ML17279A735

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/87-19 on 870803-28.Violations Noted.Major Areas Inspected:Ac & Dc Electric Power Distribution Sys, Standby Svc Water Sys & Automatic Depressurization Sys
ML17279A735
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 12/04/1987
From: Huey F, Johnston K, Pereira D, Ramsey C, Richards S, Rod K, Wagner W, Joel Wiebe
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17279A733 List:
References
50-397-87-19, NUDOCS 8712230145
Download: ML17279A735 (42)


See also: IR 05000397/1987019

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report

No. 50-397/87-19

Docket No. 50-397

License

No.

NPF-21

Licensee:

Washington Public Power Supply System

P.

0.

Box 968

Richland,

Washington

99352

Facility Name:

Washington Nuclear Project

No.

2 (WNP-2)

Inspection at:

MNP-2 Site,

Benton County, Washington

and

MPPSS Engineering

Offices, Richland,

Mashington

Inspection

conducted:

August 3,

1987 through August 28,

1987

Inspectors:

F.

R.

Huey,

Team Leader

W.

ner,

Re

tor Inspector

'PÃl

. ~Ramsey;,

Re qtor Inspector

i )

8&.'~

Pereir a,

Reactor Inspector

i2- /-8 >

Date Signed

~/-

z7

Date Signed

2- I -81

Date Signed

i~A/~z

Date Signed

K. Johnston,

Resident

Inspector

J.

Miebe, Resident

Inspector, RIII

K.

Rod, Inspector Trainee

Consultants:

G. Morris, Westec Services,

Inc.

D. Prevatte,

Westec Services,

Inc.

L. Stanley, Zytor, Inc.

Approved By:

S.

Richards,

Chief,

ngineering Section

Date Signed

>2.-H -8 l

Date Signed

s2 -"I-87

Date Signed

z,-9 -87

Date Signed

8712230145

871208

PDR

ADOCK 05000397

G

PDR

~Summar:

Ins ection

on Au ust

3 throu

h 28

1987

Re ort No. 50-397/87-19)

Ins ection

Ob 'ective

The objective of this inspection

was to assess

the operational

readiness

of

selected

safety

systems

at WNP-2.

Ins ection Method:

A Safety System Functional

Inspection

(SSFI)

was performed

on selected

safety systems.

An SSFI type inspection is

a design

based

inspection process.

One of the chief advantages

of this type of inspection is

that it concentrates

a comprehensive,

multi-discipline review into a

relatively narrowly defined area.

The intent of the inspection is to define

an inspection

area that is not only important to plant safety

or accident

mitigation, but to select

an area involving a broad cross-section

of

activities by the various disciplines in the licensee

organization.

This type

of approach

allows the inspectors

to develop

a fairly accurate

perspective

of

how well the licensee organization integrates

the various aspects

of plant

design,

engineering,

operation,

maintenance,

etc.

Recent experience with this

type of inspection

has

shown it to be effective at pointing out deficiencies

both in the area of adequate

licensee

understanding

of the design basis for

the plant and in the area of control of the design process.

Basis

and

Sco

e of Ins ection:

In defining the scope of this inspection,

the

NRC adapted

generic

PRA data to

the specific

WNP-2 plant design in order to determine significant plant

failure modes.

Recent

NRC findings relating to engineering

and quality

assurance

problems (e.g.

root cause

assessment)

were also considered.

This

review process

resulted in the selection of the

AC and

DC electric power

distribution systems

as the primary areas

of emphasis for the inspection.

The

inspection

scope also included the Standby Service Water System

(a significant

emergency

power support system)

and the Automatic Depressurization

System

(a

significant accident mitigating system in the event of a loss of power event).

Results of the Ins ection:

Ma or Concerns Identified

1.

Inade uate Control of Plant Desi

n

Re uirements

The team noted several

examples of problems in which the licensee

appeared

to have lost control of the plant design process.

Specific

concerns

in this regard involve both

a lack of licensee

understanding

of

the plant design basis

and

a loss of control of implementation of design

requirements

into plant modifications

and procedures.

In addition, the

types of problems

noted raises

a concern

as to the adequacy of quality

assurance

controls in the deficient areas.

-3-

2.

Plant Material Condition and Housekee

in

Deficiencies

The team observed

several

examples of plant material condition and plant

housekeeping

deficiencies.

3.

Inade uate

Root Cause

Assessment

and Corrective Action

The team identified some instances

in which it did not appear that the

licensee

had implemented aggressive

root cause

assessment

or timely

corrective action following specific plant malfunctions.

A more detailed

summary of the team findings is provided

as Appendix

B to the

transmittal letter accompanying this inspection report.

Summar

of Violations Identified

Of the areas

inspected,

ten apparent violations of NRC requirements

were

identified,

as

summarized

below:

A.

Failure to comply with requirements

for establishing,

implementing

and maintaining procedures

for the surveillance

and testing of

safety related

equipment.'.

Failure to comply with Technical Specification requirements

for

minimum fuel oil supply for emergency

diesel

generators.

C.

Failure to properly implement quality assurance

program requirements

for compliance with station procedures.

0.

Failure to comply with Technical Specification requirements

for

obtaining review and approval of station procedure

changes.

E.

Failure to comply with requirements for periodic testing of safety

related time delay relays.

It should

be noted that several

areas of potential violation of NRC

requirements

remain unresolved,

pending completion of additional

licensee

review of the specific problems involved.

Further actions in this regard will

be the subject of future correspondence,

following review of additional

licensee

information on these

items.

DETAILS

Persons

Contacted

Licensee

personnel

attending the exit meeting

on August 28,

1987

included:

S.

S. Allen, Engineer I, Fire Protection

J.

W. Baker, Assistant Plant Manager

G. Brastad,

Technical Specialist (Electrical/I&C)

J.

P.

Burn, Director of Engineering

S.

Chaudhuri,

Principal Electrical Engineer

J. Civay, Principal Electrical Engineer

J.

D. Cooper,

Principal

Engineer,

Maintenance

C.

D.

Eggen,

Principal Engineer,

Fire Protection

C. J.

Foley, Technical Specialist

G.

Freeman,

Principal Test Engineer

F.

D. Frisch, Principal Engineer,

Operations

P.

W. Harness,

Technical Specialist

L. T. Harrold, Manager,

Generation

Engineering

D.

A. Injerd, Engineer I, Mechanical

Systems

W.

M. Kelso, Principal

Engineer

R. Koenigs,

Supervisor Plant Engineering

G.

Lawrence,

Principal Electrical

Engineer

J.

Massey,

Supervisor Electrical Maintenance

R. Matthews,

Principal Electrical

Engineer

G. Moore, Senior Electrical

Engineer

J.

C.

Mowery, Principal

Engineer

D.

M. Myers, Principal

Engineer

B.

D.

Ngo, Engineer I, Mechanical

Systems

C.

R.

Noyes,

Manager,

Mechanical

Systems

N. Porter,

Manager, Electrical/I

8

C Systems

C.

M. Powers,

Plant Manager

M. Rice, I 8

C Engineer

(Diesel Generator)

D. Thorn, Principal Electrical Engineer

S.

N. True, Clerk, Records

Management

A. Warren,

Nuclear Plant Engineer

(DC Systems)

C.

M. Whitcomb,

Leader,

Technical

Program

D.

L. Whitcomb, Technical Specialist

S.

G. Willman, Engineer I

In addition to the individuals identified above,

various other

engineering,

quality assurance,

maintenance,

and operations

personnel

and

other members of the licensee's

staff were interviewed during the

inspection.

For the

NRC, J.

B. Martin and

R.

P.

Zimmerman of Region V, the,NRC

licensing project manager,

and the resident inspector,

attended

the exit

meeting,

in addition to the inspection

team members.

2.

Plant

En ineerin

and Desi

n Modification

Plant-engineering

and design modifications were reviewed in the

mechanical, electrical,

instrumentation

and controls,

HVAC, and fire

protection disciplines.

The review focused

on the

Emergency Electrical

Systems

(both ac and dc) and their support

systems.

These

included the

emergency

Diesel Generators

and their auxiliaries,

the

AC and

DC

Electrical Distribution Systems,

the Standby Service Mater System,

the

125

VDC and

250

VDC Batteries

and their associated

hardware,

the

essential

HVAC for these

systems,

and the fire protection for these

systems.

In addition,

the Automatic Depressurization

System

and its

support

systems

were reviewed.

The team findings in this area are

summarized

in the following sub-paragraphs:

Class

lE Batter

Sizin

The Division 1 and Division 2 125 volt batteries

and the Division 2

250 volt battery were replaced in 1983 with. different type Exide

cells than

used in the original batteries.

The

common battery

sizing calculation (Calculation

No. 2.05.01,

Revision 6, 3/5/84)

was

revised to address

the

new 125 volt cells only.

The team reviewed

the battery sizing calculation

and

had the following concerns.

The data documentation

used to develop the load profile was

deficient in that many of the inputs,

such

as

dc motor loads,

switchgear control,

and

demand

and diversity factors,

were not

sufficiently referenced

to permit verification.

The team attempted

to duplicate the loads

on the Class lE battery profiles and found

problems in both the

125 volt and 250 volt profiles reviewed.

The

250 volt Division 1 battery motor loads

used in the calculation did

not agree with the dc single line drawing (Drawing No.

E505,

Revision 41, 7/21/86).

Additionally, the motor starting currents

were

assumed

in the calculation to be limited to 200K full load

current,

however,

the team found that the calculation (Calculation

No. 2.05.08,

Revision 1, 7/21/83) which sized the starting

resistors,

permitted

a motor starting current of 300K.

This

inconsistency

alone could account for an additional profile load of

over 300 amperes

in the first minute

on the 250 volt battery.

Additional errors

noted by the team were associated

with both the

250 volt and the 125 volt safety-related

inverter loads,

including

corrections to battery loading for inverter dc input voltages at

less than nominal voltage

and decreased

inverter efficiency at less

than rated load.

The team also identified problems with the methodology

used in the

calculation.

The calculation

was performed looking only at the

total length of battery discharge

and failed to consider the

incremental effect of each step in the load profile.

This was most

significant in the 125 volt Division 1 battery in which the

licensee's

calculation concluded that

a cell with only 2 positive

plates

would provide adequate

margin.

In fact, based solely on the

original profile, the team calculated that

a cell with 6 positive

plates

would be required to maintain the battery voltage

above

105

volts during this initial transient.

The methodology for this type

calculation

was published

by EXIDE as early as

1954 with HOXIE'S

AIEE paper,

"Some Discharge Characteristics

of Lead Acid Batteries".

This paper

formed the basis for IEEE-485,

Recommended

Practice for

Sizing Large

Lead Acid Storage Batteries.

In addition, the

calculation failed to account for the degraded

battery conditions

permitted

by the plant technical specifications

(Technical Specification 4.8.2. 1) and should

have included correction factors

for the minimum permitted operating temperature

of 60 degrees

F,

aging,

and maintenance

margins.

If all these

margins

were included

in the original load profile, as

recommended

by current industry

,

standards

(IEEE 485-1978

and 1983),

both the existing 125 volt and

250 volt Division 1 batteries

would appear to be undersized.

Only

because

these batteries

are relatively new and tested capacity

shows

these batteries

have greater

than rated capacity,

does the team

believe that this is not an immediate safety concern.

The Division 3 battery

was modified to a 58 cell battery by design

change

PMR-2-85-0181-0.

The sizing for this battery is documented

by Supply System calculation

no. E/I 02-85-02,

Revision 0, 5/3/85.

The load profile for this calculation is based

upon the Final Safety

Analysis Report

(FSAR) load Table 8, 3-6.

The calculation did not

attempt to confirm these

FSAR loads.

Similar to Division 1, the

team found

a problem with the motor starting current

assumed

for the

diesel

standby fuel

pump.

The

FSAR table

assumed

the starting

current

was limited to 10 amperes

(200K of full load current).

However, the motor test record indicated the starting current could

exceed

20 amperes.

In addition, while the calculation included margins for minimum

temperature,

aging,

and design margin, the team found that the

correction factor for minimum temperature

was based

upon

65 degrees

F, not the allowable

60 degrees

F minimum temperature.

Corrections

for these errors would require

a battery cell with 5 positive plates

to permit battery replacement

at 80K rated capacity.

The present

Division 3 cells contain only 4 positive plates

and the latest

battery performance test dated 4/18/87 revealed that the battery

has

already

degraded

to 88.35K capacity.

The team is concerned that

little margin remains in this battery.

Failure to assure that the design basis for the safety-related

batteries

was correctly translated

into station

documents

appears

to

be

a violation of 10 CFR 50 Appendix B, Criterion III.

This item

remains

unresolved,

pending additional

licensee

evaluation

(50-397/87-19-01).

DC

S stem

Minimum Volta e

The team reviewed voltage drop calculations

(Calculation Series

2.06.xx) for voltage drops

from motor control centers to their

associated

loads.

(1)

The team selected

Calculation

No. 2.06.04,

Revision 13, dated

3/11/87, to review the Division 1,

125 volt dc motor operated

valve

(MOV) supply cable voltage drop determination.

The team

4

observed that the calculation correctly stated

the requirement

that the voltage drop calculations for dc motor operated

valves

must consider four (4) times the one-way distance to the valve

in order to account for the reversal

of the current through the

armature windings required to change

valve direction.

The team

noted,

however, that the voltage drop calculation for many of

the valves did not consider this assumption.

The team

was

informed by- the. licensee that instead of including four times

the length of cable run in the calculation,

the conductors

were

paralleled to reduce

the conductor resistance

in half.

During

this review, the team learned that the parallel conductors,

which were in fact identified in the calculation

by noting

a

cable construction

o'f 9 conductors

versus

the original

5

conductors,

were never installed.

The team was informed that

the reason

the additional conductors

had not been installed in

the

DC'MOV circuits was that the Startup organization

had

performed

a test which was intended to demonstrate

that

sufficient voltage would exist at the valves without the

parallel conductors.

As a result of this test,

the design

modification was voided.

The team found the test results

recorded in PED-S218-E-C640 deficient for the following

reasons:

(a)

Bus voltage

was measured

to be varying between

125 and

135

volts during the test, indicating that other factors were

affecting the recorded voltage measurements.

(b)

The valves did not appear to be under design

load

conditions

when tested.

(c)

Starting currents

were not considered

in a majority of the

valves tested.

The combined starting currents of the

valves could significantly reduce the terminal voltage

available at the valves.

(d)

Test results

recorded

for the valves in question did not

include valve CAC-V-8..

The team observed that the calculation

assumed

a total

allowable drop from battery to load of only 4X (125V x .04 = 5

volts).

This criteria was contained in the calculation

apparently to account for the worst case

voltage degradation

during battery discharge

(105 volts - 5 volts drop = 100 volts

at the loads).

However, neither this calculation,

nor

Calculation

No. 2.07.04,

Revision 3, 7/6/83,

which was to

account for the

1X drop between the battery

and the

MCC,

considered

the voltage drop in the cabling during transient

conditions including motor starting.

This initial total

voltage drop should

be considered

to confirm the adequacy of

the voltage at the valves at the time the valves first start to

stroke.

Based

upon the WNP-2 original battery load profile,

the team estimated

the battery voltage at degraded

conditions

during

a battery discharge

and concluded that the starting

voltage at five of the

125 volt dc motor operated

valves in

Division 1 would drop below the specified

minimum starting

voltage of 100 volts.

The voltage drop from the battery to the

MCC could account for an additional

8X voltage drop under worst

case conditions.

This is an apparent violation of 10 CFR 50,

Appendix B, Criterion

V (50-397/87-19-02).

(2)

The team also noted that

no voltage drop calculations

had been

performed for the safety-related

inverter

dc supply or for the

125 volt switchgear control circuits.

The team estimated,

based

on the original load profile, that the voltage at the

inverters

and certain safety-related

4kV switchgear control

circuits could fall below the manufacturer's

rated

minimum

voltage of 105 volts.

While the team believes that margin

exists

below the published Westinghouse

rated

minimum voltage

of 105 volts (Application Data 32-262,

Type DH-P air circuit

breakers)

for the close coils, the safety-related

inverter

manufacturer's

(Elgar) instruction manual

(Inv 203-101) states

that the inverter will automatically shutdown

when the battery

is discharged

to 105 volts.

It is the teams

understanding

that, in response

to this inspection,

the licensee

has performed preliminary voltage calculations,

based

upon

a new load profile, which will demonstrate

adequate

voltage at

these

components.

This is an open item (50-397/87-19-03).

Motor 0 crated Valve Overload Selection

The team reviewed the overload protection provided for a number of

the service water valves required to support the diesel

generator.

The majority of the associated

motor control centers

were

manufactured

by ITE and

use

3 single phase

overload relays to

protect their motor loads.

The team found that overload heaters

were selected

to trip the valve motors

based

upon Burns

and

Roe

technical

memorandum

T.M.

No.

1129,

dated 8/11/78.

This document

implied that if the overload heaters

were selected

at 140K of motor

full load current, sufficient locked rotor current protection would

result.

No supporting documentation

could be found by the licensee

at the time of the inspection to support this conclusion.

The failure to confirm the assumption that thermal

overload, relays

selected

at 140X of motor full load current would provide adequate

protection for short time duty motor operated

valves

appears

to be

a

violation of 10 CFR 50 Appendix B, Criterion III.

This item remains

unresolved,

pending additional

licensee

evaluation.

(50-397/87-19-04).

The team independently

sized overload protection for these valves

based

upon the valve actuator manufacturer's

recommendation,

obtained

from the licensee,

as presented

in IEEE technical paper

F79669-3,

dated 5/1/79.

This document

recommended that for short

time duty motors

used

on motor operators,

the locked rotor current

time should

be limited to 10 to 15 seconds

in order to protect the

motor windings from thermal

damage.

With the over load heaters

selected

by the licensee at 140K of" full load current,

no running

protection

and insufficient locked rotor protection would result.

The team determined that at locked rotor current,

the heaters

would

require approximately

one minute to actuate.

The team estimated,

based

upon

a review of valves

SW-V-2A, 2B,

4A

and 4B, that overload heaters

six sizes

smaller than presently

installed would provide both running and locked rotor protection

and

still provide at least

700K margin on valve stroke time at motor

full load current.

An overload heater size smaller would still

.

provide 200K margin

on full load current at rated valve stroke time.

Other valves

checked

by the team produced similar results.

In addition to the above,

the team found that most of the valves in

the

RHR system

and

some valves in other systems

appeared

to have the

B phase

overload

heatet

wired for alarm only and not to trip the

breaker.

However, these

heaters,

used for alarm purposes

only, were

also found to be selected

by the

same original

TM 1129 criteria so

that the alarm would not be received prior to motor damage.

In contrast,

the team found that the overloads

provided

on

a

GE

motor control center

(MC4A) included

a three

phase

overload relay to

trip on motor overload

and

a single phase

overload relay with a

smaller heater to alarm on a smaller overload.

However, the

licensee

had elected

not to wire these

alarm relays to take

advantage

of the early alarm feature.

The team

was not able to

confirm the adequacy of these

GE overload relays during the

inspection

because

of time constraints.

En ineerin

and Desi

n Modification

The methods

and instructions for the identification, control,

implementation,

documentation

and closeout of plant modifications is

addressed

in Administrative Procedure

No. 1.4. 1, "Plant

Modifications," Revision 6, of April 17,

1987.

This procedure

describes activities to ensure that plant modifications properly

implement plant design

changes.

The program, in part, requires

the

proposed plant modification to be described

in a Design

Change

Package

(DCP) which, when approved,

is implemented

by a Material

Work Request resulting from initiation of a Plant Modification

Record

(PMR).

The

PMR, therefore,

is the controlling document

because it identifies the plant modification to be performed,

including the

MWRs; it provides authorization for implementation;

and requires verification that the installation is complete

and the

system operable.

Review of the plant modification procedure

by the

team indicated that the program does not contain provisions

addressing partial implementation of design modifications.

The

concern

expressed

by the team was that if, due to unforeseen

circumstances,

a modification is partially implemented,

there are

no

procedures

to describe

what actions to take to ensure that the

partial implementation is acceptable.

Discussions with licensee

management

personnel

involved with outage

scheduling

and

imp 1 ementati on of wor k authori zed by PMRs concurred

with thi s

observation.

Their position was essentially that their procedures

do not allow partial implementation of design

changes.

The team reviewed the records of DCPs processed

over the past

several

years looking for design modifications involving more than

one

DCP or multi-disciplined groups.

The team also interviewed

licensee

engineering

personnel

regarding implementation of design

changes.

This effort revealed

a discrepancy

regarding

a plant

design modification covered

by

DCP 84-1096-OA and

OB and approved

for implementation in September

1984.

This modification installed

two new safety-related

auxiliary steam isolation valves

(OA) and

missile shielding for these

valves

(OB).

Each of the design

packages

(OA and

OB) required that both

DCPs

be completed in order

to consider either

DCP to be complete.

Both

PMRs written to

implement the

DCPs were signed off as complete

and design drawings

were revised in July 1985 to show the additional valves

and

shielding.

However,

when the team reviewed the completed

installations, it was observed that the shielding

was not installed.

Subsequent

review of the modification package

revealed that the

field work was never specified

on a

MMR and therefore

not

implemented.

The licensee initiated

NCR No. 287-297 to document

this problem.

The team reviewed the modification program and

concluded that had the responsible

Technical

Engineers

followed

their procedure,

this problem would not have occurred.

Specifically,

the procedure

in effect in June

1985 was Revision

2 of Procedure

No.

1. 4. 1.

Section

1. 4. 1. 6 required

the Plant System Engineer to

initiate the

HWRs to implement the change.

The

MMRs for the missile

shielding were not prepared.

Attachment 1, the

PMR form, Block 18

required the signature

and date of the Plant System

Engineer

indicating that the installation of the modification was complete.

Although Block 18 was signed off as complete,

the work was

never'nitiated.

These

events

led

up to the Shift Manager reviewing

a

supposedly

complete

PMR package

and signing off that the system is

considered

operable,

thus returning the system to service.

Failure to install the missile shield

as required

by the Plant

Modifications procedure is an apparent violation of 10 CFR 50

Appendix 8, Criterion V (50-397/87-19-05).

The inspectors'valuation

into the probable root cause of this

problem identified two weaknesses

in the current modification

program

as addressed

in Procedure

1.4. 1.

First, there

are

no

provisions to assure

the

MMRs are initiated covering the entire

scope of a modification.

Second,

there are

no specific requirements

assuring that the entire

scope of a modification was actually

implemented.

The inspector discussed this with the Plant Technical

staff which resulted in the licensee initiating a Procedure

-Deviation to revise

Procedure

1.4. 1- to include these provisions.

The

inspector

reviewed the proposed revision and

recommended

that the

licensee

consider including a joint verification as-built walkdown

of completed

DCPs by the Plant Technical

and Design Engineering

groups.

Although no commitment was

made

on this matter,

during the

exit meeting,

the licensee

did respond favorably to the idea.

Other examples of

PMR signoffs indicating completion of a

modification when, in fact, the entire work was not completed are:

(a)

NCR No.

287-294 written on August 14, 1987, identifying that two

pipe supports,

DSA-4275-12

and 13, to be installed during the April

1986 outage,

were not installed.

As a result, this system

was

declared

operable without justification that failure would not

occur.

However, justification was obtained

from the design

engineering

group on August 14,

1987, stating that no actual fai lure

of the line would occur

had

a seismic event occurred;

(b) standby

service water valves

SWS-PCV-38A and

38B were modified to eliminate

automatic pressure

control

and valve position indication (VPI) in

the control

room,

and (c) condensate

valves

COND-V-9A and

9B were

also modified to eliminate VPI in the control

room.

In examples

(b)

and (c), instrumentation

and controls in the control

room did not

provide indication,

as required

on the

MWRs, that their related

systems

have

been retired.

How the licensee

plans

on addressing

the

issue of partial implementation

and partial justification for

declaring

an effective system operable is an open item.

(50-397/87-19-06).

Fire Protection

S stems for Diesel Generators

WNP-2 is equipped with three diesel

generators,

Division 1 and

Division 2 units which supply onsite

emergency

AC power for the two

basic trains of ECCS equipment,

and the Division 3 unit which

supplies onsite

emergency

AC power for the

HPCS

pump only.

They are

located in separate

rooms of one building, these

rooms having 3-hour

fire rated walls and doors.

Each

room has

two access

points,

one to

the south opening to the outside

and another to the north opening

into a

common hallway.

The doors

open outward away from the room.

The north doors are equipped with a curb approximately

3 1/4 inches

high; the south doors

have

no curb.

Fire protection is provided in the

rooms by a pre-action sprinkler

system with fusible sprinkler heads.

Drainage for the

rooms is

through several floor drains in each

room connecting to a

common six

inch line in the Division 1 and

2 rooms

and

a

common four inch line

in the Division 3 room.

These drains are capable of carrying only a

limited flow from the sprinklers.

The fuel oil transfer

pumps for all three divisions are located in

three separate

rooms adjacent to the Division 3,

HPCS diesel

generator

room.

The only entrances

to these

rooms are from the

HPCS

diesel

generator

room.

They are also protected

by pre-action

sprinklers.

No drains are provided for these

rooms.

The design of the diesel

generators

and the associated

systems

and

components

is governed

by several

codes,

standards,

and regulatory

documents,

which specifically address

the fire protection

requirements

and the separation

and redundancy

requirements.

These

include 10 CFR 50, Appendix A; and

NRC Branch Technical

Position

APCSB 9.5-1.

In response

to these

requirements,

the licensee

made the following

commitments in the

FSAR:

FSAR; Appendix F, Fire Protection Evaluation,

Amendment

No.

37

dated August 1986,

response

to Branch Technical Position

APCSB

9.5-1,

NRC Position Dl(a), states

"All Appendix

R

safety-related

systems

have

been separated

from unacceptable

fire hazards

through remote separation

or fire barriers to the

extent that is possible."

FSAR response

to Po'sition Dl(i) states

"Actuation of the fixed

fire protection

system would not adversely affect any

safety-related

equipment

by flooding.

FSAR response

to Position D2(a) states

"Safety-related

systems

have

been isolated or separated

from combustible materials to

the extent possible."

FSAR, Section 8.3. 1. 1.8 - Standby

AC Power System,

Amendment

No.

34 dated January

1984, states

"Design provisions ensure

that flooding in one diesel

generator

room does not jeopardize

the operation of the other diesel

generators."

FSAR, Section 9.5.4.2,

Amendment

No.

36 dated

December

1985,

states

"Although a single failure may result in loss of fuel to

one diesel

generator,

the other diesel

generator

can provide

sufficient capacity for emergency conditions,

including safe

shutdown of the reactor,

coincident with loss of offsite

power."

Several

inadequacies

were observed

by the team in the coordination

of the design of the fire protection

systems

and the floor drainage

systems

of the diesel

generator

rooms.

These

problems

are discussed

in more detail

as follows:

Failure of the Fuel Transfer

Pum

s

As discussed

above,

the fuel oil transfer

pump rooms for all

three

emergency diesel

generator

units are located adjacent to

the Division 3 diesel

generator

room with their only entrances

being from this room.

The fuel oil transfer

pumps are

electrically driven and are located in pits in the

rooms just

above the ends of the main fuel storage

tanks.

These pits have

no curbs

around their upper edges

and

no drains.

The rooms

have

no floor drains.

Therefore,

any fluid entering the

rooms

will fill the pits and potentially drown out the

pump motors.

At the door to each

room is

a curb approximately

7 5/8" high

separating it from the Division 3 diesel

generator

room.

The primary accident

scenario of concern is the single failure

of a pump seal or a flexible fuel line on the discharge

side of

the fuel oil pump on the Division 3 diesel

generator

followed

by a fire in the room.

The worst case of this scenario

would

be when

a large

amount of oil would be leaked onto the floor

10

and would spread

over a large area before being ignited by some

heat source

on the engine.

In this case

the initial fire could

be quite large,

and

many of the sprinkler heads

in the

room

could be fused,

causing

a high flow rate of water into the

room.

If the rate of flow into the

room exceeded

the drainage

rate,

the level would eventually rise to the point where it

would spill over the curbs of the Division 1 and Division 2

transfer

pump rooms, at which time both pumps could be

incapacitated.

Within as little as

5 1/2 hours after this,

both Division 1 and Division 2 diesel generators'ay

tanks

would be empty, their engines

would stop,

and all onsite

AC

power could potentially be lost.

This would be particularly

significant if it occurred during a loss of offsite power

(loop).

For less

severe fires, the number of sprinkler heads

fused

would be less; therefore,

the time until spillover would occur

would be longer.

An exacerbating

condition is the licensee's

use of absorbant

pads

around the diesel

generator

units to absorb oil drips.

These

pads

are not secured,

and additional

pads,

wiping rags,

and other extraneous

material

are loosely stored in the rooms.

These would tend to be washed to the drains

and under the south

door early in the event, potentially blocking all drainage.

The licensee

was asked if there

was any analysis

which showed

that actuation of the fire protection would not flood the

room.

None was produced,

although

a quick, on-the-spot,

unverified

calculation

done by the licensee

showed that spillover into the

fuel oil transfer

pump rooms would occur at about

17 minutes

after fire initiation assuming

no drainage

from the room.

The licensee

also could produce

no evidence that the drains

had

ever been verified open.

This together with the potential for

plugging provided by the loose material

observed

in the

rooms

strengthens

the assumption

used in the calculation that

no

drainage

would occur.

The licensee

presented

a position that the flooding would not

likely occur because

the site fire brigade would arrive at the

scene

minutes after the fire started

and they would shut off

the sprinklers and/or

open

one or both of the doors to the

Division 3 diesel

generator

room, releasing

the water.

The

team did not consider this to necessarily

be

a valid response

for several

reasons:

(1)

The licensee

was apparently

not

aware of this threat prior to this inspection,

and there is no

plant procedure

which gives any special

instructions

on how to

deal with water in this room.

.There is therefore,

no reason to

expect that the fire brigade would take any deliberate action

in time to prevent flooding to the critical stage.

(2)

An

argument

can

be made that, without specific direction to the

contrary,

a reasonable

response

of the fire brigade might be to

leave the doors shut and allow the sprinklers to perform their

function.

This would be particularly true if it were suspected

that flooding did exist in the room, since opening of the doors

might risk allowing burning oil to move to other areas

not

previously threatened.

And finally (3), even if the fire

brigade desires

to open the doors, there is no reason to expect

that they necessarily

could in a timely manner.

Flooding

pressure

against

the latches

may prevent their being opened

normally. Additionally, oil spreading

under the doors could

also

be burning,

impeding timely access.

With the scenario

described

above,

as

a result of a single

credible failure, all three

sources

of onsite

AC electrical

power could potentially be lost.

This item remains

unresolved,

pending additional evaluation

by the licensee

and

NRR.

(50-397/87-19-07).

Fire Threat to Both Safe

Shutdown Divisions

In the

common hallway outside the diesel

generator

rooms are

raceways for all three divisions of emergency

power with only

Division 2 Safe

Shutdown cables

being fire protected

by

sprinklers

and by being wrapped with a one-hour fire barrier

material.

Division 2 is the designated

Safe

Shutdown Division

for the plant.

In all three

rooms the fire accident scenario

described

in (1)

above also

has the potential to spread

the hazard outside the

3-hour barrier of the

room where the fire has occurred

and

threaten

the other

two unprotected

divisions of LOCA required

cables

in the

common hallway.

The mechanism for this threat

is,

as described

above,

flooding of the

rooms

due to actuation

of the sprinkler system.

This flooding would cause spillover

at the curbs at the north doors,

and the liquid would flow

under the doors

and into the

common hallway.

Since the oil

would tend to float on top of the water, it would be the first

liquid to spill over,

and therefore, this transient combustible

would be in the hallway where it would be

a threat to all three

divisions of cables.

If the fire scenario

were to occur in the

Division 2 diesel

generator

room at any time including normal

operation,

the ability of the plant to achieve

safe

shutdown

could be compromised.

Fire in Division 1 or Division 2 Fuel Oil Transfer

Pum

Rooms

The diysel fuel transfer

pump

rooms for the Division 1,

Division 2,

and Division 3 emergency

diesel

generators

are

located adjacent to the Division 3 diesel

generator

room with

their only doors opening

from this room.

The fuel transfer

pumps are located in pits in the rooms,

and fire protection is

provided by sprinklers.

There are

no floor drains or other

drains in the rooms.

At the entrance

to each

room is a sill

approximately eight inches high.

12

The event of concern

here is

a fuel oil leak in either the

Division 1 or Division 2 fuel transfer pit area

being ignited

by an electrical

spark.

In this case,

the sprinklers in the

room would be activated.

Such

a fire could occur at any time a

transfer

pump is running,

such

as during an, engine test,

when

an operator is topping off an engine

day tank in preparation

for filling the main storage tank, or during engine

response

to

an event.

With activation of the sprinkler system,

the pit

will fill with water,

and after

some finite time, if the

sprinklers

are not secured

by the fire brigade,

the

room will

fill to the point that the liquid will spill over the door sill

and into the Division 3 diesel

generator

room.

Since oil would

be part of the fluid spilling over, the Division 3 equipment

could

now be threatened

by the uncontrolled flammable liquid on

the floor.

In this fire scenario,

one division of emergency

power would be

disabled

by the initial fire, and

a second division, Division 3

could be threatened

as

a result of this single failure.

Although this particular scenario

does

not prevent achieving

safe

shutdown

from normal plant operations

since either

Division 1 or Division 2 will not be affected, it does

degrade

the condition of the plant.

Items (2) and (3) above

remain

unresolved,

pending additional

review by the licensee

and

NRR

(50-397/87-19-08).

The licensee

has

agreed to take several

corrective actions to

alleviate the problems

caused

by fires in the diesel

generator

rooms.

These include:

Installation of automatic acting scupper flappers

on the south

doors of the

rooms to allow drainage to the outside.

Securing or removing all oil soak

up pads

and other articles

capable of plugging the drains in the rooms.

Verifying the drains to be open

and clearing those not found

open.

Training of the fire brigades

on the special

hazards

to plant

safety associated

with fires in these

r corns.

No remedial action

has

been

suggested

by the licensee with regard to

the hazards

associated

with fire in the fuel transfer

pump rooms.

f.

Air Filtration for Emer enc

Diesel Generator

Units

10 CFR 50, Appendix A, Criterion 2, Design Basis for Protection

Against Natural

Phenomenon

requires. that systems

important to safety

shall

be designed

to withstand the effects of natural

phenomenon.

One natural

phenomenon for which the diesel

generator

and their

support

systems

as well as other systems

in the plant must be

designed

is particulate matter in the air.

Air in large volumes is

required for operation of the diesels for both combustion

and

13

ventilation of the spaces,

and the particulate matter must be

removed to assure reliable operation of the systems.

The

concentration of matter which must be dealt with ranges

from

relatively minute during normal conditions, to dust storms which are

common in the area,

to volcanic ash fallout which is rare but

credible in view of the Mt. St.

Helens eruption which generated

heavy ash fall in close proximity to the plant.

The designs

to deal with these conditions consist of oil bath

filters for the combustion air for each diesel

generator unit for

normal operation

and design basis

dust storms;

dry disposable

paper

filters for the ventilation systems for normal operation

and design

basis

dust storms;

and dry disposable

paper filters for the design

.

basis

ash fall event,

which are temporarily installed

upstream of

and provide

common prefilter banks for both the combustion air

and

ventilation filters for the Division 1 and Division 2 diesel

generators.

Abnormal Conditions Procedure

4. 12.4.5,

Design Basis

Ash Fallout,

requires that these

temporary filters be installed

and the plant

shut

down upon being notified of an eminent

ash fall event.

No

prefi lter banks are required to be installed for the

HPCS diesel

generator.

The team found numerous

discrepancies

and inadequacies

with the

design,

and examples of non-integration of the operational

or

maintenance

requirements

for the diesel

generator

systems with the

design requirements.

The following paragraphs

describe

the

conditions

found and the remedial

actions

taken or planned by the

licensee:

(1)

No Anal sis of Oil Bath Combustion Air Filters for Dust Storm

The licensee

had

no analysis

which documented

the capability of

the Division 1 and Division 2 oil bath combustion air filters

to function for the design basis

dust storm.

An analysis

was

performed during the inspection which did show their

capability, but it had not been verified or approved at the

close of the inspection.

(2)

No Anal sis of Tem orar

Filters for Ash Fall

The licensee

had

no analysis

which documented

the adequacy of

the temporary filters for the design basis

ash fall event.

An

analysis

was performed during the inspection which indicated

the filters could be fully loaded at 19 minutes into the event

if the systems

were operated

per the existing abnormal

conditions procedure.

