit 4 as required by license condition (COL 2.D.(3)(e)). According to the COL, upon this notification, Vogtle Unit 4 is authorized to go critical and operate at steady-state core power levels not to exceed 5% thermal power. Vogtle Unit 4 is the second AP1000 reactor to be built and operated in the US.
No specific response to the subject SNC letter is required and an email acknowledgement of receipt has been sent to SNC and will be added to ADAMS.
If you have responsibilities per the attached Vogtle Communication Plan for License Condition Milestones 2022 - Rev1.docx, please make the appropriate notifications.
If you have any questions, please contact Cayetano Tanny Santos Jr or Billy Gleaves.
Region II will issue an EDO Daily Note.
Sincerely, Billy William (Billy) Gleaves Senior Project Manager NRR/DNRL/NLIB Licensing and Infrastructure Branch US Nuclear Regulatory Commission The contents of this message may be sensitive. If this message has been received in error, please delete it without reading it. Your receipt of this message is not intended to waive any applicable privilege. Do not disseminate this message without the permission of the author. Communications by this author do not represent NRC policy or staff positions and are not binding on the Commission.
Hearing Identifier:
Vogtle_COL_Docs_Public Email Number:
703 Mail Envelope Properties (PH0PR09MB799505928933B1D8958A9377A5442)
Subject:
RE FYI - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests Sent Date:
2/8/2024 12:47:06 PM Received Date:
2/8/2024 12:47:11 PM From:
Mike King Created By:
Michael.King2@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@usnrc.onmicrosoft.com>
Tracking Status: None "Michelle Hayes" <Michelle.Hayes@nrc.gov>
Tracking Status: None "Brian Smith - NRR" <Brian.Smith@nrc.gov>
Tracking Status: None "Lauren Nist (She)" <lauren.nist@nrc.gov>
Tracking Status: None GROUP: "NRR_VPO Distribution"
<Bill.Gleaves@nrc.gov>
Tracking Status: None
<Cayetano.Santos@nrc.gov>
Tracking Status: None
<Christopher.Welch@nrc.gov>
Tracking Status: None
<Garry.Armstrong@nrc.gov>
Tracking Status: None
<James.Gaslevic@nrc.gov>
Tracking Status: None
<Jennifer.Majano@nrc.gov>
Tracking Status: None
<lauren.nist@nrc.gov>
Tracking Status: None
<Phil.O'Bryan@nrc.gov>
Tracking Status: None
<Thomas.Fredette@nrc.gov>
Tracking Status: None "Billy Gleaves" <Bill.Gleaves@nrc.gov>
Tracking Status: None "Lynnea Wilkins (She/Her)" <Lynnea.Wilkins@nrc.gov>
Tracking Status: None "Scott Burnell" <Scott.Burnell@nrc.gov>
Tracking Status: None "Dave Gasperson" <David.Gasperson@nrc.gov>
Tracking Status: None "David Roth OGC" <David.Roth@nrc.gov>
Tracking Status: None "Michael Spencer" <Michael.Spencer@nrc.gov>
Tracking Status: None
"Andrea Veil" <andrea.veil@nrc.gov>
Tracking Status: None "Laura Dudes" <Laura.Dudes@nrc.gov>
Tracking Status: None "John Lubinski" <John.Lubinski@nrc.gov>
Tracking Status: None "Mirela Gavrilas" <Mirela.Gavrilas@nrc.gov>
Tracking Status: None "Raymond Lorson" <Raymond.Lorson@nrc.gov>
Tracking Status: None "Jack Giessner (He/Him)" <John.Giessner@nrc.gov>
Tracking Status: None "Robert Lewis" <Robert.Lewis@nrc.gov>
Tracking Status: None "Jason Eargle" <Jason.Eargle@nrc.gov>
Tracking Status: None "Brian Griman" <Brian.Griman@nrc.gov>
Tracking Status: None "JP Parent" <Jason.Parent@nrc.gov>
Tracking Status: None "Cayetano Santos" <Cayetano.Santos@nrc.gov>
Tracking Status: None "Bradley Davis" <Bradley.Davis@nrc.gov>
Tracking Status: None "Nicole Coovert" <Nicole.Coovert@nrc.gov>
Tracking Status: None "John Lamb" <John.Lamb@nrc.gov>
Tracking Status: None "Michael Markley" <Michael.Markley@nrc.gov>
Tracking Status: None "Andrea Johnson" <Andrea.Johnson@nrc.gov>
Tracking Status: None "Todd Keene" <Todd.Keene@nrc.gov>
Tracking Status: None "John Tappert" <John.Tappert@nrc.gov>
Tracking Status: None "Scott Morris" <Scott.Morris@nrc.gov>
Tracking Status: None Post Office:
PH0PR09MB7995.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3140 2/8/2024 12:47:11 PM Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date: