ML17279A732

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-397/87-19 on 870803-28,notice of Violation & Summary of Significant Findings.Insp Overview & Conclusions Discussed
ML17279A732
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 12/08/1987
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML17279A733 List:
References
NUDOCS 8712230134
Download: ML17279A732 (7)


See also: IR 05000397/1987019

Text

REGULATORY INFORMATION, DISTRIBUTION SYSTEM (RIDS)

CESSION

NBR: 8712230134

DOC. DATE: 87/12/08

NOTARIZED:

NO

DOCKET

CIL: 50-397

WPPSS Nuclear

Prospect.

Unit 2i

Washington Public Poee

05000397

AUTH. NAME

AUTHOR AFFILIATION

MARTINiJ. B.

Region

5.

Ofc of the Director

REC IP. NAME

RECIPIENT AFFILIATION

SORENSENi G. C.

Washing ton

Pub lie Poeer

Supp lg

Sg stem

SUBJECT:

Foreard s

'

'

on 870803-28i

summary of significant findings. Insp overviee

5

conc usions

discussed.

e

DISTRIBUTION CODE:

IE01D

COPIES

RECEIVED: LTR l

ENCL

SIZE:

TITLE: General

(50 Dkt)-Insp Rept/Notice of Violation Response

NOTES:

RECIPIENT

E/NAME

INTERNAL: ACRS

DEDRO

NRR/DLPG/PEB

. NRR/DREP/EPB

NRR/DR IS

DIR

OE LIEBERMANi J

REG FILE

RGN5

FILE

01

EXTERNAL:

LPDR

NSIC

COPIES

LTTR ENCL

1

2

2

1

1

1

1

1

1

1

1

1

1

1

1

1

1

RECIPIENT

ID CODE/NAME

SAMWORTHi R

AEOD

NRR MORISSEAUi D

NRR/DOE* DIR

NRR/DREP/RPB

NRR/PMAS/ ILRB

OGC/HDS2

RES

DEPY GI

NRC

PDR

COPIES

LTTR ENCL

2

2

1

1

1

1

1

1

2

2

1

1

1

1

1

gS REq

(4

P

~

L

~4

0~i

Docket No. 50-397

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1460 MARIALANE. SUITE 210

WALNUTCREEK, CALIFORNIASl696-6366

DEC

8 1987

Washington Public Power Supply System

P.O.

Box 968

3000 George Washington

Way

Richland, Washington

99352

Attention: Mr. G.

C. Sorensen,

Manager

Regulatory

Programs

Gentlemen:

Subject:

NRC Inspection at WNP-2

This refers to the special

team inspection,

conducted

by Mr. F.

R.

Huey and

other members -of our staff on August 3 through August 28, 1987.

This

inspection

examined your activities as authorized

by NRC License

No.

NPF-21.

Discussion of our findings were held with members of your staff at the

conclusion of the inspection.

Areas examined during this inspection are described

in the enclosed

inspection

report.

Within these

areas,

the inspection consisted of selective

examinations

of procedures

and representative

records,

interviews with

personnel

and observations

by the inspectors.

Based

on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements,

as set

forth in the Notice of Violation, enclosed

herewith

as Appendix A.

Your

1

p

of 10 CFR 2.201,

as stated in the Notice of Violation.

I

Ins ection Overview

The inspection

conducted

by the team was a safety system functional inspection

(SSFI).

The objective of an SSFI is to assess

the operational

readiness

of

selected safety systems

to function under all operational

and analyzed

accident conditions.

For this inspection,

the

AC and

DC electrical

distribution systems,

the standby service water system,

and the automatic

depressurization

system were selected for review.

These

systems

were selected

because it is considered

essential

that they function correctly following an

event

such

as

a loss of offsite power or a major plant transient.

Additionally, Probabilistic Risk Assessment

studies of boiling water reactors

have indicated that the failure of the selected

systems,

following a loss of

offsite power or a major plant transient,

contribute highly to the probability

of occurrence of a core melt event or an event with significant offsite

consequences.

In assessing

the operational

readiness

of these

systems,

the

team focused heavily on the capability of your engineering organization to

access

the design basis of the systems;

and their capability to maintain the

design basis

when modifying the systems.

Additionally, the team considered

maintenance,

surveillance, testing, quality assurance,

and plant operational

aspects

associated

with the systems

selected.

As di'scussed

in detail below,

the team identified a large number of deficiencies

and raised

many significant

questions with regard to these

systems.

8712230134

871208

2

DEC

8 1987

It is worthwhile to 'more carefully consider the basic approach of this type of

inspection

and the manner in which findings are reached.

The first step

involves the selection of a small

number of plant systems that have

significant impact on plant safety

and which involve a broad cross section of

site activities.

As noted above,

the team selected

the site

AC and

DC

electrical

systems,

with additional attention to the standby service water and

automatic depressurization

systems.

The second

step involves

a thorough

and methodical

review of the licensee's

design

and engineering

processes,

as applied to the selected

systems.

An SSFI

inspection is based

on the premise that an effective design

and engineering

organization

incorporates

the following basic functions in a logical and

disciplined manner:

1.

The system design basis is valid and can

be

shown to fulfill

specified design requirements.

2.

The system design basis is well documented,

available

and understood

by the licensee.

3.

Effective administrative

programs

are implemented to control design

and engineering activities such that system design requirements

are

properly factored into applicable site activities (e.g.

construction, testing, operation,

maintenance,

training).

4.

Effective quality assurance

controls are implemented to ensure

a

continuing high standard

of performance.

Overall Conclusions

The team identified a number of significant deficiencies in the management

control of engineering

work at MNP-2.

Specific concerns

involve an incomplete

understanding

of the design basis for important plant equipment

and examples

of inadequate

control of implementation of design requirements

into site

activities.

The team observed

weaknesses

in your design control processes

which allowed errors in design modification activities to go undetected

and

which failed to ensure that necessary

design related parameters

were properly

factored into station operating

documents.

Implementing the inspection

approach

discussed

above, the team identified the following concerns

which, to

varying degrees,

are applicable to each of the systems

reviewed:

1.

Several

examples of significant errors in design basis

documents

were identified.

In the area of DC electrical

systems,

design errors

significantly reduced available margin for battery performance

under accident conditions.

In the area of AC electrical

systems,

design errors contributed

to a potentially significant reduction in the ability of

emergency

diesel

generators

to function as designed following a

fire or volcanic ash event.

DE<

8i9S7

In the area of the standby service water and other safety

related

systems,

the lack of a properly defined design basis

.

for time delay relays resulted in failure to perform required

testing

and raised questions

as to the design

adequacy of time

delay settings.

In the area of the automatic depressurization

system,

inconsistencies

between the design basis in the

FSAR and system

design

documents

raised questions

as to the adequacy of the

system to fulfillits design requirements.

2.

Several

examples

were identified in which inadequate

administrative

control of the design process

resulted in improper implementation of

design requirements.

In the area of DC electrical

systems,

design control

deficiencies

resulted

in, instances

of improperly revised design

calculations

and improper testing of station batteries.

In the area of AC electrical

systems,

design control problems

resulted in examples of improper testing of emergency diesel

generators

and improper modification of system

components.

In the area of the standby service water system

and other

safety related

systems,

inadequate

control of testing of motor

operated

valve thermal overload devices

raised questions

as to

the adequacy of these

components

to fulfilltheir design

functions.

In addition, lack of proper control over the

equipment modification process

resulted in cases

where specific

modifications, required

by completed

design

change

packages,

had not been

accomplished

as mandated.

In the area of the automatic depressurization

system,

j

inadequate

design controls allowed the installation of a system

defeat circuit without necessary

limitations for use of this

function being properly factored into site operating

procedures.

In addition to design related problems,

the team noted other areas of

deficiencies warranting increased

management

attention.

In particular:

1.

The team observed

several

examples of the need for increased

management

attention to plant material condition and housekeeping

in

general.

2.

The team noted instances

in which your staff did not appear to have

properly addressed

root cause

evaluations

associated

with safety

related

equipment malfunctions.

The number of design control related deficiencies identified during this

inspection indicates

a significant weakness

in the basic administrative

programs

implemented at WNP-2 for control of these

processes.

Ouring the

course of the inspection,

the team identified several

examples of

administrat'ive procedure deficiencies

which contributed to specific problems.

4

DEC

8 ~g87

The number

and type of problems

noted is also indicative of the need for

additional

and better focused quality assurance

attention to design related

activities.

In this regard,

the team

had several

discussions

with licensee

quality assurance

management

personnel.