For this event, with the plant shutdown,

at least

one diesel

generator

must be operational

per the

Technical Specifications.

Since,'er

the licensee,

the

changeout

time for the filters would be three hours,

the

Technical Specifications

requirement

cannot

be met and the

design and/or procedure is inadequate.

Additional analysis

was performed which showed that if the

abnormal

conditions procedure

were changed to require shut off

of the ventilation air drawn through these filters, the time

until changeout

was required would be increased

to

approximately 6.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

However, the potential

adverse

effects of this mode of operation,

such

as infiltration of ash

into the rooms,

had not been fully analyzed.

No Anal sis of Oil Bath Combustion Air Filters for Ash Fall

The licensee

had

no analysis

which documented

the ability of

the Division 1 and Division.2 oil bath combustion air filters

to function for the design basis

ash fall event with the

temporary prefi lters in place.

This analysis

was performed

during the inspection

showing their adequacy,

but it .was not

verified or approved at the close of the inspection.

Inade uate

Abnormal

0 eratin

Procedure

The Design Basis

Ash Fallout Procedure,

4. 12.4.5,

requires that

if the diesel

generators

are not required for operations (it is

not clear what plant condition this refers to), the operator

is'o

manually adjust

two ventilation

dampers

in each diesel

generator

room "so that approximately

2000

CFM of outside air

is drawn through the filter bank to insure pressurization

of

the room."

However,

no provisions are

made for the operator to

accomplish this task;

the damper positions

are not pre-marked

and there is

no instrumentation

which would facilitate this

action.

As written, the filters will load

up faster than they

can

be changed

and ventilation air flow cannot

be adjusted

as

required

by procedure.

No Documentation of Filter Structural

Ade uac

The mountings for the temporary filters are permanently

installed grid type frameworks.

They are installed in the

reverse direction from the normal position

recommended

by the

manufacturer.

That is, the flow induced

dp tends to unseat

rather than seat the filters, potentially allowing some blowby

of the ash,

and the 24 inch by 24 inch cardboard filter frames

are supported at four points

by the attachment clips rather

than uniformly around the filter periphery.

The licensee

had

no documentation that the filters are structurally adequate

with this configuration to sustain

the differential pressure

they would experience

at loaded conditions.

The licensee

contacted

the vendor

and received verbal

assurance

that the

filters were structurally adequate

and

a commitment by the

vendor to provide written documentation to that effect.

No Testin

of Tem orar

Filter Arran ement

The licensee

had performed

no testing of the diesel

generator

systems with the ash fall temporary filters installed or trial

fittings of the filters.

Such testing would have the potential

15

to reveal difficulties with installation,

time required to

perform installation,

engine performance

problems associated

with higher inlet differential pressure,

HVAC adjustments

required for higher inlet differential pressure,

etc.

Other Ash Fal 1 Filters

Abnormal Conditions Procedure

4.12.4.5,

Design Basis

Ash

Fallout requires that temporary filters such

as at the diesel

generator air intakes

be installed at 19 other locations in the

plant.

In further discussion with the licensee, it was learned

that,

as with the diesel

generator filters, no analyses

have

been performed for the design basis

ash fall event or the

design basis

dust storm for these other locations.

(either

have there

been

any preoperational

tests

performed with the

filters in place or any trial fitups.

Considering that at

these other locations,

the filters serve purely ventilation

functions,

which at the diesel

generator

location produced

unacceptable filter changeout

times, it is expected that the

same results

may be found at these

other locations.

The licensee

was asked

how many of the temporary filters of the

size required

by the diesel

generator

were maintained onsite.

The reply was

666.

Per the procedure,

404 are required for the

initial loading of diesel

generator

locations plus all the

other locations which, require this size filter.

Considering

the time to changeout that was calculated for the diesel

generator

location and the 20-hour duration of the event, it is

highly unlikely that when the changeouts

required for the other

locations

are finally calculated,

there are

enough filters to

last the duration of the event.

Another consideration

which may require the licensee's

attention is the manpower to effect the required.changeouts.

Considering what the probable

changout rate will be for all of

the filters and the time required to effect a changeout of any

one of them, it would appear to be unreasonable

to expect that

they all could be changed

out as fast as they would load

up

with the manpower resources

that would likely be available.

Additionally, with a design basis

ash fallout event occurring,

these

resources

could not be augmented

by outside resources.

Overall, the licensee's

entire program for handling the design

basis

ash fall event

was found to be poor.

The design

does not

appear

to be well thought out.

The operating procedure is

unrealistic,

untested

by walkthroughs,

and apparently

unable to

be performed in certain areas.

No preoperational

testing

was

performed

on the system,

and insufficient resources

appears

to

be available onsite to carry out the design intent of the

system.

This is considered

by the team to be

a major

example

of lack of coordination

between

the various facets of the

licensee

s organization-Engineering,

Operations,

Maintenance,

and guality Assurance.

Items (1) through (7) above

remain

16

unresolved

pending additional evaluation

by the licensee

and

NRR (50-397/87-19-09).

Overdue Maintenance

on Permanent Filters

Cleaning of the permanently installed oil bath combustion air

filters is currently controlled by the plant's

Scheduled

Maintenance

System

(SMS),

a computerized

scheduling

and

tracking system.

The filters are currently on

a 52-week

cleaning cycle.

At the time of the inspection,

the filter for

the Division 3 engines

was past

due for its required cleaning.

When asked

why the maintenance

had been deferred,

the licensee

responded

that

a plant outage

was required to perform this

work.

The team considers this to be questionable

for two

reasons:

(1) the filters can apparently

be cleaned

when the

plant is in operation

by taking one diesel at

a time out of

service while the plant is in an

LCO action statement,

and (2)

an outage

has occurred since the maintenance

was due.

In further investigation of this situation,

the licensee

was

asked

how it is determined, i.e.,

by what criteria, that

scheduled

maintenance

on safety-related

equipment is acceptable

to, be defer red.

The licensee

replied that the decision is made

at the discretion of the maintenance

supervisor.

The licensee

was asked

how such deferred

maintenance

is tracked.

The reply

was,

through the

SMS system.

The licensee

was then asked,

what

ensures

that maintenance. is not deferred for an inordinate

period of time.

The reply was that it is deferred at the

judgment of the maintenance

planner/supervisor.

It was

acknowledged that there are

no proceduralized

safeguards

to

ensure that deferred

maintenance

on safety-related

equipment

receives

adequate

formal evaluation

and control of

rescheduling.

The team feels that this is

a weakness

in the

plant's

maintenance

program which has the potential to

negatively affect plant safety.

This is an open item

(50-397/87-19-10).

Nitro en Tank Threat

To Diesel Generators

During normal operation of the plant, the primary containment

is inerted with gaseous

nitrogen to prevent

an explosion of

hydrogen which may result from an

LOCA.

This nitrogen is

supplied

from an approximately 11,000 gallon liquid nitrogen

storage

tank located at the southeast

corner of the diesel

generator building.

This is a nonsafety-related

system

and was

not originally designed to withstand the effects of natural

phenomenal

such

as earthquake

or tornado.

Were the tank to be

ruptured

due to being toppled over by an earthquake

or tornado

or due to being struck by a tornado

gener ated missile, its

contents

could be spilled

on the ground in close proximity to

the diesel

generator air intakes.

Since liquid nitrogen must

be kept at cryogenic temperatures

to remain liquid, it would

very quickly vaporize, potentially starving the diesel

generator

intakes of oxygen.

It is also of some concern what

17

negative effects the sudden dramatic

change in environmental

temperature

might have

on the engines.

(10)

This event scenario

could occur coincident with an

LOCA or

during normal operation

when the diesel

generators

may

automatically start in response

to a loss of offsite power

which would also

be likely to occur as

a result of an

earthquake

or tornado.

Although the licensee

could produce

no analyses

to refute this

accident scenario,

analyses

were initiated during the

inspection.

This is an open item (50-397/87-19-11).

Diesel Generator

Fuel

Su

1

Technical Specification 3.8. 1. 1.6.2 requires that the Division

1 and Division 2 diesel

generators

have

minimum of 53,000

gallons of fuel in their respective

main fuel oil storage

tanks

at all times the plant is in mode 1,

2 or 3.

Per

FSAR Section

9.5.4.3,

the minimum storage

capacity is sufficient for 7 days.

This is consistent with the requirements

of Regulatory

Guide

1. 137, which requires that fuel oil storage

capacity

be

calculated

based

on assuming

the diesel

generator

operates

continuously for 7 days at its rated capacity or based

on the

time-dependent

post

LOCA load.

The capacity at WNP-2 was apparently

based

on

7 days operation

at rated capability as per Burns

and

Roe calculation

number

5.43.02.

This calculation is based

on the actual

fuel

consumption rates at rated

load that were observed

during the

engines'uel

consumption tests.

The number

one engine rate

was

5. 10 gallons/minute,

or 51,408 gallons for 7 days.

The

number two engine rate

was 5.4039 gallons/minute

or 54,437

gallons for 7 days.

Therefore,

the Technical Specification

minimum storage

requirement for the number

2 engine is not

consistent with the regulatory guide or the

FSAR statement.

This inconsistency

is not a violation of requirements,

per se,

since (1) the licensee is not committed to Regulatory

Guide

1. 137 and (2) if the licensee

were to calculate

the fuel

requirement

based

on time-dependent

load profile, it would

almost certainly be less than 53,000 gallons.

However, it is

an inconsistency

which has the potential to confuse the

operator or engineer

using this information.

An additional factor which may generate

operator confusion is

the inconsistency

in units of measure

used in determining the

actual

amounts of fuel in the main storage

tanks.

The

Technical Specifications

require 53,000 gallons.

Annunciator

procedures

4.800.C1-9. 1 and 4.800.C5-9. 1 for the tank low level

alarms indicate the set points at 81K (this is consistent with

the local gage)

~

The sounding devices at the tanks

(a steel

tape

and

a rod) are graduated

in feet and inches.

There are

no

correlations

in the Technical Specifications

or the annunciator

18

procedures

between

any of these.

Additionally, the 81K value

in the annunciator

procedure

is subject to misinterpretation,

to wit, 81K of tank volume,

81K of tank level, or 83% of the

instrument

range.

This observation

would call into question

the consistency

of values with which the operator

must deal

which are contained in other operating procedures.

Subsequent

to completion of the inspection,

the licensee

determined that misinterpretation of tank measurement

parameters

had resulted in errors in the licensee

procedures

for determining diesel

generator

tank fuel oil capacities.

As

a result,

the licensee

determined that the minimum fuel oil

limits specified in plant Technical Specifications

had not been

maintained

on several

instances.

The specific discrepancies

are described

in licensee

LER 87-026.

This is an apparent

violation of Technical Specification

requirements

(50-397/87-19-12).

(11) Diesel

Fuel Oil Loadin

The inspector walked through the method

used to fill the diesel

fuel oil storage

tanks with emphasis

on methods of preventing

inadvertent contamination (introduction of foreign material).

The review included procedures

PPM 7.4.8. 1. 1.2.3,

"Diesel

Generator

Fuel Test,"

and

PPM 12.5.21,

"Diesel Fuel."

These

procedures

specified requirements

for sampling the

storage

tank periodically and fuel shipments prior to

transferring the contents to the storage

tanks.

The parameters

to be analyzed

and their specifications

are listed in the

procedure.

The method of sampling is not specified in the

procedure

but standard practice is to use

a sampling

bomb which

opens at the bottom of the tank.

There is no procedure

which

specifies

the method of connecting

and transferring the diesel

fuel shipment to the storage

tanks

and there is

no guality

Assurance

involvement.

The inspector also noted that the locks

on the fuel oil fill

connections

are ineffective because

the screwed fitting just

below the lock can

be disconnected

with the pipe wrench stored

at the station.

This fitting is, according to the operators

present,

the connection

used to connect the shipment to the

fill line.

This is an open item (50-397/87-19-13).

Instrument Set oint Calculations'nd

Methodolo

The team reviewed the setpoint calculation methodology

used at WNP-2

for safety-related

instruments.

The methodology

used to determine

instrument

loop inaccuracy is required by NRC Regulatory Guides

1. 105 and 1.89, to take into account

any inaccuracies

resulting from

normal plant operation

as well as those inaccuracies

resulting

from

LOCA, HELB, seismic,

and radiation exposure effects.

