ML17151B013
Text
WOLF CREEK CHAPTER 14.0 TABLE OF CONTENTS INITIAL TEST PROGRAM
Section Title Page
14.1 SPECIFIC INFORMATION TO BE INCLUDED 14.1-1 IN THE PSAR
14.2 INITIAL TEST PROGRAM 14.2-1
14.2.1
SUMMARY
OF TEST PROGRAM AND OBJECTIVES 14.2-1
14.2.1.1 Preoperational Test Program 14.2-1
14.2.1.2 Initial Startup Test Program 14.2-2
14.2.2 ORGANIZATION AND STAFFING 14.2-3 14.2.2.1 General Description 14.2-3
14.2.2.2 Startup Organization 14.2-4
14.2.2.3 Operating Staff 14.2-6
14.2.2.4 Major Participating Organizations 14.2-6 14.2.2.5 Quality Assurance 14.2-8 14.2.2.6 Qualifications of Key Personnel 14.2-8
14.2.3 TEST PROCEDURES 14.2-8
14.2.3.1 Startup Test Procedures 14.2-8 14.2.3.2 Procedure Review and Approval 14.2-10
14.2.4 CONDUCT OF TEST PROGRAM 14.2-12
14.2.4.1 Administrative Procedures 14.2-12
14.2.4.2 Turnover From Construction to KG&E 14.2-13 Startup 14.2.4.3 Component and Prerequisite Testing 14.2-14
14.2.4.4 Preoperational Testing 14.2-14
14.2.4.5 Initial Startup Testing 14.2-14
14.2.4.6 Test Prerequisites 14.2-15 14.2.4.7 Test Evaluation 14.2-15 14.2.4.8 Design Modifications 14.2-15
14.2.5 REVIEW, EVALUATION, AND APPROVAL OF 14.2-15
TEST RESULTS 14.2.6 TEST RECORDS 14.2-16
14.2.7 CONFORMANCE OF TEST PROGRAMS WITH 14.2-16
REGULATORY GUIDES
14.2.8 UTILIZATION OF REACTOR OPERATING AND 14.2-16 TESTING EXPERIENCE IN DEVELOPMENT
OF TEST PROGRAMS
14.2.9 TRIAL USE OF PLANT OPERATING AND EMERGENCY 14.2-18 PROCEDURES
14.0-i Rev. 29 WOLF CREEK TABLE OF CONTENTS (CONTINUED)
Section Title Page 14.2.10 INITIAL FUEL LOADING CRITICALITY AND POWER 14.2-18
ASCENSION
14.2.10.1 Fuel Loading 14.2-19 14.2.10.2 Initial Criticality 14.2-22 14.2.10.3 Low Power Testing 14.2-23
14.2.10.4 Power Level Ascension 14.2-23
14.2.11 TEST PROGRAM SCHEDULE 14.2-24 14.2.12 INDIVIDUAL TEST DESCRIPTIONS 14.2-25
14.2.12.1 Safety-Related Preoperational Test 14.2-25
Procedures
14.2.12.2 Nonsafety-related Preoperational Test 14.2-121 Procedures
14.2.12.3 Startup Test Procedures 14.2-158
14.0-ii Rev. 29 WOLF CREEK TABLE OF CONTENTS (CONTINUED)
LIST OF TABLES Table No. Title
14.2-1 Safety-Related Preoperational Test Procedures 14.2-2 Non-Safety-Related Preoperational Test Procedures
14.2-3 Initial Startup Test
14.0-iii Rev. 0
WOLF CREEK CHAPTER 14.0 INITIAL TEST PROGRAM
14.1 SPECIFIC INFORMATION TO BE INCLUDED IN PRELIMINARY SAFETY ANALYSIS REPORTS This section is not applicable to a USAR.
14.1-1 Rev. 1 WOLF CREEK CHAPTER 14.0 INITIAL TEST PROGRAM 14.2 INITIAL TEST PROGRAM 14.2.1
SUMMARY
OF TEST PROGRAM AND OBJECTIVES
The Initial Test Program encompassed the scope of events following completion of construction and construction-related inspections and tests and terminating
with Power Ascension Testing. The Initial Test Program was conducted in two
separate and sequential subprograms: the Preoperational Test Program and the
Initial Startup Test Program. At the conclusion of these subprograms, the
plant was ready for normal power operation. Testing during the Initial Test
Program was accomplished in four sequential phases:
Preoperational Test Program
Phase I - Preoperational Testing Initial Startup Test Program
Phase II - Initial Fuel Loading and Zero Power Testing
Phase III - Low Power Physics Testing
Phase IV - Power Ascension Testing
Prior to preoperational testing of a particular system, certain prerequisite
and construction tests were conducted in order to verify the integrity, proper
installation, cleanliness, and functional operability of the system components.
14.2.1.1 Preoperational Test Program The Preoperational Test Program is defined as that part of the Initial Test
Program that commences with the completion of construction and construction-
related inspections and tests and terminates with commencement of nuclear fuel loading.
The Preoperational Test Program included both safety-related and nonsafety-
related preoperational tests. The Preoperational Test Program used a graded
approach to determine the extent of testing to be performed. The safety-
related preoperational tests (Table 14.2-1) demonstrated the capability of
safety-related structures, systems, and components to meet performance
requirements and to satisfy design criteria. The nonsafety-related
preoperational tests (Table 14.2-2) were conducted on nonsafety-related systems
and components to satisfy reliability and availability. Preoperational tests were conducted on those systems that:
14.2-1 Rev. 0 WOLF CREEK
- a. Are relied upon for safe shutdown and cooldown of the reactor under normal plant conditions and for
maintaining the reactor in a safe condition for an
extended shutdown period;
- b. Are relied upon for safe shutdown and cooldown of the
reactor under transient and postulated accident
conditions and for maintaining the reactor in a safe
condition for an extended shutdown period following such
conditions;
- c. Are relied upon for establishing conformance with safety
limits or limiting conditions for operations that are
included in the technical specifications;
- d. Are classified as engineered safety features actuation systems or are relied upon to support or ensure
operation of engineered safety features actuation
systems within design limits;
- e. Are assumed to function during an accident or for which
credit is taken in the accident analysis;
- f. Are used to process, store, control, or limit the
release of radioactive materials.
The objectives of the Preoperational Test Program were to:
- a. Verify that plant components and systems, including
alarms and indications, are constructed and fulfill their design intent;
- b. Demonstrate, to the extent practicable, proper
system/component response to postulated accidents;
- c. Familiarize plant staff operating, technical, and
maintenance personnel with plant operation.
The completion of preoperational testing constituted the completion of Phase I
of the Initial Test Program.
14.2.1.2 Initial Startup Test Program The Initial Startup Test Program is defined as that part of the Initial Test
Program that commences with the start of nuclear fuel loading and terminates
with the completion of power ascension testing. The initial startup tests (Table 14.2-3) ensured that fuel loading was accomplished in a safe manner, confirmed the
14.2-2 Rev.0 WOLF CREEK design basis, demonstrated, where practical, that the plant operates and responds properly to anticipated transients and postulated accidents, and
ensured that the plant can be safely brought to rated capacity and sustained
power operation.
The objectives of the Initial Startup Test Program were to:
- a. Accomplish a controlled, orderly, and safe initial core
loading;
- b. Accomplish a controlled, orderly, and safe initial
criticality;
- c. Conduct low power testing sufficient to ensure that
design parameters are satisfied and safety analysis assumptions are conservative;
- d. Perform a controlled, orderly, and safe power ascension
with testing terminating at plant rated conditions;
- e. Provide sufficient testing of transient and accident
conditions to verify safe operation during transient or
accident conditions.
The completion of initial startup testing constituted the completion of Phases
II, III, and IV of the Initial Test Program.
14.2.2 ORGANIZATION AND STAFFING
14.2.2.1 General Description The Operating Agent, as defined in Section 1.4, was responsible for the overall
administration and technical direction of the WCGS startup program. In
recognition of this responsibility, the Director of Nuclear Operations, under the direction of the Vice President - Nuclear, established a startup
organization to coordinate and direct the comprehensive planning, development, implementation and performance of the test program. The Startup Organization
was headed by the Startup Manager who reported to the Plant Manager both
administratively and technically.
During the preoperational startup program, the Startup Manager acted to
coordinate activities between the Startup Organization, the construction staff, and the operating staff.
Prior to commencing preoperational testing activities, a Joint Test Group (JTG) as described in Section 14.2.3.2.2 was formed to review and recommend for
approval startup administrative procedures, preoperational test procedures, and
preoperational test
14.2-3 Rev. 0 WOLF CREEK results. A Plant Safety Review Committee (PSRC) as described in Section 14.2.3.2.3 was organized with the Plant Manager acting as chairman and it
reviewed and recommended for approval initial startup test procedures and
results.
14.2.2.2 Startup Organization
The Startup Organization was directly responsible for the conduct of the WCGS
preoperational test program. The duties and responsibilities of the startup
organization also included:
- a. Familiarization of support personnel with specific
tests.
- b. Direction to support personnel and others during performance of tests including appropriate interface with station operators.
- c. Authority to disallow or terminate testing due to
conditions which could endanger personnel or equipment.
- d. Identification of deficiencies that could adversely
affect test performance.
- e. Assembly of test data and preparation of test reports
for evaluation of test results by others.
The Startup Organization was composed of system startup engineers, technicians, planners, craft labor, and other support personnel. The Operating Agent
provided these personnel and used contractors to supply manpower for those positions that it could not staff. The staffing level for the Startup Organization increased as the test program progressed and construction
activities decreased. Typical schedules for the test program are given in
Section 14.2.11. Staffing and training of personnel involved in testing at
WCGS were planned to provide sufficient manpower to support the testing
schedule.
The Startup Organization reported administratively and technically to the
Startup Manager; the duties performed by key individuals within the Startup
Organization are summarized below.
14.2.2.2.1 Startup Manager
The Startup Manager had the authority and responsibility, as delegated by the
Plant Manager, for the overall direction and administration of the functions
and activities required to conduct the Startup Program. The responsibilities
and duties of the Startup Manager also included:
14.2-4 Rev. 0 WOLF CREEK
- a. Development of plans and schedules regarding the status of the startup program.
- b. Review and approval of administrative and technical test
procedures and results.
- c. Continuing analysis of construction and equipment
installation schedules for compatibility with testing
schedules and recommendations for corrective actions to
minimize conflict.
- d. Review and submittal of design related problems
requiring engineering resolution, encountered by the
Startup Organization in accordance with the appropriate
Startup Administrative Procedures.
- e. Maintaining liaison with all organizations supporting
Startup and coordinating their activities.
14.2.2.2.2 Startup Section
The Startup Section was comprised primarily of the System Test Group, the
Electrical Test Group and the Instrumentation and Control Group which had
primary responsibility within the Startup Organization to perform testing.
This section also reviewed and recommended the acceptance of system or
subsystem turnover documentation from Construction and coordinated system
turnover and any subsequent system rework. It was responsible for preparing the
test procedures, conducting the tests, and reporting the test results. For
preoperational testing, this section documented the test results and presented
them before the Joint Test Group for its review and recommendation for approval.
14.2.2.2.3 Operations Technical Support Section
The Operations Technical Support Section was responsible for providing
technical support to the Startup Section during testing. The areas in which
this support was given were instrumentation and control, chemistry, computer, health physics and reactor engineering.
This section was a permanent part of the WCGS operating staff until these functions were incorporated into other sections. They were involved in training, procedure preparation, and general preparation for support of plant operations.
14.2.2.2.4 Startup Scheduling Section
The Startup Scheduling Section prepared and updated the Startup Schedule, utilizing input from cognizant system startup engineers and the construction
organizations.
14.2-5 Rev.7 WOLF CREEK 14.2.2.2.5 Quality Control Section
The Quality Control Section formulated and implemented the Startup Quality
Control Program. This program monitored the conduct of the Startup
Organization's testing activities by reviewing administrative and technical test procedures, by witnessing major evolutions and selected flushes, hydros, and preoperational tests and by reviewing turnover packages. The Quality
Control Section was under the direction of the Director - Quality. They
provided support to the Startup Manager.
14.2.2.2.6 Startup Technical Support Section
The Startup Technical Support Section was responsible for providing technical
support to the Startup Organization during the conduct of the Startup Program.
Their responsibilities included test procedure and test results review and approval, technical planning of major milestone activities, startup organization training and startup program compliance to FSAR commitments.
14.2.2.3 Operating Staff The WCGS operating staff was involved in the startup program in several
capacities throughout preoperational and initial startup testing. This
involvement included review of test procedures and results and the direct participation in test activities. Operating staff personnel were utilized by
the startup organization as required for performance of testing under the
direction of system startup engineers. Station operators assisted system
startup engineers in performing tests and in the routine operations of systems.
The operating staff directed the fuel loading and was responsible for plant
operation during initial startup testing.
The operating staff was divided into sections headed by the Superintendent
Operations, Superintendent of Maintenance, Superintendent of Plant Support, Superintendent of Technical Support, Nuclear Training Manager and Superintendent Regulatory Quality and Administrative Services. These section
superintendents reported administratively and technically to the Plant Manager.
The duties and responsibilities of the operating staff during plant operations
are described in Chapter 13.0.
14.2.2.4 Major Participating Organizations 14.2.2.4.1 Bechtel
Bechtel provided engineering input into the startup program. Bechtel was contacted to provide personnel experienced in nuclear plant startup to augment
the startup organization for WCGS. Bechtel employees were assigned consistent
with the startup program schedules.
14.2-6 Rev. 12 WOLF CREEK 14.2.2.4.2 Daniel International Corporation (DIC)
DIC, as contractor for WCGS, was responsible for the construction completion, and orderly release of components and turnover of systems to KG&E consistent
with the startup program schedules. This responsibility included:
- a. Certification that documentation for components, systems
and structures, as required by purchase and installation
specifications, is complete and available; and the
maintenance of these certification files which provide
the documentary evidence, and
- b. Provision of dedicated craft manpower support as
required for performance of the startup program.
14.2.2.4.3 Westinghouse Electric Corporation
Westinghouse, as the Nuclear Steam Supply System (NSSS) supplier, was
responsible for providing technical assistance to KG&E during preoperational
and initial startup testing performed on the NSSS equipment and systems.
Technical assistance is defined as technical guidance, advice and counsel based
on current engineering, installation, and testing practices. Westinghouse
employees were assigned consistent with the Startup Program schedules. This
responsibility included:
- a. Assignment of personnel to provide advice and assistance
to KG&E for test and operation of all equipment and
systems in the Westinghouse area of responsibility.
- b. Supportive engineering services, including special assistance during the initial fuel loading.
- c. Providing test procedure outlines and technical
assistance for tests of Westinghouse furnished
components and systems.
14.2.2.4.4 General Electric (GE)
GE is the supplier and installer of the turbine generator. GE supplied
technical support for the startup and testing of the turbine generator. Some
of the prerequisite testing (i.e., turbine oil flush) was performed by the GE
personnel. GE has supplied recommended procedures for starting, operating, and
shutting down equipment in their technical manuals for the turbine generator.
14.2-7 Rev. 0 WOLF CREEK 14.2.2.5 Quality Assurance The KG&E Quality Branch was responsible for assuring the quality of
construction, plant testing, and operations activities in accordance with the
WCGS Quality Program which is described in the Quality Program Manual.
14.2.2.6 Qualifications of Key Personnel
The qualifications for key plant operating personnel are described in Chapter
13.0.
The qualification requirements for startup personnel involved in the WCGS
startup program conformed to capability levels per ANSI N45.2.6 and Regulatory
Guide 1.8 recommendations.
All test personnel were indoctrinated in the startup administrative procedures, methods and controls.
14.2.3 TEST PROCEDURES
The Initial Test Program was conducted in accordance with detailed preoperational and initial startup test procedures. KG&E maintained the overall responsibility for test procedure preparation, review, and approval
during the preparational stages. KG&E was responsible for final procedure
revision, review, and approval. These activities were completed in a timely
fashion to ensure that the approved procedures for satisfying FSAR testing
equipment commitments were available for review approximately 60 days prior to
scheduled implementation or fuel load for preoperational and initial startup
tests, respectively. Preoperational and initial start-up testing commitments
not available for review approximately 60 days prior to scheduled
implementation or fuel load, respectively, were handled on a case- by-case
basis.
The following sections describe the general methods employed to control
procedure development and review, and they also describe the responsibilities
of the various organizations which participated in this process. The detailed controls and methods were described in the startup administrative procedures.
14.2.3.1 Procedure Preparation Test procedures for the powerblock systems and components were developed by
Westinghouse and Bechtel. Bechtel also prepared test procedures for the site
safety-related systems and components. Test procedures for the site nonsafety-related systems and components were developed by various entities as
coordinated by KG&E.
14.2-8 Rev. 21 WOLF CREEK The format and content of the test procedures developed for the standard plant and safety-related site systems and components reflected the guidance provided
in Regulatory Guide 1.68. The procedures contained as a minimum the following
sections:
1.0 Objectives
The objectives section identified the general results to
be accomplished by the test.
2.0 Acceptance Criteria
The acceptance criteria section clearly defined
quantitative and/or qualitative criteria against which
the success or failure of the test procedure is judged.
3.0 References
The references section identified those FSAR sections, vendor manuals, drawings, etc. that were pertinent to
the performance and/or development of the test
procedure.
4.0 Test Equipment
The test equipment section identified temporary
equipment required to conduct the test procedure and/or
collect data.
5.0 Notes and Precautions The notes and precautions sections listed limitations
and precautions necessary to ensure personnel and
equipment safety. Additional instructions needed to
clarify the test procedure were also listed in this
section.
6.0 Prerequisites
The prerequisites section identified those prerequisite
tests and initial conditions that had to be completed
and/or satisfied prior to the performance of the test
procedure.
7.0 Test Procedure
The test procedure section provided a detailed step-by-
step test method and instructions for data collection.
All nonstandard arrangements required by the test
procedure section were restored either in the test
procedure section or the system restoration section.
14.2-9 Rev. 0 WOLF CREEK 8.0 Test Data Sheets
The test data sheet section provided specific forms for
data collection. Additional instructions, if necessary, were also identified for each data sheet.
9.0 System Restoration
The system restoration section returned the system to a
safe operating or standby condition. Instructions for
the removal and/or return of system temporary
modifications required by the prerequisite and/or test
procedure sections were clearly defined.
The procedural sections included, as applicable, appropriate requirements for initials and/or signatures to control the performance and sequencing of the test.
The test procedures were prepared using the latest design information available
and functional requirements provided by the design engineers. This information
was utilized in developing the detailed test methods which verified the ability
of systems and components to function within their design specifications. The
procedure preparation efforts were started more than 2 years before the first
procedure to be performed. This early start allows for an orderly development
of the test procedure program and of the test procedures.
The test procedures were reviewed by the cognizant design organization to
ensure that the test procedure objectives and acceptance criteria are
consistent with current design document requirements. Subsequent changes to
test procedure objectives or acceptance criteria during the preparational stage were based on approved changes to design documents with the design organization's concurrence.
14.2.3.2 Procedure Review and Approval Following initial procedure preparation, and prior to submittal to the JTG for
review and approval recommendation, the test procedures were reviewed by the
SNUPPS utilities (KG&E and Union Electric). Review comments were resolved between the SNUPPS utilities and the writing organization.
A final revision was made by the writing organization, incorporating all
applicable design changes, and was submitted to the utilities for their review
and approval.
14.2-10 Rev. 0 WOLF CREEK Each utility had various organizations, groups, and committees, such as a startup organization, initial test group, and a plant safety review committee, comprised of individuals having appropriate technical backgrounds and
experience. Individuals within these organizations, groups, and committees
were responsible for:
- a. Reviewing procedures for accuracy and technical content;
- b. Verifying that the procedure has been revised to
incorporate known design changes;
- c. Verifying procedure compatibility with field
installation of equipment;
- d. Verifying procedure conformance with FSAR requirements and plant operating technical specifications;
- e. Reviewing procedures against reactor operating and
testing experiences of similar power plants.
14.2.3.2.2 Joint Test Group (JTG)
A subcommittee of the PSRC, the JTG was organized by the Operating Agent to
review preoperational test procedures and preoperational test results.
The primary JTG functions were to:
- a. Review preoperational test procedures and recommend
their approval by the Startup Manager.
- b. Evaluate and authorize changes to preoperational test procedures as detailed in the Startup Administrative
Manual.
- c. Evaluate preoperational test procedure results and
recommend their approval to the Startup Manager and
Plant Manager.
- d. Review safety-related aspects of the startup
administrative procedures.
Membership in the JTG included the following personnel or their designated
representatives:
- a. Superintendent Operations - Chairman
- b. Superintendent of Plant Support
14.2-11 Rev. 12 WOLF CREEK
- c. Superintendent of Regulatory, Quality and Administrative Services
- d. Startup Technical Support Supervisor
- e. Assistant Startup Manager
- f. Operations Quality Assurance (non-voting member)
- g. Bechtel Power Corporation-Engineering (non-voting
member)
- h. Westinghouse-Engineering (non-voting member)
Others were requested to provide technical support to the JTG. This support was based on the procedure being reviewed, required technical expertise or other applicable factors. Participation in the JTG meeting was with the concurrence
of the JTG and was limited to technical input only.
14.2.3.2.3 Plant Safety Review Committee (PSRC)
The PSRC was organized by the Operating Agent to ensure effective coordination
of the engineering, construction, and operations activities affecting the
startup program.
The appropriate PSRC members ensured sufficient review of initial startup test
procedures and results.
The primary PSRC startup functions were:
- a. Review all initial startup test procedures and make recommendations to the Plant Manager.
- b. Evaluation and authorization of changes to initial
startup test procedures.
- c. Evaluation of initial startup test procedure results.
Membership in the PSRC is given in the Quality Program Manual.
14.2.4 CONDUCT OF TEST PROGRAM
14.2.4.1 Administrative Procedures
The conduct of the preoperational startup program was controlled by
administrative procedures. The preparation, maintenance, and implementation
of these procedures was the responsibility of the Startup Manager. The startup administrative procedures prescribed controls for startup activities such as:
14.2-12 Rev. 21 WOLF CREEK
- a. Organization and interfaces;
- b. Indoctrination and training;
- c. Preparation, review, approval, and modification of test procedures;
- d. Format and content of test procedures;
- e. Tagging procedures;
- f. Test scheduling and test conduct;
- g. Test deficiencies and resolution;
- h. Startup quality control; and
- i. Startup document control.
14.2.4.2 Turnover from Construction to KG&E Startup Construction completion was scheduled in accordance with engineered system or
subsystem boundaries. As systems or sub- systems were completed to support
Startup testing, a turnover of the system or subsystem to KG&E Startup was processed. Turnover was conducted in accordance with established
administrative procedures.
As part of the turnover process, each safety-related system or subsystem
received physical walkdowns to provide assurance of readiness for Startup
testing and verification that installation requirements had been met.
Walkdowns were performed jointly by KG&E Startup and KG&E Construction
personnel under the direction of the KG&E Construction Manager. Discrepancies
identified during the walkdowns were tracked and resolved in accordance with
established administrative and quality procedures.
The system or subsystem Turnover Package prepared by the constructor was
reviewed by KG&E Construction and KG&E Startup personnel for accuracy, completeness and acceptability for Startup testing. In conjunction with the
Turnover Package review, Startup personnel verified that the system or
subsystem procurement and installation documentation review had been performed
by Construction, and that discrepancies had been addressed. Acceptance of the
Turnover Package by Startup followed satisfactory completion of the Turnover
Package review. The Startup Manager was responsible for the approval and
acceptance of the system or subsystem and the associated Turnover Package.
14.2-13 Rev. 0 WOLF CREEK Individual components could be released to Startup for calibration, testing or temporary operation prior to turnover.
All components released in this manner were incorporated into the scope of a
subsequent system or subsystem turnover.
14.2.4.3 Component and Prerequisite Testing Upon Startup acceptance of a turned-over system, subsystem, or released
component, prerequisite-type testing was performed to demonstrate proper
operability and functional ability in support of, and prior to, the performance of preoperational testing. Local containment leak rate testing, as described in
Section 14.2.12.2.13, was performed at WCGS as part of the prerequisite test
program.
Administrative procedures were established to ensure that all prerequisites
were met before testing was initiated. Upon completion of all prerequisite
tests applicable to a system or subsystem, a documented review was conducted by
Startup personnel to verify that appropriate documentation was able and that
required prerequisite tests had been satisfactorily completed. All deficiencies
which would prevent performance of preoperational tests or generate negative test results were identified and dispositioned prior to implementation of the preoperational tests.
14.2.4.4 Preoperational Testing Technical direction and administration, including test execution and data
recording, of the preoperational testing were the responsibility of the startup
organization. The system startup engineers were responsible for the performance of tests and providing appropriate interface with station
operators. The Startup Manager was responsible for the administration and
surveillance of all testing activities during the preoperational test program.
14.2.4.5 Initial Startup Testing During the initial startup testing phase, the Plant Manager had overall
authority and responsibility for the startup program. The Startup Organization
provided support to the plant operating staff which had responsibility for performing equipment operations and maintenance in accordance with the
provisions of the plant operating license. The WCGS operating staff was also
responsible for ensuring that the conduct of testing did not place the plant in
an unsafe condition at any time.
The shift supervisors had the authority to terminate or disallow testing at any
time.
14.2-14 Rev. 0 WOLF CREEK 14.2.4.6 Test Prerequisites Each test procedure contained a set of prerequisites and initial conditions as
prescribed by the startup administrative procedures. The system startup
engineer ensured that all specified prerequisites were met prior to performing the test. The format for test procedures is described in Section 14.2.3.1.
14.2.4.7 Test Evaluation Upon completion of system preoperational testing, the test results were
submitted to the JTG for its review and subsequent recommendation for approval
to the Startup Manager and Plant Manager.
Between each major phase of the initial startup test program, the test results
for all tests that were performed were reviewed by the PSRC. This review
ensured that all required systems were tested satisfactorily and that test
results were approved before proceeding to the next stage of testing.
These reviews are described in Section 14.2.5.
14.2.4.8 Design Modifications Modifications to the design of the equipment during the test program could be
initiated in order to correct deficiencies discovered as a result of testing.
Any such modifications were either developed by the original design organization or other designated organizations. Modifications made to
components or systems after completion of preoperational or initial startup
testing were reviewed for retesting requirements on affected portions of the
system.
14.2.5 REVIEW, EVALUATION, AND APPROVAL OF TEST RESULTS
The responsibility for review, evaluation, and recommendation for approval of
test results from all preoperational tests rested with the JTG. In the case of
all initial start-up tests, it rested with the PSRC.
Following completion of a preoperational test, the responsible system startup
engineer assembled the test data package for submittal to the members of the
JTG for evaluation. Each test data package was reviewed to ensure that the
test has been performed in accordance with the approved procedure and that all
required data, checks, and signatures were properly recorded and that system
performance met the approved acceptance criteria.
14.2-15 Rev. 0 WOLF CREEK Members of the JTG reviewed the evaluation findings and recommended corrective action to be taken to resolve any outstanding deficiencies. If the
deficiencies were not resolved to the satisfaction of the JTG, then appropriate
retesting was required. If the evaluation indicated that deficiencies in the
test method were responsible for unsatisfactory test results, the test procedure was revised accordingly before retesting was initiated. The review
and approval process for procedure revisions was carried out in the manner
described in Section 14.2.3. Whenever an evaluation of test results indicated
deficiencies in system performance, the JTG referred the problem to the
responsible engineering organization for evaluation.
If the test documentation and system performance were acceptable, the JTG
recommended approval of the test by the Startup Manager and the Plant Manager.
Following each major phase of the initial startup test program, the PSRC verified that all required tests were performed and that the test results were approved. This verification ensured that all required systems were operating
properly and that testing for the next major phase was conducted in a safe and
efficient manner. This type of review was performed to the extent required
before major initial startup test phases such as fuel load, initial
criticality, and power ascension. During the power ascension phase, review and
approval of initial startup test procedure results was completed as described
in KMLNRC-84-235.
14.2.6 TEST RECORDS
Test procedures and test data relating to preoperational and initial startup
testing are retained in accordance with the measures described in the Quality Program Manual.
14.2.7 CONFORMANCE OF TEST PROGRAMS WITH REGULATORY GUIDES
The regulatory guides applicable to the test program are listed, with
positions, in Appendix 3A, Conformance to NRC Regulatory Guides.
14.2.8 UTILIZATION OF REACTOR OPERATING AND TESTING EXPERIENCE IN
DEVELOPMENT OF TEST PROGRAMS
Available information on reactor operating experiences was utilized in the
development of the Initial Test Program, as follows:
14.2-16 Rev. 21 WOLF CREEK
- a. Bechtel reviewed and distributed pertinent Licensee Event Reports for use in the development of
preoperational test procedures as follows:
- 1. The Licensee Event Summary Reports and other pertinent information were reviewed on a periodic
basis, and those reports deemed to be useful for
updating test procedures and items of a generic
nature were cataloged. A summary of these reports
was distributed within Bechtel.
- 2. Copies of the specific reports were then made and
distributed for use in the preparation of
procedures. In addition, these reports were coded
and filed in a computer retrieval system.
- b. The operating experience assessment for Wolf Creek
Generating Station Unit No. 1 (WCGS) was conducted by
the nuclear divisions and plant staff who possess the
appropriate experience in the area of concern. The
sources of operating experience information included the
use of the NETWORK and the INPO/NSAC SEEIN system. An
administrative system which controlled the flow of
information from NETWORK, INPO/NSAC SEEIN, etc., to the
cognizant organizations including the Independent Safety
Engineering Group (ISEG) was developed and functioning
prior to fuel load.
The Licensing Section was responsible for coordinating
the review of the NRC Information and Enforcement (IE)
Bulletins, Circulars, and Information Notices.
The Startup Group reviewed information provided by the
other KG&E Nuclear Divisions and information provided by
Bechtel and Westinghouse to determine its effect on the
Wolf Creek Initial Test Program, making revisions to
test and administrative procedures as required.
An instrumented auxiliary feedwater water-hammer test was performed only at
Wolf Creek. (This test was not required to be performed. It was being
performed for the purpose of gathering engineering data only.) Procedure S-
O3AL04, Auxiliary Feedwater System Water Hammer Test, required a visual and
audible water hammer test and was completed prior to the issuance of an
operating license. See new Section 14.2.12.1.10.
Procedure S-070017, Loss of Heater Drain Pump Test, was performed on Callaway
only. This test was conducted to verify analytical assumptions. No
additional loss of heater drain pump tests are
14.2-17 Rev. 0 WOLF CREEK required, since the data obtained from the first unit test is equally valid for subsequent units. See Section 14.2.12.3.41.
Procedure S-07SF09 RCCA or Bank Worth Measurement at Power, was performed at 50
percent power only at Callaway. Wolf Creek and Callaway have the same core and Nuclear instrumentation system design and the test at Callaway is considered a
prototypical test for Wolf Creek. This position was accepted by the NRC in a
July 3, 1985 letter to KG&E.
A natural circulation test was performed at Callaway only to demonstrate the
length of time to stabilize natural circulation, core flow distribution, and
the ability to establish and maintain natural circulation. Operators
participating in the tests were able to recognize when natural circulation had
stabilized and were able to control saturation margin, RCS pressure, and heat
removal rate without exceeding specified operating limits. These tests were conducted insofar as possible to include all available licensed operators.
Licensed operators were trained in these same areas on the simulator. The
simulator has full capability of simulating natural circulation, using
Westinghouse data initially. When the above tests were accomplished on the
Callaway plant, actual data was incorporated into the Wolf Creek simulator
program. See Chapter 18, item I.G.1, and Section 14.2.12.3.43.
14.2.9 TRIAL USE OF PLANT OPERATING AND EMERGENCY PROCEDURES
The plant operating procedures were utilized, where applicable during the test
program, to support testing, maintain plant conditions, and facilitate
training. The trial use of operating procedures served to familiarize
operating personnel with systems and plant operation during the testing phase
and also served to ensure the adequacy of the procedures under actual or
simulated operating conditions before plant operation begins. The emergency procedures were verified during startup as plant conditions, testing, and training warrant. Surveillance tests were performed as conditions warrant
during the testing program, to demonstrate their adequacy.
Plant operating procedures were developed in approximately the same time frame
as the preparation of preoperational and initial startup tests. The operating
procedures were revised as necessary to reflect experience gained during the
testing program.
14.2.10 INITIAL FUEL LOADING, CRITICALITY, AND POWER
ASCENSION
Prior to the commencement of fuel loading, required preoperational test
procedures were evaluated, and appropriate remedial action
14.2-18 Rev. 0 WOLF CREEK was taken if the acceptance criteria was not satisfied. At the completion of fuel loading, the reactor upper internals and pressure vessel head were
installed, and additional mechanical and electrical tests were performed to
prepare the plant for nuclear operation. After final precritical tests, nuclear operation of the reactor began. This phase of testing included initial criticality, low power testing, and power level ascension. The purpose of
these tests was to establish the operational characteristics of the unit and
core, to acquire data for the proper calibration of setpoints, and to ensure
that operation is within license requirements. Section 14.2.12.3 summarizes
the tests which are performed from fuel load to rated power. The fuel loading
and post loading tests are described below.
14.2.10.1 Fuel Loading The Plant Manager or his designated representative with technical assistance
provided by Westinghouse, was responsible for the coordination of initial core
loading. The overall process of initial core loading was, in general, directed from the operating floor of the containment structure by a licensed senior
reactor operator. The licensed senior reactor operator had no additional
responsibilities other than core load operations.
The core configuration was specified as part of the core design studies
conducted well in advance of fuel loading. In the event mechanical damage was
sustained during core loading operations to a fuel assembly of a type for which
no spare was available onsite, an alternate core loading scheme could have been
determined. Any such changes would have been approved by the appropriate
Westinghouse personnel.
Core loading procedures specified the condition of fluid systems to prevent
inadvertent changes in boron concentration of the reactor coolant; the movement
of fuel to preclude the possibility of mechanical damage; the conditions under
which loading could proceed; and the responsibility and authority for
continuous and complete fuel and core component accountability.
The following conditions were met prior to core loading:
- a. The reactor containment structure was complete and
containment integrity had been demonstrated.
