ML24106A052

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031)
ML24106A052
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/12/2024
From: John Lamb
NRC/NRR/DORL/LPL2-1
To: Pournaras D
Southern Nuclear Operating Co
References
L-2024-LLA-0031
Download: ML24106A052 (3)


Text

From:

John Lamb Sent:

Friday, April 12, 2024 7:11 PM To:

Pournaras, DeLisa S.

Cc:

Joyce, Ryan M.

Subject:

Acceptance Review - Vogtle 1 and 2 - EDG Voltage and Frequency LAR (L-2024-LLA-0031

DeLisa, By letter dated March 20, 2024 (Agencywide Document Access and Management System Accession No. ML24080A455), Southern Nuclear Operating Company (SNC, the licensee) submitted a license amendment request (LAR) for Vogtle Electric Generating Plant (Vogtle),

Units 1 and 2. The proposed LAR revises emergency diesel generator (EDG) frequency and voltage acceptance criteria for Technical Specification (TS) 3.8.1, AC Sources - Operating, and TS 3.8.1, SURVEILLANCE REQUIREMENTS. SNC needs the proposed LAR to correct a non-conservative TS, based on the discovery by SNC in September 2016, that some safety-related pumps could not be demonstrated to perform as specified in the design basis over the full range of EDG voltages and frequencies allowed by the TSs without more detailed analysis.

Vogtle, Units 1 and 2, operations by SNC are currently administratively controlled.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the TSs) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications.

Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your LAR submittal and discussions during the pre-licensing meeting on May 23, 2022 (ML22145A449), the NRC staff has estimated that this LAR will take approximately 625 hours0.00723 days <br />0.174 hours <br />0.00103 weeks <br />2.378125e-4 months <br /> to complete. The NRC staff expects to complete this review by April 12, 2024. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted

hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the LAR and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

John G. Lamb, Senior Project Manager Plant Licensing Branch 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier:

NRR_DRMA Email Number:

2473 Mail Envelope Properties (MN2PR09MB50841D42E5E87DCBAC96B90AFA042)

Subject:

Acceptance Review - Vogtle 1 and 2 - EDG Voltage and Frequency LAR (L-2024-LLA-0031 Sent Date:

4/12/2024 7:11:25 PM Received Date:

4/12/2024 7:11:00 PM From:

John Lamb Created By:

John.Lamb@nrc.gov Recipients:

"Joyce, Ryan M." <RMJOYCE@southernco.com>

Tracking Status: None "Pournaras, DeLisa S." <DSPOURNA@SOUTHERNCO.COM>

Tracking Status: None Post Office:

MN2PR09MB5084.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3945 4/12/2024 7:11:00 PM Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date: