ML17059A244
| ML17059A244 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 03/20/1994 |
| From: | Cheung L, Ruland W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17059A243 | List: |
| References | |
| 50-410-93-81, NUDOCS 9403290028 | |
| Download: ML17059A244 (58) | |
See also: IR 05000410/1993081
Text
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
REPORT/DOCKET NO.
LICENSE NO.
LICENSEE:
FACILITYNAME:
INSPECTION DATES:
50-410/93-81
Niagara Mohawk Power Corporation
Nine Mile Point Unit 2
November 29, 1993 through December
17, 1993,
and January 24-28, 1994
'RC
CONSULTANTS:
J. Hailer, Electrical Engineer
M. Shlyamberg, Mechanical Engineer
TEAMLEADER'eonard
S. Cheung, Sr.
eactor Engineer
Electrical Section, EB, DRS
Date
APPROVED BY:
William H. Ruland, Chief, ES, EB, DRS
ggo F
Date
9403290028
940322
ADOCK 050004i0
8
d : A"
d
I I
"Ad
AI
I
d
dd
the functionality of Nine Mile Point Unit 2 electrical distribution system.
R~e~ul:
As described in the Executive Summary.
TABLE OF CONTENTS
~Pa
e No.
EXECUTIVE SUMMARY
1V
1.0
INTRODUCTION
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
2.0
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
ELECTRICAL SYSTEMS
2.1
Offsite Power and Grid Configuration..............
2.2
Bus Alignment During Startup, Normal Power and Shutdown
Ope rations
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Bus Transfer Schemes
Class 1E AC Power Systems
Degraded Voltage Protection Schemes for Class 1E Buses
2.6.1
First Level Voltage Protection ..............
2.6.2
Second Level Voltage Protection
Class 1E 120 VAC System
Class 1E 125 VDCSystems....................
Class 1E AC Power System Equipment.............
COnClUSlon
a
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
2
3
5
5
6
7
8
8
8
9
9
10
12
3.0
MECHANICALSYSTEMS
3.1
Power Demands for Major Loads
3.2
Diesel Generator and Auxiliary Systems
3.3
Heating, Ventilation, and Air Conditioning (HVAC) Systems
3
0
.4
COnCluS10nS
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
a
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
13
13
14
15
16
4.0
ELECTRICALDISTRIBUTIONSYSTEM EQUIPMENT
4.1
Equipment Walkdowns .................
4.2
Electrical Equipment Maintenance and Testing
4.2.1
Emergency Diesel Generator Testing ....
4.2.2
Station Batteries.................
4.2.3
Relay Testing
4.3
Conclusions........................
~
~
~
0
~
~
~
~
~
~
~
~
~
~
16
16
17
17
18
19
19
5.0
REVIEW OF NMPC's SELF-ASSESSMENT OF ELECTRICAL
DISTRIBUTIONSYSTEM.......................
19
6.0
UNRESOLVED ITEMS
20
7.0
XITMEETING
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
E
20
ATTACHMENT 1 - Persons
Contacted
ATTACHMENT2 - Abbreviations
ATTACHMENT3 - Nine Mile 2 Electrical Distribution System
111
EXECUTIVE SUMMARY
During the period between November 29, 1993, and January 28, 1994, a Nuclear Regulatory
Commission (NRC) inspection team conducted
an electrical distribution system functional
inspection (EDSFI) at the Nine Mile Point Unit 2 (NMP2). The inspection was performed to
determine the adequacy of the Niagara Mohawk Power Corporation (NMPC) self-assessment,
and whether the electrical distribution system (EDS) at NMP2 was capable of performing its
intended safety functions as designed,
installed,"and configured.
This inspection also
~
included a review of NMPC response
to the deficient condition that the high pressure core
spray (HPCS) system injection valve failed to open during testing as reported in licensee
event report (LER) 93-10.
The team reviewed the NMPC self-assessment
reports and selected questions and responses,
including an independent review conducted by a contractor.
NMPC's self-assessment
covered a scope similar to an NRC EDSFI, and identified 57 open items and 43 observations
during the course, of the inspection.
Based on these open items, NMPC initiated 52
deviation/event reports (DERs).