- b. Fuel handling tools and equipment were checked out and
operators familiarized in the use and operation of
equipment. Inspections of fuel assemblies, rod cluster control assemblies, and reactor vessel were satisfactorily completed.
14.2-19 Rev. 0 WOLF CREEK
- c. The reactor vessel and associated components were in a state of readiness to receive fuel. The water level was
maintained above the bottom of the nozzles and
recirculation maintained to ensure the required boron
concentration could be increased via the recirculation path or directly to the open vessel.
Criteria for safe loading required that loading operations stop immediately if
any of the following conditions occur.
- a. An unanticipated increase in the neutron count rates by a
factor of two occurs on all responding nuclear channels
during any single loading step after the initial nucleus
of eight fuel assemblies is loaded.
- b. An unanticipated increase in the count rate by a factor of five on any individual responding nuclear channel
during any single loading step after the initial nucleus
of eight fuel assemblies is loaded.
- c. An unanticipated decrease in boron concentration greater
than 20 ppm is determined from two successive samples of
the reactor coolant.
Loading operations could not be restarted until the situation was evaluated.
An alarm in the containment and main control room was coupled to the source
range channels with a setpoint equal to or less than five times the current
count rate. This alarm automatically alerts the loading operation personnel of
high count rate, and an immediate stop of all operations would be required
until the situation was evaluated. In the event the evacuation alarm was actuated during core loading and after it has been determined that no hazards to personnel exist, preselected personnel would be permitted to reenter the
containment to evaluate the cause and determine future action.
The core was assembled in the reactor vessel and submerged in the reactor grade
water containing sufficient dissolved boric acid to maintain a calculated core
effective multiplication factor of 0.95 or lower. The refueling pool could be
wet or dry during initial core loading. Core moderator, chemistry conditions (particularly boron concentration) were prescribed in the core loading
procedure document and verified by chemical analysis of moderator samples taken
prior to and during core loading operations.
At least two artificial neutron sources were introduced into the core at
specified points in the core during the loading program to ensure a detector
response of at least 2 counts per second attributable to neutrons.
14.2-20 Rev. 0 WOLF CREEK Core loading instrumentation consisted of two permanently installed source range (pulse type) nuclear channels and two temporary incore source range
channels. A third temporary channel could also be used as a spare. The
permanent channels, when responding, were monitored in the main control room, and the temporary channels were installed and monitored in the containment. At least one permanent channel was equipped with an audible count rate indicator.
Both plant channels have the capability of displaying the neutron flux level on
a strip chart recorder. The temporary channels indicated on scalers, and a
minimum of one channel was recorded on a strip chart recorder. Normally minimum
count rates of two counts per second attributable to core neutrons were
required on at least two of the four (i.e. two temporary and two permanent
source range detectors) available nuclear source channels at all times
following installation of the initial nucleus of eight fuel assemblies. A
response check of nuclear instruments to a neutron source was performed within
8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> prior to loading of the core, or upon resumption of loading if delay was for more than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
Fuel assemblies, together with inserted components (control rod assemblies, burnable, poison assemblies, source spider, or thimble plugging devices) were
placed in the reactor vessel one at a time, according to a previously
established and approved sequence developed to provide reliable core monitoring
with minimum possibility of core mechanical damage. The core loading procedure
documents prescribed the successive movements of each fuel assembly and its
specified inserts from its initial position in the storage racks to its final
position in the core. Fuel assembly status boards were maintained throughout
the core loading operation.
An initial nucleus of eight fuel assemblies, one containing a neutron source, is the minimum source-fuel nucleus which permitted subsequent meaningful
inverse count rate monitoring. This initial nucleus was determined by calculation to be markedly subcritical (K eff 0.95) under the required conditions of loading.
Each subsequent fuel addition was accompanied by detailed neutron count rate
monitoring to determine that the just-loaded fuel assembly did not excessively
increase the count rate and that the extrapolated inverse count rate ratio was
behaving as expected. These results for each loading step were evaluated before
the next fuel assembly was loaded. The final, as loaded, core configuration
was subcritical (K eff < 0.95) under the required loading conditions.
14.2-21 Rev. 0 WOLF CREEK 14.2.10.2 Initial Criticality Prior to initial criticality, the following tests were performed and the
results evaluated.
- a. At the completion of core loading, the reactor upper
internals and pressure vessel head were installed. A
pressure test was conducted after filling, and venting
was completed to check the leaktightness of the vessel
head installation.
- b. Mechanical and electrical tests were performed on the
control rod drive mechanisms. These tests included a
complete operational checkout of the mechanisms and
calibration of the individual rod position indicators.
- c. Tests were performed on the reactor trip circuits to
test manual trip operation, and actual control rod
assembly drop times were measured for each control rod
assembly. At all times that the control rod drive
mechanisms were being tested, the boron concentration in
the coolant was maintained so that the shutdown margin
requirements specified in the Technical Specifications
were met. During individual RCCA or RCC bank motion, source range instrumentation was monitored for
unexpected changes in core reactivity.
- d. The reactor control and reactor protection systems were
checked with simulated inputs to produce trip signals
for various trip conditions.
- e. A functional electrical and mechanical check was made of
the incore nuclear flux mapping system near normal
operating temperature and pressure.
Initial criticality was achieved by a combination of shutdown and control bank
withdrawal and reactor coolant system boron concentration dilution. The plant
conditions, precautions, and specific instructions for the approach to
criticality were specified by approved procedures.
Initially, the shutdown and control banks of control rods were withdrawn
incrementally in the normal withdrawal sequence, leaving the last withdrawn
control bank partially inserted in the core to provide effective control when
criticality was achieved. The boron concentration in the reactor coolant
system was reduced and criticality achieved by boron dilution or by subsequent
rod withdrawal following boron dilution. Throughout this period, samples of
the primary coolant were obtained and analyzed for boron concentration.
14.2-22 Rev. 0 WOLF CREEK Inverse count rate ratio monitoring using data from the normal plant source range instrumentation was used as an indication of the proximity and rate of
approach to criticality. Inverse count rate ratio data was plotted as a
function of rod bank position during rod motion and as a function of reactor
makeup water addition during reactor coolant system boron concentration reduction.
14.2.10.3 Low Power Testing Following initial criticality, a program of reactor physics measurements was
undertaken to verify that the basic static and kinetic characteristics of the
core were as expected and that the values of the kinetic coefficients assumed in the safeguards analysis were conservative.
Procedures specified the sequence of tests and measurements to be conducted and
the conditions under which each was performed in order to ensure both safety of
operation and the validity and consistency of the results obtained. If test
results deviated significantly from design predictions, if unacceptable
behavior had been revealed, or if unexplained anomalies had developed, the
plant would have been brought to a safe stable condition and the situation
reviewed to determine the course of subsequent plant operation.
These measurements were made at low power and primarily at or near normal operating temperature and pressure. Measurements were made in order to verify
the calculated values of control rod bank reactivity worths, the isothermal
temperature coefficient under various core conditions, differential boron
concentration reactivity worth, and critical boron concentrations as functions
of control rod configuration. In addition, measurements of the relative power
distributions were made, and concurrent tests were conducted on the
instrumentation, including source and intermediate range nuclear channels.
Gamma and neutron radiation surveys were performed at selected points
throughout the station. Periodic sampling was performed to verify chemical and
radio-chemical analysis of the reactor coolant.
14.2.10.4 Power Level Ascension After the operating characteristics of the reactor were verified by low power
testing, a program of power level ascension brought the unit to its full rated
power level in successive stages. At each successive stage, hold points were provided to evaluate and approve test results prior to proceeding to the next
stage. The minimum test requirements for each successive stage of power
ascension were specified in the initial startup test procedures.
14.2-23 Rev. 0 WOLF CREEK Measurements were made to determine the relative power distribution in the core as functions of power level and control assembly bank position.
Secondary system heat balance measurements ensured that the indications of
power level were consistent and provide bases for calibration of the power range nuclear channels. The ability of the reactor coolant system to respond
effectively to signals from primary and secondary instrumentation under a
variety of conditions encountered in normal operations was verified.
At prescribed power levels, the dynamic response characteristics of the primary
and secondary systems were evaluated. System response characteristics were
measured for design step load changes, rapid load reduction, and plant trips.
Adequacy of radiation shielding was verified by gamma and neutron radiation
surveys at selected points throughout the station at various power levels.
Periodic sampling was performed to verify the chemical and radio-chemical analysis of the reactor coolant.
14.2.11 TEST PROGRAM SCHEDULE
Detailed schedules for testing were prepared, reviewed, and revised on a
continuing basis as plant construction progressed.
Preoperational tests which were not performed according to schedule were
reviewed on a case-by-case basis. Administrative procedures were established
to ensure that all prerequisites were met before testing was initiated. Upon
completion of all prerequisite tests applicable to a system or subsystem, a
documented review was conducted by Start-up personnel to verify that
appropriate documentation was available and that required prerequisite tests
were satisfactorily completed. All deficiencies which would have prevented performance of preoperational tests or generated negative test results were identified and dispositioned prior to implementation of the preoperational
tests.
Preoperational testing was scheduled to commence approximately 18 months prior
to fuel loading. The preoperational tests were performed and sequenced during
this period as a function of system turnover, system interrelationships, and
acceptance for testing.
Initial startup testing was scheduled to be conducted over a period of
approximately 3 to 5 months, commencing with fuel loading. The sequential
schedule for initial startup tests ensured, insofar as practicable, that test
requirements were completed
14.2-24 Rev. 0 WOLF CREEK prior to exceeding 25-percent power for all plant structures, systems, and components that are relied upon to prevent, limit, or mitigate the consequences
of postulated accidents.
The development of the test procedures was an ongoing process consisting of preparation, review, and revision. Preoperational test procedures were
available for NRC review approximately 60 days prior to the performance of an
individual test. If an individual test procedure was not available 60 days
prior to the test, the NRC was notified of the test date and the date the test
procedure was available. Initial startup test procedures were available for
NRC review at least 60 days prior to fuel loading.
14.2.12 INDIVIDUAL TEST DESCRIPTIONS
Test abstracts were provided for both safety-related and selected nonsafety-related preoperational tests. The abstracts included test prerequisites and summaries of test methods, objectives, and acceptance criteria.
14.2.12.1 Safety-Related Preoperational Test Procedures The following sections contain test abstracts used for safety- related
preoperational tests. Table 14.2-1 provides an index of these tests.
The preoperational test procedures were designated SO3 (Safety- Related/Common
to WCGS and Callaway), SU3 (Safety-Related/WCGS Specific), SO4 thru SO9 (Nonsafety-Related/Common to WCGS and Callaway) and SU4 thru SU9 (Nonsafety-
Related/WCGS Specific) as appropriate.
14.2.12.1.1 Steam Dump System Preoperational Test (S-03AB01)
14.2.12.1.1.1 Objectives
- a. To demonstrate the operability of the steam dump control system control circuits in both the average temperature and steam pressure modes of operation.
- b. To demonstrate the operation of the main steam dump
valves and main steam cooldown valves, including valve
response to safety signals.
- c. To verify the operation of the main steam line drain
valves' control circuits, including valve response to a
turbine trip signal.
14.2-25 Rev. 0 WOLF CREEK
- d. To verify the operation of the main steam to turbine-driven feedwater pump supply valves' control logics, including valve response to an auxiliary feedwater
actuation signal (AFAS).
- e. To verify the operation of the main steam atmospheric relief valves' control circuits.
14.2.12.1.1.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are completed.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.1.3 Test Method
- a. Operability of the steam dump control system control
circuits is verified in both the average temperature and
steam pressure modes.
- b. Operability of the main steam dump valves' and main steam cooldown valves' control circuits is verified, including valve response to turbine impulse low
pressure, low-low average temperature, and condenser
shell high pressure signals.
- c. Operability of the main steam line drain valves' control
circuits is verified, including valve response to a
turbine trip signal.
- d. Operability of the main steam to turbine-driven
auxiliary feedwater pump supply valves' control logics
is verified, including valve response to an AFAS.
- e. Operability of the main steam atmospheric relief valves' control circuits is verified.
14.2.12.1.1.4 Acceptance Criteria
- a. The response of the main steam dump valves and the main steam cooldown valves to the associated turbine impulse
low pressure, low-low average temperature, and condenser
shell high pressure signals is in accordance with system
design.
- b. The main steam line drain valves open on receipt of a
turbine trip signal.
14.2-26 Rev. 13 WOLF CREEK
- c. The main steam to turbine-driven auxiliary feedwater pump supply valves open on receipt of an AFAS.
- d. The response of the main steam atmospheric relief valves to pressure signals is in accordance with system
design.
14.2.12.1.2 Main Steam Safety Valve Test (SU3-AB02)
14.2.12.1.2.1 Objectives
To verify the pressure relief setpoints of the main steam
safety valves.
NOTE: This objective may be accomplished either by bench
testing or with a pneumatic test device.
14.2.12.1.2.2 Prerequisites
The following prerequisites apply when a pneumatic test device is used.
- a. Required instrument calibration is complete.
- b. Hot Functional Testing is in progress.
- c. A Source of compressed air is available to provide air
to the air set pressure device installed on the valve
under test.
The following prerequisites apply when bench testing is
performed.
- a. Bench testing facility is available.
- b. An approved WCGS procedure is available to accomplish
- c. A source of compressed gas is available to provide
pressure to the valve under test.
14.2.12.1.2.3 Test Method
The following test method applied when a pneumatic test
device is used.
Main steam pressure is adjusted within the required range, and air is admitted to the air set pressure device on the
safety valve under test. Actual lift pressure is calculated, using the steam pressure and converted air pressure at the
time of lift.
14.2-27 Rev. 13 WOLF CREEK The following test applies when bench testing is performed.
With the main steam safety valve mounted on the bench test
facility, the spring assembly is preheated and the safety
valve is pressurized with compressed gas. Actual set pressure is determined at the time of lift.
14.2.12.1.2.4 Acceptance Criteria
Each main steam safety valve lifts within its respective
setpoint tolerance.
14.2.12.1.3 Main Steam Line Isolation Valve Test (S-03AB03)
14.2.12.1.3.1 Objectives
- a. To verify the response of the main steam bypass, drain, and auxiliary feedwater turbine warmup valves to steam
line isolation signals.
- b. To demonstrate the operability of the main steam
isolation valve control circuits, including control
circuit response to a steam line isolation signal
(SLIS).
14.2.12.1.3.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The main steam line isolation valve accumulators are
charged, and the associated hydraulic systems are
operational.
14.2.12.1.3.3 Test Method
An SLIS is initiated, and the response of the main steam bypass, main steam
drain, and auxiliary feedwater turbine warmup valves is verified.
14.2.12.1.3.4 Acceptance Criteria
- a. The main steam bypass, drain, and auxiliary feedwater
turbine warmup valves close on receipt of an SLIS.
14.2.12.1.4 Main Steam System Preoperational Test (S-03AB04)
14.2-28 Rev. 0 WOLF CREEK 14.2.12.1.4.1 Objectives
- a. To determine, during hot functional testing, the
operating times of the main steam isolation valves, main steam bypass valves, main steam dump valves, main steam cooldown valves, and the main steam atmospheric relief valves.
- b. To verify the response of the main steam isolation
valves to steam line isolation signals.
14.2.12.1.4.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Hot functional testing is in progress.
- d. The condenser is available to receive steam from the main steam system.
14.2.12.1.4.3 Test Method
- a. The main steam isolation valves, main steam bypass
valves, main steam dump valves, main steam cooldown
valves, and the main steam atmospheric relief valves are operated, and operating times are recorded.
- b. An SLIS is initiated, and the response of the main steam
isolation valves is verified.
14.2.12.1.4.4 Acceptance Criteria
- a. The operating times of the main steam isolation valves, main steam dump valves, main steam bypass valves, main
steam cooldown valves, and the main steam atmospheric relief valves are within design specifications.
- b. The main steam isolation valves close on receipt of a
steam line isolation signal.
14.2.12.1.5 Main Feedwater System Preoperational Test (S-03AEO1)
14.2.12.1.5.1 Objectives
- a. To demonstrate the operation of the feedwater system
valves and to verify the response of the feedwater
system valves to a feedwater isolation signal (FIS).
14.2-29 Rev. 13 WOLF CREEK
- b. To perform the initial operation of the steam generator feedwater pumps (SGFP).
14.2.12.1.5.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The closed cooling water system is available to provide
cooling water to the SGFP lube oil coolers.
- d. The compressed air system is available to provide air to system air-operated valves.
- e. The steam seal system is available to provide seal steam
and packing exhaust for the SGFPs.
- f. The main turbine is available for turning gear
operation.
- g. The condensate system is available to supply suction for
the SGFPs.
- h. The main condenser is available to receive SGFP turbine
exhaust.
- i. The auxiliary steam system is available to provide steam flow to the SGFP turbines.
14.2.12.1.5.3 Test Method
- a. Feedwater system valves are operated, and the proper
response of required system valves to an FIS is
verified.
- b. The turbine-driven SGFPs are operated as limited by
steam, and operating data are recorded.
- c. The motor-driven SGFP is operated, and operating data
are recorded.
14.2.12.1.5.4 Acceptance Criteria
- a. The feedwater control valves, steam generator feedwater
isolation valves, feedwater chemical injection isolation
valves, and feedwater bypass control valves close on
receipt of an FIS.
14.2-30 Rev. 0 WOLF CREEK
- b. The closing time of the feedwater isolation valves is within design specifications.
- c. The performance of the motor-driven SGFP is within
design specifications.
14.2.12.1.6 Steam Generator Level Control Test (S-03AE02)
14.2.12.1.6.1 Objectives
- a. To demonstrate the operability of the feedwater control
valves (FWCVs).
- b. To demonstrate the operability of the FWCV bypass
valves.
- c. To demonstrate the response of the FWCVs and bypass
valves to signals generated by the steam generator level
control system.
14.2.12.1.6.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.6.3 Test Method
- a. The FWCVs are operated from their respective controllers, and the FWCVs' response to feedwater flow, steamline flow, and steam generator level is verified.
- b. The FWCV bypass valves are operated from their
respective controllers, and their response to steam
generator level and neutron flux signal is verified.
14.2.12.1.6.4 Acceptance Criteria
- a. The response of the FWCVs to feedwater flow, steamline
flow, and steam generator level is in accordance with
system design.
- b. The response of the FWCV bypass valves to steam
generator level and neutron flux signal is in accordance
with system design.
14.2-31 Rev. 0 WOLF CREEK 14.2.12.1.7 Auxiliary Feedwater Motor-Driven Pump and Valve Preoperational Test (S-03ALOl)
14.2.12.1.7.1 Objectives
To demonstrate the operability of the motor-driven auxiliary feedwater pumps, determine by flow test their ability to supply water to the steam generators, and verify their response to safety signals. The operation of system motor-
operated valves, including their response to safety signals, is also verified.
14.2.12.1.7.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The condensate storage tank contains an adequate supply
of demineralized water for the performance of this test.
- d. The steam generators are available to receive water from
the auxiliary feedwater system.
14.2.12.1.7.3 Test Method
- a. Performance characteristics of the motor-driven
auxiliary feedwater pumps are verified while discharging
to the steam generators.
- b. System component control circuits are verified, including the operation of the motor-driven auxiliary
feedwater pumps and system valves on receipt of safety
signals.
14.2.12.1.7.4 Acceptance Criteria
- a. Motor-driven auxiliary feedwater pump performance
characteristics must be within design specifications.
- b. Motor-driven auxiliary feedwater pumps automatically
start on receipt of an engineered safety features
actuation signal (ESFAS) in the absence of an SIS signal
and a Class IE 4.16 kV bus undervoltage signal.
- c. Auxiliary feedwater suction valves from essential
service water system open, and suction valves from
condensate storage tank close, on condensate storage
tank low-suction-pressure signals, coincident with an
auxiliary feedwater pump ESFAS.
14.2-32 Rev. 0 WOLF CREEK 14.2.12.1.8 Auxiliary Feedwater Turbine-Driven Pump and Valve Preoperational Test (SU3-AL02)
14.2.12.1.8.1 Objectives
- a. To verify the auxiliary feedwater pump turbine
mechanical trip and throttle valve automatic operation
on an auxiliary feedwater actuation signal (AFAS).
- b. To perform the initial coupled operation of the turbine-
driven auxiliary feedwater pump. Full flow
characteristics of the turbine-driven pump will be
demonstrated during hot functional testing.
- c. To perform five consecutive, successful, cold starts of the turbine-driven auxiliary feedwater pumps.
14.2.12.1.8.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
b Required electrical power supplies and control circuits
are operational.
- c. The steam generators are available to receive water from
the auxiliary feedwater pumps.
- d. The steam generator blowdown system is available to
maintain the normal operating levels in the steam generators during auxiliary feedwater pump operation.
- e. The auxiliary steam system is available to supply steam
to the auxiliary feedwater pump turbine.
- f. For the performance characteristic test of this pump, hot functional testing (HFT) is in progress.
14.2.12.1.8.3 Test Method
- a. An AFAS is simulated, and opening of the mechanical trip
and throttle valve is verified.
- b. The turbine-driven auxiliary feedwater pump is operated
during HFT, and performance characteristics are
recorded.
- c. The ability of the turbine-driven auxiliary feedwater
pumps to start successfully five consecutive times from
cold conditions is verified.
14.2-33 Rev. 0 WOLF CREEK 14.2.12.1.8.4 Acceptance Criteria
- a. The auxiliary feedwater pump mechanical trip and
throttle valve opens automatically on an AFAS.
- b. Operating characteristics of the turbine-driven
auxiliary feedwater pump are in accordance with design.
- c. The turbine driven auxiliary feedwater pump starts
successfully five consecutive times from a cold start.
14.2.12.1.9 Auxiliary Feedwater Motor-Driven Pump Endurance Test
(SU3-AL03)
14.2.12.1.9.1 Objectives
- a. To demonstrate that the motor-driven auxiliary feedwater
pumps can operate for 48 continuous hours without
exceeding any of their limiting design specifications.
- b. To demonstrate that the motor-driven auxiliary feedwater
pumps can operate for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after a cooldown from the
48-hour test.
- c. To demonstrate that the room environmental conditions
are not exceeded during the 48-hour test.
14.2.12.1.9.2 Prerequisites
- a. Required component testing, instrument calibration and system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The appropriate auxiliary feedwater pump room coolers
are operational.
- d. The condensate storage tank is available as a water
source and to receive recirculation flow.
14.2.12.1.9.3 Test Method
Each motor-driven pump is started and operated for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after reaching
rated speed and rated discharge pressure and flow, or a greater pressure and
less flow. During the endurance run, pump- operating data and the pump room
environmental conditions are recorded. At the completion of each endurance
test, the pump is cooled for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and until pump data returns to within 20 F
of the original pretest data. The pump is then started and operated for 1
hour.
14.2-34 Rev. 0 WOLF CREEK 14.2.12.1.9.4 Acceptance Criteria
- a. The operating parameters (vibration, bearing
temperatures, etc.) of each motor-driven auxiliary
feedwater pump do not exceed the design specifications.
- b. The environmental conditions of each motor-driven
auxiliary feedwater pump room do not exceed the design
specifications.
14.2.12.1.10 Auxiliary Feedwater System Water Hammer Test (S-
03AL04)
14.2.12.1.10.1 Objectives
To demonstrate that the injection of auxiliary feedwater at rated flow into a steam generator at or near normal operating temperatures will not cause
damaging water hammer to the steam generators and/or feedwater system.
14.2.12.1.10.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The steam generators are at or near normal operating
temperature.
- d. The condensate storage tank is available as a water source.
14.2.12.1.10.3 Test Method
Auxiliary feedwater is injected into each steam generator. The feedwater system
piping and the steam generators are monitored visually and audibly to verify
that no damaging water hammer occurs.
14.2.12.1.10.4 Acceptance Criteria
No damaging water hammer occurs.
14.2.12.1.11 Auxiliary Feedwater Turbine-Driven Pump Endurance
Test (SU3-AL05)
14.2.12.1.11.1 Objectives
14.2-35 Rev. 0 WOLF CREEK
- a. To demonstrate that the turbine-driven auxiliary feedwater pump can operate for 48 continuous hours
without exceeding any of its limiting design
specifications.
- b. To demonstrate that the turbine-driven auxiliary
feedwater pump can operate for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after a cool down
from the 48-hour test.
- c. To demonstrate that the room environmental conditions
are not exceeded during the 48-hour test.
14.2.12.1.11.2 Prerequisites
- a. Required component testing, instrument calibration and system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The appropriate auxiliary feedwater pump room coolers
are operational.
- d. The condensate storage tank is available as a water
source and to receive recirculation flow.
- e. A steam source is available.
14.2.12.1.11.3 Test Method
The pump is started and operated for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after reaching rated speed and rated discharge pressure and flow, or a greater pressure and less flow. The
turbine-driven auxiliary feedwater pump operating steam is as close to normal
operating temperature as possible and is at least 400 F. During the endurance
run, pump-operating data and the pump room environmental conditions are
recorded. At the completion of the endurance test, the pump is cooled for 8
hours and until pump data returns to within 20 F of the original pretest data.
The pump is then started and operated for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
14.2.12.1.11.4 Acceptance Criteria
- a. The operating parameters (vibration, bearing
temperatures, etc.) do not exceed the design
specifications.
- b. The environmental conditions of the turbine-driven
auxiliary feedwater pump room do not exceed the design
specifications.
14.2-36 Rev. 0 WOLF CREEK 14.2.12.1.12 Reactor Coolant Pump Initial Operation (S-03BB01)
14.2.12.1.12.1 Objectives
To demonstrate the operating characteristics of the reactor coolant pumps and verify the operation of their associated oil lift pumps.
14.2.12.1.12.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The chemical and volume control system is available to provide seal water to the reactor coolant pump seals.
- d. The component cooling water system is available to
supply cooling water to the reactor coolant pumps.
14.2.12.1.12.3 Test Method
The reactor coolant pumps and associated oil lift pumps are operated, and pump
operating data are recorded.
14.2.12.1.12.4 Acceptance Criteria
Reactor coolant pump and oil lift pump operating characteristics are within
design specifications.
14.2.12.1.13 Pressurizer Relief Tank Cold Preoperational Test
(SU3-BB02)
14.2.12.1.13.1 Objectives
To demonstrate that the reactor makeup water system can supply design
pressurizer relief tank (PRT) spray flow against design backpressure. The
operation of the PRT nitrogen isolation valves, including their response to a
containment isolation signal, is also verified.
14.2.12.1.13.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-37 Rev. 0 WOLF CREEK
- c. The reactor makeup water system is available to supply water to the PRT.
- d. The service gas system is available to pressurize the
PRT.
14.2.12.1.13.3 Test Method
- a. With a design backpressure in the PRT, a reactor makeup
water pump is operated to obtain the spray flow to the
PRT.
containment isolation signal is verified.
14.2.12.1.13.4 Acceptance Criteria
- a. The reactor makeup water system supplies the design
spray flow to the PRT with design backpressure in the
PRT.
containment isolation signal. Valve closure times are
within design specifications.
14.2.12.1.14 RTD Bypass Flow Measurement (SU3-BB03)
At WCGS, test S-07BB01 (USAR Section 14.2.12.3.3) was used to satisfy the
requirement for verification of design specifications.
14.2.12.1.15 Pressurizer Pressure Control Test (S-03BB04)
14.2.12.1.15.1 Objectives
To demonstrate the stability and response of the pressurizer pressure control
system, including the verification of pressurizer pressure alarm and control
functions.
14.2.12.1.15.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The plant is at normal operating temperature and
pressure with all reactor coolant pumps running, and hot
functional testing is in progress.
14.2-38 Rev. 0 WOLF CREEK 14.2.12.1.15.3 Test Method
- a. Pressurizer pressure is varied, and the ability of the
pressurizer pressure control system to automatically
control and stabilize pressurizer pressure is verified.
- b. Pressurizer pressure is varied, and pressurizer pressure
control system alarm and control setpoints are verified.
14.2.12.1.15.4 Acceptance Criteria
- a. The pressurizer pressure control system responds, in
accordance with system design, to an increase and
decrease in system pressure.
- b. Pressurizer pressure control system alarm and control setpoints are within design specifications.
14.2.12.1.16 Reactor Coolant System Hot Preoperational Test
(S-03BB05)
14.2.12.1.16.1 Objectives
- a. To operate the reactor coolant system at full flow
conditions for a minimum of 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br /> to provide the
necessary vibration cycles on the vessel's internal
components prior to their inspection at core loading.
- b. To provide coordination and initial conditions necessary
for the conduct of those preoperational tests to be performed during heatup, normal operating temperature and pressure, and cooldown of the reactor coolant
system.
14.2.12.1.16.2 Prerequisites
- a. The reactor coolant system cold hydrostatic test is
complete.
- b. The reactor vessel internals and head are installed, and
the vessel is available to support this test.
- c. All systems and components required to support heatup, operations at normal temperature and pressure, and
cooldown of the reactor coolant system are available.
- d. Required instrument calibration is complete.
14.2-39 Rev. 0 WOLF CREEK
- e. The examination of the reactor internals in accordance with Section 3.9(N).2.4, is complete
14.2.12.1.16.3 Test Method
- a. The reactor coolant system is operated at full flow
conditions for a minimum of 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br />.
- b. Those preoperational tests required to be performed
during heatup, normal operating temperature and
pressure, and cooldown of the reactor coolant system are
completed, as coordinated by this test.
14.2.12.1.16.4 Acceptance Criteria
The reactor coolant system has operated at full flow conditions for a minimum of 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br />.
Notes: 1. The acceptance criteria for individual systems are a
part of the individual test procedures sequenced by
this procedure.
- 2. A post-hot functional examination of the reactor
internals is performed as described in Section
3.9(N).2.4.
14.2.12.1.17 Thermal Expansion (S-03BB06)
14.2.12.1.17.1 Objectives
To verify that during heatup and cooldown of the reactor coolant system the associated components, piping, support, and restraint deflections are
unobstructed and within design specifications.
14.2.12.1.17.2 Prerequisites
- a. This test is conducted in conjunction with hot
functional testing.
- b. Supports, restraints, and hangers are installed and
reference points and predicted movements established.
- c. Required instrument calibration is complete.
14.2.12.1.17.3 Test Method
During the reactor coolant system heatup and cooldown, deflection data are
recorded.
14.2-40 Rev. 0 WOLF CREEK 14.2.12.1.17.4 Acceptance Criteria
- a. Unrestricted expansion and movements are verified to be
within design specifications.
- b. Components, piping, supports, and restraints return to
their baseline cold position in accordance with system
design.
14.2.12.1.18 Pressurizer Level Control Test (S-03BB07)
14.2.12.1.18.1 Objectives
To demonstrate the stability and response of the pressurizer level control
system, including the verification of pressurizer level alarm and control functions.
14.2.12.1.18.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The letdown and charging portions of the chemical and
volume control system are available to vary pressurizer
level.
- d. The plant is at normal operating temperature and pressure, and hot functional testing is in progress.
14.2.12.1.18.3 Test Method
- a. Pressurizer level is varied and the ability of the
pressurizer level control system to automatically
control and stabilize pressurizer level is verified.
- b. Pressurizer level is varied, and pressurizer level
control system alarm and control setpoints are verified.
14.2.12.1.18.4 Acceptance Criteria
- a. The response and stability of the pressurizer level
control system are within design specifications.
- b. The pressurizer level control system alarm and control
functions are within design specifications.
14.2-41 Rev. 0 WOLF CREEK 14.2.12.1.19 Pressurizer Heater and Spray Capability Test (SU3-BB08)
14.2.12.1.19.1 Objectives
To determine the electrical capacity of the pressurizer heaters, and the rate
of pressure increase from the operation of all pressurizer heaters.
14.2.12.1.19.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The plant is at normal operating temperature and
pressure with all reactor coolant pumps running, and hot
functional testing is in progress.
14.2.12.1.19.3 Test Method
- a. Pressurizer heaters are energized, and heater capacity
is calculated.
- b. With the pressurizer spray valves closed, all
pressurizer heaters are energized, and the time to reach
a 2,300 psig system pressure is measured and recorded.
14.2.12.1.19.4 Acceptance Criteria
- a. The capacity of the pressurizer heaters is within design
limits.
- b. The pressurizer pressure response to the actuation of
all pressurizer heaters is within design limits.
14.2.12.1.20 Reactor Coolant System Flow Measurement Test
(SU3-BB09)
At WCGS, Test S-07BB03 (USAR Section 14.2.12.3.5) is used to satisfy the
requirements for verification of design specifications.
14.2.12.1.21 Reactor Coolant System Flow Coastdown Test
(SU3-BB10)
14.2-42 Rev. 0 WOLF CREEK At WCGS, Test S-07BB04 (USAR Section 14.2.12.3.6) is used to satisfy the requirements for verification of design specifications.
14.2.12.1.22 Reactor Coolant System Hydrostatic Test (S-03BBll)
14.2.12.1.22.1 Objectives
To verify the integrity and leaktightness of the reactor coolant system and the
high-pressure portions of associated systems.
14.2.12.1.22.2 Prerequisites
- a. Required system flushing/cleaning are complete.
- b. The reactor coolant pumps are available to support this test.
- c. The reactor vessel's lower internals, upper internals, filter assembly, and the closure head are installed.
The studs are tensioned to design value for the
associated hydrostatic test pressure
- d. Temporary temperature instrumentation is installed for
measuring the temperature of the steam generator tube
sheets, the bottom of the pressurizer, and the closure
flange of the reactor vessel.
- e. A charging pump or test pump is available to pressurize
the system.
- f. Required instrument calibration is complete.
14.2.12.1.22.3 Test Method
The minimum temperature for pressurizing the system is established. The
reactor coolant pumps are operated as required to establish the required
temperature. The system is then pressurized to test pressure, and system
welds, flanges, piping, and components are monitored for leakage.
14.2.12.1.22.4 Acceptance Criteria
The reactor coolant system and associated high-pressure systems are verified
leaktight in accordance with the requirements of the ASME Boiler and Pressure
Vessel Code,Section III, "Nuclear Components," through the Winter 1975
Addenda.