The General

19

Electric

BWR setpoint methodology,

as

shown in specification

22A5261

and licensing topical report NEDC-31336, considered

only normal

plant conditions

and did not take into account the effect of harsh

environment conditions.

Burns

and

Roe setpoint calculations

also

did not take into account

harsh

environment

or seismic effects

on

instrument accuracy.

WNP-2 environmental qualification evaluations

did not apparently

combine

normal operation

and accident environment

effects.

Pressure

switches

LPCS-PS-1

and -9, used for the automatic

depr essurization

system

AC inter lock permissive,

were selected for

detailed

review.

These

switches

have

a Technical Specification

inaccuracy limit of 8 percent of full scale.

The normal operation

inaccuracy calculated

by General Electric was 4 percent of full

scale,

and the environmental effect inaccuracy calculated

by WPPSS

was estimated to be 3.44 percent of full scale.

These results

had

not been

combined,

nor had seismic effects

been evaluated.

Algebraic

summing of these results for these particular

instruments

appears

to

leave very little margin with respect to Technical Specification

limits.

This item remains

unresolved,

pending additional evaluation

by the

licensee

of the combined effects of normal operation with

environmental

and seismic considerations

on setpoint methodology

(50-397/87-19-14).

h

Desi

n Verification Criteria in Procedure

EI 2.15 Revision 4

ANSI N45.2.11 requires that safety-related

calculations

be design

verified to assure

design

adequacy.

In Revision

4 of WNP-2

procedure

EI 2. 15, the criteria used the phrase "significant affect"

to determine

whether

design verification was required or not;

however,

no definition was provided for "significant" to provide

guidance for implementation

by the engineer.

The team reviewed

a

number of WNP-2 safety-related

and nonsafety-related

calculations

and found that each

had

been verified.

During the inspection,

WPPSS

issued

Revision

5 of this procedure

which eliminated the phrase

"significant affect" from the design verification criteria.

This

action was satisfactory to resolve this concern.

Incor rect Desi

n Documents

Several

examples

were discovered

where the actual physical

configuration of plant structures,

systems,

or components

were not

in accordance

with the most current design

documents.

Examples:

(1)

Drawings M852, Revision 12,

shows

a floor drain located in the

HPCS Diesel

Fuel Oil Day Tank

Room.

This drain does not exist

in the plant.

(2)

Drawing M512, Sheet

1, Revision 3,

shows the piping inboard of

the Fill Isolation Valve on Diesel Oil Storage

Tank ¹2 as

20

Seismic Category II and the piping outboard

as Seismic Category

I.

The reverse is actually the case.

(3)

Drawing M512, Sheets

2 and 3, Revision 1,

shows valves

DO-RV-4A1 and DO-RV-4Bl respectively

as relief, valves.

In

fact, they are spring loaded check valves.

(4)

Pressure

switches

DLO-PS-4A1, 4A2, 4B1 and 4B2 shown

on

drawings

M512, Sheet

2, Revision 1,

and M512, Sheet

3, Revision

1, respectively,

are labeled

as

L.O. circulating pump low

pressure

alarms.

They cannot perform this function since they

are isolated

from the circulating pump discharge

by a check

valve.

Therefore,

the labeling is incorrect.

Additionally,

these

pressure

switches

have

been deactivated,

and this is not

noted

on the drawings.

(5)

Check Valves

DSA-V-37A1 and 37A2,

shown

on drawing N512,

Sheet

2, Revision 1;

and DSA-V-37B1 and

37B2 shown

on drawing N512,

Sheet

3, Revision 1, are

shown backwards

from the required

direction of flow.

The actual installations of the valves

appear

correct.

(6)

Check valves

DO-V-53Al and DO-V-53A2 and associated

lines,

indicated

on drawing M512, Sheet

2, Revision 2, are not

installed.

(7)

Several

Restricting Orifices R0-3A-l, R0-4A-l, R0-3A-2,

and

RO-4A-2 and associated

lines, indicated

on drawing N512,

Sheet

2, Revision 2, are not installed.

Restricting Orifices R0-3B1,

R0-4B-1,

R0-3B-2,

and

RO-4B-2 and associated

lines, indicated

on drawing M512, Sheet

3, Revision 2, are not installed.

The above

examples

note

a lack of design control

and attention to

detail in that the licensee

has failed to correct or keep current

diesel

generator

flow diagram

M512. If the basic design

documents

for the plant do not accurately reflect the actual plant

configuration,

then they cannot

be relied upon by operations

and

engineering

personnel

in the performance of their respective

functions, or if they are relied upon,

can foster errors in plant

operations

or subsequent

engineering.

This item remains

unresolved,

pending additional

licensee

evaluation of the failure of design

documents

to accurately reflect actual plant configuration.

(50-397/87-19-15).

j.

Procedural

Control Over Use of ADS Inhibit Switch

For

FSAR Chapter

15 design basis

events,

the operator

has the

capability to prevent the opening of the

ADS valves

by pressing

a

timer reset pushbutton

in the control

room at 90 to 105 second

intervals.

A two position inhibit switch was

added to the control

room panel

by DCP-85-0073-OA for the purpose of preventing

ADS

operation for the anticipated transient without scram

(ATWS) event.

For this unlikely event where failure of the control

rods to insert

into the reactor core is postulated,

the operator is required to

21

inhibit ADS actuation in order to prevent dilution of the sodium

pentaborate

solution injected into the reactor core by the standby

liquid control system.

WNP-2 procedure

5. 1. 1,

"RPV Level Control," was modified in

mid-1985, but placed

no constraints

on the

use of the two position

ADS inhibit switch.

The

ADS inhibit switch,

when activated,

prevents

ADS operation which may be required for small break

LOCA

events,

and reduces

the availability and reliability of the

ADS

safety function.

The WNP-2 procedure

should

have designated

use of

the timer reset pushbutton for design basis

events

and constrained

any use of the

ADS inhibit switch to only the

ATWS event.

Potential

use of the

ADS inhibit switch, in lieu of the timer

pushbutton

switch, is safety significant in that it reduces

the

availability and reliability of the

ADS toward performing its

ECCS

safety function.

This item remains

unresolved,

pending additional

licensee

evaluation of requirements

for constraints

on use of the

ADS inhibit switch (50-397/87-19-16).

k.

ADS Backu

Nitro en

Su

1

Discre ancies

Several

discrepancies

were noted by the team with the safety-related

backup nitrogen supply system for the automatic depressurization

valves.

This system is required to provide

a 30-day supply of

nitrogen to operate

the

ADS valves in the event of failure of the

nonsafety-related

normal nitrogen supply.

It is also designed

to

provide the ability to replenish the backup supply from a remote

location that is accessible

post-LOCA.

(1)

Bottle

Ca acit

Not Per

FSAR

FSAR, Section 9.3. 1.2.2, states that the

ADS backup nitrogen

bottles

have sufficient capacity to provide

a 30-day supply

using conservative

leakage

estimates

and considering

48 cycles

of the

ADS valves.

WPPSS calculation 5.46.05; Revision 1, dated August 28, 1984,

shows that with a 30-day supply in the bottles,

only 18

ADS

valve cycles

can

be performed.

The source of this error was determined to be

a Technical

Specification

change that was

made early in the plant life to

reduce the minimum required

backup bottle pressure

from 2490

psig to 2200 psig.

No attendant

change

was

made in the

FSAR.

The design basis for the original 48 cycle. requirement

could

not be produced

by the licensee.

However,

an argument

was

made

that considering the worst case

long-term function the

ADS

valves

must perform, i.e., provide an alternate

shutdown

cooling section of flowpath, the 18 cycles would be adequate.

This argument will be presented

in support of the

FSAR change

the licensee

intends to make.

22

It should also

be noted that the

number

of cycles addressed

in

the

FSAR is the number of individual

ADS valve openings

rather

the number of times all of the valves

can

be cycled.

The

current

FSAR wording is not clear

on this point and can easily

be misinterpreted.

This item remains

unresolved,

pending

additional licensee

evaluation (50-397/87-19-17).

Time Avai 1 abl e for Bottle Chan cput

The backup nitrogen system for the

ADS valves

has

two divisions

with each division having two sources

of nitrogen.

The primary

.

source is

a bank of bottles containing the 30-day supply and

located in the reactor building.

The secondary

source is a

station located in the diesel

generator building hallway where

one bottle for each division is located

and other bottles

can

be connected.

This station

can

be manually placed into service

whenever the primary source is exhausted.

Its location allows

operation

when the reactor building may be inaccessible

post-LOCA.

Warning that the primary source pressure

is approaching

the

critically low stage is provided by a low header

pressure

alarm.

Burns and

Roe calculation

number 5.46.05,

Revision 1,

dated

September

3, 1982,

was generated

to determine

the time

available

from receipt of the alarm until the

ADS valves would

begin to close

and therefore the time available to valve in the

secondary bottles.

It addressed

the situations

where the

valves would require

one cycle open for each valve after the

alarm and where the valves would only require being held open.

The results

were

54 and

57 minutes for the

A and

B divisions

respectively for the

one cycle scenario

and 3.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

and 3.97

hours for,the held open scenario.

In generating this calculation,

Burns

and

Roe

used

two

apparently incorrect non-conservative

design inputs.

A Drywell

temperature

of 200

F was

used whereas for the small break

LOCA

for which this system is required,

the temperature

given by

FSAR is 340

F.

The second error was the

use of 75 psid as the

minimum differential pressure

required to operate

the

ADS valve

operation piston.

The vendor manual for the valves

(Crosby

manual

VPF6115-18 (1) states

the minimum required differential

pressure

as

88 psig.

The effect of these errors would be to

lower the actual

response

time available.

The current annunicator

response

procedure for the low pressure

alarm have

no indication to the operator

of the time available

to put the secondary

supply in service after the alarm is

received.

Since this time may be very short, the team

considers this to be

a significant weakness

in the procedures.

This item remains

unresolved,

pending additional evaluation

by

the licensee

(50-397/87-19-18).

Bottle Installation Not Per Desi

n Drawin

23

The design of the racks to seismically restrain the backup

nitrogen bottles for the

ADS valves is shown

on MNP-2 drawing

FSK-346, Revision 3, dated

June

18,

1983.

Note

6 on this

drawing requires that shims

be placed

under the bottles

as

required depending

on the individual bottle height to achieve

a

snug fit between

the top of the bottle and the collar of the

rack.

These

shims

had not been installed for any of the

bottles for either the primary or secondary

stations in both

divisions.

As a result, all of the bottles were free to move

around in the collars during a seismic event, potentially

causing failure of the bottles and/or the rack.

At the conclusion of the inspection,

the licensee

had initiated

a design

change to the restraining

system for the bottles

because

the licensee felt that the existing design

was not

"user friendly" for maintenance

personnel

who perform the

bottle replacements.

In addition to their not being installed in accordance

with the

design drawing, the racks were also assembled

in a very

careless

manner.

Bottles were missing,

nuts were missing,

and

when they were present,

they were not even

assembled

hand tight

in most cases.

-The fai lure to install the backup nitrogen bottles in

accordance

with the design

drawings is an apparent violation of

10 CFR 50 Appendix B, Criterion V (50-397/87-19-19).

3.

Maintenance

and Surveillance

The team reviewed maintenance

and surveillance activities associated

with

the systems

under review by the team.

The results of this review are

summarized

below:

a e

Batter

Surveillance

Testin

The licensee

uses

24 VDC, 125

VDC and 250

VDC batteries

to supply

Division 1 and

2 vital D.C. electrical

power.

In addition the

licensee

uses

a 125

VDC battery to supply division three vital D.C.

electrical

power.

Technical Specification 4.8.2. 1 lists weekly,

quarterly,

once per 18 months,

and once per 60 months surveillance

requirements.

The weekly and quarterly surveillances

require

battery inspections.

The

18 month test requires

the verification

that the battery capacity is adequate

to supply

a

dummy load,

based

on the battery design criteria, while maintaining the battery

terminal voltage greater

than or equal to a specified

minimum

voltage.

The 60 month test requires

the verification that the

battery capacity is at least

80K of the manufacturer's

rating by

subjecting the battery to a performance

discharge test.

The team reviewed the licensee's

surveillance

procedures

against the

Technical Specification

requirements

and

had the following findings:

The team observed that the battery load profiles contained in

the Division 1 and

2 125 Volt 18 month battery surveillance

tests did not agree with the latest calculations

(2.05.01)

or

the

FSAR Load Tables.