Based on these findings, the team determined that NMPC's
self-assessment
was comprehensive
and of high quality.
Three NRC findings were not
identified by the NMPC inspection team.
These findings are:
1) there was insufficient
evidence that the capacity of the day tanks and storage fuel oil tanks met the final safety
analysis report (FSAR) commitment; 2) the emergency diesel generators
were tested above
their two-hour ratings; and 3) lack of an analysis of the impact of the uninterruptible power
supplies output voltage total harmonic distortion (THD) in excess of 5% of the fundamental.
In addition, there were two significant deficiencies that were also missed by the NMPC self-
assessment
EDSFI, but were later identified and corrected by NMPC:
1) incorrect tap
setting on the 4160-600V transformer which served the HPCS system auxiliaries, and 2)
inadequate pickup voltage characteristics of motor starter contactors for the HPCS system
motor-operated valves (MOVs). However, the NRC findings and the deficiencies that were
identified later by NMPC were, in the team's opinion, a rare exception, rather than a lack of
indepth, comprehensive review by the NMPC self-assessment
team.
The team selected samples from the EDS in the electrical and mechanical design, and
maintenance and test areas for independent review.
The scope included a plant walkdown,
technical reviews of studies, calculations, design drawings, and station procedures pertaining
.to the EDS.
Interviews were conducted of corporate and plant personnel.
Based on the sample documents reviewed and equipment inspected,
the team concluded that
the electrical distribution system at Nine Mile Point Unit 2 is capable of performing its
intended functions, and that NMPC's actions in response to the deficient condition that the
HPCS system injection valve failed to open during testing, were appropriate.
However, the
team determined that this deficient condition constitutes an apparent violation of Technical Specifications, Section 3.5.1, Item C, as discussed
in paragraph 2.9 of this inspection report.
The team identified three unresolved items; one in the electrical design area, one in the
mechanical design area, and one in the electrical equipment test area.
0
Discussed
0
A
Vil i
I~Ph
HPCS System Inoperable
2.9
Three
nres Ived Item
Item Number
EEI93-81-04
2.7
greater than 5% of the
fundamental
50-410/93-81-01
EDG fuel oil reserve
not meeting FSAR
commitment
3.2
50-410/93-81-02
EDGs were tested above
4.2.1
their two-hour rating
50-410/93-81-03
0
1.0
INTRODUCTION
DETAILS
During inspections in the past years, the Nuclear Regulatory Commission (NRC) staff
observed that, at several operating plants, the functionality of related systems had been
compromised by design modifications affecting the electrical distribution system (EDS).
The
observed design deficiencies were attributed, in part, to improper engineering and technical
support.
Examples of these deficiencies included:
unmonitored and uncontrolled load
growth on safety-related
buses; inadequate review of design modifications; inadequate design
calculations; improper testing of electrical equipment; and use of unqualified commercial
grade equipment in safety-related applications.
In view of the above, the NRC developed an electrical distribution system functional
inspection (EDSFI) program for operating plants.
In response
to this, Niagara Mohawk
Power Corporation (NMPC) conducted two electrical self-assessments
at NMP2 from
mid-1991 to October 10, 1993.
Their review covered areas similar to an NRC EDSFI,
Fifty-seven open items were identified by NMPC.
Some of these issues were not yet
resolved when this inspection started.
This inspection was conducted to supplement and follow up on NMPC's self-assessment.
During this inspection, the NRC team reviewed the NMPC self-assessment
report and
selected questions and answers from those reviews.
In addition, the NRC team also selected
areas that they considered important to safety for detailed review, using techniques and past
experience developed during previous EDSFIs.
The NRC team's review covered portions of onsite and offsite electrical power sources
and
included the 115 kV buses,
reserve service station transformers, 4.16 kV power system,
600V Class 1E buses and motor control centers,
station
batteries, battery chargers,
125 Vdc Class 1E buses, uninterruptible power supplies (UPS)
and the 120 Vac Class 1E vital distribution system.
The NRC team verified the adequacy of the emergency onsite and offsite sources for the
EDS equipment by reviewing regulation of power to essential loads and circuit independence.
The team also assessed
the adequacy of those mechanical systems that interface with and
support the EDS.