14.2.12.1.23 Pressurizer Continuous Spray Flow Verification Test
(SU3-BB12)
14.2-43 Rev. 0 WOLF CREEK At WCGS, Test S-07BB05 (USAR Section 14.2.12.3.7) was used to satisfy the requirements for verification of design specifications.
14.2.12.1.24 Pressurizer Relief Valve and PRT Hot Preoperational
Test (S-03BB13)
14.2.12.1.24.1 Objectives
To demonstrate that the operating times of the pressurizer power- operated
relief valves are within design specifications. The ability of the reactor
coolant drain tank portion of the liquid radwaste system to cool down the
pressurizer relief tank (PRT) at the design rate is also verified.
14.2.12.1.24.2 Prerequisites
- a. Required component testing and instrument calibration are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The PRT is at a normal operating level and is aligned
for normal operation.
- d. The liquid radwaste system is available to cool down the
PRT via the reactor coolant drain tank heat exchanger.
- e. The plant is at normal operating temperature and pres-
sure, and hot functional testing is in progress.
14.2.12.1.24.3 Test Method
- a. Pressurizer power-operated relief valves are operated, and opening times recorded.
- b. Following the operation of the pressurizer power-
operated relief valves, the PRT is cooled down via the
reactor coolant drain tank heat exchanger, and the
cooldown rate is calculated and recorded.
14.2.12.1.24.4 Acceptance Criteria
- a. Power-operated relief valve operating times are within
design specifications.
14.2-44 Rev. 0 WOLF CREEK
- b. The reactor coolant drain tank portion of the liquid radwaste system cools down the PRT at a rate within
design specifications.
14.2.12.1.25 Reactor Coolant Loop Vibration Surveillance Test (S-03BB14)
14.2.12.1.25.1 Objectives
To verify that the dynamic effects experienced during reactor coolant loop
steady flow and reactor coolant loop pump transients as measured during hot
functional testing (HFT) do not exceed acceptance criteria for the primary loop
piping and components.
14.2.12.1.25.2 Prerequisites
- a. Hot functional testing is in progress.
- b. Reference points for vibrational measurement of the
reactor coolant piping and components are established.
- c. All subject systems are available for the specified
dynamic operation.
- d. Required instrument calibration is complete.
14.2.12.1.25.3 Test Method
- a. The systems are aligned for the specified dynamic
operation.
- b. The specified dynamic event is initiated and the reactor
coolant piping and component responses are monitored.
14.2.12.1.25.4 Acceptance Criteria
The measured deflections for each of the test measurement points are within a
specified percent of the calculated reference deflections.
14.2.12.1.26 Leak Detection System Preoperational Test
(SU3-BB15A)
14.2.12.1.26.1 Objectives
- a. To determine, during hot functional testing, the amount
of identified and unidentified leakage from the reactor
coolant system and verify that the leakage is within
design limits.
14.2-45 Rev. 0 WOLF CREEK
- b. To demonstrate the ability to detect an increase in reactor coolant system leakage.
14.2.12.1.26.2 Prerequisites
- a. Required instrument calibration is complete.
- b. Hot functional testing is in progress, and the reactor
coolant system is at normal operating temperature and
pressure.
- c. The volume control tank contains an adequate supply of
water to support this test.
- d. The reactor coolant drain tank and associated pumps are available to support this test.
14.2.12.1.26.3 Test Method
- a. The reactor coolant system identified and unidentified
leakage rates are determined by monitoring the reactor
coolant system water inventory.
- b. A known leakage rate is initiated, and the ability to
detect an increase in leakage is verified.
14.2.12.1.26.4 Acceptance Criteria
- a. Reactor coolant system identified and unidentified
leakage is within design limits.
- b. The ability to detect an increase in reactor coolant
system leakage is verified.
14.2.12.1.27 Leak Detection System Preoperational Test
(SU3-BB15B)
14.2.12.1.27.1 Objectives
- a. To demonstrate the operation of the leak detection
system and to verify the ability of the system to detect
leakage within the required time limit as specified by
design.
- b. The operation of the containment particulate and
radioactive gas monitoring portions of the Leak
Detection System are verified in SU4-SP01, Process
Radiation Monitoring System Preoperational Test.
14.2-46 Rev. 0 WOLF CREEK 14.2.12.1.27.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. The containment normal sumps, instrument tunnel sump, floor drain tank, auxiliary building sump and associated
pumps are available to support this test.
14.2.12.1.27.3 Test Method
- a. A known simulated leakage is initiated, and the ability
of the system to detect the leakage within the design
time is verified.
14.2.12.1.27.4 Acceptance Criteria
- a. The ability of the leak detection system to detect a
leak within the design time is verified.
14.2.12.1.28 RTD/TC Cross Calibration (S-03BB16)
14.2.12.1.28.1 Objectives
To provide a functional checkout of the reactor coolant system resistance
temperature detectors (RTDs) and incore thermocouples and to generate
isothermal cross-calibration data for subsequent correction factors to
indicated temperatures.
14.2.12.1.28.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Initial plant heatup, during hot functional testing, is
in progress, and all reactor coolant pumps are
operating.
14.2.12.1.28.3 Test Method
At various temperature plateaus, RTD and incore thermocouple data are recorded.
Isothermal cross-calibration correction factors for individual thermocouples
and the installation corrections for individual RTDs are determined.
14.2-47 Rev. 0 WOLF CREEK 14.2.12.1.28.4 Acceptance Criteria
- a. Individual RTD readings are within the design
specifications.
- b. The installation corrections of the RTDs are within
design specifications.
14.2.12.1.29 Chemical and Volume Control System Major Component
Test (S-03BG01)
14.2.12.1.29.1 Objectives
To demonstrate the operation of the centrifugal charging pumps and associated minimum flow valves, including their response to safety signals.
14.2.12.1.29.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The refueling water storage tank contains an adequate
supply of demineralized water for the performance of
this test.
- d. The component cooling water system is available to provide cooling water to the centrifugal charging pump oil coolers.
14.2.12.1.29.3 Test Method
- a. Centrifugal charging pumps are operated, and performance
characteristics are verified.
- b. Centrifugal charging pump and minimum flow valve control
logics are verified, including their response to safety
signals.
14.2.12.1.29.4 Acceptance Criteria
- a. Centrifugal charging pump performance characteristics
are within design specifications.
- b. Each centrifugal charging pump receives a start signal
from the load sequencer.
14.2-48 Rev. 0 WOLF CREEK
- c. If a safety injection signal is present, a centrifugal charging pump minimum flow valve will open if the
associated pump flow is low and will close if the
associated pump flow is above the minimum flow
requirement of the pump.
14.2.12.1.30 Seal Injection Preoperational Test (SU3-BG02)
14.2.12.1.30.1 Objective
To demonstrate the ability of the chemical and volume control system to supply
adequate seal water injection flow to the reactor coolant pumps and verify the
operation of the seal water return containment isolation valves, including
their response to a CIS.
14.2.12.1.30.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The volume control tank contains an adequate supply of
demineralized water for the performance of this test.
- d. Cooling water is available to the charging pumps.
14.2.12.1.30.3 Test Method
- a. With a charging pump in operation, seal water throttle valves are adjusted to maintain the required flow to
each reactor coolant pump.
- b. Seal water return containment isolation valves control
logics are verified, including their response to a CIS.
14.2.12.1.30.4 Acceptance Criteria
- a. Seal water injection flow to each reactor coolant pump
is within design specifications.
- b. Seal water return containment isolation valves close on
receipt of a CIS. Valve closure times are within design
specifications.
14.2-49 Rev. 0 WOLF CREEK 14.2.12.1.31 Charging System Preoperational Test (SU3-BG03)
14.2.12.1.31.1 Objective
To demonstrate positive displacement charging pump (replaced by the normal charging pump per DCP 04590) operating characteristics and to verify the operation of the regenerative heat exchanger inlet isolation valves and the
letdown isolation valves, including their response to a safety injection signal (SIS).
14.2.12.1.31.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The volume control tank contains an adequate supply of
demineralized water for the performance of this test.
- d. Cooling water is available to the positive displacement charging pump (replaced by the normal charging pump per DCP 04590).
- e. The reactor coolant system is available to receive
charging system flow.
14.2.12.1.31.3 Test Method
- a. The positive displacement charging pump (replaced by the normal charging pump per DCP 04590)is operated, and pump operating data are recorded.
- b. Regenerative heat exchanger inlet isolation valve and
letdown system isolation valve control circuits are
verified, including valve response to safety injection signals.
14.2.12.1.31.4 Acceptance Criteria
- a. Positive displacement charging pump (replaced by the normal charging pump per DCP 04590)operating characteristics are within design specifications.
- b. Charging pump to regenerative heat exchanger inlet
isolation valves close on receipt of an SIS. Valve
closure times are within design specifications.
- c. The letdown line containment isolation valves close on
receipt of a containment isolation signal. Valve
closure times are within design specifications.
14.2-50 Rev. 12 WOLF CREEK 14.2.12.1 32 Boron Thermal Regeneration System Preoperational Test (SU3-BG04)
14.2.12.1.32.1 Objective
To verify the operation of the boron thermal regeneration system, and
associated control circuits. Performance characteristics of the chemical and
volume control system chiller pumps are also verified.
14.2.12.1.32.2 Prerequisites
- a. Required component testing, instrument calibration and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The volume control tank contains an adequate supply of
demineralized water for the performance of this test.
- d. The chemical and volume control system chiller surge
tank contains an adequate supply of demineralized water
for the performance of this test.
14.2.12.1.32.3 Test Method
- a. The chemical and volume control system chiller pumps are
operated and performance characteristics are verified.
- b. Boron thermal regeneration system component control circuits are verified.
14.2.12.1.32.4 Acceptance Criteria
- a. The chemical and volume control system chiller pumps'
operating characteristics are within design
specifications.
- b. The chemical and volume control system chiller pumps
start automatically when the boron thermal regeneration
system is placed in the borate or dilute mode of
operation.
14.2.12.1.33 Boric Acid Blending System Preoperational Test (SU3-
BG05)
14.2.12.1.33.1 Objectives
- a. To demonstrate the operating characteristics of boron
injection makeup and boric acid transfer pumps and
14.2-51 Rev. 0 WOLF CREEK verify the ability of the boric acid blending system to make up at design flow rates to the chemical and volume
control system (CVCS).
- b. To verify the operation of system component control circuits in all modes of operation.
- c. To demonstrate by flow test the ability of the reactor
makeup water system to supply water to the boric acid
blender.
- d. To demonstrate by flow test the ability of the boric
acid system to supply an emergency boration flow to the
charging pump suction.
- e. To verify the operation of volume control tank valves and associated control circuits, including valve
response to safety signals.
14.2.12.1.33.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor makeup water system is available to supply
water to the boric acid blender and boric acid batching
tank.
- d. A charging pump is available to receive and discharge
flow from the boric acid transfer pumps.
- e. The volume control tank (VCT) contains an adequate
supply of demineralized water for the performance of
this test.
14.2.12.1.33.3 Test Method
- a. The boron injection makeup and boric acid pumps are
operated, performance data recorded, and the ability of
the system to make up to the CVCS at design flow rates
is verified.
- b. System component control circuits are verified in all
modes of operation.
14.2-52 Rev. 0 WOLF CREEK
- c. With a reactor makeup water pump in operation, flow is verified to the boric acid blender and boric acid
batching tank.
- d. With both boric acid transfer pumps in operation and a charging pump taking a suction from the VCT and
discharging to the reactor coolant loops, the emergency
boration flow rate from the transfer pumps to the
charging pump suction is recorded.
- e. The emergency boration flow rate via gravity feed from
the boric acid tanks to the charging pump suction is
recorded.
- f. Proper operation of the reactor makeup water system is verified when the reactor makeup control system (RMCS) is operated in the manual, dilute, alternate dilute, and
automatic modes.
- g. The operation of the VCT outlet valves control circuits
is verified, including their response to a safety
injection signal.
14.2.12.1.33.4 Acceptance Criteria
- a. The boron injection makeup and boric acid transfer pump
operating characteristics are within design
specifications.
- b. The flow rate to the boric acid blender from the reactor makeup water system is within design specifications.
- c. The emergency boration flow rates to the charging pump
suction are within design specifications.
- d. The boric acid transfer pumps and the reactor makeup
water pumps start automatically on a low level in the
volume control tank when the RMCS is in the automatic
mode.
- e. VCT outlet valves close on receipt of a safety injection
signal when the associated charging pump supply valve
from the refueling water storage tank is open.
- f. Refueling water storage tank to charging pump suction
valves open on receipt of a safety injection signal.
- g. The boric acid transfer pumps stop on receipt of a load
shed signal.
14.2-53 Rev. 0 WOLF CREEK
- h. The boric acid filter to charging pump valve supply breaker trips open on receipt of a load shed signal.
14.2.12.1.34 Chemical and Volume Control System Hot
Preoperational Test (S-03BG06)
14.2.12.1.34.1 Objectives
- a. To determine by flow test that all letdown and cleanup
flow rates are within design specifications.
- b. To determine, by comparison of boron concentrations, that boric acid addition to the reactor coolant system
has occurred, using the normal and emergency flow paths.
- c. To determine by flow test the ability of the chemical and volume control system (CVCS) to make up at design
flow rates and boron concentrations to the reactor
coolant system in all modes of operation.
- d. To determine by operational test that the letdown
containment isolation valve closure times are within
design specifications.
- e. To demonstrate the ability of the pump room coolers to
maintain room temperatures within design limits.
14.2.12.1.34.2 Prerequisites
- a. Required component testing, instrument calibration, and system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The plant is at normal operating temperature and
pressure, and hot functional testing is in progress.
- d. The CVCS pump rooms are closed, and their associated
pump room coolers are operational.
14.2.12.1.34.3 Test Method
- a. The letdown throttle valves are adjusted to establish
letdown flow within design specifications.
- b. Boric acid addition to the reactor coolant system is
verified, using the normal and emergency flow paths, by
comparing the change in boron concentrations.
14.2-54 Rev. 0 WOLF CREEK
- c. With a charging pump in operation, the ability of the CVCS, in all modes of operation, to make up at design
flow rates and boron concentrations to the reactor
coolant system is verified.
- d. With letdown flow established, the letdown containment
isolation valves are operated, and operating times are
recorded.
- e. During CVCS pump operation, pump room temperature data
are recorded.
14.2.12.1.34.4 Acceptance Criteria
- a. All letdown and cleanup flow rates are within design specifications
- b. The boric acid addition system is capable of adding
boron to the reactor coolant system via both the normal
and emergency flow paths.
reactor coolant system are within design specifications
in all modes of operation.
- d. The letdown containment isolation valves' closure times
are within design specifications.
- e. The CVCS pump room coolers maintain the room temperature
within design limits.
- f. The boron thermal regeneration system (BTRS) can vary
the reactor coolant boron concentration as required for
daily load cycle at 85 percent core life.
14.2.12.1.35 Fuel Pool Cooling and Cleanup System Preoperational
Test (SU3-EC01)
14.2.12.1.35.1 Objectives
- a. To demonstrate the operating characteristics of the fuel
pool cooling, fuel pool cleanup, and pool skimmer pumps
and to verify that the associated instrumentation and
controls are functioning properly.
- b. To verify that the fuel pool cleanup pump refueling
water storage tank (RWST) suction isolation valves close
on receipt of a safety injection signal (SIS).
14.2-55 Rev. 0 WOLF CREEK
- c. To verify that each fuel pool cooling pump room cooler starts when the associated fuel pool cooling pump
starts.
14.2.12.1.35.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Cooling water is available to the fuel pool cooling and
cleanup system heat exchangers.
- d. The liquid radwaste system is available to drain the refueling pool to the RWST.
- e. The essential service water system is available to
provide cooling water to the spent fuel pool pump room
coolers.
- f. The spent fuel pool and fuel transfer canals are filled
to their normal operating levels.
14.2.12.1.35.3 Test Method
- a. The fuel pool cooling, fuel pool cleanup, and pool
skimmer pumps are operated in their various modes, and
pump operating data are recorded.
- b. System component control circuits are verified, including the operation of system pumps and valves on
receipt of safety signals.
- c. The ability of each fuel pool cooling pump room cooler
to start when the associated fuel pool cooling pump
starts is verified.
14.2.12.1.35.4 Acceptance Criteria
- a. The operating characteristics of the fuel pool cooling, fuel pool cleanup, and pool skimmer pumps are within
design specifications.
- b. The fuel pool cleanup pumps RWST suction isolation
valves close on receipt of an SIS.
14.2-56 Rev. 0 WOLF CREEK
- c. Each fuel pool cooling pump trips on a low spent fuel pool level signal.
- d. Each fuel pool cooling pump trips on receipt of a load
shed signal.
- e. Each fuel pool cooling pump room cooler starts when the
associated fuel pool cooling pump starts.
14.2.12.1.36 Spent Fuel Pool Leak Test (S-03EC02)
14.2.12.1.36.1 Objectives
- a. To demonstrate the integrity of the spent fuel pool, cask loading pit, and fuel transfer canal.
- b. To demonstrate the leaktightness of the cask loading pit
gate and the fuel transfer canal gate.
14.2.12.1.36.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The spent fuel pool is filled to the normal operating
level.
- d. The cask loading pit level is below the level of the fuel pool gate.
- e. The fuel transfer canal level is below the level of the
fuel pool gate.
- f. The reactor makeup water system is available to provide
demineralized water to the spent fuel pool.
- g. A source of compressed air is available to pressurize
the system standpipes.
14.2.12.1.36.3 Test Method
The cask loading pit gate and fuel transfer canal gate are visually inspected
for leakage. A leak test is performed on the spent fuel pool, cask loading
pit, and fuel transfer canal, using the associated leak chase standpipes.
14.2-57 Rev. 0 WOLF CREEK 14.2.12.1.36.4 Acceptance
No leakage is observed from the spent fuel pool, cask loading pit, fuel
transfer canal, cask loading pit gate, and fuel transfer canal gate.
14.2.12.1.37 Essential Service Water System Preoperational Test
(SU3-EF01)
Test SU3-EF02 combined with Test SU3-EF01, Essential
Service Water System Preoperational Test.
14.2.12.1.37.1 Objectives
- a. To demonstrate the capability of the essential service
water system to provide cooling water flow during the LOCA mode of operation. The operation and response of system valves to align the system in the LOCA flow mode
on safety injection signals, load sequence signals, and
low suction pressure signals are also verified.
- b. To demonstrate the operating characteristics of the
essential service water (ESW) pumps and verify their
response to safety signals.
- c. To demonstrate the operability of the backpressure
control valves, including their response to safety
signals.
14.2.12.1.37.2 Prerequisites
- a. Required component testing, instrument calibration, and system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The compressed air system is available to the system
air-operated valves.
14.2.12.1.37.3 Test Method
- a. System operating characteristics are verified in the
LOCA mode of operation.
- b. Safety signals are simulated, and the responses of the
system valves and the ESW pumps are verified.
- c. The ESW pumps are operated and pump operating data are
recorded.
14.2-58 Rev. 0 WOLF CREEK
- d. The operability of the backpressure control valves, including their response to safety signals is verified.
14.2.12.1.37.4 Acceptance Criteria
- a. Components supplied by the essential service water
system receive flows that are within design
specifications in the LOCA mode of system operation.
- b. System valve operation in response to safety signals is
within design requirements.
- c. System valve operating times are within design
specifications.
- d. The ESW pumps' operating characteristics are within design specifications.
- e. Each ESW pump responds properly to load sequence and
load shed signals.
- f. The time required for each ESW pump to reach rated flow
is within design specifications.
- g. System backpressure valves close upon receipt of a LOCA
sequencer or safety injection signal.
- h. An auxiliary feedwater pump low suction pressure signal
will close the ESW pump breakers if a zero sequencer
signal is not present.
14.2.12.1.38 Component Cooling Water System Preoperational Test
(S-03EG01)
14.2.12.1.38.1 Objectives
- a. To demonstrate the capability of the component cooling
water system to provide cooling water during the normal, shutdown, and post-LOCA modes of operation.
- b. To demonstrate the operating characteristics of the
component cooling water pumps and to verify that the
associated instrumentation and controls are functioning
properly, including system response to safety signals.
14.2.12.1.38.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
14.2-59 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
14 2.12.1.38.3 Test Method
- a. System operating characteristics are verified in the
normal, shutdown, and post-LOCA modes of operation.
- b. Safety signals are simulated, and the response of system
pumps and valves is verified.
14.2.12.1.38.4 Acceptance Criteria
- a. The performance characteristics of each component
cooling water pump are within design specifications.
- b. Components supplied by the component cooling water
system receive flows that are within design
specifications with the system operating in the normal, shutdown, and post-LOCA modes.
- c. Component cooling water pump and valve responses to load
sequence, containment isolation, and safety injection
signals are within design specifications.
- d. Closure times for the component cooling water supply and
return valves to the reactor coolant system are within
design specifications.
- e. Component cooling water pump response to centrifugal charging pump start signals is in accordance with system design.
14.2.12.1.39 Residual Heat Removal System Cold Preoperational
Test (SU3-EJ01)
14.2.12.1.39.1 Objective
To demonstrate the operability of the Residual Heat Removal (RHR) pumps, demonstrate by flow test their ability to supply water at rated pressure and
flow, and verify their response to safety signals. The operation of system
motor-operated valves, including their response to safety signals, are also
verified. The RWST control and alarm circuits are also verified.
14.2.12.1.39.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
14.2-60 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
- c. The reactor vessel head is removed and the water level
is above the nozzles.
- d. The refueling water storage tank contains an adequate
supply of demineralized water for the performance of
this test.
- e. Cooling water is available to the RHR pumps and heat
exchangers.
- f. The instrument air system is available to supply air to
system air-operated valves.
14.2.12.1.39.3 Test Method
- a. Performance characteristics of the RHR pumps are
verified during discharge to the reactor coolant hot and
cold loops and test recirculation.
verified, including the operation of the RHR pumps and
system valves on receipt of safety signals.
14.2.12.1.39.4 Acceptance Criteria
- a. RHR pump performance characteristics are within design
specifications.
- b. RHR system components align or actuate in accordance
with system design to safety injection, containment
isolation, load sequencing, load shed, and tank level
signals.
- c. The time required for each RHR pump to reach rated speed
is within design specifications.
- d. RHR system motor-operated valve closure times are within
design specifications.
14.2.12.1.40 Residual Heat Removal System Hot Preoperational Test
(S-U3-EJ02)
14.2.12.1.40.1 Objectives
- a. To demonstrate the ability of the residual heat removal
(RHR) system to cool down the reactor coolant system
(RCS) at its design rate.
14.2-61 Rev. 0 WOLF CREEK
- b. To demonstrate the ability of the RHR pump room coolers to maintain room temperature within design limits.
14.2.12.1.40.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The component cooling water system is supplying water to
each RHR heat exchanger.
- d. The RCS is being cooled down during hot functional testing.
- e. The RHR pump rooms are closed, and their associated pump
room coolers are operational.
14.2.12.1.40.3 Test Method
- a. While the RCS is being cooled down with the RHR system, the heat transfer is obtained by performing a heat
balance across each RHR heat exchanger.
- b. When RHR pump room temperatures have stabilized, room
temperature data is recorded.
14.2.12.1.40.4 Acceptance Criteria
- a. The RHR system is capable of cooling down the reactor
coolant system at its design rate.
- b. The RHR pump room coolers can maintain room temperature
within design limits.
14.2.12.1.41 Safety Injection System Cold Preoperational Test
(SU3-EM01)
14.2.12.1.41.1 Objectives
To demonstrate the response of the safety injection pumps and associated valves
to safety signals.
14.2.12.1.41.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete
14.2-62 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
14.2.12.1.41.3 Test Method
The response of the safety injection pumps and associated valves to safety
signals is verified
14.2.12.1.41.4 Acceptance Criteria
- a. The safety injection pumps and associated valves align
or actuate in accordance with system design to
containment isolation signals, load shedding signals, and load sequencing signals.
14.2.12.1.42 Safety Injection Flow Verification Test (SU3-EM02)
14.2.12.1.42.1 Objectives
- a. To demonstrate the operating characteristics of the
safety injection pumps and the centrifugal charging
pumps.
- b. To demonstrate the capability of the safety injection
pumps to provide balanced flow to the reactor coolant
system and prevent runout flow in the cold leg and hot
leg injection modes.
- c. To demonstrate the capability of the charging pumps to
provide balanced flow to the reactor coolant system and prevent runout flow in the boron injection mode.
- d. To demonstrate the capability of the residual heat
removal pumps to provide required net positive suction
head to the safety injection pumps and the centrifugal
charging pumps.
- e. To demonstrate that the safety injection and centrifugal
charging pump room coolers maintain room temperature
within design limits.
- f. To demonstrate that associated system valve operating
times are within specified limits.
14.2.12.1.42.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
14.2-63 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
- c. The CVCS is available to supply rated flow to the
reactor coolant system via the boron injection path, while simultaneously supplying other required loads.
- d. The residual heat removal system is available to supply
adequate suction head to the safety injection and
centrifugal charging pumps during required injection
modes.
- e. The borated refueling water storage tank contains an
adequate supply of demineralized water for this test.
- f. The reactor vessel is available to receive water, and the temporary reactor vessel pumpdown system is
operational (if required).
- g. The auxiliary building HVAC system is available to cool
the pump rooms and verify associated pump interlocks.
- h. The accumulator safety injection system piping from the
safety injection system to the reactor coolant system is
available, and an accumulator tank is capable of
receiving water.
- i. Cooling water is available to required pumps and heat
exchangers.
- j. The compressed air system is available to supply air to associated system valves.
- k. The residual heat removal system hot leg and cold leg
flow orifices have been sized for required flow.
14.2.12.1.42.3 Test Method
- a. The safety injection pumps are operated in the cold leg
flow mode to verify pump performance characteristics and
to identify the weaker pump.
- b. The safety injection cold leg branch lines are balanced
using the weaker safety injection pump and the balance
checked with the stronger pump. The balance is
performed so that injection flow is maximized while
preventing pump runout.
14.2-64 Rev. 0 WOLF CREEK
- c. The safety injection hot leg branch lines are balanced, using their respective safety injection pump. The
balance is performed so that injection flow is maximized
while preventing pump runout.
- d. The centrifugal charging pumps are operated in the boron
injection mode to determine pump performance
characteristics and to identify the weaker pump.
- e. The boron injection branch lines are balanced, using the
weaker centrifugal charging pump and the balance checked
with the stronger pump. The balance is performed such
that injection flow is maximized while preventing pump
runout.
- f. Each residual heat removal pump is operated in series with the centrifugal charging pumps and safety injection
pumps to verify that the residual heat removal pumps can
supply adequate suction head.
- g. With each centrifugal charging pump and safety injection
pump operating, pump room temperatures are allowed to
stabilize, and room temperature data are recorded.
14.2.12.1.42.4 Acceptance Criteria
- a. The safety injection and centrifugal charging pump
response times and valve operating times are within
design specifications.
- b. The safety injection pump room coolers start with their respective pump.
- c. The NPSH provided by the residual heat removal pumps to
the centrifugal charging pumps and safety injection
pumps is within system design specifications.
- d. Safety injection cold leg, hot leg, and safety injection
pump flows are within design specifications.
- e. Boron injection and centrifugal charging pump flows are
within design specifications.
- f. The safety injection and centrifugal charging pump room
coolers can maintain room temperature within design
limits.
14.2-65 Rev. 0 WOLF CREEK 14.2.12.1.43 Safety Injection Check Valve Test (SU3-EM03)
14.2.12.1.43.1 Objectives
To demonstrate the integrity of accumulator outlet line and loop safety injection line check valves and backup check valves by performing backleakage
tests. The operability of the various safety injection line check valves under
their design pressure conditions is also verified.
14.2.12.1.43.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The reactor coolant system is at normal operating
pressure.
14.2.12.1.43.3 Test Method
- a. Check valve leak testing is performed with the reactor
coolant system at normal operating pressure.
- b. Check valve operability is performed by verifying flow
through the check valves at reduced reactor coolant
pressure.
14.2.12.1.43.4 Acceptance Criteria
- a. Check valve leakage rates are within limits established
by Technical Specifications Section 3.4.6.2f.
- b. Injection line check valve operability is demonstrated
by verification of flow through the check valves in each
of the safety injection lines to the reactor coolant
system.
14.2.12.1.44 Boron Injection Tank and Recirculation Pump Test
(SU3-EM04)
This test has been deleted at Wolf Creek since the boron injection requirements
have been eliminated due to the decrease in required boron concentration.
14.2-66 Rev. 0 WOLF CREEK 14.2.12.1.45 Containment Spray System Nozzle Air Test (S-03EN01)
14.2.12.1.45.1 Objectives
To demonstrate that the spray nozzles in the containment spray header are clear of obstructions.
14.2.12.1.45.2 Prerequisites
A source of compressed air is available to pressurize the spray headers.
14.2.12.1.45.3 Test Method
Air flow is initiated through the containment spray headers, and unobstructed
flow is verified through each nozzle.
14.2.12.1.45.4 Acceptance Criteria
All containment spray nozzles are clear and unobstructed, as evidenced by air
passing through each nozzle.
14.2.12.1.46 Containment Spray System Preoperational Test
(SU3-EN02)
14.2.12.1.46.1 Objectives
- a. To demonstrate the operation of system components, including their response to safety signals, and verify
that the associated instrumentation and controls are
functioning properly. System flow characteristics in the test and simulated accident modes are also verified.
- b. To demonstrate the ability of the pump room coolers to
maintain room temperatures within design limits.
14.2.12.1.46.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The refueling water storage tank contains an adequate
supply of demineralized water for the performance of
this test.
- d. The auxiliary building HVAC system is available to cool
the pump rooms and verify associated pump interlocks.
14.2-67 Rev. 0 WOLF CREEK
- e. The containment spray pump rooms are closed.
14.2.12.1.46.3 Test Method
- a. Performance characteristics of the containment spray pumps are verified in the test mode, recirculating to
the refueling water storage tank, and in the simulated
accident mode.
- b. System component control circuits are verified, including the operation of system pumps and valves on
receipt of load sequence/shedder and CSAS/CIS signals, respectively.
- c. During system operations, spray additive eductor operating characteristics are verified.
- d. During containment spray pump operation, pump room
temperature data are recorded.
14.2.12.1.46.4 Acceptance Criteria
- a. Containment spray pump performance characteristics are
within design specifications for the tested modes of
operation.
- b. Containment spray pump and valve response to load
sequence/shedder and CSAS/CIS is verified, and the
associated response times are within design
specifications.
- c. Spray additive eductor operating characteristics are
within design specifications.
- d. The containment spray pump room coolers maintain the
room temperature within design limits.
14.2.12.1.47 Accumulator Testing (S-03EP01)
14.2.12.1.47.1 Objectives
To determine the operability of each safety injection accumulator and obtain, by flow test, each accumulator's discharge line resistance to flow. The
ability of the accumulator discharge line isolation valves to open under
maximum differential pressure conditions is verified, as is the response of
accumulator system valves to safety signals.
14.2-68 Rev. 0 WOLF CREEK 14.2.12.1.47.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor vessel head and reactor internals are not
installed, and the vessel is available to receive water.
- d. A source of compressed air and nitrogen is available.
- e. The refueling water storage tank contains an adequate
supply of demineralized water for the performance of this test.
14.2.12.1.47.3 Test Method
- a. Each accumulator is filled and partially pressurized with
the discharge valves closed. The discharge valves are
opened, discharging the accumulators to the reactor
vessel, and performance data are recorded.
- b. Each accumulator discharge line isolation valve is
operated under maximum differential pressure conditions
of normal accumulator precharge pressure and zero reactor
coolant pressure, and the valve operating times are
recorded.
- c. Accumulator system valve control circuits are verified, including their response to safety injection and
containment isolation signals.
14.2.12.1.47.4 Acceptance Criteria
- a. Each accumulator's discharge line resistance to flow
(L/D) is in accordance with design specifications.
- b. Each accumulator's discharge line isolation valve
opening time under maximum differential pressure
conditions is within design specifications.
- c. The accumulator system nitrogen supply containment
isolation valve closes on receipt of a containment
isolation signal. Valve closure time is within design
specifications.
- d. Each accumulator discharge isolation valve opens on
receipt of a safety injection signal.
14.2-69 Rev. 0 WOLF CREEK 14.2.12.1.48 Auxiliary Feedwater Pump Turbine Preoperational Test (SU3-FC01)
14.2.12.1.48.1 Objectives
- a. To demonstrate the operation of the auxiliary feedwater
pump (AFWP) turbine and its support equipment, while
uncoupled from the pump.
- b. To demonstrate control of the AFWP turbine from the
control room as well as the auxiliary shutdown panel.
14.2.12.1.48.2 Prerequisites
- a. Required component testing, instrument calibration and system flushing/cleaning are complete.
- b. Steam is available to the AFWP turbine.
14.2.12.1.48.3 Test Method
- a. AFWP turbine system valves are operated and required
response to various signals is verified.
- b. The turbine is operated and proper control is verified
from the control room as well as the auxiliary shutdown
panel, and operating data are recorded.
- c. The turbine is brought to high speed at which time the
mechanical and electronic overspeed trips are verified.
14.2.12.1.48.4 Acceptance Criteria
- a. The AFWP turbine can be controlled from the control room
panel and the auxiliary shutdown panel.
- b. The mechanical and electronic overspeed trips actuate to
shut down the turbine in accordance with the design.
14.2.12.1.49 Essential Service Water Pumphouse HVAC
Preoperational Test (SU3-GD01)
14.2.12.1.49.1 Objectives
- a. To demonstrate the capacity of the essential service
water (ESW) pumproom supply fans.
- b. To demonstrate ESW pumproom unit heater response to a
load shed signal.
14.2-70 Rev. 0 WOLF CREEK 14.2.12.1.49.2 Prerequisites
- a. Required component testing and instrument calibration
are completed.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.49.3 Test Methods
- a. The ESW pumphouse supply fans are operated and flow data
are recorded.
- b. Response of the ESW pumproom unit heaters to load shed signal is verified.
14.2.12.1.49.4 Acceptance Criteria
- a. The ESW pumphouse supply fan capacities are within
design specification.