This discrepancy

had already

been

identified by the licensee prior to this inspection

and

had

been

documented

in Nonconformance

Report

(NCR-237-013 (1/7/87),

however this discrepancy

was not resolved prior to the latest

outage battery testing,

prompting the

60 month performance test

to be substituted

for the 18 month service. test.

The battery capacity is affected

by electrolyte temperature.

Capacity decreases

with decreasing

temperature

and increases

with increased

temperature.

Batteries

are rated

by the

manufacturer at 77'F and will lose approximately

llew capacity

at 60 F; the minimum temperature

permitted for the

WNP-2

batteries

by the technical specifications.

Likewise a battery

would gain approximately

9X capacity. at the WNP-2 maximum

permitted temperature

of 100

F.

The team observed that the 18

month service test disregards

any effect that electrolyte

temperature

during the test would have

on the apparent

capability of the battery to meet the technical specification

requirement to demonstrate

the battery's ability to maintain

the emergency

loads operable.

With no regard to the

electrolyte temperature

existing at the start of the test,

no

judgement

can

be

made from the results of the service test to

state whether or not the battery is satisfactory for its design

requirements

which includes operating the emergency

loads at

the minimum permissible cell temperature.

The chart recorder

used in the test device for the

18 and

60

month survei llances

was scaled

such that voltage

changes

could

not be accurately

determined.

As a result of the battery surveillance test deficiencies listed

above,

the

18 month service tests

performed in 1986 failed to

demonstrate

the capability of the batteries

to meet design

requirements.

This item remains

unresolved,

pending additional

licensee

evaluation

(50-397/87-19-20).

The team observed that

a temperature

monitor exists for the safety

related battery rooms.

The team determined that the operating

temperature

range for the Class lE battery

rooms

was

65 to 100

degrees

F.

Burns and

Roe calculation 5.52.084

sheet

58 calculated

only a high temperature

alarm setpoint at 100 degrees

F.

No low

temperature limit was established

even though the batteries

may

begin to lose

a significant portion of its capacity at approximately

60 degrees

F.

WPPSS subsequently

revised procedure

PPM 7:0.0 on

September

2nd to add local temperature criteria of greater

than

65

and less

than 104 degrees

F for shift monitoring of each of the

three battery

rooms,

and provided

an action statement

to restore

the

room temperature within these limits by immediate corrective action.

These

added procedural

controls satisfy this concern.

b.

Thermal Overload Testin

25

Technical Specification 4.8.4.3 requires that thermal

overload

protection devices for valves listed in Table 3.8.4.3-1

be

demonstrated

operable at least

once per 18 months

by the performance

of a channel calibration of at least

25K of all thermal

over loads

for the required valves.

The licensee

has

used oversized

thermal

overloads

so that during accident conditions the thermal

overload

protection will not prevent safety-related

valves

from performing

their function.

This is consistent with Regulatory Guide 1. 106;

"Thermal Overload Protection for Electric Motors on Motor Operated

Valves," Revision 1, March 1977.

Procedures

7.4.8.4.3. 1 through .4

establish testing for the four groups of valves.

The team reviewed these, procedures

and test results

from three

groups of valves

and

made the following findings:

For

Group Four thermal overloads,

tested

in 1985, the test

current prescribed

by the procedure

did not match the time to

trip criteria specified

by the manufacturer.

For

Group Four thermal overloads,

maintenance

personnel

recognized that five thermal

overloads installed did not match

the size listed'n the procedure.

In all cases,

maintenance

adjusted

the test current without appropriate

review.

In two

cases

the test current did not match the time to trip criteria.

For Group

Two thermal overloads,

tested

in May, 1987, revisions

made to the procedure

in accordance

with the deviation

procedure,

1.2.3,

changed five thermal

over load heater sizes,

but did not change

corresponding test currents

used in the

surveillance

procedure.

For Group

Two and Three thermal overloads,

in four cases

the

test currents

prescribed

by the procedure

did not match the

time to trip criteria specified

by the manufacturer.

Thermal overload relay trip time is current dependent.

To test

thermal

overloads

the procedure

should establish

a current

and

a

corresponding

minimum time to trip criteria.

Group 4 thermal

overloads,

tested

in 1985,

were the first overloads tested

by the

licensee.

Due to calculational errors,

most group 4 valves were

tested at approximately

275K of the full-load motor current

specified

by the vendor.

This corresponds

to a time to minimum trip

of approximately

50 seconds.

The licensee's

procedures

specify 40

seconds

which corresponds

to 300K of full-load motor current.

A

review of the data taken during the 1985 testing

shows that none of

the overloads tested at 275K tripped quicker than

50 seconds,

indicating they performed

as designed,

however this is an example of

an inadequate

procedure.

A review of the group four test results

shows that in five cases

maintenance

personnel

identified heaters

of sizes different from

that specified in the procedure.

In all five cases

the maintenance

personnel

tested

the overloads at a current other than that

specified in the procedure.

The test current

used

and the as

found

26

heater

sizes

were noted by those performing the test in the comments

section of the procedure.

In two cases,

for valves

RCC-V-6 and

RHR-V-3A, the cur rent used did not correspond

to the minimum trip

time criteria specified in the procedure.

In these

two cases,

test

data

shows that the thermal

overloads

performed

as designed.

However,

changing thermal

overload test currents is an example of

maintenance

personnel

making

a procedure

revision without the

appropriate

review.

In March 1986, revision

1 to the thermal overload procedures

for all

groups

was issued.

The team reviewed the group four procedure

revision and noted that the five overloads

mentioned in the previous

paragraph

were not revised to reflect the hardware installed.

In

addition, the testing current was changed

from 275K of full load

motor current to 375K of the nominal trip current.

However, the

time to trip criteria remained at 40 seconds.

The appropriate

minimum time to trip for the revised test current was

22 seconds.

This revised procedure

was never

used.

Prior to the testing of group two and three thermal overloads,

the

minimum time to trip criteria was recognized to be in error and

revised to 22 seconds.

In addition, for both groups,

thermal

overload sizes in the procedures

were compared to the sizes in

licensee

drawings

and revised accordingly.

For five group two

thermal

overloads

the corresponding test currents

were not revised.

Of the five thermal overloads,

there are two outlying examples.

In

the first, valve RRC-V-16A was originally listed in procedure

7.4.8.4.3.2

as having G30T45 thermal overloads,

requiring a test

cur rent of 60 amps.

The revision to the procedure

changed

the

thermal

overloads to size G30Tll.

Although the test current

was not

changed,

the correct current for G30Tll overloads

corresponding

to a

minimum time to trip of 22 seconds

is 1.9 amps.

Test results

indicate that the three thermal

overloads tripped between

35.3 and

42.4 seconds.

Had 60 amps

been applied across

a G30Tll heater for

35.3

seconds it would have burned out.

The inspector

observed that

G30Tll heaters

were installed for valve RRC-V-16A and that there

was

no evidence that the heaters

had burned out.

In the second

example,

valve SW-V-24 was originally listed as having

G30T21 heaters,

requiring

a test current of 5.4 amps.

The procedure

revision changed the heaters

to size

G30T26 which require 8.7

amps

to have

a minimum trip time of 22 seconds.

Again, the trip current

was not changed.

According to the vendor drawings, at 5 '

amps

one

would expect

a minimum time to trip of approximately

80 seconds.

. Test results indicate that the three thermal

overloads tripped

between

40.6 and 50.0 seconds.

The inspector observed that G30T26

heaters

were installed for valve SW-V-24A.

This indicates that if

the three overloads

had been tested, in accordance

with the

procedure, all three tripped faster

than design.

On August 28,

1987,

the licensee

tested

the thermal

overloads for SW-V-24A and

found them to operate appropriately.

27

In addition to the previously mentioned procedural

inaccuracies,

the

inspector

found four examples of group two and three overloads test

currents

inappropriate for the heater size were specified

by the

procedure.

All four examples

were in the conservative direction so

there

was

no question of thermal overload operability.

Finally, although deviations existed for group two and three

testing,

at the time of the inspection

no deviations

had been issued

for group

one

and group four.

In addition

no document

was presented

tracking the future revision to group

one

and four based

on the

errors

found in group two and three procedures.

Had changes

been

made in accordance

with the methods

used to revise the group three

procedure,

the errors in the testing of group two overloads wouldn'

have

happened.

The inadequacy of procedures

7.4.8.4.3.2,

3,

and 4 is an apparent

violation of Technical Specification 6.8. 1 (50-397/87-19-21).

Failure to properly implement changes

to procedures

7. 4.8.4. 3. 2 and

. 4 is an apparent violation of Technical Specification

6. 8. 3

(50-397/87-19-22).

Loss of Offsite Power Testin

The inspector

reviewed the licensee's

surveillance

procedures

corresponding

to the Technical Specification requirements

to verify

the transfer

between

the offsite transmission

network and the onsite

Class

lE distribution system.

Specifically, the inspector reviewed

procedure 7.4.8. 1. 1, "18 month manual

and auto transfer test,

startup to backup station power," corresponding

to Technical Specification 4.8. 1. l.l.b, procedure 7.4.8. 1. 1.2.5,

"Standby Diesel

Generator

Loss of Power Test (Divisions 1 and 2)," corresponding

to

portions of Technical Specification 4.8. l. 1.2.e,

and procedure

7.4.8. 1. 1.2.7,

"Standby Diesel Generator

LOCA Test (Divisions 1 and

2)" corresponding

to portions of Technical Specification 4.8. 1. 1.2.e.

The following findings were

made:

Procedure

7.4.8. 1. 1.2.5 did not specify which breakers

open

on

vital bus undervoltage.

Procedure

7.4.8. 1. l. 1.2 did not require the functional testing

of the backup transformer.

Division One and

Two bus primary undervoltages initiate a two second

time delay relay.

The time delay relay initiates,

among other

things,

load shedding.

Seven breakers

on three separate

buses

are

opened

on load shedding.

Procedure

7.4.8. 1. 1.2.5 states,

"verify

that... loads are

shed

from the bus."

Technical Specification 4.8. 1. 1.2.e.4.a)l)

requires that verification be

made of load

shedding

from the buses.

Although the procedure

quotes

the

technical specification,

the lack of a verification of specific

breakers

opening is a weakness

since

upon load shedding

not all

breakers off the main 4

KV vital buses

open nor are all breakers

that open off the main 4

KV buses

(SM-7 and SM-8).

The

28

inspector discussed

this weakness

with the engineer

responsible for

the procedure

who committed to address it prior to performing the

test during the next outage.

The second

weakness

identified was the lack of a full functional

test of the backup offsite power source for the 4

KV vital buses.

At

the time of inspection it was apparent that the backup offsite power

source,

and specifically the backup power transformer

TR-B, was only

being functionally tested

to a fraction of its design

load

requirements.

TR-B supplies

both main 4KV vital buses

SM-7 and.

SN-8.

Procedure

7.4.8. 1. 1. 1.2 Revision 3, tests

the transfer from

startup

power to TR-B.

Prior to the test, all rotating equipment

with redundant

equipment available

on the bus not tested

are shut

down and the redundant

equipment started.

During the test,

TR-B is

only loaded with the non-shed

loads of one bus excluding those

mentioned

above.

The licensee

should evaluate

the

need for

increased

functional testing of TR-B.

This is an .open item (50-397/87-19-23).

Functional

Test and Calibration of Time Dela

Rela

s

Time delay relays

are

used in a number of safety-related

control

circuits.

These safety-related

Class lE components

are not usually

explicitly identified in Technical Specifications;

nevertheless,

they are required to have design basis setpoint calculation values

and to be periodically tested

and calibrated in accordance

with the

WNP-2 Chapter

7

FSAR commitments to IEEE Std. 279-1971

and

IEEE Std. 338-1975.

The team requested

both setpoint calculations

and

periodic test surveillance instructions for various time delay

relays in safety-related

systems,.but

was informed that

no such

documentation

existed.

For the majority of such time delay relays,

there

was

no indication that any periodic surveillance testing

had

been performed since the initial plant preoperational

tests

had been

completed.

During the inspection,

the licensee

provided

an April 19,

1985,

inter-office memorandum that identified 22 time delay relays in the

4KV switchgear requiring calibration.

There

was

no indication that

any other safety-related

time delay relays were subsequently

identified as being subject to periodic test

and calibration.

Seven

specific time delay relays

were selected

by the team to illustrate

this concern.