These included the air start, lube oil, and cooling systems for the
emergency diesel generator and the cooling and heating systems for the electrical distribution
equipment.
A physical examination of the EDS equipment verified its configuration and ratings and
included original installations as well as equipment installed through modifications.
In
addition, the team reviewed maintenance
and surveillance activities for selected EDS
components.
In addition to the above, the team verified general conformance with General Design Criteria (GDC) 17 and 18, and appropriate criteria of Appendix B to 10 CFR Part 50.
The team also
reviewed the plant technical specifications,
the Updated Final Safety Analysis Report, and
appropriate safety evaluation reports to ensure that technical requirements
and licensee's
commitments were being met.
This inspection also included a review of NMPC response
to the deficient condition that the
high pressure core spray system injection valve failed to open during testing as reported in
LER 93-10.
The details of specific areas reviewed, the NRC team's findings, and the applicable
conclusions are described in Sections 2.0 through 5.0 of this report.
2.0
ELECTRICALSYSTEMS
The team reviewed the Nine Mile Point Unit 2 (NMP2) electrical distribution system (EDS)
self-assessment
performed by Niagara Mohawk Power Corporation (NMPC). The scope of
this self-assessment
was similar to an NRC-performed EDSFI and included the efforts by
NMPC and an independent consulting firm, Ogden Environmental and Energy Services.
The
team noted that several significant issues were identified in the EDS design area:
o
Incorrect operational mode for the reserve station service transformer automatic load
tap changers;
inconsistencies,
non-conservative considerations
and the lack of transient voltage and
transient frequency analyses in the emergency diesel generator (EDG) loading studies;
lack of sizing calculation for the EDG neutral grounding resistors;
potential for the short circuit current to exceed the 4.16 kV switchgear interrupting
, capability and the lack of short circuit analysis for the Division III600V system; and
incomplete analysis in the degraded grid protection setpoint study regarding the
impact of relay tolerances and the operation of low voltage equipment with degraded
terminal voltage.
Additional details of this review are discussed,
in part, by the following subsections
and
Section 5.0 of this report,
The team also reviewed a sample of the key features and components of the Class 1E portion
of the EDS design and equipment ratings.
The review addressed
both ac and dc systems and
included:
a) normal and emergency power sources;
b) load analysis and load flow; c)
equipment ratings versus worst-case loading; d) voltage regulation; and e) degraded voltage
protection.
2.1
Offsite Power and Grid Configuration
The electrical power output of the NMP2 main generator was rated 1348.4 MVA, 0.9 power
factor at 25 kV. The generator output voltage was stepped up to 345 kV by a 408 MVA
transformer bank located at the station.
Connection of this transfer bank to the NMPC grid
was made at the Scriba 345/115 kV switchyard which is located approximately 3000 feet
from NMP2. In addition to this connection from NMP2, the 345 kV section of the Scriba
switchyard also had connections to (a) the NMP1 output, (b) the Fitzpatrick nuclear station
output, and (c) the NMPC network via two transmission lines.
The 345 kV section of the
Scriba switchyard utilized a breaker and a half scheme with two 345-115 kV
These two autotransformers
were equipped with automatic load tap
changers (ALTC) and each served a separate
bus in the 115 kV section.
These ALTCs were
in the auto-mode and the output voltage of each auto transformer was set at 118 kV. The
NMP2 electrical distribution system is shown in Attachment 3.
The offsite power supply to the NhlP2 was the 115 kV section of the Scriba switchyard.
Two separate lines, one from each Scriba 115 kV bus, were routed on separate
structures to
a three section
115 kV bus located a the NMP2.
One line, source A (switchyard line 5)
served reserve station service transformer 1A (2RTX-XSRIA)via one bus end section, and
the other, source B (switchyard line 6), served reserve station service transformer 1B (2RTX-
XSRIB) via the other bus end section.
The center bus section served the auxiliary boiler
service transformer (2ABS-Xl). The 115 kV bus sections were equipped with disconnect
switches which were normally positioned to align the center section with source A gine 5);
the disconnect between the center section and the section served by source B (line 6) was
normally open.
Thus, source A normally supplied transformers 2RTX-XRIAand 2ABS-XI
while source B normally supplied transformer 2RTX-XRIB. An ALTC was provided for
each of the two reserve station service transformers
(RSST).