- b. A load shed signal will trip the ESW pumproom unit
heaters' circuit breaker.
14.2.12.1.50 Miscellaneous Building HVAC System Preoperational
Tests (SU3-GF01, SU3-GF02, SU3-GF03)
14.2.12.1.50.1 Objectives To demonstrate the capacity of; 1) the auxiliary feedwater pump room cooler
fans, 2) the main steam enclosure building supply and exhaust fans and 3) the
tendon access gallery transfer fans and to verify that the associated
instrumentation and controls are functioning properly. The responses of the
main steam enclosure building dampers and tendon access gallery dampers to
safety signals are also verified.
(At Wolf Creek Generating Station, this test was performed in three independent
parts. In addition, the auxiliary boiler room fan was treated as part of
preoperational test SU4-GF01.)
14.2.12.1.50.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-71 Rev. 0 WOLF CREEK
- c. The miscellaneous building HVAC system is air balanced.
14.2.12.1.50.3 Test Method
- a. Flow data are recorded while the fans are operating.
- b. The response of system dampers to a safety injection
signal (SIS) is verified.
14.2.12.1.50.4 Acceptance Criteria
- a. System fan capacities are within design specifications.
- b. The main steam enclosure building and tendon access
gallery dampers close on receipt of a SIS.
14.2.12.1.51 Fuel Building HVAC System Preoperational Test
(S-03GG01)
14.2.12.1.51.1 Objectives
To demonstrate that the emergency exhaust fans are capable of maintaining a
negative pressure in the fuel building or the auxiliary building during
accident conditions with the buildings isolated. To demonstrate the capacities
of the fuel building supply unit fans, emergency exhaust fans, and the spent
fuel pool pump room cooler fans. The operability of system instrumentation and
controls, including the components' response to safety signals, is also
verified.
14.2.12.1.51.2 Prerequisites
- a. Required component testing, instrument calibration, and
system air balancing are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The compressed air system is available to supply the
air-operated dampers in the fuel building.
- d. Required portions of the auxiliary building HVAC system
have been air balanced and are available to support this
test.
14.2.12.1.51.3 Test Method
- a. With the fuel building closed, the system is operated in
its normal configuration, and the fuel building supply
14.2-72 Rev. 0 WOLF CREEK unit fan and spent fuel pool pump room cooler fan capacities are verified.
- b. With a fuel building isolation signal (FBIS) present, the emergency exhaust fan capacities and negative fuel building pressures are verified.
- c. With a safety injection signal (SIS) present and the
auxiliary building isolated, the emergency exhaust fan
capacities and negative auxiliary building pressures are
verified.
14.2.12.1.51.4 Acceptance Criteria
- a. The auxiliary building and fuel building pressures maintained by the emergency exhaust fans are within design specifications.
- b. The fuel building supply fans, emergency exhaust fans, and spent fuel pool pump room cooler fans' capacities
are within design specifications.
- c. The fuel building ventilation system fans and dampers
properly respond to FBIS and SIS, in accordance with
system design.
14.2.12.1.52 Control Building HVAC System Preoperational Test
(SU3-GK01)
14.2.12.1.52.1 Objectives To demonstrate the capacities of the control building supply air unit, control
building exhaust fans, access control exhaust fans, control room pressurization
fans, control room filtration fans, control room air conditioning units, access
control fan coil units, counting room fan coil unit, and Class IE electrical
equipment ac units. To demonstrate that the control room pressurization fans
are capable of maintaining a positive pressure in the control room following a
control room ventilation isolation signal (CRVIS). The system instrumentation
and controls, including the components' responses to safety signals, are also
verified. To demonstrate that the ventilation to battery rooms 1 through 4 is
in accordance with system design.
14.2.12.1.52.2 Prerequisites
- a. Required component testing, instrument calibration, and
system air balancing are complete.
14.2-73 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
- c. The compressed air system is available to supply air to
system air-operated dampers.
14.2.12.1.52.3 Test Method
- a. The control building system fans are operated, and fan
capacities are verified.
- b. Proper response of system components to control room
ventilation isolation signals (CRVIS) and safety
injection signals (SIS) is verified.
- c. With a CRVIS present, the ability of each control room pressurization fan to maintain the control room at a
positive pressure is verified.
- d. The air flow to battery rooms 1 through 4 is verified.
14.2.12.1.52.4 Acceptance Criteria
- a. The control building HVAC system fan capacities are
within design specifications.
properly respond to CRVIS and SIS in accordance with
system design.
- c. The control room pressure maintained by the control room pressurization fans is within design specification.
- d. The air flow to battery rooms 1 through 4 is in
accordance with system design.
14.2.12.1.53 Auxiliary Building HVAC System Preoperational Test
(SU3-GL01)
14.2.12.1.53.1 Objectives
To demonstrate the capacities of the auxiliary building supply unit fans, auxiliary/fuel building normal exhaust fans, the auxiliary building fan coil
units, pump room coolers, penetration room coolers, decon tank exhaust scrubber
fans, access tunnel transfer fan, and penetration cooling fan. The system
instrumentation and controls, including components' response to safety and fire
signals, are also verified.
14.2-74 Rev. 0 WOLF CREEK 14.2.12.1.53.2 Prerequisites
- a. Required component testing, instrument calibration, and
system air balancing are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The compressed air system is available to supply the
air-operated dampers in the auxiliary building.
- d. The fuel building HVAC system has been air balanced, and
is available to support this test.
14.2.12.1.53.3 Test Method
- a. The system is operated in its normal configuration, and
the system fan capacities are verified.
- b. Proper responses of system components to safety
injection and fire signals are verified.
14.2.12.1.53.4 Acceptance Criteria
- a. The auxiliary building fan capacities are within design
specifications.
- b. The auxiliary building fans and dampers properly respond
to safety injection and fire signals, in accordance with
system design.
14.2.12.1.54 Diesel Generator Building HVAC Preoperational Test
(S-03GM01)
14.2.12.1.54.1 Objectives
To demonstrate the capacities of the diesel generator room supply fans and to
verify that the system instrumentation and controls function properly, including the response of fans and associated dampers to a diesel generator run
signal and room temperature signals.
14.2.12.1.54.2 Prerequisites
- a. Required component testing and instrument calibration
are completed.
- b. Required electrical power supplies and control circuits
are operational.
14.2-75 Rev. 0 WOLF CREEK
- c. The diesel generator building HVAC system is air balanced.
- d. The respective diesel generator is not operating while
the room is under test.
14.2.12.1.54.3 Test Method
- a. Flow data are recorded, while the diesel generator room
supply fans are operating.
- b. The responses of the diesel generator room supply fans
and exhaust dampers to a diesel generator run signal and
to room temperature signals are verified.
14.2.12.1.54.4 Acceptance Criteria
- a. The capacities of the diesel generator room supply fans
are within design specifications.
- b. The diesel generator room exhaust dampers open on
receipt of a diesel generator run signal.
- c. The diesel generator room supply fans start on a high
room temperature signal and stop on a low room
temperature signal.
14.2.12.1.55 Containment Cooling System Preoperational Test
(SU3-GN01)
14.2.12.1.55.1 Objectives
To demonstrate the capacities of the hydrogen mixing, containment cooling, and
pressurizer cooling fans and verify their associated instrumentation and
controls function properly, including fan response to safety signals.
14.2.12.1.55.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The essential service water system is available to
supply water to the containment coolers.
- d. The containment cooling system has been air balanced.
14.2-76 Rev. 0 WOLF CREEK 14.2.12.1.55.3 Test Method
- a. The hydrogen mixing, containment cooling, and
pressurizer cooling fans are operated, flow data
recorded, and fan capacities calculated.
- b. The response of the hydrogen mixing and containment
cooling fans to safety signals is verified.
14.2.12.1.55.4 Acceptance Criteria
- a. The capacities of the hydrogen mixing, containment
cooling, and pressurizer cooling fans are within design
specifications.
- b. The hydrogen mixing and containment cooling fans align or actuate in response to safety injection, shutdown
sequencer, and LOCA sequencer signals, in accordance
with system design.
14.2.12.1.56 CRDM Cooling Preoperational Test (S-03GN02)
14.2.12.1.56.1 Objectives
To demonstrate the operating characteristics of the cavity cooling, control rod
drive mechanism (CRDM), and the elevator machine room exhaust fans and verify
their associated instrumentation and controls, including their response to
safety signals.
14.2.12.1.56.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The CRDM and cavity cooling portions of the containment
cooling system are air balanced.
14.2.12.1.56.3 Test Method
- a. The cavity cooling, elevator machine room exhaust, and
CRDM fans are operated, flow data recorded, and fan
capacities calculated.
- b. The response of the CRDM fans to a safety injection
signal is verified.
14.2-77 Rev. 0 WOLF CREEK 14.2.12.1.56.4 Acceptance Criteria
- a. The capacities of the cavity cooling, elevator machine
room exhaust, and CRDM fans are within design
specifications.
- b. The appropriate CRDM fans supply breakers open on
receipt of a safety injection signal.
14.2.12.1.57 Integrated Containment Leak Rate Test (SU3-GP01)
14.2.12.1.57.1 Objective
To demonstrate that the total leakage from the containment does not exceed the
maximum allowable leakage rate at the calculated peak containment internal pressure. The operability of the containment cooling fans at design accident pressure is also verified.
14.2.12.1.57.2 Prerequisites
- a. The containment penetration leakage rate tests (type B
tests) and containment isolation valve leakage tests
(type C tests) are complete and the containment has been
pressurized to 115 percent of the design pressure.
- b. All containment isolation valves are closed by normal
actuation methods.
- c. Containment penetrations, including equipment hatches
and personnel airlocks, are closed.
- d. Portions of fluid systems that are part of the
containment boundary, that may be opened directly to the
containment or outside atmosphere under post-accident
conditions, are opened or vented to the appropriate
atmosphere to place the containment in as close to post-
accident conditions as possible.
- e. Required instrument calibration is complete.
14.2.12.1.57.3 Test Method
- a. The integrated containment leak rate test (type A test)
is conducted, using the absolute method, described in
the ANSI/ANS 56.8-1981 Containment System Leakage
Testing Requirements. Measurements of containment
atmosphere dry-bulb temperature, dew point and pressure
are taken to calculate the leakage rate. A standard
14.2-78 Rev. 0 WOLF CREEK statistical analysis of data is conducted, using a linear least squares fit regression analysis to
calculate the leakage rate.
- b. On completion of the leak rate test, a verification test is conducted to confirm the capability of the data
acquisition and reduction system to satisfactorily
determine the calculated integrated leakage rate. The
verification test is accomplished by imposing a known
leakage rate on the containment, or by pumping back a
known quantity of air into the containment through a
calibrated flow measurement device.
- c. While at the design accident pressure, data is recorded
for the containment cooling fans.
14.2.12.1.57.4 Acceptance Criteria
The containment integrated leakage does not exceed the maximum allowable
leakage rate at a calculated peak containment internal pressure, as defined in
The containment cooling fan operation at design accident pressure is in
accordance with design.
14.2.12.1.58 Reactor Containment Structural Integrity Acceptance
Test (SU3-GP02)
14.2.12.1.58.1 Objectives
To demonstrate the structural integrity of the reactor containment building.
14.2.12.1.58.2 Prerequisites
- a. Containment penetrations are installed, and penetration
leak tests are completed.
- b. Containment penetrations, including equipment hatches
and personnel airlocks, are closed.
- c. Required instrument calibration is complete.
14.2.12.1.58.3 Test Method
The containment is pressurized at 115 percent of the design pressure, and
deflection measurements and concrete crack inspections are made to determine
that the actual structural response is within the limits predicted by the
design analyses.
14.2-79 Rev. 0 WOLF CREEK 14.2.12.1.58.4 Acceptance Criteria
The containment structural response is within the limits predicted by design
analyses.
14.2.12.1.59 Post-Accident Hydrogen Removal System
Preoperational Test (S-03GS01)
14.2.12.1.59.1 Objectives
- a. To demonstrate that the hydrogen recombiner performance
characteristics are within design specifications.
- b. To determine the operation of system dampers and valves, including the response of hydrogen purge and hydrogen monitoring containment isolation valves to a CIS.
- c. To demonstrate the operability of the hydrogen analyzers
and their ability to sample the containment atmosphere.
14.2.12.1.59.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.59.3 Test Method
- a. Performance characteristics are recorded, while the hydrogen recombiners are operating.
- b. System valve and damper control circuits are verified, including the response of hydrogen purge and hydrogen
monitoring containment isolation valves to a CIS.
- c. The hydrogen analyzers are operated, and performance
data recorded.
14.2.12.1.59.4 Acceptance Criteria
- a. Hydrogen recombiner performance characteristics are
within design specifications.
isolation valves close on receipt of a CIS. Valve
closure times are within design specifications.
14.2-80 Rev. 0 WOLF CREEK 14.2.12.1.60 Containment Purge System HVAC Preoperational Test (S-03GT01)
14.2.12.1.60.1 Objectives
To demonstrate the capacities of the containment minipurge supply and exhaust, shutdown purge supply and exhaust, and containment atmospheric control fans.
The operation of system instrumentation and controls, including the response of
system fans and dampers to safety signals, is also verified.
14.2.12.1.60.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The containment purge HVAC system has been air balanced.
- d. The compressed air system is available to supply air to
system valves and dampers.
14.2.12.1.60.3 Test Method
- a. The containment minipurge supply and exhaust, shutdown
purge supply and exhaust, and containment atmospheric
control fans are operated, flow data recorded, and fan
capacities calculated.
- b. The response of system fans and dampers to safety signals is verified.
14.2.12.1.60.4 Acceptance Criteria
- a. The capacities of the containment minipurge supply and
exhaust, shutdown purge supply and exhaust, and
containment atmospheric control fans are within design
specifications.
- b. System fans and dampers align or actuate in response to
containment purge isolation and safety injection
signals, in accordance with system design. Damper
closure times are within design specifications.
14.2-81 Rev. 0 WOLF CREEK 14.2.12.1.61 Gaseous Radwaste System Preoperational Test (S-03HA01)
14.2.12.1.61.1 Objectives
- a. To demonstrate the performance characteristics of the
gas decay tank drain pump, waste gas compressors, and
catalytic hydrogen recombiners, including their response
to safety signals.
- b. To verify the operability of system valves, including
the response of the waste gas discharge valve to a high-
radiation signal.
- c. To verify that system instrumentation and controls function properly.
14.2.12.1.61.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The component cooling water system is available to
supply cooling water to the waste gas compressors and
catalytic hydrogen recombiners.
- d. The service gas system is available to provide nitrogen, hydrogen, and oxygen to the catalytic hydrogen recombiners.
- e. The reactor makeup water system is available to provide
water to the waste gas compressors, catalytic hydrogen
recombiners, and the waste gas decay tank drain header.
14.2.12.1.61.3 Test Method
- a. Performance characteristics of the gas decay tank drain
pump, and waste gas compressors are verified.
- b. Hydrogen is introduced to the system and the catalytic
hydrogen recombiners performance are verified.
- c. System component control circuits are verified, including component response to safety signals.
14.2.12.1.61.4 Acceptance Criteria
- a. Performance characteristics of the gas decay tank drain
pump, waste gas compressors, and catalytic hydrogen
recombiners are within design specifications.
14.2-82 Rev. 0 WOLF CREEK
- b. The waste gas discharge valve automatically closes on a high-radiation signal.
- c. The waste gas compressors trip on a high-high or low-low
moisture separator level, high or low moisture separator pressure, low compressor suction pressure, or low
component cooling water flow.
high-high hydrogen concentration in the recombiner feed, high-high oxygen concentration in the recombiner
discharge, high cooler-condenser discharge temperature, high-high recombiner discharge temperature, low-low
recombiner flow, and high-high recombiner reactor inlet
temperature.
blocked on high oxygen concentration in the recombiner
feed and high catalyst bed temperature.
- f. The volume control tank vent valve closes on a hydrogen
recombiner trip, low volume control tank pressure, and
low waste gas compressor suction pressure.
14.2.12.1.62 Emergency Fuel Oil System Preoperational Test
(S-03JE01)
14.2.12.1.62.1 Objectives
To demonstrate the capability of the system to provide an adequate fuel supply to the emergency diesel generator fuel oil day tanks and verify that the associated instrumentation and controls are functioning properly.
14.2.12.1.62.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.62.3 Test Method
- a. Fuel oil is transferred from the fuel oil storage tank
to the fuel oil day tanks by means of the transfer
pumps. Flow and pressure characteristics are recorded.
- b. Fuel oil day tank levels are varied to verify the
transfer pump automatic operations.
14.2-83 Rev. 0 WOLF CREEK
- c. Response to fire and emergency diesel generator start signals are verified.
14.2.12.1.62.4 Acceptance Criteria
- a. The transfer pump flow capacity is verified for later
comparison to the fuel consumption rate (S-03NF02).
- b. Control circuit automatic operation from fuel oil day
tank levels, fire signals, and diesel generator start
signals is within design specifications.
14.2.12.1.63 Spent Fuel Pool Crane Preoperational Test
(SU3-KE01)
14.2.12.1.63.l Objectives
- a. To demonstrate proper operation of the spent fuel pool
bridge crane control circuits and associated interlocks.
- b. To document the data obtained during testing of the
spent fuel pool bridge crane at 125 percent of rated
load.
- c. To verify the ability of the spent fuel pool bridge
crane and associated fuel handling tools to transfer a
dummy fuel assembly.
14.2.12.1.63.2 Prerequisites
- a. Required component testing and instrument calibration are completed.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
14.2.12.1.63.3 Test Method
- a. Operability of the spent fuel pool bridge crane control
circuits and associated interlocks is verified.
- b. Ability of the spent fuel pool bridge crane and
associated fuel handling tools to transfer a dummy fuel
assembly is verified.
14.2-84 Rev. 0 WOLF CREEK 14.2.12.1.63.4 Acceptance Criteria
- a. The spent fuel pool bridge crane electric and manual
hoists support 125 percent of their rated load.
- b. The spent fuel pool bridge crane monorail center span
deflection at rated load is within design
specifications.
- c. The spent fuel pool crane bridge, trolley and hoist
speeds at rated loads are within design specifications.
- d. All control circuits and interlocks associated with the
spent fuel pool bridge crane operate in accordance with
system design.
- e. While transferring a dummy fuel assembly, the spent fuel
pool bridge crane and associated fuel handling tools
operate in accordance with system design.
14.2.12.1.64 New Fuel Elevator Preoperational Test (SU3-KE02)
14.2.12.1.64.1 Objectives
- a. To demonstrate proper operation of the new fuel elevator
control circuits and associated interlocks.
- b. To verify the ability of the new fuel elevator to raise
and lower a dummy fuel assembly.
14.2.12.1.64.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
14.2.12.1.64.3 Test Method
Operability of the new fuel elevator including control circuits and associated
interlocks is verified.
14.2.12.1.64.4 Acceptance Criteria
- a. All control circuits and interlocks associated with the
new fuel elevator operate in accordance with system
design.
14.2-85 Rev. 0 WOLF CREEK
- b. While raising and lowering a dummy fuel assembly, the new fuel elevator operates in accordance with system
design.
14.2.12.1.65 Fuel Handling and Storage Preoperational Test (SU3-KE03)
14.2.12.1.65.1 Objectives
- a. To verify the ability of the spent fuel cask handling
crane, and associated fuel handling tools to transfer a
dummy fuel assembly.
- b. To demonstrate proper operation of the spent fuel cask
handling crane control circuits and associated interlocks.
- c. To document the data obtained during testing of the
spent fuel cask handling crane at 125 percent of rated
load.
14.2.12.1.65.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
14.2.12.1.65.3 Test Method
- a. During the transfer of a dummy fuel assembly, the
operability of the spent fuel cask handling crane and
associated fuel handling tools is verified.
- b. Operability of the spent fuel cask handling crane
control circuits and associated interlocks is verified.
14.2.12.1.65.4 Acceptance Criteria
- a. While transferring a dummy fuel assembly, the spent fuel
cask handling crane and associated fuel handling tools
operate in accordance with system design.
- b. All control circuits and interlocks associated with the
spent fuel cask handling crane operate in accordance
with system design.
14.2-86 Rev. 0 WOLF CREEK
- c. The spent fuel cask handling crane hoist supports 125 percent of rated load.
- d. The spent fuel cask handling crane bridge center span
deflection at rated load is within design specifications.
- e. The spent fuel cask handling crane bridge, trolley and
hoist speeds at rated loads are within design
specifications.
14.2.12.1.66 Fuel Transfer System Preoperational Test
(SU3-KE04)
14.2.12.1.66.l Objectives
- a. To demonstrate proper operation of the fuel transfer
system control circuits and associated interlocks.
- b. To verify the ability of the fuel transfer system and
associated handling tools to transfer a dummy fuel
assembly.
14.2.12.1.66.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
14.2.12.1.66.3 Test Method
- a. Operability of the fuel transfer system control circuits
and associated interlocks is verified.
- b. During the transfer of a dummy fuel assembly, the
operability of the fuel transfer system and associated
handling tools is verified.
14.2.12.1.66.4 Acceptance Criteria
- a. All control circuits and interlocks associated with the
fuel transfer system operate in accordance with system
design.
14.2-87 Rev. 0 WOLF CREEK
- b. While transferring a dummy fuel assembly, the fuel transfer system and associated handling tools operate in
accordance with system design.
14.2.12.1.67 Refueling Machine and RCC Change Fixture Preoperational Test (SU3-KE05)
14.2.12.1.67.1 Objectives
- a. To demonstrate proper operation of the refueling
machine, rod cluster control change fixture and
containment building polar crane control circuits and
associated interlocks.
- b. To document the data obtained during testing of the containment building polar crane at 125 percent of rated load.
- c. To verify the ability of the refueling machine to
transfer a dummy fuel assembly.
14.2.12.1.67.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
- d. A dummy control rod assembly is available.
14.2.12.1.67.3 Test Method
- a. Operability of the refueling machine and rod cluster
control change fixture control circuits and associated
bridge, trolley, hoist and gripper interlocks is
verified.
- b. Operability of the containment building polar crane
control circuits and associated interlocks is verified.
14.2.12.1.67.4 Acceptance Criteria
- a. All control circuits and interlocks associated with the
refueling machine and rod cluster control change fixture
operate in accordance with system design.
14.2-88 Rev. 0 WOLF CREEK
- b. The control circuits and interlocks associated with the containment building polar crane operate in accordance
with system design.
- c. The containment polar crane main and auxiliary hoists support 125 percent of their rated load.
- d. The containment polar crane bridge center span
deflection at rated load is within design
specifications.
- e. The containment polar crane bridge, trolley, and hoist
speeds at rated loads are within design specifications.
- f. While transferring a dummy fuel assembly, the refueling machine operates in accordance with system design.
14.2.12.1.68 Refueling Machine Indexing Test (S-03KE06)
14.2.12.1.68.1 Objectives
- a. To verify the indexing of the refueling machine and
establish bridge rail reference points for future
operations.
- b. To demonstrate the ability to transfer the dummy fuel
assembly to the reactor vessel.
14.2.12.1.68.2 Prerequisites
- a. Required component testing and instrument calibration are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. A dummy fuel assembly is available.
14.2.12.1.68.3 Test Method
- a. While transferring a dummy fuel assembly with the
refueling machine, the bridge rail is marked at key
transfer points.
14.2.12.1.68.4 Acceptance Criteria
- a. The refueling machine can load a dummy fuel assembly in
each of the reactor vessel fuel loading locations.
14.2.12.1.69 Fuel Handling System Integrated Preoperational Test
(SU3-KE07)
14.2-89 Rev. 0 WOLF CREEK 14.2.12.1.69.1 Objective
To verify the ability of the refueling machine, new fuel elevator, fuel
transfer system, spent fuel bridge crane, spent fuel cask handling crane and
associated fuel handling tools to transfer a dummy fuel assembly.
14.2.12.1.69.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor vessel, refueling pool, refueling canal and spent fuel pool are filled with demineralized water.
- d. A dummy fuel assembly is available.
14.2.12.1.69.3 Test Method
During the transfer of a dummy fuel assembly, the operability of the refueling
machine, new fuel elevator, fuel transfer system, spent fuel bridge crane, spent fuel cask handling crane and associated fuel handling tools is verified.
14.2.12.1.69.4 Acceptance Criteria
While transferring a dummy fuel assembly, the refueling machine, new fuel
elevator, fuel transfer system, spent fuel bridge crane, spent fuel cask
handling crane and associated fuel handling tools operate in accordance with system design.
14.2.12.1.70 Diesel Generator Mechanical Preoperational Test
(S-03KJ01)
14.2.12.1.70.1 Objectives
- a. To demonstrate the performance characteristics of the
diesel generators and associated auxiliaries, and verify
that each diesel reaches rated speed within the required
time.
- b. To verify the operability of all control circuits
associated with the diesel generator and diesel
auxiliaries, including the control circuits response to
safety signals.
14.2-90 Rev. 0 WOLF CREEK
- c. To demonstrate the capability of each air storage tank to provide five diesel cranking cycles without being
recharged.
14.2.12.1.70.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The essential service water system is available to
provide cooling water to the diesel engine intercooler
heat exchanger.
- d. The emergency fuel oil system is available to provide
fuel oil to the diesel generators.
- e. The fire protection system is available to support this
test.
14.2.12.1.70.3 Test Method
- a. The diesel generators are started, and the time required
to reach rated speed is recorded.
- b. With the diesel generators and associated auxiliaries
operating, performance characteristics are verified.
- c. The operability of all control circuits associated with the diesel generator and diesel auxiliaries, including
the control circuits' response to safety signals, is
verified.
- d. The ability of each air storage tank to provide five
diesel cranking cycles, without being recharged, is
verified.
14.2.12.1.70.4 Acceptance Criteria
- a. The time required for each diesel generator to reach
rated speed is within design specifications.
- b. The performance characteristics of the diesel generators
and associated auxiliaries are within design
specifications.
- c. Each diesel generator starts automatically on receipt of
a safety injection signal or a bus under-voltage signal.
14.2-91 Rev. 0 WOLF CREEK
- d. Each diesel generator trips automatically on receipt of each of the following signals:
Lube oil pressure low
Jacket coolant temperature high Crankcase pressure high
Start failure
Engine overspeed
Diesel generator ground overcurrent
Diesel generator differential current
- e. The diesel generator neutral ground overcurrent trip
signal is bypassed when the diesel generator is
operating in the emergency mode.
- f. Each air storage tank is capable of providing five diesel cranking cycles, without being recharged.
- g. Each starting air compressor has the ability to charge
its respective air tank from minimum to normal pressure
within the required time.
14.2.12.1.71 4160-V (Class IE) System Preoperational Test
(S-03NB01)
14.2.12.1.71.1 Objectives
- a. To demonstrate that the 4,160-V Class IE busses can be
energized from their normal and alternate sources.
- b. To verify that a 4,160-V Class IE bus digital undervoltage signal trips the associated incoming feeder
breakers.
- c. To verify that a degraded bus voltage condition will
trip the associated incoming feeder breakers.
- d. To verify proper operation of system instrumentation and
alarms.
14.2.12.1.71.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-92 Rev. 0 WOLF CREEK 14.2.12.1.71.3 Test Method
- a. The 4,160-V Class IE busses are energized from their
normal source, and bus voltages are recorded.
- b. The 4,160-V Class IE busses are energized from their
alternate source, and bus voltages are recorded.
- c. 4,160-V Class IE bus undervoltage signals are simulated, and proper operation of the 4,160-V Class IE feeder
breakers is verified.
14.2.12.1.71.4 Acceptance Criteria
- a. The voltage of each 4,160-V Class IE bus, when supplied from its normal source, is within design specifications.
- b. The voltage of each 4,160-V Class IE bus, when supplied
from its alternate source, is within design
specifications.
- c. A 4,160-V Class IE bus digital undervoltage signal will
trip the appropriate bus incoming feeder breakers.
- d. A degraded voltage condition on either 4,160-V Class IE
bus will cause an alarm and, if it continues, trip the
appropriate bus incoming feeder breakers.
- e. A degraded voltage condition on either 4,160-V Class IE
bus coincident with a safety injection actuation signal will immediately trip the bus incoming feeder breakers.
14.2.12.1.72 Diesel Generator Electric Preoperational Test
(S-03NE01)
14.2.12.1.72.1 Objectives
- a. To demonstrate that each diesel generator is capable of
35 consecutive valid starts with no failure.
- b. To demonstrate the ability of each diesel generator to
carry the design load for the time required to reach
equilibrium temperature plus l hour, without exceeding
design limits.
- c. To demonstrate the ability of each diesel generator to
attain and stabilize frequency and voltage within the
design limits and time.
14.2-93 Rev. 0 WOLF CREEK
- d. To demonstrate the capability of each diesel generator to withstand a full-load rejection without exceeding
speeds or voltages that cause tripping or damage.
- e. To demonstrate the operability of each diesel generator feeder breaker and associated interlocks.
- f. To demonstrate the ability of the diesel cooling water
system to maintain the diesel temperature within design
specifications, while the diesel generators are
operating at full load.
- g. To demonstrate the ability of each diesel generator to
start and shed the largest single motor while supplying
all other sequenced loads, maintaining voltage and frequency within design limits.
14.2.12.l.72.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The essential service water system is available to
provide cooling water to the diesel generator
intercooler heat exchanger.
- d. The emergency fuel oil system is available to provide fuel oil to the diesel generators.
- e. The fire protection system is available to support this
test.
- f. The 4.16-kV busses are available for loading to support
this test.
14.2.12.1.72.3 Test Method
- a. The ability of each diesel generator to undergo 35
consecutive starts with no failure is verified.
- b. The ability of each diesel generator to carry the design
load for the time required to reach equilibrium
temperature, plus 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, without exceeding design
limits, is verified.
14.2-94 Rev. 0 WOLF CREEK
- c. The ability of each diesel generator to attain and stabilize frequency and voltage within the design limits
and time is verified.
- d. The ability of each diesel generator to withstand a full-load rejection, without exceeding speeds or
voltages that cause tripping, is verified.
- e. The operability of each diesel generator feeder breaker
and associated interlocks is verified.
- f. While operating each diesel generator at full-load
conditions, the ability of the diesel cooling water
system to maintain diesel temperatures within design
specifications is verified.
- g. The ability of each diesel generator to start and shed
the largest fully loaded single motor while supplying
all other sequenced loads and maintain voltage and
frequency within design limits is verified.
14.2.12.1.72.4 Acceptance Criteria
- a. Each diesel generator is capable of carrying the design
load for the time required to reach equilibrium
temperature, plus 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, without exceeding design
limits.
- b. Each diesel generator can attain and stabilize frequency
and voltage within design limits and time.
- c. Each diesel generator is capable of withstanding a full-
load rejection without exceeding speeds or voltages that
cause tripping.
- d. When a diesel generator is operating in the nonemergency
(test) mode, the associated diesel generator feeder
breaker trips on receipt of any of the following
signals:
Generator overcurrent
Reverse power
Loss of field
Underfrequency
- e. The diesel generator stops and the associated diesel
generator feeder breaker trips on receipt of any of the
following signals:
Generator differential current
Neutral ground overcurrent
14.2-95 Rev. 0 WOLF CREEK
- f. When a diesel generator is operating in the emergency mode, the following trip signals are bypassed:
Neutral ground overcurrent
Generator overcurrent Reverse power
Loss of field
Underfrequency
- g. Each diesel generator cooling water system, with the
diesel generators operating at full-load, maintains the
diesel temperatures within design specifications.
- h. Each diesel generator has the capability of starting and
shedding the largest fully loaded single motor while supplying all other sequenced loads, maintaining voltage and frequency within design limits.
- i. Diesel generators are capable of 35 consecutive valid
starts with no failure.
14.2.12.1.73 Integrated Control Logic Test (SU3-NF01)
14.2.12.1.73.1 Objectives
- a. To demonstrate that the actuation of the LOCA sequencer, shutdown sequencer, safety-related load shed, and
nonsafety-related load shed circuits on receipt of the
appropriate undervoltage, safety injection, containment
spray actuation, diesel generator breaker position, and normal and alternate 4,160-V feeder breaker position signals is in accordance with system design.
- b. To demonstrate that the LOCA sequencer, shutdown
sequencer, safety-related load shed, and nonsafety-
related load shed circuits shed and sequence loads in
accordance with system design.
14.2.12.1.73.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.73.3 Test Method
- a. Undervoltage, safety injection, containment spray
actuation, diesel generator breaker position, and
normal and
14.2-96 Rev. 0 WOLF CREEK alternate 4,160-V feeder breaker position signals are initiated, and the actuation of the LOCA sequencer, shutdown sequencer, safety-related load shed, and
nonsafety-related load shed circuits is verified.
- b. Signals are initiated to actuate the LOCA sequencer, shutdown sequencer, safety-related load shed, and
nonsafety-related load shed circuits, and proper load
shed and load sequencing are verified.
14.2.12.1.73.4 Acceptance Criteria
- a. Actuation of the LOCA sequencer, shutdown sequencer, safety-related load shed, and nonsafety-related load
shed circuits on receipt of under-voltage, safety injection, containment spray actuation, diesel generator breaker position, and normal and alternate 4,160-V
feeder breaker position signals is in accordance with
system design.
- b. The LOCA sequencer, shutdown sequencer, safety-related
load shed, and nonsafety-related load shed circuits shed
and sequence loads in accordance with system design.
14.2.12.1.74 LOCA Sequencer Preoperational Test (S-03NF02)
14.2.12.1.74.1 Objectives
- a. To demonstrate that initiation of a safety injection
signal (SIS) will shed the nonsafety-related loads, start the diesel generator, and sequence the associated equipment. The ability of each 4,160-V Class IE load
group to supply the sequenced loads while maintaining
voltage within design specifications is also verified.
- b. To demonstrate that a loss of offsite power concurrent
with SIS will shed the safety-related loads, start the
diesel generator, close the diesel generator feeder
breaker, and sequence the associated equipment. The
ability of each diesel generator to supply the sequenced
loads while maintaining voltage and frequency within
design specifications is also verified.
- c. To demonstrate the ability of each diesel generator to
carry the short-time rating load for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and the
continuous rated load for 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />, without exceeding
design limits.