In each instance,

the

WNP-2 master

equipment list

correctly designated

these particular time delay relays

as Class

1E

devices,

but this information did not lead to the development of

appropriate

documentation.

These

examples

are:

(a)

SE-RLY-V/2A3 and 2A4, that provide

12 second

and 62 second

time

delay values to control the slow opening of the service water

pump discharge

valve to minimize water

hammer effects.

(b)

SGT-RLY-TK/2Al and 2A2, that provide

a 30 second

time delay for

automatic start of the redundant

standby

gas treatment

system.

29

(c)

RHR-RLY-K54A, that provides

a 10 second

time delay for minimum

flow bypass for the

RHR pump.

(d)

RHR-RLY-K70A, that provides

a 5 second

time delay for starting

of the

RHR pump.

(e)

RHR-RLY-K93A, that provides

a 10 minute time delay before the

operator

can manipulate

RHR heat exchanger

valves after the

start of an accident.

Failure to provide instructions for the periodic calibration

and

testing of time delay relays is considered

an apparent violation

(50-397/87-19-24).

Service Water

S stem

The Service Water System

(SWS) provides cooling water to several

safety-grade

components

such

as the

HPCS Diesel

Engine,

1A Diesel

Engine,

and

RHR heat exchanger.

The team reviewed maintenance activities

on the

SMS.

During the

team inspection

walkdown of the

SWS,

an overhead

crane in service

water

pumphouse

1A was observed to have its block extended

such that

it could impact safety-related

conduit during

a seismic event.

The

license

has

no procedure

covering seismic control of lifting

equipment installed in safety-related

areas.

This is

a repeat

example of a similar concern raised in a previous inspection report

(86-33-01),

and remains

an open item (50-397/87-19-25).

Emer enc

Diesel Generators

EDG)

The emergency

diesel

generators

(EDGs) provide emergency

AC power in

case of loss of offsite AC power.

The team reviewed the maintenance

activities associated

with the

EDGs and the High Pressure

Core Spray

(HPCS) diesel

generator.

No deficiencies

were noted.

Missin

Hardware

on Safet

Related Valve

During a walkdown inspection of the Service Water System,

the

hardware for butterfly valve SW-V-165B was found to be broken off.

This valve is required to be operated to the open position to bypass

the spray ring and send the service water directly to the spray pond

whenever

pond temperature

is less

than

60OF or before outside

ambient temperature

can fall below 32 F.

Mithout the hardware in

place,

the operator

cannot operate

the valve without using

a wrench

or other improper tool.

Furthermore,

the operability of the valve

is questionable

considering

the possible

cause of the failure of the

handwheel.

The licensee

has initiated action to repair the valve.

Standb

Service Water

S stem Pool

Tem erature

Elements

The team reviewed the Standby Service

Water

System pool

temperature

elements installation to determine

the adequacy of

monitoring the Technical Specification Limits on pool temperature.

30

The review showed that the pool is generally about 14.5 feet deep

(overflow point to pool bottom), the bottom end of the two foot long

temperature

probe is one foot above the general

pool bottom and is

located

under the Standby Service Water building where the pool

depth is 26.5 feet.

Since the temperature

probe is located in the

service water flow path to the pump, the temperature

of the water

being supplied to the plant (system in service) is monitored

accurately.

The WNP-2 Technical Specifications

require the water

temperature

to be less

than 77~F.

Since the system is normally

secured,

the pool water is stagnant

and there will be

a temperature

gradient with the warmest water at the top of the water in the

general

pool area

and the coolest water under the Service Mater

building in the deepest part.

Since the Surveillance

Procedure

verifies that the temperature

at the temperature

probe is less

than

77 F,

and this temperature

may not be representative

of the overall

pond temperature,

this is an apparent violation of WNP-2 Technical

Specification Surveillance

Requirement

4. 7. l. 3 which requires

verification every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> that the ultimate heat sink water

temperature

is within its limit.

This item remains

unresolved,

pending additional

licensee

evaluation

(50-397/87-19-26).

During the above review,

the inspector

reviewed Design

Change

Package

(DCP) 86-0155-OA dated April 23,

1986.

The

DCP modified the

support for the temperature

element to facilitate maintenance.

On

page

4 of the

DCP,

Note 1 of the "Notes

on Installation" indicates

that the original design

showed perforations

in the pipe containing

the temperature

element,

but because

of the slow temperature

response

of the pool, these perforations

are

no longer needed.

There are no.calculations

or analysis

concerning time response

which

support

the determination that the perforations

are not necessary.

Further review of the

DCP drawings

shows that the perforations

were

not changed

and the licensee

does

not believe that the pipe

containing the perforations

was

removed.

This item remains

open

pending additional

licensee

action to provide

a basis for the note

(50-397/87-19-27).

Automatic

De ressurization

S stem

ADS

During the

ADS system walkdown, the inspection

team noted that

seismic restraints

were improperly restored

on the backup nitrogen

cylinders for ADS following nitrogen cylinder replacement.

The

licensee

has

no procedure

addressing

the requirements

for proper

cylinder replacement.

The nitrogen cylinders mounting brackets

were

not tight around the collars of the nitrogen cylinders,

nor were the

bolts

and nuts secured properly. It was determined

from the licensee

that they use training as the method for teaching their operators

the proper replacement

of the nitrogen cylinders.

The team

considered

that

a procedure

should

have

been

issued for nitrogen

cylinder replacement

to ensure

proper collar engagement

around the

nitrogen cylinders.

In addition, the team noted that temporary

scaffolding was noted

as being installed in the vicinity of the

backup nitrogen supply for ADS since

June

1987.

This scaffolding

was constructed

in accordance

with maintenance

procedure

10.2.53

which provides guidelines

and seismic requirements

for scaffolding

31

ladders,

tool gauge

boxes

and metal storage

cabinets.

The team

felt that the scaffolding was constructed correctly and was tagged

in accordance

with procedure

10.2.53

as required.

Thus, scaffolding

should

have

been

removed

upon completion of its intended function.

Multi le Features

of CIA Valves

Containment

Instrument Air (CIA) solenoid valves

CIA-V-39A and

39B

serve

as the safety-related

isolation valves

between

the

safety-related

and nonsafety-related

portions of the system.

Their

function is to close

upon loss of the nonsafety-related

N

bottles.

In July 1986,

CIA-V-39A was found to be inoperable during the

performance of surveillance

procedure T.S.S.7.4.5. 1.21.

NCR

286-0333

was generated

as

a result.

It was dispositioned

"use-as-is" with the reason

being given that check valve CIA-V-41A,

which is in series with CIA-V-39A, serves

as

an isolation valve and

provides sufficient isolation for the system.

This

NCR also took

credit for the normal

N2 inerting supply and the CIA compressors.

The team did not concur with this disposition for the following

reasons:

(1)

Per

values

given in the

FSAR (Section 9.3. 1.2.2), the maximum

allowable leakage rate for all components

of one branch of the

backup

N

supply is approximately

4 SCFH.

Therefore,

the

maximum allowable leakage

rate of the check value CIA-V-41A

must be less

than or equal to 4 SCFH.

Existing plant IST

procedures

do not verify the ability of these

valves to meet

this requirement.

Therefore,

a nondetectable

failure can

exist.

IEEE Standard

379-1977

on single failure states

"...identified nondetectable

failures shall

be assumed

to have

occurred."

(2)

Since the normal

N

supply and the CIA compressors

are

associated

with th3 nonsafety-related

portion of the system,

credit should not be taken for these.

Subsequent

to the immediate disposition,

the valve was cycled

manually until it would operate electrically.

However, after

sitting idle for several

minutes, it was again

found to be

inoperable electrically.

The valve was then disassembled

and

internal contamination

was found. It was then cleaned

and

reassembled.

The source of the internal contamination

was not

addressed

and

no action was taken to preclude repetition.

In June

1987, while performing the

same surveillance test,

both

valve CIA-V-39A and the

same valve in the opposite division,

CIA-V-39B, were found inoperable.

NCR 287-219

was written.

In

violation of Plant Problems

Procedure

1.3. 12, Section 1.2. 12.5, the

originator did not indicate that the

NCR was safety-related.

32

Section l. 3. 12. 5. E. 3 of the

same procedure

requires

the Plant

Technical

manager to check "yes" or "no" in the safety Significant

Block.

This block was incorrectly checked

"no" in violation of the

definition in Section 1.3. 12.2.C.

In spite of at least

one similar earlier fai lure of one of these

valves

and the simultaneous failure of both valves

(one in each

division) in an apparent

common

mode at this time, the licensee

performed

an inadequate

root cause

analysis

and

no appropriate

corrective action

as required

by the licensee's

procedure,

Section

1.3. 12.5.0.4

C and

D.

The valves were dissembled,

cleaned,

reassembled

and tested.

One of the immediate disposition actions called 'out on the June

1987

NCR was to "exercise the valve manually (through bottom hole vent)

until valve operates electrically."

This is an improper disposition

since it had been proven ineffective in the earlier

NCR,

and it

involved no action which could have defined the cause of the problem

or correct it. It could, at best,

only mask the problem.

Had the

valve been operated

successfully with manual

assistance,

there is

every reason to believe it would have

been put back into service

with no form of corrective action having been taken.

In July 1987, during

a plant shutdown,

the valves were tested

again,

and again they both failed.

At this point, the corrective action

was determined to be adding

a washer

under the valve operating

spring to increase

the closing force on the valve.

No

NCR was

written.

This is

a violation of the licensee's

procedure,

Section

1.3. 12.5.A. l.

Also, there is

no evidence that root cause analysis

was performed

on this event

as

r equired or had ever subsequently

been performed.

The above described

incidents

have significance

with respect to plant safety in that the operational

and leak tight

integrity of the solenoid valves in question

and their backup check

valves is vital to ensuring that the design basis

30-day

N2 supply

to the

ADS valves is indeed sufficient for 30 days.

The maximum

allowable leakage

rate to maintain

30 day's

supply is extremely low,

on the

same order

as containment isolation valves.

By the

licensee's

failure to define the root cause of the recurring

fai lures

and then the taking of appropriate corrective action to

preclude recurrence, it is reasonable

to expect that failure could

occur again.

Since the leakage rate of the check valves

has

never

been quantified, they can

be assumed

to leak more than the

allowable.

Therefore, it is reasonable

to conclude that with

failure of one of the solenoid valves in an

LOCA situation with loss

of the nonsafety-related

containment

instrument air supply, the

backup air supply would not be sufficient for 30 days.

Considering this, the

common

mode failures that occurred

on both

divisions

on two separate

occasions, constituted

the plant being "on

a condition that was outside the design basis of the plant..."

as

described

in 10 CFR 50.73.

The failure to identify, on multiple occasions,

nonconforming

conditions or,

when they were identified, the failure to evaluate,

33

analyze or disposition these conditions in accordance

with the

NCR

procedure

is considered

an apparent violation of 10 CFR 50 Appendix

B, Criterion V (50-397/87-19-28).

Instrument

Rack Terminations

Paragraph

8.3.1.3. 1, Class

IE Raceways,

Cables,

Equipment (Panels

and Racks), of the

FSAR identifies Instrument

Racks (IR) 67, 68,

and

69 as Class

IE.

DWG E538 W.O. 2808,

Sheets

20 and 21, note 2,

identifies IR-67, IR-68, and IR-69 as work being of equality Class

1.

Paragraph

3.2.4 (a), equality Assurance Classification, of the

FSAR

reads "...All equality Class

1 items meet the applicable provisions

of 10 CFR 50 Appendix B."

Paragraph

17. 1. 1.2 (c), Design Control

JAR-3, of the

FSAR establishes

a system of independent

reviews to

assure

applicable quality, regulatory code,

and design basis

requirements

are properly translated

into design

and procurement

documents for each structure,

system

and component.

The documented

review provides

a check for design

adequacy,

inspectability,

and

compatibility with intended

usage.

WNP-2 termination

and splicing

Instruction

No. 10.25.46 provides the direction and installation

details

required for all permanent electrical terminations.

During the inspection,

the team conducted

an evaluation of the

installation and design requirements

for low voltage

(600 or below)

terminations

and heat shrinking specifications

of plant

instrumentation wiring.

The results of the team's

evaluation is as

follows:

During plant tours,

an inspector walked

down portions of the

ADS Nitrogen Supply System where IR-67, IR-68, and IR-69 were

opened for observation of wiring installation.