The NMPC self-assessment
inspection had observed that the ALTCs for the two RSSTs were
being operated in the manual mode.
Whereas, it was indicated in Section 8.2.1.4 of NMP2
final safety evaluation report (FSAR) that the ALTCs would be operated in the auto-mode to
maintain secondary winding voltage.
NMPC documented the concern with deviation/event
report (DER) 2-91-Q-0573, dated July 23, 1991.
The RSST ALTCs had been in the manual
mode since the initial plant startup.
NMPC stated that during the preoperation
stage,
these
ALTCs were placed in the manual mode because the upstream 345-115 kV auto transformer
ALTC in the Scriba switchyard was being operated in the auto-mode.
NMPC performed an
operability determination for the ALTC being in the manual mode instead of being in the
auto-mode.
They determined that there was no operability problem because:
a)
The safety equipment was designed for loss-of-offsite-power (LOOP) and degraded
voltage conditions;
'b)
During the LOOP and degraded voltage condition, power would be transferred to the
4
c)
The ALTC being in the manual mode did not affect the undervoltage and degraded
voltage settings;
d)
NMPC evaluated the over-voltage and determined that the over-voltage would not
affect equipment operation.
The offsite power voltage was regulated by the Scriba
345-115 kV auto transformers.
The voltage level was analyzed by Stone & Webster
in their 1985 voltage profile study for different motor loading conditions, with the
ALTC being in the manual mode.
NMPC also performed a reportability evaluation and determined that this issue was not
reportable because the operability of the safety equipment was not affected.
During the 1992 refueling outage, NMPC changed the ALTC to auto-mode.
The timing of
the Scriba 345-115 kV transformers was changed from 60 seconds to 30 seconds,
and the
RSST ALTC timing was set at 60 seconds.
These settings were selected to avoid voltage
oscillation during large motor starting.
NMP2 Operation Procedure NZ-OP-72 was revised
to incorporate these changes.
NMPC also completed a 50.59 evaluation and determined that
there were no unreviewed safety questions for the above changes.
The RSST ALTCs have
been in the auto-mode since the startup from the 1992 refueling outage.
The team concluded that the actions taken by NMPC in response
to the DER were
appropriate.
The team observed that during the recent refueling outage NMP2 experienced
a partial loss
of offsite power.
Specifically, the source A, which supplies Division I equipment, was lost
while the plant was in the refueling mode.
Source B was unaffected,
This event was
reported to the NRC by licensee event reports (LER) 93-08, dated December
1, 1993, titled
"Engineered Safety Feature Actuations Due to a Partial Loss of Offsite Power Caused by a
Personnel Error," and LER 93-09, dated December 2, 1993, titled "Engineered Safety
Feature Actuations Resulting From a Loss of Power to RPS and RCIS Caused by Personnel
Error." The team found no design concerns associated
with these two LERs and that further
analysis of these LERs was outside of the scope of the EDSFI.
The team observed that the 115 kV offsite power source had been the subject of an earlier
NRC inspection on July 19-23, 1993. At that time the inspector concluded that the 115 kV
offsite power source was reasonably reliable.
The inspection findings were discussed in the
combined inspection report 50-220/93-15 and 50-410/93-15.
The EDSFI team's review of
the 115 kV power source did not identify any concerns that would change the previous
assessment.
5
2.2
Bus Alignment During Startup, Normal Power and Shutdown Operations
The medium voltage portion of the EDS consisted of the following:
two nonsafety-related
13.8 kV buses for normal unit auxiliaries (2NPS-SWG001
and
one nonsafety-related
13.8 kV bus for the auxiliary boiler auxiliaries (2NPS-
SWG002);
five nonsafety-related
4.16 kV buses for the normal unit auxiliaries (2NPS-SWG011
through SWG015) and
three safety-related 4.16 kV buses,
one each associated
with engineering safeguards
Division I (2ENS*SWG101), Division II (2ENS~SWG103) and Division III
(2ENS*SWG102).