- d. To demonstrate that each diesel generator, following
operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the short-time rated load and
14.2-97 Rev. 0 WOLF CREEK 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the continuous rated load, will start automatically on a loss of ac voltage concurrent with an
SIS, attain voltage and frequency within design limits
and time, and accept the LOCA sequenced loads, while
maintaining voltage and frequency within design limits.
- c. To demonstrate the ability of the diesel cooling water
system to maintain the diesel temperature within design
specifications, while the diesel generators are
operating for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the short-time rating load and
22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the continuous rating load.
- f. To determine the fuel oil consumption of each diesel, while operating for 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the continuous rating
load.
- g. To demonstrate the ability of the 125 V dc system to
perform its design functions while at minimum voltage.
- h. To demonstrate the independence between the redundant on
ac and dc power sources.
14.2.12.1.74.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Each diesel generator and its associated auxiliaries are
available.
- c. All components actuated by the LOCA sequencer and safety-related and nonsafety-related load shed circuits
are available.
14.2.12.1.74.3 Test Method
- a. A train A SIS is initiated, and the following are
verified:
- 1. Group l nonsafety-related loads are shed.
- 2. Group 1 diesel generator starts.
- 3. Group 1 LOCA sequencer is actuated, and associated
components are sequenced. The times for sequenced
pumps to reach full flow are verified.
- 4. With bus NB01 supplying the sequenced loads from its
normal source, bus voltage is recorded.
14.2-98 Rev. 0 WOLF CREEK
- b. With group 2 dc load group isolated from its power source and group 1 dc load group voltage set to minimum, a loss of offsite power is initiated concurrent with a
train A SIS, and the following are verified:
- 1. Safety-related group 1 loads are shed.
- 2. Group 1 diesel generator starts, and its feeder
breaker closes.
- 3. Group 1 LOCA sequencer is actuated, and associated
components are sequenced. The times for sequenced
pumps to reach full flow are verified.
- 4. With the group 1 diesel generator supplying the sequenced loads, bus voltage and frequency are recorded.
- 5. The group 2 ac and dc busses are monitored to
verify the absence of voltage on these busses and
loads, indicating no interconnection at load
groups.
- c. The ability of the group 1 diesel generator to carry the
short-time rating load for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> without exceeding
design limits is verified.
- d. The ability of the group 1 diesel generator to carry the
continuous rated load for 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> without exceeding
design limits is verified. Group l diesel fuel oil consumption is also determined.
- e. Following group 1 diesel generator operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
at the short-time rated load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the
continuous rated load, the group 1 diesel generator is
shutdown, a loss of group 1 ac voltage is initiated
concurrent with a train A SIS, and the ability of the
group l diesel generator to start, attain voltage and
frequency within design limits and time, and accept the
loads resulting from the design accident loading
sequence while maintaining voltage and frequency within
design limits is verified. If this test is not
satisfactorily completed, it is not necessary to repeat
the tests of items c and d prior to rerunning this
test. Instead, prior to rerunning this test, the diesel
generator may be operated at the continuous rated load
for l hour or until operating temperature has
stabilized.
14.2-99 Rev. 0 WOLF CREEK
- f. A train B SIS is initiated, and the following are verified:
- 1. Group 2 nonsafety-related loads are shed.
- 2. Group 2 diesel generator starts.
- 3. Group 2 LOCA sequencer is actuated, and associated
components are sequenced. The times for sequenced
pumps to reach full flow are verified.
- 4. With Bus NB02 supplying the sequenced loads from
its normal source, bus voltage is recorded.
- g. With group 1 dc load group isolated from its power source and group 2 dc load group voltage set to minimum, a loss of offsite power is initiated concurrent with a
train B SIS, and the following are verified:
- 1. Safety-related group 2 loads are shed.
- 2. Group 2 diesel generator starts, and its feeder
breaker closes.
- 3. Group 2 LOCA sequencer is actuated, and associated
components are sequenced. The times for sequenced
pumps to reach full flow are verified.
- 4. With the group 2 diesel generator supplying the
sequenced loads, bus voltage and frequency are recorded.
- 5. The group l ac and dc busses are monitored to
verify the absence of voltage on these busses and
loads, indicating no interconnection of load
groups.
- h. The ability of the group 2 diesel generator to carry the
short-time rating load for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> without exceeding
design limits is verified.
- i. The ability of the group 2 diesel generator to carry the
continuous rated load for 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> without exceeding
design limits is verified. Group 2 diesel fuel oil
consumption is also determined.
14.2-100 Rev. 0 WOLF CREEK
- j. Following group 2 diesel generator operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the short-time rated load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the
continuous rated load, the group 2 diesel generator is
shutdown, a loss of group 2 ac voltage is initiated
concurrent with a train B SIS, and the ability of the group 2 diesel generator to start, attain voltage and
frequency within design limits and time, and accept the
LOCA sequenced loads, while maintaining voltage and
frequency within design limits, is verified. If this
test is not satisfactorily completed, it is not necessary
to repeat the tests of items h and i prior to rerunning
this test. Instead, prior to rerunning this test, the
diesel generator may be operated at the continuous rated
load for l hour or until operating temperature has
stabilized.
- k. The ability of the diesel cooling water system to
maintain the diesel temperature within design
specifications, while the diesel generators are operating
for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the short-time rating load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at
the continuous rating load, is verified.
14.2.12.1.74.4 Acceptance Criteria
- a. A train A SIS initiates the following, in accordance
with system design:
- 1. Group 1 nonsafety-related loads are shed.
- 2. Group 1 diesel generator starts.
- 3. Group l LOCA sequencer actuates, and the associated
components are sequenced. Sequenced pumps reach
full flow within the required times.
- b. Bus NB01, while powered from its normal source, supplies
the sequenced loads while maintaining voltage within
design specifications.
- c. With the group 2 dc load group isolated from its power
source and the group 1 dc load group voltage at minimum, a loss of offsite power concurrent with a train A SIS
initiates the following, in accordance with system
design:
- 1. Safety-related group 1 loads are shed.
- 2. Group 1 diesel generator starts, and its feeder
breaker closes.
14.2-101 Rev. 0 WOLF CREEK
- 3. Group l LOCA sequencer actuates, and the associated components are sequenced. Sequenced pumps reach
full flow within design times.
- d. Group l diesel generator supplies the sequenced loads, while maintaining voltage and frequency within design
specifications.
- e. With load group 1 supplying loads following a loss of
offsite power concurrent with a train A SIS, the group 2
ac and dc busses are verified de-energized, indicating
no interconnection of load groups.
- f. Following group 1 diesel generator operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
at the short-time rated load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the continuous rated load, the group 1 diesel generator starts, attains voltage and frequency within design
limits and time, and accepts the LOCA sequenced loads
while maintaining voltage and frequency within design
limits, on loss of group 1 ac voltage concurrent with a
train A SIS.
- g. A train B SIS initiates the following, in accordance
with the system design:
- 1. Group 2 nonsafety-related loads are shed.
- 2. Group 2 diesel generator starts.
- 3. Group 2 LOCA sequencer actuates, and the associated components are sequenced. Sequenced pumps reach full flow within design times.
- h. Bus NB02, while powered from its normal source, supplies
the required loads while maintaining the voltage within
design specifications.
- i. With the group 1 dc load group isolated from its power
source and the group 2 dc load group voltage at minimum, a loss of offsite power concurrent with a train B SIS
initiates the following, in accordance with system
design:
- 1. Safety-related group 2 loads are shed.
- 2. Group 2 diesel generator starts, and its feeder
breaker closes.
14.2-102 Rev. 0 WOLF CREEK
- 3. Group 2 LOCA sequencer actuates, and the associated components are sequenced. Sequenced pumps reach
full flow within design times.
- j. Group 2 diesel generator supplies the required loads, while maintaining voltage and frequency within design
specifications.
- k. With load group 2 supplying loads following a loss of
offsite power concurrent with a train B SIS, the group 1
ac and dc busses are verified de-energized, indicating
no interconnection of load groups.
- l. Following group 2 diesel generator operation for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
at the short-time rated load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at continuous rated load, group 2 diesel generator starts, attains voltage and frequency within design limits and time, and
accepts the LOCA sequenced loads while maintaining
voltage and frequency within design limits, on loss of
group 2 ac voltage concurrent with a train B SIS.
- m. Each diesel generator is capable of carrying the short-
time rating load for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and the continuous rated
load for 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />, without exceeding design limits.
- n. Fuel oil consumption of each diesel, while operating at
the continuous rated load, is within design
specifications.
- o. Each diesel generator cooling water system, with the diesel generators operating for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the short-time rating load and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at the continuous rating
load, maintains the diesel temperatures within design
specifications.
- p. The controls required for the loss of offsite power
concurrent with a SIS (shedding, sequencing, etc.)
function with minimum dc voltage available.
14.2.12.1.75 Shutdown Sequencer Preoperational Test (S-03NF03)
14.2.12.1.75.1 Objectives
- a. To demonstrate that de-energization of either 4,160-V
Class IE load group will start the associated diesel
generator, close the diesel generator feeder breaker, actuate the associated group load shed, and actuate the
shutdown sequencer. All sequenced components are
verified to start within required design times.
14.2-103 Rev. 0 WOLF CREEK
- b. To demonstrate that each diesel generator will maintain voltage and frequency within design specifications while
supplying the design shutdown loads.
- c. To demonstrate the ability of the emergency 4.16-kV loads to start at maximum and minimum design voltages.
14.2.12.1.75.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Each diesel generator and its associated auxiliaries are available.
- d. All components actuated by the shutdown sequencer are
available.
14.2.12.1.75.3 Test Method
- a. Class IE 4,160-V load group 1 is de-energized and the
following are verified:
- 1. Group 1 load shedder actuates.
- 2. Group 1 diesel generator starts, and its feeder
breaker closes.
- 3. Group 1 shutdown sequencer is actuated, and
associated components are sequenced. Components
are verified to actuate within the required design
times.
- b. Class IE 4,160-V load group 2 is de-energized and the
following are verified:
- 1. Group 2 load shedder actuates.
- 2. Group 2 diesel generator starts, and its feeder
breaker closes.
- 3. Group 2 shutdown sequencer is actuated, and
associated components are sequenced. Components
are verified to actuate within the required design
times.
14.2-104 Rev. 0 WOLF CREEK
- c. Emergency 4.16-kV loads are started while their respective diesel generators are supplying:
- 1. Minimum rated voltage
- 2. Maximum rated voltage
- d. The ability of each diesel generator to maintain voltage
and frequency within the design specifications while
supplying the design shutdown loads is verified.
14.2.12.1.75.4 Acceptance Criteria
- a. De-energization of Class IE 4,160-V load group 1
initiates the following, in accordance with system design:
- 1. Group 1 diesel generator starts, and its feeder
breaker closes.
- 2. Group 1 shutdown sequencer actuates, and associated
components are sequenced. Components actuate
within required design times.
- 3. Group 1 load shedder actuates.
- b. De-energization of Class IE 4,160-V load group 2
initiates the following, in accordance with system
design:
- 1. Group 2 diesel generator starts, and its feeder breaker closes.
- 2. Group 2 shutdown sequencer actuates, and associated
components are sequenced. Components actuate
within required design times.
- 3. Group 2 load shedder actuates.
- c. The emergency 4.16-kV loads start and reach rated speed
within design times, with minimum and maximum design
voltage.
- d. Each diesel generator maintains voltage and frequency
within design specifications, while supplying the design
shutdown loads.
14.2.12.1.76 480-V (Class IE) System Preoperational Test
(S-03NG01)
14.2.12.1.76.1 Objectives
To demonstrate that the 480-V Class IE load centers can be energized from
their normal and alternate sources and verify the
14.2-105 Rev. 0 WOLF CREEK operability of system breaker protective interlocks. Proper operation of system instrumentation and controls is also verified.
14.2.12.1.76.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.76.3 Test Method
- a. The 480-V Class IE load centers are energized from their
normal source, and voltages are recorded.
- b. The 480-V Class IE load centers are energized from their
alternate source, and voltages are recorded.
- c. System breakers are operated, and breaker interlocks
verified.
14.2.12.1.76.4 Acceptance Criteria
- a. The voltage for each 480-V Class IE load center, when
supplied from its normal source, is within design
specifications.
- b. The voltage for each 480-V Class IE load center, when
supplied from its alternate source, is within design specifications.
- c. System breaker interlocks operate in accordance with the
system design.
14.2.12.1.77 480-V Class IE System (ESW) Preoperational Test
(SU3-NG02).
14.2.12.1.77.1 Objectives
To demonstrate that the nonpower block 480-V Class IE MCC can be energized from
their normal source and to verify their bus voltage phase sequence. Proper
operation of system instrumentation and controls is also verified.
14.2.12.1.77.2 Prerequisites
- a. Required component testing and instrument calibration
are completed.
14.2-106 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
14.2.12.1.77.3 Test Method
The nonpower block 480-V Class IE MCC are energized, voltages are recorded, and
phase sequence is verified.
14.2.12.1.77.4 Acceptance Criteria
is within design specification.
- b. The bus voltage phase sequence of the nonpower block
480-V Class IE MCC is in accordance with design.
14.2.12.1.78 125-V (Class IE) DC System Preoperational Test
(S-03NK01)
14.2.12.1.78.1 Objectives
To demonstrate the ability of the batteries and chargers to provide power
during normal operations and the battery to provide power during abnormal
conditions. The battery chargers' ability to recharge their respective battery
is also demonstrated. Proper operation of the system instrumentation and
controls is also verified.
14.2.12.1.78.2 Prerequisites
- a. Required component testing and instrument calibration are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Ventilation for the battery rooms is available.
14.2.12.1.78.3 Test Method
- a. Each battery is discharged, using a test load at the
design duty cycle discharge rate.
- b. Each battery is fully discharged to determine its
capacity factor.
- c. Each battery charger will charge its respective battery
to normal conditions, after the battery has undergone a
design duty cycle, while simultaneously supplying power
at a rate equivalent to the design emergency loading.
14.2-107 Rev. 0 WOLF CREEK 14.2.12.1.78.4 Acceptance Criteria
- a. Each battery is capable of maintaining output voltage
above the design minimum, during a design duty cycle.
- b. Each battery has a capacity factor greater than or equal
to design.
- c. The battery chargers are able to recharge the batteries
to normal conditions, after the battery has undergone a
design duty cycle, while simultaneously supplying power
at a rate equivalent to the design emergency loading.
14.2.12.1.79 Instrument AC System (Class IE) Preoperational Test
(S-03NN01) 14.2.12.1.79.1 Objectives
To demonstrate that the 120-V Class IE ac distribution panel- boards can be fed
from their normal source inverters and from their backup source transformers by
manual transfer. The operability of system instrumentation and controls, including breaker protective interlocks, is also verified.
14.2.12.1.79.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.79.3 Test Method
- a. The 120-V Class IE ac distribution panelboards are
energized from their normal source inverters, and
panelboard voltages are recorded.
- b. The 120-V Class IE ac distribution panelboards are
energized from their backup source transformers by
manual transfer, and panelboard voltages are recorded.
- c. The system breakers are operated, and breaker interlocks
are verified.
14.2.12.1.79.4 Acceptance Criteria
- a. Each 120-V Class IE ac distribution panelboard voltage, when supplied from the normal source inverters of the
panelboards, is within design specifications.
14.2-108 Rev. 0 WOLF CREEK
- b. Each 120-V Class IE ac distribution panelboard voltage, when supplied from the backup source transformers, is
within design specifications.
- c. System breaker interlocks operate in accordance with system design.
14.2.12.1.80 Engineered Safeguards (NSSS) Preoperational Test
(SU3-SA01)
14.2.12.1.80.1 Objectives
- a. To demonstrate the ability of the NSSS to initiate
safety injection, containment isolation, containment
spray actuation, main feedwater isolation, and steam line isolation signals on receipt of the associated input signals.
- c. To demonstrate the ability of each solid-state
protection system test panel to adequately test the
associated NSSS ESFAS and reactor protection logic
trains.
- d. To demonstrate the coincidence and redundancy of the
- e. To verify the operability of ESFAS block and permissive
interlocks.
14.2.12.1.80.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies are operational.
14.2.12.1.80.3 Test Method
injection, containment isolation, containment spray
actuation, main feedwater isolation, and steam line
isolation signals on receipt of the required coincidence
of the following input signals for each redundant
channel is verified:
. High steam line pressure rate
. Low steam line pressure
. Low pressurizer pressure
14.2-109 Rev. 0 WOLF CREEK
. High containment pressure (Hi-1, Hi-2, and Hi-3)
. High-high steam generator level
. Low Tavg
. Low-low steam generator water level
- b. Input signals are initiated, and loop response times are
verified.
- c. The ability of each solid-state protection system test
panel to test the NSSS ESFAS logic trains is verified.
- d. ESFAS block and permissive interlocks are verified.
14.2.12.1.80.4 Acceptance Criteria
- a. The NSSS ESFAS actuates safety injection, containment isolation, containment spray actuation, main feedwater
isolation, and steam line isolation signals when their
associated input signals are received from the following
signals for each applicable channel:
. High steam line pressure rate
. Low steam line pressure
. Low pressurizer pressure
. High containment pressure (Hi-1, Hi-2, and Hi-3)
. High-high steam generator level
. Low Tavg
. Low-low steam generator water level
- c. ESFAS block and permissive interlocks operate in
accordance with system design.
14.2.12.1.81 Engineered Safeguards (BOP) Preoperational Test
(SU3-SA02)
14.2.12.1.81.1 Objectives
initiate containment purge isolation, control room
ventilation isolation, fuel building ventilation
isolation, auxiliary feedwater pump actuation, auxiliary
feedwater suction valve switchover to essential service
water (ESW), and steam generator blowdown and sample
isolation signals on receipt of the associated input
signals.
14.2-110 Rev. 0 WOLF CREEK
to adequately test the associated BOP ESFAS logic
trains.
- d. To demonstrate the coincidence and redundancy of the BOP
14.2.12.1.81.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies are operational.
14.2.12.1.81.3 Test Method
purge isolation, control room ventilation isolation, fuel building ventilation isolation, auxiliary feedwater
pump actuation, auxiliary feedwater suction valve
switchover to ESW, and steam generator blowdown and
sample isolation signals on receipt of the required
coincidence of the following input signals for each
redundant channel is verified.
o Containment isolation (phase A)
o High atmospheric radiation
o High chlorine concentration o Loss of main feedwater flow o Low-low steam generator level
o Loss of offsite power
o Low feedwater pump suction pressure
o Safety injection
- b. Input signals are initiated, and loop response times are
verified.
ESFAS logic trains is verified.
14.2.12.1.81.4 Acceptance Criteria
- a. The BOP ESFAS actuates containment purge isolation, control room ventilation isolation, fuel building
ventilation isolation, auxiliary feedwater pump
actuation, auxiliary feedwater suction valve switchover
to ESW, and
14.2-111 Rev. 0 WOLF CREEK steam generator blowdown and sample isolation signals
when their associated input signals are received from
the following signals for each applicable channel:
o Containment isolation (phase A)
o High atmospheric radiation
o High chlorine concentration
o Loss of main feedwater flow
o Low-low steam generator level
o Loss of offsite power
o Low feedwater pump suction pressure
o Safety injection
14.2.12.1.82 Engineered Safeguards Verification Test (SU3-SA03)
14.2.12.1.82.1 Objectives
To demonstrate the proper response of actuated components resulting from the
following safety signals: Safety injection, containment spray actuation, main
feedwater isolation, steam line isolation, containment isolation, containment
purge isolation, control room ventilation isolation, fuel building ventilation
isolation, auxiliary feedwater pump actuation, auxiliary feedwater suction
valve switch over to ESW, and steam generator blowdown and sample isolation.
14.2.12.1.82.2 Prerequisites
- a. Required component testing and instrument calibration are complete.
- b. Required electrical power sources and control circuits
are operational.
available.
14.2.12.1.82.3 Test Method
NSSS and BOP ESFAS signals are initiated manually and the proper response and
response times of the actuated components are verified.
14.2-112 Rev. 0 WOLF CREEK 14.2.12.1.82.4 Acceptance Criteria
Components required to actuate on receipt of safety signals respond properly in
accordance with design specifications and within the times specified by design
requirements.
14.2.12.1.83 Reactor Protection System Logic Test (S-03SB01)
14.2.12.1.83.1 Objectives
- a. To demonstrate the ability of the reactor protection
system to initiate a reactor trip on input of the
associated input signals.
- b. To verify reactor protection loop response times.
- c. To verify the operability of the reactor protection
system block and permissive interlocks.
- d. To demonstrate the coincidence, redundancy, and fail
safe (power loss) design of the reactor protection
system.
14.2.12.1.83.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.1.83.3 Test Method
- a. The ability of the reactor protection system to initiate
a reactor trip on receipt of the proper coincidence of
the following trip signals for each redundant channel is
verified:
o Source range high neutron flux
o Intermediate range high neutron flux
o Power range high neutron flux (low setpoint and
high setpoint)
o Power range high positive neutron flux rate
o Power range high negative neutron flux rate o Overtemperature T o Overpower T o Low primary coolant flow o Reactor coolant pump bus undervoltage
o Reactor coolant pump bus underfrequency
14.2-113 Rev. 0 WOLF CREEK o High pressurizer pressure o Low pressurizer pressure
o High pressurizer level
o Safety injection signal
o Turbine trip signal
- b. Loop response times are measured for the above listed
trip signals.
- c. Reactor protection system block and permissive
interlocks are verified.
- d. Power is isolated from the system, and the safe failure
of the system is verified.
14.2.12.1.83.4 Acceptance Criteria
- a. The reactor protection system initiates a reactor trip
on receipt of the proper coincidence of the following
signals for each applicable channel:
o Source range high neutron flux
o Intermediate range high neutron flux
o Power range high neutron flux (low setpoint and
high setpoint)
o Power range high positive neutron flux rate
o Power range high negative neutron flux rate o Overtemperature T o Overpower T o Low primary coolant flow o Reactor coolant pump bus undervoltage o Reactor coolant pump bus underfrequency
o High pressurizer pressure
o Low pressurizer pressure
o High pressurizer level
o Safety injection signal
o Turbine trip signal
- b. Loop response times for the following trip signals are
within design limits.
o Power range high neutron flux (low setpoint and
high setpoint)
o Power range high negative neutron flux rate o Overtemperature T o Overpower T o Low primary coolant flow o Reactor coolant pump bus undervoltage
o Reactor coolant pump bus underfrequency
14.2-114 Rev. 0 WOLF CREEK o High pressurizer pressure o Low pressurizer pressure
- c. Reactor protection system block and permissive
interlocks operate in accordance with system design.
- d. The reactor protection system functions in accordance
with system design on a loss of power.
14.2.12.1.84 Primary Sampling System Preoperational Test
(S-03SJ01)
14.2.12.1.84.1 Objectives
- a. To set sample panels' flow rates and to verify the operability of the sample system containment isolation valves. Proper operation of system instrumentation and
controls is also verified.
- b. To verify that the post-accident sampling system (PASS)
containment isolation valves operate properly.
14.2.12.1.84.2 Prerequisites
- a. Required component testing instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operable.
- c. Plant conditions are established, and systems are available, as necessary, to facilitate drawing samples
from the sample points.
- d. The component cooling water system is available to
provide cooling water to the auxiliary building sample
station.
- e. The chemical and volume control system is available to
receive discharge from the nuclear sampling station.
- f. The chemical and detergent waste system is available to
receive discharge from the nuclear sampling station.
14.2.12.1.84.3 Test Method
- a. Sample panel flows are adjusted, and flow data are
recorded.
14.2-115 Rev. 0 WOLF CREEK
- b. Operability of the sample containment isolation valves is verified, including their response to an isolation
signal. Valve operating times are recorded.
14.2.12.1.84.4 Acceptance Criteria
- a. The sample containment isolation valves close on receipt
of an isolation signal.
- b. The sample containment isolation valves' closure times
are within design specifications.
14.2.12.1.85 Process Radiation Monitoring System Preoperational
Test (S-03SP01)
14.2.12.1.85.1 Objectives
To demonstrate the operation of the process radiation monitors and to verify
the ability of the process radiation monitoring system to provide alarm and
isolation signals, as applicable, upon receipt of high radiation signals.
Operability of the radioactivity monitoring control room microprocessor is also
verified.
14.2.12.1.85.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operable.
14.2.12.1.85.3 Test Method
- a. The check source for each monitor is remotely
positioned, and the actuation of each monitor and the
operability of its associated alarms and isolation
signals are verified.
- b. Operability of the radioactivity monitoring control room
microprocessor is verified.
14.2.12.1.85.4 Acceptance Criteria
The process radiation monitoring system provides alarm and isolation signals, in accordance with system design specifications.
14.2-116 Rev. 0 WOLF CREEK 14.2.12.1.86 Power Conversion and ECCS Thermal Expansion Test (SU3-0004)
14.2.12.1.86.1 Objective
To demonstrate snubber operability on all safety-related systems whose
operating temperature exceeds 250 F.
14.2.12.1.86.2 Prerequisites
- a. Preservice examinations as specified in the Tedesco
letter to KG&E dated 2/10/81 have been completed on the
systems being checked within the last 6 months.
- b. Other required component testing and instrument calibration are completed.
- c. Required electrical power supplies and control circuits
are operational.
- d. Preoperational testing is in progress.
14.2.12.1.86.3 Test Method
- a. During initial system heatup and cooldown, at specified
temperature intervals, verify the expected snubber
movement for any system which attains operating
temperature.
- b. For those systems which do not attain operating temperature, verify by observation and/or calculation that the snubber will accommodate the projected thermal
movement.
- c. Observe snubber swing clearances at specified heat-up
and cooldown intervals.
14.2.12.1.86.4 Acceptance Criteria
- a. The expected snubber movement for any system that
attains operating temperature is within design
specifications.
- b. The expected snubber movement determined by observation
and/or calculation for any system that does not attain
operating temperature is within design specifications.
- c. Snubber swing clearance observed at specified heatup and
cooldown intervals is within design specifications.
14.2-117 Rev. 0 WOLF CREEK 14.2.12.1.87 Power Conversion and ECCS Systems Dynamic Test (S-030005)
14.2.12.1.87.1 Objectives
To demonstrate during specified transients that the systems' monitored points
respond in accordance with design.
14.2.12.1.87.2 Prerequisites
- a. Reference points for measurement of the systems are
established.
- b. Hot functional testing is in progress.
- c. All subject systems are available for the specified dynamic operations.
- d. Required instrument calibration is complete.
14.2.12.1.87.3 Test Method
- a. The systems are aligned for the specified dynamic
operation.
- b. The specified dynamic event of pump operation, valve
operation, etc., is initiated, and the system is
monitored for response.
14.2.12.1.87.4 Acceptance Criteria
- a. The total stress shall not exceed applicable code
limits.
14.2.12.1.88 HEPA Filter Test (SU3-0006).
14.2.12.1.88.1 Objectives
To demonstrate the leaktightness and particulate removal efficiency of all HEPA
filters and to verify the leaktightness of their associated charcoal adsorbers.
14.2.12.1.88.2 Prerequisites
- a. The ventilation systems containing HEPA filters and
charcoal adsorbers have been air balanced and are
operational and available to support this test.
14.2-118 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operational.
- c. Required instrument calibration is complete.
14.2.12.1.88.3 Test Method
- a. HEPA filters are inplace tested with cold poly-dispersed
DOP, in accordance with the procedures set forth in ANSI
N510.
- b. Charcoal adsorbers are inplace tested with a suitable
refrigerant, in accordance with the procedures set forth
in ANSI N510.
14.2.12.1.88.4 Acceptance Criteria
- a. The airflow of each filter adsorber unit is equal to the
design flow.
- b. Air flow distribution downstream of each HEPA filter is
within 20 percent of the average velocity through the
unit.
- c. HEPA DOP penetration is less than one percent at the
design air flow.
- d. Charcoal adsorber bypass leakage is less than .05
percent at the design air flow.
14.2.12.1.89 Cooldown from Hot Standby External to the Control Room (S-030008)
14.2.12.1.89.1 Objectives
To demonstrate, using a plant procedure, the potential capability to cooldown
the plant from the hot standby to the cold shutdown condition, using
instrumentation and controls external to the control room verifying that:
- a. The reactor coolant temperature and pressure can be
lowered to permit the operation of the residual heat
removal (RHR) system.
- b. The RHR system can be operated and controlled.
- c. The reactor coolant temperature can be reduced 50 F, using the RHR system, without exceeding technical specification limits.
14.2-119 Rev. 0 WOLF CREEK 14.2.12.1.89.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The plant is in a hot standby condition.
- d. The authority and responsibility of the control room
observers has been established and is specified in this
procedure.
14.2.12.1.89.3 Test Method
- a. The plant is cooled from hot standby, RHR is initiated, and a >
50°F cooldown is performed with the RHR system transferring heat to the ultimate heat sink, using instrumentation and controls external to the control room.
- b. All actions performed by the control room observers are documented within this procedure for use in evaluating
their impact on the test results.
14.2.12.1.89.4 Acceptance Criteria
The following actions are capable of being performed, external to the control
room:
- a. The reactor coolant temperature and pressure can be
lowered to permit the operation of the RHR system.
- b. The reactor coolant temperature can be reduced 50 F, using the RHR system, without exceeding technical specification limits.
14.2.12.1.90 Compressed Gas Accumulator Testing (S-030009)
14.2.12.1.90.1 Objectives
To demonstrate the ability of the auxiliary feedwater control valve/mainsteam
atmospheric relief valve and main feedwater control valve accumulators to
provide the design backup supply of compressed gas for continued design valve
operation following a loss of the normal motive source.
14.2-120 Rev. 0 WOLF CREEK 14.2.12.1.90.2 Prerequisites
Required component testing, instrument calibration and system flushing/cleaning
are complete.
14.2.12.1.90.3 Test Method
The accumulators are isolated from the compressed gas supply header and the
associated valves are operated to demonstrate the ability of the accumulators
to provide design motive force for the required valve cycles.
14.2.12.1.90.4 Acceptance Criteria
The auxiliary feedwater control valve/mainsteam atmospheric relief valve, and
main feedwater control valve accumulators provide the design backup supply of compressed gas to their associated valves.
14.2.12.2 Nonsafety-Related Preoperational Test Procedures The following sections are the test abstract for each nonsafety- related
preoperational test. Table 14.2-2 provides an index of these tests.
14.2.12.2.1 Turbine Trip Test (S-04AC02)
14.2.12.2.1.1 Objectives
- a. To demonstrate the ability of the turbine trip and
monitoring system to initiate a turbine trip on input of
the associated input signals.
- b. To demonstrate the response of the moisture separator
reheater drain valves, feedwater heater extraction check valves, turbine main stop valves, turbine main stop valve above seat drain valves, turbine control valves, turbine control valve above seat drain valves, intermediate stop valves, main steamline drain valves, startup drain valves, and intercept valves to a turbine
trip signal.
- c. To demonstrate that a turbine trip signal initiates a
reactor trip signal.
- d. To demonstrate that the turbine main stop valves
operating times are within design specifications.
14.2-121 Rev. 0
WOLF CREEK 14.2.12.2.1.2 Prerequisites
- a. Required component testing and instrument calibration is
complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The main turbine control oil and lube oil systems are
available to provide oil to the turbine auxiliaries.
- d. The compressed air system is available to provide air to
system air-operated valves.
14.2.12.2.1.3 Test Method
- a. The ability of the turbine trip and monitoring system to
initiate a turbine trip signal on receipt of each of the
following input signals is verified:
o Manual trip pushbutton depressed
o Manual trip handle pulled
o Generator trip (EHC vital trip)
o Generator trip (unit trip)
o Loss of stator coolant
o Low lube oil pressure
o Loss of EHC 125 V dc power with turbine speed
below 75 percent
o High turbine vibration o High exhaust hood temperature o Low hydraulic fluid pressure
o Moisture separator high level
o Low bearing oil pressure
o Low condenser vacuum
o Excessive thrust bearing wear
o Backup overspeed (Electrical)
o Loss of EHC 24-volt dc power
- b. A turbine trip signal is initiated, and the response of
the following valves is verified:
o Moisture separator reheater drain valves
o Feedwater heater extraction check valves
o Turbine main stop valves
o Turbine control valves
o Intermediate stop valves
o Turbine intercept valves
o Startup drain valves
o Main steam line drain valves
14.2-122 Rev. 0 WOLF CREEK o Turbine main stop valve above seat drain valves o Turbine control valve above seat drain valves
- c. A turbine trip signal is initiated, and a reactor trip
input signal is verified.
14.2.12.2.1.4 Acceptance Criteria
- a. The turbine trip and monitoring system initiates a
turbine trip on receipt of each of the following
signals:
o Manual trip pushbutton depressed
o Manual trip handle pulled
o Generator trip (EHC vital trip) o Generator trip (unit trip) o Reactor trip
o Loss of stator coolant
o Low lube oil pressure
o Loss of EHC 125 V dc power with turbine speed
below 75 percent
o High turbine vibration
o High exhaust hood temperature
o Low hydraulic fluid pressure
o Moisture separator high level
o Low bearing oil pressure
o Low condenser vacuum
o Excessive thrust bearing wear
o Backup overspeed (electrical)
o Loss of EHC 24-volt dc power
- b. The following valves open on receipt of a turbine trip
signal:
o Turbine main stop valve above seat drain valves
o Turbine control valve above seat drain valves
o Main steam line drain valves
o Moisture separator reheater drain valves
o Startup drain valves
- c. The following valves close on receipt of a turbine trip
signal:
o Low pressure heater extraction check valves
o Main stop valves
o Turbine control valves
o Intercept valves
o Intermediate stop valves
14.2-123 Rev. 0 WOLF CREEK
- d. A turbine trip signal initiates a reactor trip signal.
- e. The turbine main stop valves operating times are within
design specifications.
14.2.12.2.2 Turbine System Cold Test (S-04AC03)
14.2.12.2.2.1 Objectives
- a. To demonstrate the operability of the turning gear and
associated control circuits.
- b. To demonstrate the operability of the electro-hydraulic
control system.