These

management

personnel

shared

this concern

and noted that comprehensive

efforts have already

been initiated

to enhance

performance in this area.

During the team exit meeting,

Mr. Burn acknowledged

the team's

conclusions

relating to design

and design control deficiencies

and described

several

planned actions to correct these deficiencies.

The team understands

that

these actions

are intended to:

1) review and update

design basis information

and calculations

associated

with plant safety systems

and bring this

information together into an accessible,

controlled format; 2) review the

operation,

maintenance,

surveillance,

and training activities associated

with

plant safety systems,

and confirm that these activities reflect design basis

information; 3) provide improved administrative control over all organizations

implementing design basis

requirements

and 4) provide improved quality

assurance

overview of the technical

aspects

of design

and modification

activities.

These corrective actions

appear to be appropriate in addressing

the areas of weakness

noted.

You are strongly encouraged

to assign

the

highest priority to efforts to improve your performance

in this area.

It is further requested

that, in addition to your response

to the enclosed

Notice of Violation,. you provide

a detailed written description of your action

plan.

We anticipate periodically meeting with you and your staff to discuss

the status of your actions.

It should also

be noted that sever'al

areas

of

potential violation of NRC requirements

remain unresolved,

pending your

completion of additional evaluations

of the specific problems involved.

Most

of the items in this category involve perceived

problems with your basic

program for controlling plant design activities.

In addition to your response

to the Notice of Violation, Appendix A, please

provide your assessment

of the apparent deficiencies identified as unresolved

items in the enclosed report, including any corrective actions taken or

planned.

In accordance

with 10 CFR 2.790(a),

a copy of this letter

and the enclosures

will be placed in the

NRC Public Document

Room.

The responses

directed

by this letter and the attached

Notice are not subject

to the clearance

procedures

of the Office of Management

and Budget

as required

by the Paperwor k Reduction Act of 1980,

PL 96-511.

Should you have

any questions

concerning this inspection,

we will be glad to

discuss

them with you.

S

rely,

J.

B. Martin

Regional Administrator

DCC

SiSS7

I

~

~

~

~

~

~

~

~

~

Encl osures:

l.

Appendix A, Notice of Violation

2.

Appendix B, Summary of Significant Findings

3.

Inspection

Report

No. 50-397/87-19

cc w/enclosures:

C.

M. Powers,

WPPSS

P.

L. Powell,

WPPSS

R.

B. Glasscock,

WPPSS

G.

E.

Doupe,

Esq.,

WPPSS

A.

L. Oxsen,

WPPSS

State of Washington

N.

S.

Reynolds,

Esq.,

BCP8R

DEC

8 l987

l..

Appendix A, Notice of Violation

2.

Appendix B,

Summary of Significant Findings

3.

Inspection

Report

No. 50-397/87-19

cc w/enclosures:

C.

H. Powers,

WPPSS

P.

L. Powell,

WPPSS

R.

B. Glasscock,

WPPSS

G.

E.

Doupe,

Esq.,

WPPSS

A.

L. Oxsen,

WPPSS

State of Mashington

N.,S.

Reynolds,

Esq.,

BCP8R

bcc w/enclosures:

Resident

Inspector

Project Inspector

Drew Persinko,

NRR

G.

Cook,

RV

.B. Faulkenberry,

RV

J. Martin,

RV

bcc w/o enclosure

3:

LFMB

M. Smith

REGION V/dot

~.)

FHuey 5

WWagner~~

CRamsey

12/g /87

12/~/87

12/ Si /87

DPereira

KJohns

on

12/G4 /87

12/9 /87

VEST

COPY ]

RE

VEST

COPY ]

R

VEST COPY ] REQUEST

COPY ]

R

UEST

COPY ]>

YE '

NO

E

/

NO

E

/

NO

/

NO

E

/

NO

JWie

e

1

87

SRicllards

12/9 /87

Rae

~

12/a/87

RZismerman

DKitsch

. l,f'Z-

12/'//87

12////87

UES

COPY ]

VEST COPY ]

EST

COPY ]

R

VEST COPY ] RE/VEST

COPY ]

YES

NO

ES /

NO

YES /

NO

E

/

NO

YES /

NO

JMa

1

/87

REQUEST

COPY ]

YES /

NO

SEND

TO

PDR

]

YE

/

NO