The inspector

noted the following deficiencies:

~Crim in

IR-68 wire terminal

87 insulation was excessively

stripped

and subsequently

inserted

and crimped to the terminal lug

exposing its conductor at the end of the connector barrel

insulator.

Two wires were additionally found in IR-67 and

another wire in IR-69 was found revealing the

same

conditions

as stated

above.

Terminal

Lu s

Terminal wires 6,7 and 36,37 were spliced from terminal

wires

5 and 35, respectively.

Terminal wires

5 and 35 are

size

16 with a larger insulator covering whereas

terminal

wires 6,7 and 36,37 are size

16 with a much smaller

insulator.

The inspector. noted that the wire insulation

is not commensurable

with the size of the terminal

connectors

jacket.

Therefore,

terminal wires 6,7 and

36,37 connector

appear to be unacceptably

modified in

IR-69.

34

Cabinet H-13,

P631,

ADS Division 2 in the control

room was

also inspected for terminations.

Terminal wires B22-FBB,

10B, 14B,

16B,

25B, 29B,

33B, 35B,

and

37B each

had

an

additional wire whose

lugs were terminated

under

one

terminal

screw which were not installed back to back.

Terminal wires 36 and

37 were spliced to terminal wire 35

in IR-69., The heat shrinking tubing was improperly

installed over the splice

and subsequently

exposing

terminal wire 37 conductor

from the splice connection.

Failure to comply with station procedure

requirements

for proper

installation of electrical terminations is an apparent violation of

10 CFR 50, Appendix B, Criterion

V (50-397/87-19-29).

1.

Seismic Considerations

and Housekee

in

During the first week of onsite inspection,

an unsecured

tool box

and breaker truck were observed

in the safety related

SM7 switchgear

room.

These

are

heavy

and relatively easily moved items which could

damage

important safety equipment during a seismic event.

It

appeared

to the

team that these

items should

be stored elsewhere

or

properly secured.

During the second

week of onsite inspection,

the

team noted that the breaker truck and tool box had been

removed;

however,

the team again noted that ladders

were left stored in both

the

SM7 and

SM8 switchgear

rooms

and several

sets of disassembled

metal brackets

and mounting hardware

were piled in the corner of the

SM7 switchgear

room.

Licensee

procedure

10.2.53,

"Seismic Control

for Scaffolding,

Ladders,

Tool Gang

Boxes

and Metal Storage

Cabinets,"

provides specific requirements

for ensuring proper

seismic restraint of equipment in safety related areas.

The team noted that the licensee

was not providing adequate

attention to plant housekeeping.

The following deficiencies

were

observed:

(1)

Piles of disposable

absorbant

towels

and several

cardboard

boxes

were observed

in the

DG rooms.

This debris would

contribute to drain plugging in the event of fire system

actuation.

(2)

A pile of drawings

and papers,

a discarded

candy wrapper

and

several

pieces of loose wire were observed

on top of breaker

cubicles in the

SM8 switchgear

room.

(3)

Numerous cigarette butts

and

a cigarette

wrapper

were observed

within the

no smoking area adjacent to the diesel

generator

fuel oil tank fill manifold.

Licensee

procedure

1.3. 19, "Housekeeping",

provides specific

requirements

for proper cleanup of work areas

following maintenance

activities.

35

The above is considered

a violation of 10 CFR 50, Appendix 8,

Criterion

V (50-397/87-19-30).

m.

Im ro erl

Controlled Plant Modification

The team noted that the licensee

had installed temporary

foam

insulation filters on the ventilation louvers for the

4KV breakers

on safety related

SM7 switchgear.

These filters were not installed

using

a maintenance

order,

as required

by station procedures,

nor

was the modification properly reviewed

as required

by 10 CFR 50.59.

This is considered

a violation (50-397/87-19-31).

4.

Control

Room Observations

The team observed

operator activities in the control

room.

The operators

appeared

to

b'e knowledgeable

concerning their duties

and

responsibilities.

The control

room was free from unnecessary

distracting

activities.

The background

noise from the control

room ventilation

system is fairly high, but did not appear to interfere. with operator

response

to audible alarms

or communications.

The operators

were alert

to unusual

noise patterns

such

as

a malfunctioning chiller and

expeditiously corrected

the problem.

The Main Control

Panel

appear ed to be well marked with little impromptu

marking to clarify labels.

Equipment controllers provide clear feedback

to the operators

as to valve or controller position.

~ADS

S stem

The team walked

down the control

room indications for the Automatic

Depressurization

System

(ADS).

The operators

were familiar with the

indications,

the indications were adequately

marked,

and all

indications

showed proper equipment lineup and operation.

The team

discussed

the operation of the

ADS inhibit switch with an operator.

The operator

was familiar with the switch and indicated

he

had

received training on the operation of the switch as

a result of the

modification which installed the switch and also

as

a result of

requalification training.

The operator

was able to describe

how the

switch was

used

and what indications occur when the switch is in the

inhibit position.

Verification of these indications is performed

by

the "Minimum Startup Checklist" which is performed prior to every

startup.

The operation of the switch is prescribed

by the

licensee's

Emergency Operating

Procedures

which are symptomatic.

These

procedures

include the

symptoms for an

ATMS. The team walked

down the control

room indications for the Electrical

Power

Distribution System including offsite power sources,

the vital 4

KV

busses,

the vital 480

V busses,

the 125

V and 250

V batteries,

and

the Emergency

Diesel Generators.

The operators

were familiar with

the indications,

the indications were adequately

marked,

and all

indications except

a ground alarm

showed proper equipment lineup and

operation.

The ground alarm was the result of a problem with the

alarm circuit and not an actual

ground. Alternate indication of the

ground status

on the affected

buss

was available,

however, there is

36

no requirement or directive in place to monitor the alternate

indication in the absence

of the alarm function.

Further review

showed that there is no system in place to provide compensatory

actions for an inoperable

annunciator

or alarm function.

This is an

open item (50-397/87-19-32).

b.

Service Water

S stem

The position indicator lights for SW-PCV-38A and

38B were not

working.

These valves are pressure

control valves for the Standby

Service Water System.

Further review showed that

a recent

modification (DCP-86-0324) deactivated

these

valves

and therefore

deenergized

the valve position indication.

A field change

(FCR-08)

to this

DCP modified the labels to the valves to identify them as

having been deactivated.

A Maintenance

Work Request

(MWR-AT-0444)

to change

the labels

was initiated but not yet completed.

The

installation completed section of the Plant Modification Record

was

signed off on May 28,

1987, without MWR-AT-0444 being completed.

This is another

example, identified by the team, of the type of

violation described

in section 2.d of this report.

The Reactor

Feed

Pump Turbine vibration recorders

have handwritten notes

dated

December'985

indicating that their labels

are incorrect.

This

appears

to be an excessive

period of time to correct his deficiency.

This is an open item (50-397/87-19-33).

The

CRT displays for the Safety Parameter

Display System

(SPDS) are

impossible to read from the Reactor Operator's

desk

and are

difficult to read

when standing at the Main Control

Panel itself.

This situation

does

not appear to be consistent with the

FSAR

description which says in Section 7.5. 1.23 the

CRT supplies

additional information via high performance

human factored displays

useful for emergency

response.

This item is unresolved

pending

NRC

review to determine if the

SPDS

meets licensee's

commitments

(50-397/87-19-34).

ualit

Assurance/Trainin

The gA/gC activity have identified similar design control deficiencies to

those

found by the inspection

team in some areas.

This is evidenced

by

the inspector's

review of gA/gC audit, surveillance,

observation

and

inspection reports.

In other areas of concern to the inspection

team,

the gA/gC activity has

been limited or nonexistent.

In response

to Region

V inspection report

No. 86-11 findings regarding

the adequacy of gA/gC involvement,

the licensee

has strengthened

the

overall site quality verification organization

and programmatic

approach

to assuring quality of facility operations.

This revised

approach is

still in the implementation process.

According to the licensee,

details

of this approach

as discussed

in the recent

Region

V SALP report are

described

accurately.

Elements of the program,

such

as onsite gA/gC,

Nuclear Safety Assurance

Group and Corporate

gA functions are expected

to

be fully implemented during

FY 1988.

During the implementation process,

the licensee

indicated that further adjustment

and fine tuning of the

approach will occur.

Therefore, it may be premature to attempt

an

37

assessment

of the effectiveness

of the licensee

revised quality

verification program at this time.

However, to the extent that the

licensee's

quality verification program should

have

impacted the

inspection team's findings, the following is evident:

a.

No evidence of quality verification activity was produced

by the

licensee for the following inspection

team findings.

(1)

Battery design calculation for DC motor in-rush current.

(2)

125

VDC and

250

VDC design calculation correction factors for

aging,

temperature

and specific gravity.

(3)

Instrument tolerance

consideration for harsh environments.

(4)

ADS instrument rack electrical terminations.

(5)

Reactor

shutdown margin response

time.

Limited evidence of quality verification activity was produced

by

the licensee

for the following inspection

team findings:

(1)

Materials (scaffolding,

loose parts,

crane

hook, etc.) stored

in the vicinity of safety-related

equipment creating

a

potential

SSE concern.

(2)

Inadequate

surveillance

procedure for MOV electrical

overload.

(3)

Inadequate

surveillance

procedure for periodic testing of

safety-related

batteries.

(4)

Monitoring of safety-related

battery

room temperature

design

limitations.

(5)

Improper closure of completed

DCPs

and

NCRs (i.e., proper

design not implemented

and failure to provide root cause

evaluations for repeated

NCRs).

(6)

Inadequate

drainage capability for D.G.

Rooms.

Licensee quality verification activities

have identified in several

surveillance,

audit and observation

reports

design control problems

associated

with and similar to repeated failures of D.

G.

day tank

valves

and repeated fai lure of automatic valves for isolation of

nonsafety-related

air to ADS control

system.

In these

cases, it

appears

that the plant staff did not perform root cause

evaluations

and did not take timely corrective action to the identified

deficiencies.

At present,

site

gA reports that there are

16

NCRs

outstanding that are over

6 months old.

While some of this work may

be done,

the documentation

is not complete.

C.

Evidence of quality verification activity was produced

by the

licensee for the following inspection

team findings:

38

Design calcs (Instrument setpoints).

(2)

Weekly and 60-month battery surveillance testing.

(3)

Automatic sprinkler system installation

and diesel

generator

room flooding

removal of oil spills.

(4)

Seismic restraints.

(5)

Time Delay Relay

(TDR) Setting (not specific to IEEE

requirements).

(6)

Thermal overload of MOV (Torque and limit switch settings).

d.

Continuing weaknesses

in the licensee's

quality verification program

appear to exist as follows:

The focus of'udits, surveillances,

inspections

and

observations

should

be increased

in the area of physical plant

conditions

and work performance.

(2)

(3)

NCR,

DCP, tQR,

PHR or

PDR completed

reviews should include

physical verification of design

implementation

by plant QA/QC.

No

NCR was issued for the nonconforming safety-related

hand

wheel for manual

valve

No.

S.W.

V-165B because

licensee policy

appears

to allow individual interpretation/discretion

in such

cases.

Furthermore,

root cause

evaluations

may not be required

unless

a 50.59 review is required.

50.59 reviews are only

required

on

NCRs if it is determined

equipment is to be used

"as is or repaired."

(4)

(5)

(6)

Proper coordination of resources

and personnel

expertise (i.e.,

onsite

QA/QC, corporate

P.A. outside consultants,

engineering,

operations,

NSAG, etc.) to further enhance

program

implementation

appears

to be in the developmental

stage.

t

Plant,

corporate/QA interface

appear to have

improved to the

extent that

a working relationship exist that produces

an

environment for effective quality verification program

implementation.

However, this environment is in its infancy

and

may not have

been disseminated

down through the ranks of

plant and corporate

personnel.

The training groups did not appear to be incorporating quality

verification results into plant training programs (i.e.,

instructions to operations

and test staff regarding reported

seismic

concerns

and operations

response

to

QASR 86-202

regarding operator requalification training).

Unresolved

Items

Unresolved

items are matters

about which more information is required to

determine whether they are acceptable

or may involve violations or

39

deviations.

The licensee is requested

to provide additional information

on these

items,

as noted in the forwarding letter to this report.

7.

Exit Interview

On August 28, 1987,

an exit interview was conducted with the licensee

representatives

identified in paragraph

1.

The inspectors

reviewed the

scope of the inspection

and findings as described

in the

Summary of

Significant Inspection Findings section of this report.