14.2.12.2.2.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The main turbine control oil and lube oil systems are
available to supply the turbine auxiliaries.
14.2.12.2.2.3 Test Method
- a. The operability of the turning gear and associated
control circuits is verified.
- b. A turbine simulator is utilized to verify the ability of
the electro-hydraulic control system to perform its
control functions.
14.2.12.2.2.4 Acceptance Criteria
- a. The turning gear motor trips on loss of bearing oil
pressure, loss of all bearing lift pumps, or closure of
the main transformer switchyard breaker.
- b. The turbine control and intercept valves close on a
power load unbalance signal.
- c. The turbine load set is run back on a reactor overtemperature T signal when in the manual mode.
- d. The turbine load set is run back on a reactor overpower T signal when in the manual mode.
14.2-124 Rev. 0 WOLF CREEK
- e. The turbine load is set back on a loss of circulating water pump signal.
- f. Turbine loading is inhibited on a C-16 control interlock
signal.
14.2.12.2.3 Condensate System Preoperational Test (S-04ADOl)
14.2.12.2.3.1 Objectives
To demonstrate the condensate pumps' operating characteristics and verify the
operation of system valves and associated control circuits. The operability of
the condensate storage and transfer system and associated components is also
verified.
14.2.12.2.3.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The feedwater system is available to receive flow from
the condensate pump discharge header.
- d. The demineralized water system is available to provide
water to the condensate pump seals and a source of
makeup to the condensate storage tank.
- e. The condensate storage tank is available to provide makeup to the condenser hotwell.
- f. The closed cooling water system is available to provide
cooling water to the condensate pump motor bearing oil
coolers.
14.2.12.2.3.3 Test Method
- a. Condensate pumps are operated, and performance
characteristics are verified.
- b. The response of each condensate pump to a condenser low-
low level trip signal is verified.
- c. The operability of the condensate pump recirculation
valves is verified.
14.2-125 Rev. 0 WOLF CREEK 14.2.12.2.3.4 Acceptance Criteria
- a. The operating characteristics of the condensate pumps
are within design specifications.
- b. Each condensate pump will receive a trip signal on a 2/3
condenser low-low level signal.
- c. Each condensate pump recirculation valve operates in
accordance with design specifications.
14.2.12.2.4 Secondary Vent and Drain System Preoperational
Test (S-04AF01)
14.2.12.2.4.1 Objectives
- a. To demonstrate the operating characteristics of the
heater drain pumps.
- b. To demonstrate the operability of system valve and pump
control circuits.
14.2.12.2.4.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The compressed air system is available to the system air-operated valves.
- d. The closed cooling water system is available to supply
cooling water to the heater drain pumps.
14.2.12.2.4.3 Test Method
- a. The heater drain pumps are operated, and performance
characteristics are verified.
- b. The operability of system valve and pump control
circuits is verified.
14.2.12.2.4.4 Acceptance Criteria
The operating characteristics of the heater drain pumps are within design
specifications.
14.2-126 Rev. 0 WOLF CREEK 14.2.12.2.5 Condensate and Feedwater Chemical Feed System Preoperational Test (S-04AQ01)
14.2.12.2.5.1 Objectives
- a. To demonstrate the operating characteristics of the
condensate oxygen control chemical addition pumps, condensate pH control chemical addition pumps, condensate oxygen control chemical circulating pumps, condensate pH control chemical circulating pumps, feedwater chemical addition pumps, and feedwater chemical addition circulating pump and verify the operation of the associated control circuits.
- b. To demonstrate the operability of the drum dispensing
pumps.
14.2.12.2.5.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The demineralized water storage and transfer system is
available to provide a source of demineralized water to the oxygen and pH control chemical supply and mixing tanks.
- d. The compressed air system is available to provide air to
the drum dispensing pumps.
- e. The service gas system is available to provide a source
of nitrogen to the oxygen and pH control chemical supply, measuring, and mixing tanks.
14.2.12.2.5.3 Test Method
- a. System pumps are operated, and performance characteristics are verified.
- b. The response of the condensate oxygen control chemical circulating pumps, condensate pH control chemical circulating pumps, and the feedwater chemical addition feed pumps to a low level in their associated tank is verified.
14.2-127 Rev. 12 WOLF CREEK 14.2.12.2.5.4 Acceptance Criteria
- a. The operating characteristics of the condensate
oxygen control chemical addition pumps, condensate pH control chemical addition pumps, condensate oxygen control chemical circulating pumps, condensate ph control chemical circulating pumps, feedwater chemical addition pumps, feedwater chemical addition circulating pump, and the drum dispensing pumps are within design specifications.
- b. The condensate oxygen control chemical circulating pumps, condensate pH control chemical circulating pumps, feedwater
chemical addition feed pumps, and the feedwater chemical addition circulating pump trip on a low level signal from their associated tanks.
14.2.12.2.6 Reactor Makeup Water System Preoperational Test
(S-04BL01)
14.2.12.2.6.1 Objectives
- a. To demonstrate the operating characteristics of the
reactor makeup water transfer pumps and verify that the
associated control circuits are functioning properly.
- b. To demonstrate the operation of the system automatic
valves, including the response of the reactor makeup
water system containment supply valve to a CIS.
14.2.12.2.6.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The demineralized water storage and transfer system is
available to provide a source of water to the reactor
makeup water storage tank.
14.2.12.2.6.3 Test Method
- a. The reactor makeup water transfer pumps are operated, and pump operating data are recorded.
- b. Reactor makeup water transfer pumps and system automatic
valves control logics are verified, including their
response to safety signals.
14.2-128 Rev. 12 WOLF CREEK
- c. The reactor makeup water containment supply valve is operated under flow conditions and operating times
recorded.
14.2.12.2.6.4 Acceptance Criteria
- a. The operating characteristics of the reactor makeup
water transfer pumps are within design specifications.
- b. Each reactor makeup water transfer pump trips on receipt
of a reactor makeup water storage tank low level signal.
- c. Each reactor makeup water transfer pump starts, after a
time delay, with the other pump running and the receipt
of a low header pressure signal.
- d. The reactor makeup water containment supply valve
closure time is within design specifications.
- e. The reactor makeup containment supply valve closes on
receipt of a CIS.
14.2.12.2.7 Condenser Air Removal System Preoperational Test
(S-04CG01)
14.2.12.2.7.1 Objectives
- a. To demonstrate the operation of the condenser air
removal portion of the turbine building HVAC system
motoroperated dampers, including automatic operation on a safety injection signal.
- b. To demonstrate the capacities of the condenser air
removal filtration fans and verify the operation of
their associated control circuits.
- c. To demonstrate the operability of the condenser air
removal system vacuum pumps, control valves, and their
associated control circuits.
14.2.12.2.7.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-129 Rev. 0 WOLF CREEK
- c. The condenser air removal filtration system portion of the turbine building HVAC system is available to support
this test.
- d. The condensate storage tank is available to provide a source of water to the vacuum pump seal water
reservoirs.
- e. The service water system is available to provide cooling
water to the mechanical vacuum pump seal water coolers.
14.2.12.2.7.3 Test Method
- a. The condenser air removal filtration fans are operated, and fan capacities are verified.
- b. Operation of the condenser air removal filtration
dampers is verified, including their response to a
safety injection signal.
- c. The ability of the mechanical vacuum pumps to reduce
condenser pressure during startup operation is verified.
- d. Operability of the mechanical vacuum pumps and their
associated control valves' control circuits is verified, including their response to a low condenser vacuum
signal.
14.2.12.2.7.4 Acceptance Criteria
- a. The condenser air removal filtration fans' capacities are within design specifications.
- b. The condenser air removal filtration dampers close on
receipt of a safety injection signal.
- c. The rate at which the mechanical vacuum pumps reduce
condenser pressure is within design specifications.
- d. The mechanical vacuum pumps start automatically on
receipt of a low condenser vacuum signal.
14.2.12.2.8 Circulating Water System Preoperational Test (SU4-
DA01)
14.2.12.2.8.1 Objective
- a. To demonstrate the operating characteristics of the
circulating water pumps, water box venting pumps, and
14.2-130 Rev. 0 WOLF CREEK the condenser drain pump and verify the operation of their associated control circuits.
- b. To demonstrate by operational test that the circulating
water pump discharge valves operating times are within design specifications.
- c. To demonstrate that the gland water system flow to the
circulating water pumps is within design specifications.
14.2.12.2.8.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are completed.
- b. Required electrical power supplies and control circuits are operational.
- c. The circulatng water system and condenser are available
to receive flow from the circulating water pumps.
14.2.12.2.8.3 Test Method
- a. The circulating water pumps, water box venting pumps, and the condenser drain pump are operated and pump
operating data is recorded.
- b. The response of the circulating water pumps and the
condenser drain pump to control signals is verified.
- c. Circulating water pump discharge valve operating times are recorded.
14.2.12.2.8.4 Acceptance Criteria
- a. The circulating water pumps operating characteristics
are within design specifications.
- b. The water box venting pumps operating characteristics
are within design specifications.
- c. The condenser drain pump operating characteristics are
within design specifications
- d. The condenser drain pump stops on receipt of a standpipe
low-level signal.
- e. Each circulating water pump trips on receipt of a two
out of three condenser pit high level signal.
14.2-131 Rev. 0 WOLF CREEK
- f. Low gland seal water pressure or low gland seal flow will prevent start of the circulating water pumps.
- g. The gland seal water flow to each circulating water pump
is within design specifications.
- h. The operating times of the circulating water pump
discharge valves are within design specifications.
14.2.12.2.9 Service Water System Preoperational Test (S-04EA01).
14.2.12.2.9.1 Objectives
- a. To demonstrate the capability of the service water
system and essential service water system to provide rated cooling water flow during the normal and normal-shutdown modes of operation to their respective loads.
- b. To demonstrate the operating characteristics of the
Service Water (SW) Pumps.
- c. To verify proper operation of site service water system
controls and instrumentation.
14.2.12.2.9.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The essential service water system has been flow
balanced in the LOCA mode.
- d. Site system controls and instruments are calibrated.
pumps.
14.2.12.2.9.3 Test Method
- a. Service water and essential service water system flows
are verified in the normal and normal-shutdown modes.
(The service water pumps provide the motive force.)
- b. The SW pumps are operated and pump operating data is
recorded.
14.2-132 Rev. 0 WOLF CREEK 14.2.12.2.9.4 Acceptance Criteria
- a. Components supplied by the service water system and
essential service water system receive flows that are
within design specifications with the system operating in the normal and normal-shutdown modes.
- b. The SW pumps operating characteristics are within design
specifications.
14.2.12.2.10 Closed Cooling Water System Preoperational Test
(S-04EB01)
14.2.12.2.10.1 Objectives
- a. To demonstrate the capability of the closed cooling water system to provide cooling water flow to its
associated components.
- b. To demonstrate the operating characteristics of the
closed cooling water pumps and to verify that the
associated instrumentation and controls are functioning
properly.
14.2.12.2.10.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
14.2.12.2.10.3 Test Method
Performance characteristics of the closed cooling water pumps and flow data to
supplied components are verified.
14.2.12.2.10.4 Acceptance Criteria
- a. The performance characteristics of each closed cooling
water pump are within design specifications.
- b. Flow to all components supplied by the closed cooling
water system is verified.
14.2-133 Rev. 0 WOLF CREEK 14.2.12.2.11 Fire Protection System Preoperational Test (SU4-FP03)
14.2.12.2.11.1 Objectives
- a. To demonstrate the operating characteristics of the Fire
Protection (FP) system jockey pump, motor-driven fire
pump and the diesel-driven fire pump and verify the
operation of their associated control circuits.
- b. To demonstrate the operability of the diesel oil system, including system instrumentation and controls.
14.2.12.2.11.2 Prerequisites
- a. Required component testing, instrument calibration, and system flushing/cleaning are completed.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.11.3 Test Method
- a. The jockey pump, the motor-driven fire pump and the
diesel-driven fire pump are operated and operating data
are recorded.
- b. The response of the motor-driven fire pump and diesel-
driven fire pump to automatic start signals are
verified.
- c. With the diesel-driven fire pump operating at rated
capacity, the capacity of the diesel oil day tank is
verified.
14.2.12.2.11.4 Acceptance Criteria
- a. The FP pumps operating characteristics are within design
specifications.
- b. The motor-driven fire pump and the diesel-driven fire
pump automatically start upon receipt of their
associated decreasing fire protection system pressure
signal.
- c. With the diesel fire pump operating at rated capacity, the capacity of the diesel oil day tank is within design
specifications.
14.2-134 Rev. 0 WOLF CREEK
- d. With the diesel fire pump operating at rated capacity and upon receipt of a diesel oil day tank low level
alarm, the remaining capacity of the diesel oil day tank
is within design specifications.
14.2.12.2.12 Radwaste Building HVAC System Preoperational Test
(S-04GH01)
14.2.12.2.12.1 Objectives
- a. To verify the radwaste building supply and exhaust fans'
control circuits, including automatic transfer between
exhaust fans.
- b. To demonstrate the fan capacities of the radwaste building supply and exhaust fans, recycle evaporator room fan coil unit, waste evaporator room fan coil unit, control room (solidification) fan coil unit, sample
laboratory fan coil unit, ground floor fan coil unit, basement floor fan coil unit, SLWS evaporator fan coil
unit, and control room fan coil unit, and to verify that
the associated instrumentation and controls function
properly.
14.2.12.2.12.2 Prerequisites
- a. Required component testing, instrument calibration, and
system air balancing are complete.
- b. Required electrical power supplies and control circuits are operational.
14.2.12.2.12.3 Test Method
- a. The radwaste building system fans are operated, and fan
capacities are verified.
- b. Operability of the radwaste building supply and exhaust
fans' control circuits is verified.
14.2.12.2.12.4 Acceptance Criteria
- a. The radwaste building system fan capacities are within
design specifications.
- b. The radwaste building supply air unit will not operate
unless either radwaste exhaust fan is operating.
14.2-135 Rev. 0 WOLF CREEK
- c. A low flow on the operating radwaste building exhaust fan will cause the operating fan to stop and the standby
fan to start.
14.2.12.2.13 Local Containment Leak Rate Test (SU8-GP01)
14.2.12.2.13.1 Objectives
To determine the leakage rate of the containment penetrations and the leakage
rate of the containment isolation valves.
14.2.12.2.13.2 Prerequisites
- a. All containment isolation valves are closed by normal
actuation methods.
- b. Associated piping is drained, and vent paths for leakage
are established.
- c. Required instrument calibration is complete.
14.2.12.2.13.3 Test Method
The containment penetrations and containment isolation valves are leak tested
by performing type B and type C tests, in accordance with 10 CFR 50, Appendix
J.
14.2.12.2.13.4 Acceptance Criteria
The combined leakage from containment penetrations and containment isolation valves is within design limits.
14.2.12.2.14 Liquid Radwaste System Preoperational Test (S-
04HB01).
14.2.12.2.14.1 Objectives
- a. To demonstrate the operating characteristics of the
liquid radwaste system pumps and to verify the operation
of their associated control circuits.
- b. To demonstrate the operation of the liquid radwaste
system containment isolation valves, including their
response to a CIS.
- c. To determine by operational test that the liquid
radwaste system containment isolation valves' closure
times are within design specifications.
14.2-136 Rev. 0 WOLF CREEK 14.2.12.2.14.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The component cooling water system is available to
provide cooling water to the reactor coolant drain tank
heat exchanger.
14.2.12.2.14.3 Test Method
- a. The liquid radwaste system pumps are operated, and performance characteristics are recorded.
- b. The operability of the system pump and valve control
circuits is verified.
- c. The liquid radwaste system containment isolation valves
are operated under flow conditions, and operating times
are recorded.
14.2.12.2.14.4 Acceptance Criteria
- a. The performance characteristics of the liquid radwaste
system pumps are within design specifications.
- b. Each pump trips on receipt of a low-level signal from its respective tank.
- c. The liquid radwaste system containment isolation valves
close on receipt of a CIS.
- d. The liquid radwaste system containment isolation valves'
closure times are within design specifications.
- e. The liquid radwaste effluent discharge valve closes on a
high process radiation signal.
14.2.12.2.15 Waste Evaporator Preoperational Test (SU4-HB02)
14.2.12.2.15.1 Objectives
To demonstrate the operability of the waste evaporator and its associated
pumps, valves, and control circuits.
14.2-137 Rev. 0 WOLF CREEK 14.2.12.2.15.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Cooling water is available to the waste evaporator.
- d. The auxiliary steam system is available to supply steam
to the waste evaporator.
- e. The waste evaporator condensate tank and the primary
evaporator bottoms tank are available to receive waste evaporator effluent.
14.2.12.2.15.3 Test Method
- a. The waste evaporator is operated, and performance data
is recorded.
- b. With the waste evaporator in operation, a low feed inlet
pressure signal is initiated, and the evaporator is
verified to shift to the recycle mode.
- c. The waste evaporator distillate pump is verified to trip
on a low evaporator condenser level.
14.2.12.2.15.4 Acceptance Criteria
- a. The waste evaporator process flow is within design
specifications.
- b. The waste evaporator goes into the recycle mode on low
feed inlet pressure.
- c. The waste evaporator distillate pump trips on a low
evaporator condenser level.
14.2.12.2.16 Solid Waste System Preoperational Test (S-04HC01)
14.2.12.2.16.1 Objectives
- a. To demonstrate the operating characteristics of the
solid waste system pumps and to verify the operation of
their associated control circuits.
14.2-138 Rev. 0 WOLF CREEK
- b. To demonstrate the ability of the decant station, drumming station, cement filling station, and the
solid radwaste bridge crane to process, solidify, and
handle waste and to verify the operation of their
associated control circuits.
- c. To demonstrate the ability of the dry waste compactors
to process compressible wastes and to verify the
operation of their associated control circuits.
14.2.12.2.16.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operable.
- c. Reactor makeup water is available to provide a source of
water to the decanting station.
14.2.12.2.16.3 Test Method
- a. The solid waste system pumps are operated, and the pump
operating data are recorded.
- b. The system component control circuits are verified, and
the ability of the solid radwaste system to process, solidify, and handle waste is verified.
14.2.12.2.16.4. Acceptance Criteria
- a. The operating characteristics of the evaporator bottoms
tank pumps (primary and secondary) are within design
specifications.
- b. There are no free liquids present in the packaged waste.
- c. The evaporator bottoms tank pumps (primary and
secondary) trip on their respective tank low level
signal.
14.2.12.2.17 Solid Waste Filter Handling System Preoperational
Test (S-04HC02)
14.2.12.2.17.1 Objectives
To demonstrate the ability of the solid radwaste filter handling system to
remove, transfer, and install a spent resin sluice filter assembly.
14.2-139 Rev. 0 WOLF CREEK 14.2.12.2.17.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.17.3 Test Method
- a. Operability of the solid radwaste monorail hoist and
handling cask winch and associated control circuits is
verified.
- b. The ability of the solid radwaste filter handling system to remove, transfer, and install a spent resin sluice filter assembly is verified.
14.2.12.2.17.4 Acceptance Criteria
The filter handling system functions in accordance with design specifications.
14.2.12.2.18 Resin Transfer Preoperational Test (SU4-HC03)
14.2.12.2.18.1 Objectives
- a. To demonstrate the ability to charge resins and
activated charcoal to those systems containing
potentially contaminated demineralizers or adsorbers.
The ability of the spent resin sluice pumps to transfer resins and charcoal from demineralizers and adsorbers is also verified.
- b. To demonstrate the operating characteristics of the
spent resin sluice pumps, chemical addition metering
pumps, and chemical drain tank pumps.
- c. To demonstrate the operability of system valve and pump
control circuits.
14.2.12.2.18.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-140 Rev. 0 WOLF CREEK
- c. Those systems containing potentially contaminated demineralizers and adsorbers are available to support
this test.
- d. The reactor makeup water system is available to provide a source of water for resin charging.
- e. A means of bulk disposal is available to receive waste
at the bulk disposal station.
14.2.12.2.18.3 Test Method
- a. Resins and charcoal are charged and transferred from
selected potentially contaminated demineralizers and
adsorbers.
- b. The spent resin sluice pumps, chemical addition metering
pumps, and chemical drain tank pumps are operated, and
performance characteristics are obtained.
- c. The response of the spent resin sluice pumps, chemical
addition metering pumps, and the chemical drain tank
pumps to a low-level trip signal from their respective
tanks is verified.
14.2.12.2.18.4 Acceptance Criteria
- a. The operating characteristics of the spent resin sluice
pumps, chemical addition metering pumps, and the
chemical drain tank pump are within design specifications.
- b. The spent resin sluice pumps, chemical addition metering
pumps, and the chemical drain tank pump trip on receipt
of a low-level trip signal from their respective tanks.
14.2.12.2.19 Fire Protection System (Water) Preoperational Test
(SU4-KC01A, SU4-KC01B)
14.2.12.2.19.1 Objectives
- a. To demonstrate the operability of the preaction
sprinkler system, wet-pipe sprinkler system, and the
automatic water spray system, including system
instrumentation, alarms, and interlocks.
- b. To demonstrate the operability of system valves, including their response to safety signals.
14.2-141 Rev. 0 WOLF CREEK
- c. To verify spray to the applicable electrical system transformers.
14.2.12.2.19.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operable.
- c. The fire water pumps are available to provide a source
of water to the fire protection system headers.
14.2.12.2.19.3 Test Method
- a. Response of the preaction sprinkler system, wet-pipe
sprinkler system, and automatic water spray system to
fire detection signals is verified, including the
operability of associated alarms, instrumentation, and
interlocks.
- b. The fire protection system containment isolation valves
are operated under flow conditions and operating times
recorded.
- c. Response of the fire protection system containment
isolation valves to a CIS is verified.
- d. Spray to the applicable electrical transformers is verified.
14.2.12.2.19.4 Acceptance Criteria
- a. The preaction sprinkler system, wet-pipe sprinkler
system, automatic water spray system and associated
alarms, and instrumentation and interlocks operate in
accordance with system design specifications.
- b. The fire protection system containment isolation valves'
closure time is within design specifications.
- c. The fire protection system containment isolation valves
close on receipt of a CIS.
- d. The spray to applicable electrical transformers is
within design specifications.
14.2-142 Rev. 0 WOLF CREEK 14.2.12.2.20 Fire Protection System (Halon) Preoperational Test (S-04KC02)
14.2.12.2.20.1 Objectives
To demonstrate the operability of the halon system, including the associated
instrumentation, control circuits, and alarms.
14.2.12.2.20.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operable.
14.2.12.2.20.3 Test Method
The operability of the halon system, including the associated instrumentation
and alarms, is verified. System response to fire detection signals is also
verified.
14.2.12.2.20.4 Acceptance Criteria
The halon fire protection system operates in accordance with system design
specifications.
14.2.12.2.21 Fire Protection System Detection and Alarm
Preoperational Test (S-04KC03)
14.2.12.2.21.1 Objectives
To demonstrate the operability of the fire protection system detectors and
alarms not verified during the performance of the halon and water system
preoperational tests.
14.2.12.2.21.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operable.
14.2.12.2.21.3 Test Method
Actuation of system alarms upon receipt of fire detection signals is verified.
14.2-143 Rev. 0 WOLF CREEK 14.2.12.2.21.4 Acceptance Criteria
Fire protection system detectors and alarms operate in accordance with system
design specifications.
14.2.12.2.22 Oily Waste System Preoperational Test (S-04LE01)
14.2.12.2.22.1 Objectives
To demonstrate the sump pumps and miscellaneous condensate drain tank pumps'
operating characteristics and response to sump/tank, level signals. The
operation of system valves and associated control circuits and sump/tank level
alarms are also verified.
14.2.12.2.22.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The compressed air system is available to supply air to
system valves and pumps.
- d. A water source (fire system) and a collection receptacle
(oil/water separator, main condenser) are available for
the testing of each sump/tank.
14.2.12.2.22.3 Test Method
- a. The sump pumps and miscellaneous condensate drain tank
pumps are operated, and performance characteristics are
verified.
- b. The response of each pump and associated alarms to sump/
tank high and low level signals is verified.
- c. The operability of system air-operated valves is
verified, including the response to a process radiation
signal.
14.2.12.2.22.4 Acceptance Criteria
- a. The performance characteristics of the system pumps are
within design specifications.
- b. The turbine building oily waste header discharge valve
closes on a high-radiation signal.
14.2-144 Rev. 0 WOLF CREEK 14.2.12.2.23 Floor and Equipment Drain System Preoperational Test (SU4-LF01)
14.2.12.2.23.1 Objectives
To demonstrate the sump pumps and hot machine shop oil interceptor pump's
capacities and response to sump/tank level signals. The operation of system
valves, their response to safety signals, and sump/tank level alarms are also
verified.
14.2.12.2.23.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. The compressed air system is available to supply air to
system valves and pumps.
- d. A water source (fire system or ESW) and a collection
receptacle (holdup tank, radwaste system, etc.) are
available for the testing of each sump/tank.
14.2.12.2.23.3 Test Method
- a. The sump pumps and hot machine shop oil interceptor pumps
are operated, and their capacities are verified.
- b. The response of each system pump, system indication, and alarms, to sump/tank high and low level signals is
verified.
- c. The operability of system air- and motor-operated valves
is verified, including their response to safety signals.
14.2.12.2.23.4 Acceptance Criteria
- a. The capacities of the floor and equipment drain system
pumps are within design specifications.
- b. System valves properly respond to safety injection
signals and containment isolation signals.
- c. The valve response times are within design
specifications.
14.2-145 Rev. 0 WOLF CREEK 14.2.12.2.24 13.8-kV System Preoperational Test (S-04PA01)
14.2.12.2.24.1 Objectives
- a. To demonstrate that the 13.8-kV busses can be energized from the startup transformer.
- b. To demonstrate that automatic fast transfer of the
busses from the unit auxiliary source to the startup
source is within design specifications.
- c. To demonstrate that the unit auxiliary source or startup
source feeder breakers will trip on a stuck breaker
condition.
- d. To demonstrate proper operation of system instrumentation and controls.
14.2.12.2.24.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The 13.8-kV system has been energized.
14.2.12.2.24.3 Test Method
- a. The 13.8-kV busses are energized from the startup transformer, and bus voltages are recorded.
- b. Automatic fast transfer from the unit auxiliary source
to the startup source is verified.
- c. Stuck breaker conditions are simulated, and proper
operation of the 13.8-kV auxiliary source and startup
source feeder breakers is verified.
14.2.12.2.24.4 Acceptance Criteria
- a. The 13.8-kV bus voltages are within design
specifications, when energized from the startup
transformer.
- b. Automatic fast transfer of the busses from the unit
auxiliary source to the startup source is within design
specifications.
14.2-146 Rev. 0 WOLF CREEK
- c. The 13.8-kV auxiliary source and startup source feeder breakers trip on receipt of a stuck breaker signal.
14.2.12.2.25 4,160-V (Non-Class IE) System Preoperational Test
(S-04PB01)
14.2.12.2.25.1 Objectives
- a. To demonstrate that the 4,160-V busses can be energized
from their normal and alternate sources, and to verify
the operability of supply breaker and bus tie breaker
protective interlocks.
- b. To demonstrate that automatic transfer is achieved
through the tie breaker from the normal source to the alternate source in the event of an electrical fault.
- c. To demonstrate proper operation of system
instrumentation and controls.
14.2.12.2.25.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The 4,160-V (non-Class IE) system has been energized.
14.2.12.2.25.3 Test Method
- a. The 4,160-V non-Class IE busses are energized from their
normal and alternate source, and bus voltages are
recorded.
- b. System supply breakers and bus tie breakers are
operated, and breaker interlocks are verified.
- c. System electrical fault signals are simulated, and
automatic transfer is verified through the tie breaker
from the normal source to the alternate source for each
4,160-V bus.
14.2.12.2.25.4 Acceptance Criteria
- a. The voltage of each 4,160-V non-Class IE bus, when
supplied from its normal source and alternate source, is
within design specifications.
14.2-147 Rev. 0 WOLF CREEK
- b. System supply breaker and bus tie breaker interlocks operate in accordance with the system design.
- c. Automatic transfer is achieved through the tie breaker
from the normal source to the alternate source, for each 4,160-V bus, upon receipt of an electrical fault signal.
14.2.12.2.26 480-Volt (Non-Class IE) System Preoperational Test
(S-04PG01)
14.2.12.2.26.1 Objectives
- a. To demonstrate that the 480-V non-Class IE load centers
can be energized from their normal sources and alternate
sources, as applicable, and verify the operability of feeder breaker and bus tie breaker protective interlocks.
- b. To demonstrate that the 480-V busses supplied by 4160-V
(Class IE) source breakers are shed on receipt of a load
shed signal.
- c. To demonstrate proper operation of system
instrumentation and controls.
14.2.12.2.26.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits are operational.
energized.
14.2.12.2.26.3 Test Method
- a. The 480-V non-Class IE load centers are energized from
their normal source and alternate source, as applicable
and voltages are recorded.
- b. System feeder breakers and bus tie breakers are
operated, and breaker interlocks verified.
- c. A load shed signal is simulated, and the 480-V busses
supplied by the 4,160-V (Class IE) source breakers are
verified to shed.
14.2-148 Rev. 0 WOLF CREEK 14.2.12.2.26.4 Acceptance Criteria
- a. The voltage for each 480-V non-Class IE load center, when supplied from its normal source and alternate
source, as applicable, is within design specifications.
- b. System feeder breaker and bus tie breaker interlocks
operate in accordance with the system design.
- c. The 480-V busses supplied by the 4160-V (Class IE)
source breakers shed on receipt of a load shed signal.
14.2.12.2.27 250-V DC System Preoperational Test (S-04PJ01)
14.2.12.2.27.1 Objectives To demonstrate the ability of the battery and battery chargers to provide power
to the busses. The battery chargers' ability to recharge their respective
battery is also demonstrated. Proper operation of system instrumentation and
controls is also verified.
14.2.12.2.27.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Ventilation for the battery room is available.
- d. The 250-V dc system has been energized.
14.2.12.2.27.3 Test Method
- a. The battery is discharged, using a test load at the
design duty cycle discharge rate.
- b. The battery is fully discharged to determine its
capacity factor.
- c. The ability of each battery charger to charge the
battery to normal conditions, after the battery has
undergone a design duty cycle, while simultaneously
supplying power at a rate equivalent to the largest
motor current load is verified.
- d. A load shed signal is initiated, and the battery charger
PJ31 ac supply breaker is verified to trip.
14.2-149 Rev. 0 WOLF CREEK 14.2.12.2.27.4 Acceptance Criteria
- a. The battery is capable of maintaining output voltage
above the design minimum, during a design duty cycle.
- b. The battery capacity factor is in accordance with design
requirements.
- c. The battery chargers are able to recharge the battery to
normal conditions, after the battery has undergone a
design duty cycle, while simultaneously supplying power
at a rate equivalent to the largest motor current load.
- d. Battery charger PJ31 ac supply breaker trips on receipt
of a load shed signal.
14.2.12.2.28 125-V (Non-Class IE) DC System Preoperational Test
(S-04PK01, S-04PK02)
14.2.12.2.28.1 Objectives
To demonstrate the ability of the batteries and chargers to provide power to
the busses. The battery chargers' ability to recharge their respective battery
is also demonstrated. Proper operation of system instrumentation and controls
is also verified.
14.2.12.2.28.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Ventilation for the battery room is available.
14.2.12.2.28.3 Test Method
- a. Each battery is discharged, using a test load at the
design duty cycle discharge rate.
- b. Each battery is fully discharged to determine its
capacity factor.
- c. The ability of each battery charger to charge its
respective battery to normal conditions, after the
battery has undergone a design duty cycle, while
simultaneously supplying power at a rate equivalent to
the design instrumentation loading.
14.2-150 Rev. 0 WOLF CREEK
- d. A safety injection load shed signal is initiated, and the battery charger PK21, PK22, PK23, and PK24 supply
breaker is verified to trip.
14.2.12.2.28.4 Acceptance Criteria
- a. Each battery is capable of maintaining output voltage
above the design minimum, during a design duty cycle.
- b. Each battery capacity factor is in accordance with
design requirements.
- c. The battery chargers are able to recharge the batteries
to normal conditions, after the battery has undergone a
design duty cycle, while simultaneously supplying power at a rate equivalent to the design load.
- d. Battery charger PK21, PK22, PK23, and PK24 supply
breaker trips on receipt of a safety injection load shed
signal.
14.2.12.2.29 Instrument AC (Non-Class IE) System Preoperational
Test (S-04PN01)
14.2.12.2.29.1 Objectives
To demonstrate that the 120-V non-Class IE ac distribution panels can be fed
from their associated supply transformers. Proper operation of system
instrumentation and controls is also verified.
14.2.12.2.29.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.29.3 Test Method
The 120-V non-Class IE ac distribution panels are energized from their
associated supply transformers, and the panel voltages are recorded.
14.2.12.2.29.4 Acceptance Criteria
Each 120-V non-Class IE ac distribution panel voltage is within design
specifications.
14.2-151 Rev. 0 WOLF CREEK 14.2.12.2.30 Emergency Lighting System Preoperational Test (S-04QD01)
14.2.12.2.30.1 Objectives
To demonstrate the capability of the emergency lighting system to provide
adequate lighting. Proper operation of system instrumentation and controls is
also verified.
14.2.12.2.30.2 Prerequisites
Required electrical power supplies and control circuits are operable.
14.2.12.2.30.3 Test Method
The ability of the emergency lighting system to provide adequate lighting is verified. The operability of associated instrumentation and control circuits
is also verified.
14.2.12.2.30.4 Acceptance Criteria
The emergency lighting system operates in accordance with system design
specifications.
14.2.12.2.31 Public Address System Preoperational Test (S-04QF01)
14.2.12.2.31.1 Objectives
To demonstrate the capability of the public address system to provide adequate
intraplant communications and to verify the operability of the evacuation alarm system.
14.2.12.2.31.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operable.
14.2.12.2.31.3 Test Method
- a. The public address system is operated from all
locations, and adequate communications verified.
- b. Operability of the evacuation alarm system is verified.
14.2-152 Rev. 0 WOLF CREEK 14.2.12.2.31.4 Acceptance Criteria
- a. The evacuation alarm system operates in accordance with
system design specifications.
14.2.12.2.32 Heat Tracing Freeze Protection System Preoperational
Test (S-04QJ01)
14.2.12.2.32.1 Objectives
To demonstrate the ability of the freeze protection system to automatically
control the associated heat tracing circuits in accordance with system design.
The operation of system instrumentation and controls is also verified.
14.2.12.2.32.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.32.3 Test Method
Temperature signals are varied and the energization/ deenergization of the
associated heat tracing circuits is verified.
14.2.12.2.32.4 Acceptance Criteria
The freeze protection system automatically controls the associated heat tracing circuits, in accordance with system design.
14.2.12.2.33 Secondary Sampling System Preoperational Test
(S-04RM01)
14.2.12.2.33.1 Objectives
- a. To demonstrate the operating characteristics of the
steam generator blowdown sample drain tank pump, sample
chiller pump, and the condenser sample pumps, and verify
the operability of their associated control circuits.
- b. To demonstrate that the system sample flows are within
design specifications.
14.2.12.2.33.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
14.2-153 Rev. 0 WOLF CREEK
- b. Required electrical power supplies and control circuits are operable.
- c. Plant conditions are established, and systems are
available, as necessary, to facilitate drawing samples from the sample points.
- d. The steam generator blowdown system is available to
receive effluent from the steam generator blowdown
sample drain tank.
- e. The closed cooling water system is available to provide
cooling water to the system sample coolers and chiller
package.
14.2.12.2.33.3 Test Method
- a. The steam generator blowdown sample drain tank pump, sample chiller pump, and the condenser sample pumps are
operated, and pump performance data recorded.
Operability of their associated control circuits is also
verified.
- b. System samples are obtained, and flows are recorded.
14.2.12.2.33.4 Acceptance Criteria
- a. The steam generator blowdown sample drain tank pump, sample chiller pump, and condenser sample pump
performance characteristics are within design specifications.
- b. Sample system flows are within design specifications.
14.2.12.2.34 Area Radiation Monitoring Preoperational Test
(S-04SD01)
14.2.12.2.34.1 Objectives
To demonstrate the operation of the area radiation monitors and to verify that
a high radiation signal at each monitor will initiate an alarm.
14.2.12.2.34.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2-154 Rev. 0 WOLF CREEK 14.2.12.2.34.3 Test Method
A calibration source is utilized to actuate the area radiation monitors, and
their operability and associated alarms are verified.
14.2.12.2.34.4 Acceptance Criteria
Each area radiation monitor actuates the associated alarms, on receipt of a
high radiation signal.
14.2.12.2.35 Seismic Monitoring Instrumentation System
Preoperational Test (S-04SG01)
14.2.12.2.35.1 Objectives
To demonstrate the operability of the seismic triggers and switches and strong motion accelerometers, including their associated alarms and recording and
playback systems.
14.2.12.2.35.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.35.3 Test Method
A test signal is initiated, and the operability of the seismic triggers and switches and strong motion accelerometers, including their associated alarms and recording and playback systems, is verified.
14.2.12.2.35.4 Acceptance Criteria
The seismic triggers and switches and strong motion accelerometers, including
their associated alarms and recording and playback systems, operate in
accordance with system design specifications.
14.2.12.2.36 Loose Parts Monitoring System Test (SU4-SQ02).
14.2.12.2.36.1 Objective
To demonstrate the operability of the accelerometers, signal conditioning
devices and diagnostic equipment, including associated alarms and recording and
playback systems.
14.2-155 Rev. 0 WOLF CREEK 14.2.12.2.36.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. Reactor coolant system is filled with water.
- d. Reactor coolant system is at normal operating
temperature and pressure with all reactor coolant pumps
running, and hot functional testing is in progress (for
those portions of the testing to be performed during hot
functional testing).
- e. Reactor coolant system is at normal operating
temperature and pressure with all reactor coolant pumps
running after fuel loading during startup testing (for
those portions of the testing to be performed during
startup testing).
14.2.12.2.36.3 Test Method
- a. Test signals are initiated and the operability of the
accelerometers, signal conditioners, and diagnostic
circuitry, including alarms and recording and playback
systems, is verified.
- b. Channel audio outputs are also recorded during hot functional testing and after fuel loading during startup testing to obtain a record of the reactor coolant system
noise "signature."
14.2.12.2.36.4 Acceptance Criteria
The accelerometers, signal conditioners, and diagnostic circuitry, including
alarms and recording and playback systems operate to detect loose parts as
specified in USAR Section 4.4.6.4.
14.2.12.2.37 Plant Performance Test (SU8-0007)
14.2.12.2.37.1 Objectives
- a. To monitor the balance-of-plant and electrical systems
under loaded conditions during hot functional and power
ascension testing. The ability of the ventilation
systems to maintain ambient temperatures within design
limits is also verified. To monitor the concrete
temperatures surrounding hot penetrations and to verify
evacuation alarm audibility in high noise areas.
14.2-156 Rev. 0 WOLF CREEK 14.2.12.2.37.2 Prerequisites
- a. Required component testing, instrument calibration, and
system flushing/cleaning are complete.
- b. Required HVAC systems have been balanced.
- c. Required electrical power supplies and control circuits
are operational.
14.2.12.2.37.3 Test Method
This procedure does not provide a test method. It provides a monitoring and
data collection function only, with the resultant datum evaluated against
provided design values, as applicable.
14.2.12.2.37.4 Acceptance Criteria
- a. Evacuation alarm audibility in high noise areas is
verified.
- b. The containment coolers maintain containment temperature
within design.
Note: Each monitored point is evaluated throughout the test to verify that the
applicable system or component is functioning per design.
14.2.12.2.38 Electrical Distribution System Voltage Verification
Test (S-090023)
14.2.12.2.38.1 Objectives
To record actual loaded electrical distribution parameters during various
steady-state and transient conditions.
14.2.12.2.38.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
14.2.12.2.38.3 Test Method
The bus voltages and loadings of the electrical distribution system (down to
the Class lE 120/208 V ac system) are recorded for
14.2-157 Rev. 0 WOLF CREEK various steady state configurations. Data is also recorded during the starting of the largest Class 1E and non-Class lE motors. All monitored busses are
loaded to at least 30 percent.
14.2.12.2.38.4 Acceptance Criteria
Not applicable.
Note: The data obtained from this test procedure are used to verify electrical
system voltage analysis.
14.2.12.3 Startup Test Procedures The following sections are the test abstracts for each startup test. Table
14.2-3 provides an index of these tests.
14.2.12.3.1 Automatic Steam Generator Level Control (S-07AB01)
14.2.12.3.1.1 Objectives
- a. To verify the stability of the automatic steam generator
level control following simulated transients at low
power conditions and the proper operation of the
variable speed feature of the feedwater pumps.
- b. To demonstrate the performance characteristics of the steam generator feedwater pumps.
14.2.12.3.1.2 Prerequisites
- a. The steam generator level control system has been
checked and calibrated.
- b. Steam generator level instruments and set points have
been set and calibrated.
- c. Main feedwater is operational.
14.2.12.3.1.3 Test Method
- a. Induce simulated steam generator level transients to verify proper steam generator level control response.
- b. Verify the variable speed features of the steam
generator feedwater pumps by manipulation of controllers
and test input signals, and verify the performance
characteristics of the steam generator feedwater pumps.
14.2-158 Rev. 0 WOLF CREEK 14.2.12.3.1.4 Acceptance Criteria
- a. Automatic steam generator level control system response
must be in accordance with the vendor's technical
manual.
- b. The steam generator feedwater pump's performance
characteristics are within design specifications.
14.2.12.3.2 Dynamic Automatic Steam Dump Control (SU7-AB02)
14.2.12.3.2.1 Objectives
To verify automatic operation of the T average steam dump control system, demonstrate controller setpoint adequacy, and obtain final settings for steam pressure control of the condenser dump valves.
14.2.12.3.2.2 Prerequisites
- a. The reactor coolant system is at normal operating
pressure and temperature.
- b. The reactor is critical.
- c. The steam dump system has been checked and calibrated.
- d. Main feedwater and the condenser are operational.
14.2.12.3.2.3 Test Method
- a. Reactor power is increased by rod withdrawal and steam dump to condenser to demonstrate setpoint adequacy.
- b. Pressure controller setpoint is increased prior to
switching to T average control, which will rapidly
modulate open condenser dump valves.
- c. Simulate turbine operating conditions with reactor at
power, then simulate turbine trip, resulting in the
rapid opening of the steam dump valves.
14.2.12.3.2.4 Acceptance Criteria
The steam dump system controllers must maintain stable reactor coolant system
T average at the controllers set point with no divergent oscillations.
14.2.12.3.3 RTD Bypass Flow Measurement (S-07BB01)
14.2.12.3.3.1 Objectives
To determine the flow rate necessary to achieve the design reactor coolant
transport time in each resistance temperature detector
14.2-159 Rev. 0 WOLF CREEK (RTD) bypass loop and to measure the flow rate in each RTD bypass loop to ensure that the transport times are acceptable.
14.2.12.3.3.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor core is installed, and the plant is at
normal operating temperature and pressure with all
reactor coolant pumps running.
14.2.12.3.3.3 Test Method
The flow rate necessary to achieve the design reactor coolant transport time
for each hot and cold leg bypass loop is calculated, utilizing the hot and cold
leg RTD bypass loop piping lengths. Hot and cold RTD bypass loop flow data are
recorded.
14.2.12.3.3.4 Acceptance Criteria
The flow rate in each hot and cold leg RTD bypass loop, required to achieve the
design reactor coolant transport time, is within design specifications.
14.2.12.3.4 Pressurizer Heater and Spray Capability Test
(S-07BB02)
14.2.12.3.4.1 Objectives
To determine the rate of pressure reduction caused by fully opening the
pressurizer spray valves and the rate of pressure increase from the operation
of all pressurizer heaters.
14.2.12.3.4.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor core is installed with the plant in the hot
shutdown condition at normal operating temperature and
pressure with all reactor coolant pumps running.
14.2-160 Rev. 0 WOLF CREEK
- d. The final setting of the continuous spray flow valves is complete.
- e. The reactor coolant system is borated to the value
required for fuel loading.
- f. This test is performed prior to initial criticality.
14.2.12.3.4.3 Test Method
- a. With the pressurizer spray valves closed, all
pressurizer heaters are energized, and the time to reach
a 2,300 psig system pressure is measured and recorded.
- b. With the pressurizer heaters deenergized, both spray valves are fully opened, and the time to reach a 2,000 psig system pressure is measured and recorded.
14.2.12.3.4.4 Acceptance Criteria
The pressurizer pressure response to the opening of the pressurizer spray
valves and to the actuation of all pressurizer heaters is within design limits.
14.2.12.3.5 Reactor Coolant System Flow Measurement (S-07BB03)
14.2.12.3.5.1 Objectives
- a. To confirm, after core installation but before initial
critical operation, that reactor coolant system (RCS)
flow rate as measured by loop elbow differential pressure readings is greater than or equal to 90 percent of the thermal design flow rate.
- b. To confirm during initial power operation that RCS flow
rate as computed from calorimetric data is greater than
or equal to the thermal design flow rate.
14.2.12.3.5.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor core is installed, and the plant is at
normal operating temperature and pressure.
14.2-161 Rev. 0 WOLF CREEK 14.2.12.3.5.3 Test Method
- a. Before critical operation, loop elbow differential
pressure readings are taken with all reactor coolant
pumps running, and RCS flow rate is calculated.
- b. During initial power operation, calorimetric data are
taken from Procedure S-07SC03, "Thermal Power
Measurement and Statepoint Data Collection," and RCS
flow rate is calculated.
14.2.12.3.5.4 Acceptance Criteria
RCS flow rate by loop elbow differential pressure measurement is greater than
or equal to 90 percent of the thermal design value and by calculation from calorimetric data is greater than or equal to the thermal design value.
14.2.12.3.6 Reactor Coolant System Flow Coastdown Test (SU7-BB04)
14.2.12.3.6.1 Objectives
- a. To measure the rate at which reactor coolant flow
changes, subsequent to simultaneously tripping all
reactor coolant pumps.
- b. To determine that the reactor coolant system low-flow
delay time is less than or equal to the total low-flow
delay time assumed in the safety analysis for loss of
flow.
14.2.12.3.6.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor core is installed, and the plant is at
normal operating temperature and pressure with all
reactor coolant pumps running.
14.2.12.3.6.3 Test Method
Flow coastdown stabilization and loss of coolant delay-time data are recorded
while tripping reactor coolant pumps.
14.2-162 Rev. 0 WOLF CREEK 14.2.12.3.6.4 Acceptance Criteria
- a. The rate of change of reactor coolant flow is within
design specifications.
- b. The reactor coolant system low-flow delay time is less
than or equal to the total low-flow delay time assumed
in the safety analysis for loss of flow.
14.2.12.3.7 Pressurizer Continuous Spray Flow Verification
(S-07BB05)
14.2.12.3.7.1 Objectives
To establish a setting for the pressurizer continuous spray flow valves to obtain an optimum continuous spray flow.
14.2.12.3.7.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The reactor core is installed with the plant in the hot
shutdown condition at normal operating temperature and
pressure with all reactor coolant pumps running.
- d. The reactor coolant system is borated to the value required for fuel loading.
- e. This test shall be performed prior to initial
criticality.
- f. The preliminary setting of the continuous spray flow
valves has been completed during hot functional testing.
14.2.12.3.7.3 Test Method
Continuous spray flow valves are adjusted to establish the optimum continuous
spray flow, and the valve throttle positions are recorded.
14.2.12.3.7.4 Acceptance Criteria
The continuous spray flow valves are throttled to establish the optimum
continuous spray flow to keep the spray line warm and minimize normal steady-
state pressurizer heater loads.
14.2-163 Rev. 0 WOLF CREEK 14.2.12.3.8 RTD/TC Cross Calibration (S-07BB06)
14.2.12.3.8.1 Objectives
- a. To provide a functional checkout of the reactor coolant system resistance temperature detectors (RTDs) and
incore thermocouples and to generate isothermal cross-
calibration data for subsequent correction factors to
indicated temperatures.
NOTE This portion of the test need be performed only if the
data collected in S-03BB16, RTD/TC Cross Calibration, during hot functional testing, so warrants.
- b. To provide a functional checkout of the core subcooling
monitor system including the detecting thermocouples.
14.2.12.3.8.2 Prerequisites
- a. Required component testing and instrument calibration
are complete.
- b. Required electrical power supplies and control circuits are operational.
- c. Plant heatup, following core loading, is in progress, and all reactor coolant pumps are operating.
14.2.12.3.8.3 Test Method
- a. At various temperature plateaus RTD and incore
thermocouple data are recorded. Isothermal
cross-calibration correction factors for individual
thermocouples and the installation corrections for
individual RTDs are determined.
- b. At normal operating temperature, the thermocouple core
subcooling monitors' operational and programmable functions are verified, including associated alarms, displays, and printouts.
14.2.12.3.8.4 Acceptance Criteria
- a. Individual RTD readings are within the design
specifications.
- b. The installation corrections of the RTDs are within
design specifications.
14.2-164 Rev. 0 WOLF CREEK
- c. The thermocouple core subcooling monitor alarms, displays, and printouts function in accordance with
design specifications.
14.2.12.3.9 Core Loading Instrumentation and Neutron Source Requirements (S-07SC01)
14.2.12.3.9.1 Objectives
To verify proper alignment, calibration, and neutron response of the temporary
core loading instrumentation prior to start of fuel- loading; to check the
neutron response of the nuclear instrumentation system (NIS) source range
channels prior to start of fuel-loading; and to check the neutron response of
the temporary and NIS source range instrumentation prior to resumption of fuel-
loading following any delay of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or more. To verify the signal to noise ratio is greater than 2.
14.2.12.3.9.2 Prerequisites
- a. Hot functional testing is completed.
- b. The nuclear instrumentation system is installed and
calibrated.
14.2.12.3.9.3 Test Method
- a. A portable neutron source (1-5 curie), plus preshipment
equipment checkout data, is used to verify proper
alignment, calibration, and neutron response of the
temporary core-loading instrumentation.
- b. A portable neutron source (1-5 curie) is used to check
the neutron response of the NIS source range detectors.
- c. A portable neutron source (1-5 curie) or movement of a
source-bearing fuel element to produce the desired
change in neutron level to verify the neutron response
of the temporary and NIS source range instrumentation
prior to resumption of fuel-loading following any delay
of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or more.
- d. Perform a statistical evaluation of 10 observations for
each channel, to verify operability of the equipment.
14.2.12.3.9.4 Acceptance Criteria
Neutron instrumentation is operational, calibrated, and indicates a
positive/negative change in count rate as the neutron level is increased and/or
decreased. The signal to noise ratio is greater than 2.
14.2-165 Rev. 0 WOLF CREEK 14.2.12.3.10 Thermal Power Measurement and Statepoint Data Collection (S-07SC03)
14.2.12.3.10.1 Objectives
To measure core thermal power and obtain data for instrumentation calibration.
14.2.12.3.10.2 Prerequisites
- a. Calorimetric instrumentation is installed.
- b. This test is performed at 30-percent, 50-percent, 75-
percent, 90-percent, and 100-percent power.
14.2.12.3.10.3 Test Method Collect data and calculate thermal power. Obtain statepoint data, compute the
average for each parameter measured, convert to the appropriate units, and
summarize the data for each RCS loop.
14.2.12.3.10.4 Acceptance Criteria
This test is for the collection of data.
14.2.12.3.11 Nuclear Instrumentation System Test (SU7-SE01)
14.2.12.3.11.1 Objectives
The purpose of this test is to verify that the nuclear instrumentation system
performs the required indications and control functions through the source, intermediate, and power ranges of operation prior to core loading.
14.2.12.3.11.2 Prerequisites
- a. The nuclear instrumentation system is installed, calibrated, aligned, and operational for a period of at
least 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
- b. The plant is at ambient temperature and pressure.
14.2.12.3.11.3 Test Method
- a. The source and intermediate range channels are subjected
to various test signals to verify that the appropriate
indicators alarm, illuminate, or actuate, and the source
range local and remote speakers function.
14.2-166 Rev. 0 WOLF CREEK
- b. The power range channels are subjected to various test signals to observe proper meter reading and function of
the comparator and rate circuitry.
- c. The high voltage circuitry of the source and intermediate range channels is tested.
14.2.12.3.11.4 Acceptance Criteria
The control and indication functions and the reactor trip set points of the
nuclear instrumentation system source, intermediate, and power range channels
have been verified.
14.2.12.3.12 Operational Alignment of Nuclear Instrumentation
(S-07SE02) 14.2.12.3.12.1 Objectives
To establish and determine voltage settings, trip settings, operational
settings, alarm settings, and overlap of channels on source range, intermediate
range, and power range instrumentation from prior to initial criticality to at
or near full reactor power.
14.2.12.3.12.2 Prerequisites
- a. The nuclear instrumentation system has been aligned.
- b. This test is conducted prior to criticality, during
power escalation, and at or near full power.
14.2.12.3.12.3 Test Method
- a. All functions are calibrated, tested, and verified, utilizing permanently installed controls and adjustment
mechanisms.
- b. Operational modes of the source range, intermediate
range, and power range channels are set for their proper
functions, as per the test instructions.
14.2.12.3.12.4 Acceptance Criteria
The overlap between the source, intermediate, and power range channels must be
at least 1-1/2 decades, and the power range channels are capable of being
adjusted to agree with the results of plant calorimetric calculations.
14.2-167 Rev. 0 WOLF CREEK 14.2.12.3.13 Axial Flux Difference Instrumentation Calibration (S-07SE03)
14.2.12.3.13.1 Objectives
To derive calibration factors for overpower, overtemperature, and
T setpoints, based on incore flux data, calorimetric data, and excore nuclear
instrumentation detector currents.
14.2.12.3.13.2 Prerequisites
- a. The axial flux difference instrumentation system has
been aligned.
- b. Data has been obtained from flux maps taken at 30-percent and 50-percent power.
14.2.12.3.13.3 Test Method
Collect data, as required by test instruction, at 50-percent and 75-percent power, perform FI calculations to calibration factors, and extrapolate results for use at the 100-percent power plateau.
14.2.12.3.13.4 Acceptance Criteria
Calibration factors agree with Technical Specifications.
14.2.12.3.14 Control Rod Drive Mechanism Operational Test (S-
07SF01)
14.2.12.3.14.1 Objectives
To demonstrate the proper operation of the rod drive mechanisms under both cold
and hot plant conditions and to provide verification of proper slave cycler
timing.
14.2.12.3.14.2 Prerequisites
- a. The control rod drive mechanisms are installed.
- b. The rod drive motor-generator sets are installed and
power is available.
- c. For the control rod drive mechanism timing test, the
core is installed, rod position indication is installed, and the control rod driving mechanism cooling fans are
operational.
- d. Nuclear instrumentation channels operable and operating.
14.2-168 Rev. 0 WOLF CREEK
- e. A fast speed oscillograph (Visicorder or equivalent) to monitor test parameters is available.
14.2.12.3.14.3 Test Method
- a. With the reactor core installed and reactor in the cold
shutdown condition, confirm that the slave cycler
devices supply operating signals to the proper CRDM
stepping magnet coils.
- b. Verify proper operation of all CRDMs under both cold and
hot shutdown conditions. CRDM magnet coil currents and
audio noise signals are recorded.
14.2.12.3.14.4 Acceptance Criteria The control rod drive mechanisms conform to the requirements for proper
mechanism operation and timing as described in the magnetic control rod drive
mechanism instruction manual.
14.2.12.3.15 Rod Control System (S-07SF02)
14.2.12.3.15.1 Objectives
To demonstrate and document that the rod control system performs the required
control and indication functions just prior to initial criticality. To
demonstrate operation of the rod inhibit functions.
14.2.12.3.15.2 Prerequisites
- a. The reactor coolant system is at normal operating pressure and temperature.
- b. The rod control system is installed and aligned.
- c. The source range nuclear instruments are operable.
- d. The rods are capable of withdrawal.
- e. The rod position indication system is operable.
14.2.12.3.15.3 Test Method
- a. With the reactor at no load operating temperature and
pressure, and just prior to initial criticality, the
control is checked for each applicable position of the
bank selector switch for proper operation.
14.2-169 Rev. 0 WOLF CREEK
- b. Status lights, alarms, and indicators are verified.
14.2.12.3.15.4 Acceptance Criteria
The control and indication functions in accordance with the rod position indication system and rod control system manuals. Rod motion is inhibited upon
application of an inhibit function.
14.2.12.3.16 Rod Drop Time Measurement (SU7-SF03)
14.2.12.3.16.1 Objectives
To determine the rod drop time of each rod cluster control assembly under no-
flow and full-flow conditions, with the reactor in the cold shutdown condition
and at normal operating temperature and pressure.
14.2.12.3.16.2 Prerequisites
- a. Initial core loading is completed.
- b. Rod control system is installed and tested.
- c. Individual rod position indication is installed and
checked.
14.2.12.3.16.3 Test Method
Withdraw each rod cluster control assembly, interrupt the electrical power to
the associated rod drive mechanism, and measure and record the rod drop time.
This test is performed with the reactor at cold and hot conditions and at no-flow and full- flow.
14.2.12.3.16.4 Acceptance Criteria
The rod drop times are acceptable in accordance with plant technical
specifications.
14.2.12.3.17 Rod Position Indication System (SU7-SF04)
14.2.12.3.17.1 Objectives
To verify that the rod position indication system satisfactorily performs
required indication functions for each individual rod and that each rod
operates satisfactorily over its entire range of travel.
14.2-170 Rev. 0 WOLF CREEK 14.2.12.3.17.2 Prerequisites
- a. Plant system conditions are established as follows:
- 1. Test performed at T avg <200°F, nominal RCS pressure for T avg noted 2. Test results verified at T avg nominally 557°F, RCS pressure nominally 2235 psig and at least one reactor coolant pump in service.
14.2.12.3.17.3 Test Method
- a. All shutdown rod banks are fully withdrawn by bank
stopping at 18,210 and 228 steps to record the rod
position, the Digital Rod Position Indication display
(DRPI), and the group step position indication.
- b. All control rod banks are fully withdrawn by bank in 24
step increments while recording rod position as
indicated by the plant control room DRPI readout, and
the group step position indication.
- c. In addition, the pulse-to-analog converter chassis bank
position digital readout is recorded for all control rod
banks.
14.2.12.3.17.4 Acceptance Criteria
The rod position indication system performs the required indication functions, and each rod operates over its entire range of travel within the limits of the
rod position indication instruction manual and the plant precautions, limitations,setpoints manual, and WCGS Technical Specifications.
14.2.12.3.18 Automatic Reactor Control System (S-07SF05)
14.2.12.3.18.1 Objectives
To demonstrate the capability of the reactor control system to respond properly
to input signals and to transmit proper control signals to other plant control
systems and components.
14.2.12.3.18.2 Prerequisites
- a. The reactor is at approximately 30-percent power.
14.2-171 Rev. 0 WOLF CREEK
- b. Pressurizer level and pressure, steam dump, steam generator level, and main feed pump speed control
systems are in automatic.
14.2.12.3.18.3 Test Method
T average will be successively varied from the T ref set point to verify the transient recovery capabilities of the auto reactor control system.
14.2.12.3.18.4 Acceptance Criteria
- a. No manual intervention should be required to bring the
plant conditions to equilibrium values following
initiation of a 6 F temperature transient.
- b. T avg should return to within +
1.5 F of T ref following initiation of a 6 F temperature transient.
- c. Rod motion is inhibited by application of the
appropriate inhibit inputs.
14.2.12.3.19 Incore Flux Mapping (S-07SR01, S-07SR02)
14.2.12.3.19.1 Objectives
To obtain core power and temperature profiles for evaluating core performance.
14.2.12.3.19.2 Prerequisites
- a. The incore monitoring system has been functionally
tested.
- b. This test is performed at low power, 30-, 50-, 75-, 90-,
and 100-percent power.
- c. The reactor is stabilized prior to taking a map.
14.2.12.3.19.3 Test Method
The movable detectors are inserted into the core, data is obtained, and
thermocouples are monitored while at a stable power. The obtained data is
retained for evaluation.
14.2.12.3.19.4 Acceptance Criteria
Flux and temperature data is obtained at the various power levels.
14.2-172 Rev. 0 WOLF CREEK 14.2.12.3.20 Incore Instrumentation Test (S-07SR03, S-07SR04)
14.2.12.3.20.1 Objectives
To set up and demonstrate operation of the incore instrumentation system.
14.2.12.3.20.2 Prerequisites
- a. The incore instrumentation system is installed.
- b. Proper rotation and limit switch operation has been
verified.
- c. Testing is performed at cold shutdown and hot standby.
14.2.12.3.20.3 Test Method
At cold shutdown a dummy cable is inserted into each thimble, and proper
rotation and limit switch operation is verified. At hot standby the detectors
are inserted into the thimbles to demonstrate performance in all operational
modes.
14.2.12.3.20.4 Acceptance Criteria
The incore instrumentation system is capable of taking a flux map.
14.2.12.3.21 Operational Alignment of Process Temperature
Instrumentation (S-07SF06)
14.2.12.3.21.1 Objectives To align T and T avg process instrumentation under isothermal conditions, prior to criticality and at power.
14.2.12.3.21.2 Prerequisites
- a. This alignment is performed prior to initial criticality
and again at 75-percent power. Alignment is checked at
100-percent power.
- b. All reactor coolant pumps shall be operating.
14.2.12.3.21.3 Test Method
- a. Align T and Tavg per test instructions under isothermal conditions prior to criticality and at approximately 75
14.2-173 Rev. 0 WOLF CREEK percent power. Extrapolate the 75-percent power data to determine T and T avg values for the 100-percent power plateau.
- b. At or near full power, check the alignment of the T and T avg channels for agreement with the results of thermal power measurement. Realign any channels, as necessary, to meet test specifications.
14.2.12.3.21.4 Acceptance Criteria
The 100 percent power indications for T and T avg channels must be within the maximum design values as specified in vendor design documents.
14.2.12.3.22 Startup Adjustments of Reactor Control System (S-07SF07)
14.2.12.3.22.1 Objectives
To obtain the optimum plant efficiency.
14.2.12.3.22.2 Prerequisites
- a. The reactor coolant system is at normal operating
pressure and temperature.
- b. Plant instrumentation shall have been aligned according
to Operational Alignment of Process Temperature
Instrumentation.
- c. The turbine control system shall have been aligned.
14.2.12.3.22.3 Test Method
- a. Obtain system temperature and steam pressure data at
steady-state conditions for zero power and at hold
points during power escalations.
- b. Evaluation of these data will provide the basis for
adjustments to the reactor control system.
14.2.12.3.22.4 Acceptance Criteria
The Tavg controller must be capable of maintaining full load steam pressure
within turbine pressure limitations specified in the vendor's technical manual.
14.2-174 Rev. 0 WOLF CREEK 14.2.12.3.23 RCCA or Bank Worth Measurement at Zero Power (S-07SF08)
14.2.12.3.23.1 Objectives
To determine the differential and integral reactivity worth of a rod cluster
control bank (RCC) or an individual rod cluster control assembly (RCCA).
14.2.12.3.23.2 Prerequisites
- a. The reactor is critical with the neutron flux level
within the range established for zero power physics
testing.
- b. The reactor coolant system is at normal operating pressure and temperature.
14.2.12.3.23.3 Test Method
RCC and RCCA worth are validated by constant addition and/or dilution of boron
in the reactor coolant system, causing rod movement to compensate for the boron
addition and/or dilution. This rod movement will cause step changes in
reactivity which are used to compute the worths.
14.2.12.3.23.4 Acceptance Criteria
The integral reactivity worth of the RCC or RCCA over its entire range of
travel agrees with acceptance criteria given in the Nuclear Design Report
within tolerance values specified in vendor design documents.
14.2.12.3.24 RCCA or Bank Worth Measurement at Power (SU7-SF09)
14.2.12.3.24.1 Objectives
- a. To measure RCCA worth for a rod ejected from the HFP rod
insertion limit position.
- b. To determine in-core response resulting from a dropped
rod with all other control rods near fully withdrawn.
14.2-175 Rev. 0 WOLF CREEK 14.2.12.3.24.2 Prerequisites
Testing will be performed at 30-percent power with the reactor stable.
- 14.2.12.3.24.3 Test Method
- a. Ejected rod - Compute the change in reactivity
associated with the change in RCCA position.
- b. Dropped rod - Determine the quadrant power tilt ratio
and hot channel factors by use of the in-core flux
mapping system.
14.2.12.3.24.4 Acceptance Criteria
- a. Ejected rod - The rod worth of the ejected rod is within tolerance values specified in vendor design documents.
- b. Dropped rod - The peaking factors are within the limits
specified in vendor design documents.
14.2.12.3.25 Reactor Systems Sampling for Core Load (S-07SJ01)
14.2.12.3.25.1 Objectives
To verify uniform boron concentration, prior to core load, in the reactor
coolant system and directly connected auxiliary systems.
14.2.12.3.25.2 Prerequisites
- a. Boric acid tanks, pumps, and transfer lines are all filled with 4 percent boric acid solution.
- b. Reactor coolant system is filled with reactor grade
water which has been borated to a concentration as
specified in the technical specifications.
14.2.12.3.25.3 Test Method
- a. Filling and circulating the reactor coolant system with
borated water should be accomplished, utilizing normal
flow paths as much as possible.
_______________________
- This test was performed at 50 percent power at Callaway.
Callaway has the same core and Nuclear Instrumentation System
as Wolf Creek. Wolf Creek Core parameters measured prior to
the pseudo rod drop test were compared with the corresponding
results for Callaway to verify that the plant response was the
same. This exemption was approved in a July 3, 1985 letter
from the NRC.
14.2-176 Rev. 0 WOLF CREEK
- b. Collect and analyze four samples taken at equidistant depths in the reactor vessel simultaneously with one
sample from the operating residual heat removal loop to
check uniform boron concentration.
14.2.12.3.25.4 Acceptance Criteria
Boron concentration of the samples obtained from the designated sample points
must be within a 30-ppm range of values.
14.2.12.3.26 Initial Core Loading (SU7-0001)
14.2.12.3.26.1 Objectives
- a. To load fuel in a controlled manner.
- b. To measure boron concentration.
14.2.12.3.26.2 Prerequisites
- a. Sufficient preoperational testing has been completed to
ensure the necessary equipment and attendant
instrumentation is functional.
- b. Required technical specification surveillance is
completed and the necessary systems are operable.
14.2.12.3.26.3 Test Method
Instruction includes a core-loading sequence which specifies the loading in a step-by-step fashion with the appropriate data collection records.
14.2.12.3.26.4 Acceptance Criteria
A permanent record of the final as-loaded core configuration has been made, and
the configuration is consistent with the fuel assembly core loading plan.
Boron concentration is as specified in the Technical Specifications.
14.2.12.3.27 Inverse Count Rate Ratio Monitoring For Core Loading
(S-070002)
14.2.12.3.27.1 Objectives
- a. To obtain nuclear monitoring data during initial core
loading.
- b. To prevent criticality during core loading.
14.2-177 Rev. 0 WOLF CREEK 14.2.12.3.27.2 Prerequisites
- a. Temporary and plant source range nuclear instrumentation
has been operational for a minimum of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to achieve
stable operation.
- b. Plant is prepared for initial core loading.
14.2.12.3.27.3 Test Method
Data from the nuclear monitoring channels is used to assess the safety with
which core loading operations may be conducted. Inverse count rate ratio is
plotted and evaluated to prevent any unexpected deviation from subcriticality.
The core is monitored and maintained in a subcritical configuration throughout
the core loading.
14.2.12.3.27.4 Acceptance Criteria
The core is loaded without achieving criticality.
14.2.12.3.28 Inverse Count Rate Ratio Monitoring for Approach to
Initial Criticality (S-070003)
14.2.12.3.28.1 Objectives
- a. To obtain nuclear monitoring data during initial
criticality.
- b. To anticipate and determine criticality.
14.2.12.3.28.2 Prerequisites
- a. Both source range and intermediate range nuclear
channels alarm, trip functions, and indicating devices
have been checked out and calibrated.
- b. Both source range and intermediate range nuclear
channels have been energized a minimum of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to
insure stable operation.
14.2.12.3.28.3 Test Method
- a. Obtain base line count rates prior to rod withdrawal and
boron dilution. After each increment of rod withdrawal, and periodically during boron dilution, count rates are
obtained, and inverse count rate ratio is evaluated.
- b. Core reactivity is monitored during the approach to
criticality.
14.2-178 Rev. 0 WOLF CREEK 14.2.12.3.28.4 Acceptance Criteria
To determine criticality.
14.2.12.3.29 Initial Criticality (S-070004)
14.2.12.3.29.1 Objectives
To achieve initial criticality in a controlled manner.
14.2.12.3.29.2 Prerequisites
- a. Initial core loading is completed.
- b. Required technical specification surveillance is completed and the necessary systems operable.
- c. Sufficient post-core loading precritical testing has
been completed to ensure the necessary equipment and
attendant instrumentation is functional.
14.2.12.3.29.3 Test Method
- a. At preselected points during rod withdrawal and/or boron
dilution, data is taken and inverse count rate plots
made to enable extrapolation to be carried out to the
expected critical point.
- b. Initial criticality is achieved by boron dilution or, if
desired, by withdrawing control rods.
14.2.12.3.29.4 Acceptance Criteria
The reactor is critical with the flux level established at approximately 1 x 10-8 amps on the intermediate range nuclear channels.
14.2.12.3.30 Determination of Core Power Range for Physics
Testing (S-070005)
14.2.12.3.30.1 Objectives
To determine the reactor power level at which effects from fuel heating is
detectable and to establish the range of neutron flux in which zero power
reactivity measurements are to be performed.
14.2.12.3.30.2 Prerequisites
- a. The reactor is critical and stable in the intermediate
range.
14.2-179 Rev. 0 WOLF CREEK
- b. Control rods are sufficiently deep in the core to allow positive reactivity insertion by rod withdrawal.
- c. Reactor coolant temperature is established at a value
that minimizes the moderator temperature coefficient reactivity feedback.
14.2.12.3.30.3 Test Method
- a. Withdraw control rod bank and allow the neutron flux
level to increase until nuclear heating effects are
indicated by the reactivity computer.
- b. Record the reactivity computer picoammeter flux level
and, if possible, the corresponding IR channel currents at which nuclear heating occurs, to obtain zero power testing range.
14.2.12.3.30.4 Acceptance Criteria
The power level at which zero power testing is conducted is determined.
14.2.12.3.31 Boron Endpoint Determination (S-070006)
14.2.12.3.31.1 Objectives
To determine the critical reactor coolant system boron concentration
appropriate to an endpoint configuration (RCC configuration).
14.2.12.3.31.2 Prerequisites
- a. The reactor is critical within the range for zero power
testing and stable.
- b. The reactor coolant is at normal operating pressure and
temperature.
- c. Rods are at the approximate end point configuration.
14.2.12.3.31.3 Test Method
Boron endpoints are measured by determining the boron concentration of the
reactor coolant system with the rods close to or at the desired configuration.
If not, the rods are then quickly moved to the desired configuration with no
boron adjustment. The change in reactivity is measured, and this reactivity is
converted to an equal amount of boron to yield the endpoint at that particular
rod configuration.
14.2-180 Rev. 1 WOLF CREEK 14.2.12.3.31.4 Acceptance Criteria
The results of the boron endpoint calculations meet the requirements of the
Nuclear Design Report within tolerance values specified in vendor design
documents.
14.2.12.3.32 Isothermal Temperature Coefficient Measurement
(S-070007)
14.2.12.3.32.1 Objectives
To determine isothermal temperature coefficient, then derive the moderator
temperature coefficient from the isothermal data.
14.2.12.3.32.2 Prerequisites
- a. The reactor is critical within the range for zero power
testing and stable.
- b. The reactor coolant is at normal operating pressure and
temperature.
- c. Control rods are at the approximate end point
configuration.
14.2.12.3.32.3 Test Method
The isothermal temperature coefficient is determined by heating/cooling the
reactor coolant system at a constant rate and plotting temperature versus
reactivity. The moderator temperature coefficient may be derived from isothermal data, if desired.
14.2.12.3.32.4 Acceptance Criteria
The average of the measured values of the isothermal and, if desired, the
derived moderator temperature coefficient agrees with acceptance criteria given
in the Nuclear Design Report within tolerance values specified in vendor design
documents.
14.2.12.3.33 Power Coefficient Determination (S-070008)
14.2.12.3.33.1 Objectives
To verify the power coefficient of reactivity.
14.2.12.3.33.2 Prerequisites
- a. Reactor power level, reactor coolant temperature and
pressures, and RCCA and RCC bank configuration are as
follows:
14.2-181 Rev. 1 WOLF CREEK
- 1. RCS pressure - nominal 2235 psig
- 2. RCCA, RCC bank configuration - nominally all rods
out, D at bite position
- 3. Reactor power level - nominally 30, 50, 75, and 90
percent RTP
- 4. T avg - consistent with the nominal value corresponding to the T avg program at the identified nominal power levels.
- b. All subsystems which affect overall plant transient
response should be in automatic mode of operation with
the exception of the rod control system and automatic makeup. The CVCS demineralizer shall be bypassed.
14.2.12.3.33.3 Test Method
- a. As generator electrical load is changed, the primary side
is permitted to freely respond without any control rod
motion.
- b. The power coefficient verification factor is calculated
by measuring the change in RCS temperature and the
corresponding change in core power.
14.2.12.3.33.4 Acceptance Criteria
The average value of the measured verification factor agrees with that obtained
from design predictions of the isothermal temperature coefficient and doppler
power coefficient. This agreement is within limits given in the test
instructions.
14.2.12.3.34 Load Swing Tests (S-070009)
14.2.12.3.34.1 Objectives
To verify proper nuclear plant transient response, including automatic control
system performance, when load changes are introduced at the turbine generator.
14.2.12.3.34.2 Prerequisites
Step load changes are initiated from steady state conditions at approximately
30-, 75-, and 100-percent power.
14.2-182 Rev. 1 WOLF CREEK 14.2.12.3.34.3 Test Method
- a. Manually reduce the turbine generator output as rapidly
as possible to achieve an approximate 10-percent load
decrease/increase.
- b. Plant variables are recorded, along with values observed
on the normal plant instrumentation, during the load
transient for those parameters required.
14.2.12.3.34.4 Acceptance Criteria
The following acceptance criteria are to be used to determine successful test
completion. Failure to meet these criteria does not constitute a need for
stopping the test program, but correction of any deficiences should be accomplished, as required, consistent with the current plant schedule.
- a. Reactor and turbine must not trip.
- b. Safety injection is not initiated.
- c. Neither steam generator atmospheric relief valves nor safety valves shall lift.
- d. Neither pressurizer relief valves nor safety valves shall
lift.
- e. No manual intervention shall be required to bring plant conditions to steady state.
- f. Nuclear power overshoot (undershoot) must be less than 3
percent for load increase (decrease).
14.2.12.3.35 Large Load Reduction Test (S-070010)
14.2.12.3.35.1 Objectives
To demonstrate satisfactory plant transient response to various specified load changes, to monitor the reactor control systems during these transients, and, if necessary, optimize the reactor control system setpoints.
14.2.12.3.35.2 Prerequisites
Step load reduction changes of 50 percent are initiated from steady state
conditions at approximately 75- and 100-percent power.
14.2-183 Rev. 13 WOLF CREEK 14.2.12.3.35.3 Test Method
- a. Manually reduce the turbine generator output to achieve
an approximate 50-percent load reduction.
- b. Monitor plant response during the transient and record
plant variables, as required.
- c. If necessary, adjust the reactor control system setpoints
until optimal response is obtained.
14.2.12.3.35.4 Acceptance Criteria
The following acceptance criteria are to be used to determine successful test
completion. Failure to meet these criteria does not constitute a need for stopping the test program, but correction of any deficiencies should be accomplished, as required, consistent with the current plant schedule.
- a. Reactor and turbine must not trip.
- b. Safety injection is not initiated.
- c. Steam generator safety valves shall not lift.
- d. Pressurizer safety valves shall not lift.
- e. No manual intervention shall be required to bring plant
conditions to steady state.
14.2.12.3.36 Plant Trip From 100 Percent Power (S-070011) 14.2.12.3.36.1 Objectives
To verify the ability of the plant automatic control systems to sustain a trip
from 100 percent and to bring the plant to stable conditions following the
transient, to determine the overall response time of the hot leg resistance
temperature detectors, and to evaluate the data resulting from the trip to
determine if changes in the control system setpoints are warranted to improve
transient response based on actual plant operations.
14.2.12.3.36.2 Prerequisites
- a. The rod control system, steam generator level, pressurizer pressure and level, and the steam dump system
are in the automatic control mode.
- b. The plant is operating at normal steady state full power.
- c. Diesel generators in standby idling condition.
14.2-184 Rev. 1 WOLF CREEK 14.2.12.3.36.3 Test Method
- a. Initiate a plant trip by opening the main generator
output breaker, monitor plant response, and record plant
variables, as required.
- b. If necessary, adjust the control system setpoints to
obtain optimal response.
14.2.12.3.36.4 Acceptance Criteria
The system parameters must stay within the limitations specified in the
vendor's design transient analysis document.
14.2.12.3.37 Rods Drop and Plant Trip (S-070012) 14.2.12.3.37.1 Objectives
To demonstrate that the negative rate trip circuit will trip the reactor and to
monitor plant response.
14.2.12.3.37.2 Prerequisites
- a. The rod control system, steam generator level, pressurizer pressure and level, and the feedwater pump
speed control are in the automatic control mode. Steam
dump control system is in the Tavg mode.
- b. The plant is operating at a steady state power of 30 to
50 percent.
- c. The rod group and the selected rods to be dropped have
been identified.
14.2.12.3.37.3 Test Method
- a. Drop two RCCAs from a common group which, because of
their worth and location, are the most difficult to
detect by the nuclear instrumentation system (NIS).
- b. Monitor systems behavior and plant response to trip from
an intermediate power level prior to the plant trip test
from full power.
14.2.12.3.37.4 Acceptance Criteria
The following acceptance criteria are to be used to determine successful test
completion:
14.2-185 Rev. 1 WOLF CREEK
- a. The reactor shall have tripped as a result of the negative rate trip.
- b. All RCCAs shall release and bottom on receipt of a trip
signal.
- c. The pressurizer safety valves shall not lift.
- d. Steam generator safety valves shall not lift.
- e. Safety injection is not initiated.
14.2.12.3.38 Shutdown and Maintenance of Hot Standby External to
the Control Room (S-070014)
14.2.12.3.38.1 Objectives
To demonstrate, using a plant procedure, that the plant can be taken from >
10 percent power to hot standby conditions, and verify that the plant can be maintained in hot standby for at least 30 minutes with a minimum shift crew, using controls and instrumentation external to the control room.
14.2.12.3.38.2 Prerequisites
- a. Required component testing and instrument calibration are
complete.
- b. Required electrical power supplies and control circuits
are operational.
- c. The plant is at normal operating conditions at >
10 percent power.
- d. The authority and responsibility of the control room
observers has been established and is specified in this procedure.
14.2.12.3.38.3 Test Method
- a. The plant is taken from >
10 percent power to hot standby conditions, using a plant procedure, minimum shift crew, and controls and instrumentation external to the control
room.
- b. Hot standby conditions are maintained for at least 30
minutes.
14.2-186 Rev. 1 WOLF CREEK
- c. All actions performed by the control room observers is documented within this procedure for use in evaluating
their impact on the test results.
14.2.12.3.38.4 Acceptance Criteria
The plant can be taken from >
10 percent power to hot standby conditions which are maintained for >
30 minutes, using a plant procedure, minimum shift crew, and controls and instrumentation external to the control room.
14.2.12.3.39 Power Ascension Thermal Expansion and Dynamic Test (S-070015)
14.2.12.3.39.1 Objectives
- a. To demonstrate during specified power ascension
transients that the systems' monitored points respond in
accordance with design.
- b. To demonstrate during the heatup to full power
temperature that the systems' piping can expand without obstruction and that the expansion is in accordance with design. Also, during the subsequent cooldown to ambient
temperature, the piping returns to its cold position in
accordance with system design.
14.2.12.3.39.2 Prerequisites
- a. Reference points for measurement of the systems are
established.
- b. Power ascension testing is in progress.
- c. All subject systems are available for the specified
dynamic operations.
- d. Required instrument calibration is complete.
- e. A preservice inspection of the associated piping snubbers
has been completed within 6 months.
14.2.12.3.39.3 Test Method
- a. Record cold baseline data.
- b. Obtain measurement data at various specified temperature
plateaus.
14.2-187 Rev. 1 WOLF CREEK
- c. The systems are aligned for the specified dynamic operation.
- d. The specified dynamic event of pump operation, valve
operation, etc., is initiated, and the system is monitored for response.
- e. On completion of cooldown to ambient temperature, obtain
measurement data.
14.2.12.3.39.4 Acceptance Criteria
- a. There shall be no evidence of blocking of the thermal
expansion of any piping or components, other than by
design.
- b. The total stresses shall not exceed applicable code
limits.
- c. Spring hanger movement must remain within the hot and
cold set points, snubber swing clearance remains
satisfactory., and snubbers must not become fully
retracted or expanded.
- d. Piping and components must return to their baseline
position on cooldown in accordance with system design.
- e. The measured thermal movement shall be within 25 percent
of the analytical value or +
0.25 inch, whichever is greater.
14.2.12.3.40 Biological Shield Testing (S-070016)
14.2.12.3.40.1 Objectives
- a. To measure and record the neutron and gamma ray radiation
levels in accessible areas of the plant where radiation
levels above background are anticipated.
- b. To determine locations if any, where shielding is
deficient.
- c. To ensure that plant personnel are not subjected to overexposure from radiation as a result of inadequate shielding.
14.2.12.3.40.2 Prerequisites
- a. Required instrument calibration is complete.
14.2-188 Rev. 1
WOLF CREEK
- b. Appropriate reactor power levels are attained.
14.2.12.3.40.3 Test Method
Neutron and gamma ray surveys are conducted in each of the following reactor power level ranges.
Test % Reactor Power Range Preoperational Shield Tests <
0 Low Power Tests 0-5
Intermediate Power Tests 5-50
High Power Tests 50-100
14.2.12.3.40.4 Acceptance Criteria
Neutron and gamma ray radiation surveys in all accessible areas of the plant
where radiation levels above background are anticipated reveal no shielding
deficiencies; or identify and implement appropriate administrative controls in
accordance with 10 CFR 20 for the areas determined to be radiation areas.
14.2.12.3.41 Loss of Heater Drain Pump Test (S-070017)*
14.2.12.3.41.1 Objectives To verify proper nuclear plant response to a loss of heater drain pump
accident.
14.2.12.3.41.2 Prerequisites
The plant is operating at steady state conditions at 90-percent power.
14.2.12.3.41.3 Test Method
The heater drain pumps are tripped and plant variables are recorded, along with
values observed on the normal plant instrumentation, during the transient for
those parameters required.
_______________________
- This test was performed at Callaway only, with the consent of
the NRC, as Callaway and Wolf Creek have identical Heater Drain
Systems.
14.2-189 Rev. 1 WOLF CREEK 14.2.12.3.41.4 Acceptance Criteria
The following acceptance criteria are to be used to determine successful test
completion. Failure to meet these criteria does not constitute a need for
stopping the test program, but correction of any deficiencies should be accomplished as required, consistent with the current plant schedule.
- a. Reactor and turbine must not trip.
- b. Safety injection is not initiated.
- c. Neither steam generator atmospheric relief valves nor safety valves shall lift.
- d. Neither pressurizer relief valves nor safety valves shall
lift.
- e. No manual intervention shall be required to bring plant conditions to steady state.
14.2.12.3.42 Calibration of Steam and Feedwater Flow
Instrumentation at Power Test (S-070018)
14.2.12.3.42.1 Objectives
- a. To calibrate the steam flow transmitters against feed-
water flow.
- b. To perform a cross-check verification of all signals indicating feedwater and steam flow.
14.2.12.3.42.2 Prerequisites
- a. Test equipment, including transmitters, has been
calibrated for expected ranges of plant conditions.
- b. The plant shall be at steady state conditions for each
power level at which testing is performed.
14.2.12.3.42.3 Test Method
At 30 and 50 percent power, perform Step a if the steam flow/ feedwater flow
mismatch alarm actuates. At 75 and 100 percent power, perform Steps a and b.
- a. Verify calibration of the steam flow by comparing steam
flow signal to referenced feedwater flow.
14.2-190 Rev. 13 WOLF CREEK
- b. Compare, using plots, the steam and feedwater flow values to determine if recalibration is necessary prior to the
next power escalation.
14.2.12.3.42.4 Acceptance Criteria
- a. Steam flow/feedwater flow mismatch alarm does not actuate
at 30, 50, 75, and 100 percent power.
- b. Steam flow indication should be within +
4 percent of feedwater flow panel indicator at 75 and 100 percent power.
- c. The test feedwater flow instrument versus plant feed-water flow instrument and plant steam flow instrument
curves should be within +
2.5 percent and +
3.0 percent of their respective ideal curves at 75 and 100 percent power.
14.2.12.3.43 Natural Circulation Test (S-090024)*
14.2.12.3.43.1 Objectives
To demonstrate the length of time required to stabilize natural circulation; to
demonstrate core flow distribution during natural circulation using incore
thermocouples.
14.2.12.3.43.2 Prerequisites
- a. Required low power physics testing has been completed.
- b. Required instrumentation is installed and calibration
complete.
- c. The plant is operating at steady state conditions at 3
percent power.
14.2.12.3.43.3 Test Method
All reactor coolant pumps are simultaneously tripped while at 3 percent rated
power. The transients are monitored and establishment of natural circulation
verified.
- Due to similar plant design for Callaway and Wolf Creek, the
NRC allowed WCGS to use Callaway Natural Circulation test data
and pertinent results.
14.2-191 Rev. 1 WOLF CREEK 14.2.12.3.43.4 Acceptance Criteria Natural circulation has been demonstrated. The measured core T as a function of core power under natural circulation conditions is no greater than the
limiting reactor coolant system T based on design requirements.
14.2-192 Rev. 1
WOLF CREEK TABLE 14.2-1 SAFETY-RELATED PREOPERATIONAL TEST PROCEDURES Test Abstract Test Number Title USAR Section S-03AB01 Steam Dump System Preoperational Test 14.2.12.1.1
SU3-AB02 Main Steam Safety Valve Test 14.2.12.1.2
S-03AB03 Main Steam Line Isolation Valve Test 14.2.12.1.3 S-03AB04 Main Steam System Preoperational Test 14.2.12.1.4 S-03AE01 Main Feedwater System Preoperational
Test 14.2.12.1.5 S-03AE02 Steam Generator Level Control Test 14.2.12.1.6 S-03AL01 Auxiliary Feedwater Motor-Driven Pump
and Valve Preoperational Test 14.2.12.1.7 SU3-AL02 Auxiliary Feedwater Turbine-Driven Pump and Valve Preoperational Test 14.2.12.1.8
SU3-AL03 Auxiliary Feedwater Motor-Driven Pump Endurance Test 14.2.12.1.9 S-03AL04 Auxiliary Feedwater System Water
Hammer Test 14.2.12.1.10 SU3-AL05 Auxiliary Feedwater Turbine-Driven Pump Endurance Test 14.2.12.1.11
S-03BB01 Reactor Coolant Pump Initial Operation 14.2.12.1.12 SU3-BB02 PRT Cold Preoperational Test 14.2.12.1.13 SU3-BB03 RTD Bypass Flow Measurement 14.2.12.1.14
S-03BB04 Pressurizer Pressure Control Test 14.2.12.1.15 S-03BB05 Reactor Coolant System Hot Preoperational Test 14.2.12.1.16
S-03BB06 Thermal Expansion 14.2.12.1.17 d-03BB07 Pressurizer Level Control Test 14.2.12.1.18 SU3-BB08 Pressurizer Heater and Spray Capability
Test 14.2.12.1.19 SU3-BB09 Reactor Coolant System Flow Measurement Test 14.2.12.1.20
SU3-BB10 Reactor Coolant System Flow Coastdown Test 14.2.12.1.21 S-03BB11 Reactor Coolant System Hydrostatic Test 14.2.12.1.22
SU3-BB12 Pressurizer Continuous Spray Flow Verification Test 14.2.12.1.23 S-03BB13 Pressurizer Relief Valve and PRT Hot
Preoperational Test 14.2.12.1.24 S-03BB14 Reactor Coolant Loop Vibration Surveillance Test 14.2.12.1.25
SU3-BB15A Leak Detection System Preoperational Test 14.2.12.1.26 SU3-BB15B Leak Detection System Preoperational
Test 14.2.12.1.27 S-03BB16 RTD/TC Cross Calibration 14.2.12.1.28 Rev. 0 WOLF CREEK TABLE 14.2-1 (Sheet 2)
Test Number Title USAR Section S-03BG01 Chemical and Volume Control System Major Component Test 14.2.12.1.29 SU3-BG02 Seal Injection Preoperational Test 14.2.12.1.30 SU3-BG03 Charging System Preoperational Test 14.2.12.1.31 SU3-BG04 Boron Thermal Regeneration System Preoperational Test 14.2.12.1.32
SU3-BG05 Boric Acid Blending System Preopera-tional Test 14.2.12.1.33 S-03BG06 Chemical and Volume Control System
Hot Preoperational Test 14.2.12.1.34 SU3-EC01 Fuel Pool Cooling and Cleanup System Preoperational Test 14.2.12.1.35
S-03EC02 Spent Fuel Pool Leak Test 14.2.12.1.36 SU3-EF01 Essential Service Water System Pre-operational Test 14.2.12.1.37
SU3-EF02 Essential Service Water Pump Preopera-tional Test 14.2.12.1.37 S-03EG01 Component Cooling Water System Pre-
operational Test 14.2.12.1.38 SU3-EJ01 Residual Heat Removal System Cold Pre-operational Test 14.2.12.1.39
SU3-EJ02 Residual Heat Removal System Hot Preoperational Test 14.2.12.1.40 SU3-EM01 Safety Injection System Cold Pre-
operational Test 14.2.12.1.41 SU3-EM02 Safety Injection Flow Verification Test 14.2.12.1.42 SU3-EM03 Safety Injection Check Valve Test 14.2.12.1.43 SU3-EM04 Boron Injection Tank and Recirculation Pump Test 14.2.12.1.44 S-03EN01 Containment Spray System Nozzle Air Test 14.2.12.1.45 SU3-EN02 Containment Spray System Preoperational Test 14.2.12.1.46
S-03EP01 Accumulator Testing 14.2.12.1.47 SU3-FC01 Auxiliary Feedwater Pump Turbine Preoperational Test 14.2.12.1.48
SU3-GD01 Essential Service Water Pumphouse HVAC Preoperational Test 14.2.12.1.49 SU3-GF01 Miscellaneous Building HVAC System
SU3-GF02 Preoperational Tests SU3-GF03 14.2.12.1.50 S-03GG01 Fuel Building HVAC System Preoperational
Test 14.2.12.1.51 SU3-GK01 Control Building HVAC System Preopera-tional Test 14.2.12.1.52
SU3-GL01 Auxiliary Building HVAC System Pre-operational Test 14.2.12.1.53 S-03GM01 Diesel Generator Building HVAC Pre-
operational Test 14.2.12.1.54 Rev. 3 WOLF CREEK TABLE 14.2-1 (Sheet 3)
Test Number Title USAR Section SU3-GN01 Containment Cooling System Preoperational Test 14.2.12.1.55 S-03GN02 CRDM Cooling Preoperational Test 14.2.12.1.56 SU3-GP01 Integrated Containment Leak Rate Test 14.2.12.1.57 SU3-GP02 Reactor Containment Structural Integ-
rity Acceptance Test 14.2.12.1.58 S-03GS01 Post-Accident Hydrogen Removal System Preoperational Test 14.2.12.1.59
S-03GT01 Containment Purge System HVAC Pre-operational Test 14.2.12.1.60 S-03HA01 Gaseous Radwaste System Preoperational
Test 14.2.12.1.61 S-03JE01 Emergency Fuel Oil System Preoperational Test 14.2.12.1.62
SU3-KE01 Spent Fuel Pool Crane Preoperational Test 14.2.12.1.63 SU3-KE02 New Fuel Elevator Preoperational Test 14.2.12.1.64
SU3-KE03 Fuel Handling and Storage Preoperational Test 14.2.12.1.65 SU3-KE04 Fuel Transfer System Preoperational
Test 14.2.12.1.66 SU3-KE05 Refueling Machine and RCC Change Fixture Preoperational Test 14.2.12.1.67
S-03KE06 Refueling Machine Indexing Test 14.2.12.1.68 SU3-KE07 Fuel Handling System Integrated Preoperational Test 14.2.12.1.69
S-03KJ01 Diesel Generator Mechanical Preopera-tional Test 14.2.12.1.70 S-03NB01 4160-V (Class IE) System Preoperational
Test 14.2.12.1.71 S-03NE01 Diesel Generator Electrical Preopera-tional Test 14.2.12.1.72
SU3-NF01 Integrated Control Logic Test 14.2.12.1.73 S-03NF02 LOCA Sequencer Preoperational Test 14.2.12.1.74 S-03NF03 Shutdown Sequencer Preoperational Test 14.2.12.1.75
S-03NG01 480-V (Class IE) System Preoperational Test 14.2.12.1.76 SU3-NG02 480-V Class IE System (ESW) Preopera-
tional Test 14.2.12.1.77 S-03NK01 125-V (Class IE) DC System Preopera-tional Test 14.2.12.1.78
S-03NN01 Instrument AC System (Class IE) Pre-operational Test 14.2.12.1.79 SU3-SA01 Engineered Safeguards (NSSS) Preopera-
tional Test 14.2.12.1.80 Rev. 0 WOLF CREEK TABLE 14.2-1 (Sheet 4)
Test Number Title USAR Section SU3-SA02 Engineered Safeguards (BOP) Pre-operational Test 14.2.12.1.81 SU3-SA03 Engineered Safeguards Verification Test 14.2.12.1.82 S-03SB01 Reactor Protection System Logic Test 14.2.12.1.83 S-03SJ01 Primary Sampling System Preoperational Test 14.2.12.1.84
S-03SP01 Process Radiation Monitoring System Preoperational Test 14.2.12.1.85 SU3-0004 Power conversion and ECCS Systems
Thermal Expansion Test 14.2.12.1.86 S-030005 Power Conversion and ECCS Systems Dynamic Test 14.2.12.1.87
SU3-0006 HEPA Filter Test 14.2.12.1.88 S-030008 Cooldown from Hot Standby External to the Control Room 14.2.12.1.89
S-030009 Compressed Gas Accumulator Testing 14.2.12.1.90 Rev. 0 WOLF CREEK TABLE 14.2-2 NONSAFETY-RELATED PREOPERATIONAL TESTS Test Number Title USAR Section S-04AC02 Turbine Trip Test 14.2.12.2.1 S-04AC03 Turbine System Cold Test 14.2.12.2.2 S-04AD01 Condensate System Preoperational Test 14.2.12.2.3 S-04AF01 Secondary Vent and Drain System Pre-operational Test 14.2.12.2.4 S-04AQ01 Condensate and Feedwater Chemical Feed System Preoperational Test 14.2.12.2.5 S-04BL01 Reactor Makeup Water System Preopera-tional Test 14.2.12.2.6 S-04CG01 Condenser Air Removal System Pre-operational Test 14.2.12.2.7
SU4-DA01 Circulating Water System Preoperational Test 14.2.12.2.8 S-04EA01 Service Water System Preoperational Test 14.2.12.2.9 S-04EB01 Closed Cooling Water System Preopera-tional Test 14.2.12.2.10 SU4-FP03 Fire Protection System Preoperational Test 14.2.12.2.11 S-04GH01 Radwaste Building HVAC System Pre-operational Test 14.2.12.2.12 SU8-GP01 Local Containment Leak Rate Test 14.2.12.2.13 S-04HB01 Liquid Radwaste System Preoperational Test 14.2.12.2.14
SU4-HB02 Waste Evaporator Preoperational Test 14.2.12.2.15 S-04HC01 Solid Waste System Preoperational Test 14.2.12.2.16 S-04HC02 Solid Waste Filter Handling System Preoperational Test 14.2.12.2.17 SU4-HC03 Resin Transfer Preoperational Test 14.2.12.2.18 SU4-KC01A Fire Protection System (Water) Pre-
SU4-KC01B operational Test 14.2.12.2.19 S-04KC02 Fire Protection System (Halon) Pre-operational Test 14.2.12.2.20 S-04KC03 Fire Protection System Detection and Alarm Preoperational Test 14.2.12.2.21 S-04LE01 Oily Waste System Preoperational Test 14.2.12.2.22
SU4-LF01 Floor and Equipment Drain System Pre-operational Test 14.2.12.2.23 S-04PA01 13.8-kV System Preoperational Test 14.2.12.2.24
S-04PB01 4,160-V (Non-Class IE) System Pre-operational Test 14.2.12.2.25 S-04PG01 480-Volt (Non-Class IE) System Pre-
operational Test 14.2.12.2.26 Rev. 0 WOLF CREEK TABLE 14.2-2 (Sheet 2)
Test Number Title USAR Section S-04PJ01 250-V DC System Preoperational Test 14.2.12.2.27 S-04PK01 125-V (Non-Class IE) DC System Pre-
S-04PK02 operational Test 14.2.12.2.28 S-04PN01 Instrument AC (Non-Class IE) System Pre-operational Test 14.2.12.2.29 S-04QD01 Emergency Lighting System Preopera-tional Test 14.2.12.2.30 S-04QF01 Public Address System Preoperational Test 14.2.12.2.31 S-04QJ01 Heat Tracing Freeze Protection System Preoperational Test 14.2.12.2.32 S-04RM01 Secondary Sampling System Preoperational Test 14.2.12.2.33 S-04SD01 Area Radiation Monitoring Preoperational Test 14.2.12.2.34 S-04SG01 Seismic Monitoring Instrumentation System Preoperational Test 14.2.12.2.35 SU4-SQ02 Loose Parts Monitoring System Test 14.2.12.2.36 SU8-0007 Plant Performance Test 14.2.12.2.37 S-090023 Electrical Distribution System Voltage
Verification Test 14.2.12.2.38 Rev. 0 WOLF CREEK TABLE 14.2-3 INITIAL STARTUP TEST Test Number Title USAR Section S-07AB01 Automatic Steam Generator Level Control 14.2.12.3.1 SU7-AB02 Dynamic Automatic Steam Dump Control 14.2.12.3.2 S-07BB01 RTD Bypass Flow Measurement 14.2.12.3.3 S-07BB02 Pressurizer Heater and Spray Capability Test 14.2.12.3.4 S-07BB03 Reactor Coolant System Flow Measurement 14.2.12.3.5 SU7-BB04 Reactor Coolant System Flow Coastdown Test 14.2.12.3.6 S-07BB05 Pressurizer Contiuous Spray Flow Verification 14.2.12.3.7 S-07BB06 RTD/TC Cross Calibration 14.2.12.3.8
S-07SC01 Core Loading Instrumentation and Neutron Source Requirements 14.2.12.3.9 S-07SC03 Thermal Power Measurement and Statepoint Data Collection 14.2.12.3.10 SU7-SE01 Nuclear Instrumentation System Test 14.2.12.3.11 S-07SE02 Operational Alignment of Nuclear Instru-mentation 14.2.12.3.12 S-07SE03 Axial Flux Difference Instrumentation Calibration 14.2.12.3.13 S-07SF01 Control Rod Drive Mechanism Operational Test 14.2.12.3.14 S-07SF02 Rod Control System 14.2.12.3.15
SU7-SF03 Rod Drop Time Measurement 14.2.12.3.16 SU7-SF04 Rod Position Indication System 14.2.12.3.17 S-07SF05 Automatic Reactor Control System 14.2.12.3.18 S-07SR01/ Incore Flux Mapping S-07SR02 14.2.12.3.19 S-07SR03/ Incore Instrumentation Test
S-07SR04 14.2.12.3.20 S-07SF06 Operational Alignment of Process Temperature Instrumentation 14.2.12.3.21 S-07SF07 Startup Adjustments of Reactor Control System 14.2.12.3.22 S-07SF08 RCCA or Bank Worth Measurement at
Zero Power 14.2.12.3.23 SU7-SF09 RCCA or Bank Worth Measurement at Power 14.2.12.3.24
S-07SJ01 Reactor Systems Sampling for Core Load 14.2.12.3.25 SU7-0001 Initial Core Loading 14.2.12.3.26
S-070002 Inverse Count Rate Ratio Monitoring for Core Loading 14.2.12.3.27 Rev. 0 WOLF CREEK TABLE 14.2-3 (Sheet 2)
Test Number Title USAR Section S-070003 Inverse Count Rate Ratio Monitoring for Approach to Initial Criticality 14.2.12.3.28
S-070004 Initial Criticality 14.2.12.3.29 S-070005 Determination of Core Power Range for Physics Testing 14.2.12.3.30 S-070006 Boron Endpoint Determination 14.2.12.3.31 S-070007 Isothermal Temperature Coefficient Measurement 14.2.12.3.32 S-070008 Power Coefficient Determination 14.2.12.3.33 S-070009 Load Swing Tests 14.2.12.3.34 S-070010 Large Load Reduction Test 14.2.12.3.35 S-070011 Plant Trip from 100 Percent Power 14.2.12.3.36 S-070012 Rods Drop and Plant Trip 14.2.12.3.37 S-070014 Shutdown and Maintenance of Hot Standby External to the Control Room 14.2.12.3.38 S-070015 Power Ascension Thermal Expansion and Dynamic Test 14.2.12.3.39 S-070016 Biological Shield Testing 14.2.12.3.40 S-070017 Loss of Heater Drain Pump Test 14.2.12.3.41 S-070018 Calibration of Steam and Feedwater
Flow Instrumentation at Power Test 14.2.12.3.42 S-090024 Natural Circulation Test 14.2.12.3.43 Rev. 0