During unit startup and shutdown, half of the unit normal auxiliary buses were served by
reserve transformer 2RTX-XRIA; the other half of the auxiliary buses were served by
reserve transformer 2RTX-XRIB. The auxiliary boiler bus was served by transformer 2ABS-
XI. The Division I and Division IIIbuses were served exclusively by a tertiary winding of
reserve transformer 2RTX-XRIAand the Division II bus was served exclusively by a tertiary
winding on reserve transformer 2RTX-XRIB. However, in the event either reserve station
service transformer was temporarily out of service, the associated Division I or Division II
bus could be served by a 4.16 kV tertiary winding of the auxiliary boiler service
transformer.
Following startup, the units normal auxiliary buses were manually transferred to the normal
station service transformer 2STX-XNS1 which was connected to the unit main generator
2.3
Bus Transfer Schemes
The team observed that following a unit trip, the normal auxiliary buses were transferred
from the normal station service transformer to the reserve station service transformers by an
automatically initiated fast dead-bus transfer scheme.
Since the Division I, IIand IIIbuses
remained connected to the reserve transformers during normal operation, no transfer was
required for these buses following a unit trip.
The team observed in the NMPC self-assessment
that the impact of the above fast dead-bus
transfer on the safety-related Division I, II and IIIbuses had been addressed.
NMPC had
analyzed the transfer and concluded that the scheme was acceptable.
The team did not
review the analysis.
f
S
2.4
Class 1E AC Power Systems
The team observed that the Class 1E ac power systems included a 4.16 kV system and a
600V system.. The 4.16 kV Class 1E systems consisted of three separate
and independent
buses for Division I, II and III. Division I and Division IIIwere served by offsite source A
while Division II was served by offsite source B.
Each division had a standby emergency
supply from its own dedicated emergency diesel generator.
Division I and Division II
systems were essentially redundant and served load center transformers and pump drive
motors associated with the low pressure core spray system, service water system, residual
heat removal system and the spent fuel pool cooling system.
Division IIIserved the high
pressure core spray system pump drive motor and a motor control center.
The 600V Class 1E systems included three separate
and independent
sets of load center
switchgear and motor control centers.
Division I and Division II load centers were each
double-ended, i.e., had the capability of being served by one of two 4.16 kV-600V
transformers.
These load centers served the larger low voltage motors (150 HP and larger),
larger low voltage non-motor loads (60 kW and larger) and motor control centers.
The
Division III600V system had a single 4.16 kV-600V transformer which served the division's
motor control center.
Division IIIhad no load center switchgear.
The team noted that the NMPC self-assessment
had implied that all 4.16 kV-600V
transformers were provided with appropriately rated surge arresters.
However, in response
to the team's query, NMPC advised that, in fact, the Division III4.16 kV-600V transformer
was not provided with surge arresters.
Further, in response
to the team's concern NMPC
performed an evaluation which concluded that the basic impulse level (BIL) provided for the
transformer insulation would withstand the potential surges on the 4.16 kV system to which
it could be exposed.
The team reviewed the electrical distribution equipment loadings for the Class 1E ac
electrical distribution system equipment based on the NMPC calculation EC-151, Revision 0,
dated November 13, 1992, titled "AuxiliarySystem Performance Using ELMS-AC,"
including the calculation dispositions 00A, 00B and 00C, dated January 7, 1993,
May 4, 1993, and May 6, 1993, respectively.
This documentation indicated that, under
worst-case loss of reactor coolant (LOCA) conditions, the reserve station service
transformers, 4.16 kV switchgear, 4.16 kV-600V transformers,
motor control centers would be operated within their designed ratings.
In their self-assessment,
NMPC had identified a concern with the potential fault duty to
which the 4.16 kV switchgear could be exposed while testing either the Division I or
Division II EDG in parallel with the 115 kV system through the auxiliary boiler service
transformer.
NMPC addressed
this concern in DER 2-92-3960, dated November 3, 1992.
Resolution involved a rerun of the ELMS-AC program for calculation EC-151 using a more
realistic short circuit time constant for the emergency diesel generator.
The self-assessment
also identified a lack of a short circuit analysis for the Division III600V system.
This
concern was addressed
by NMPC in their DER 2-92-Q-1788, dated April21, 1992.
Resolution involved the generation of calculation EC-151, Revision 0, which indicated
acceptable fault levels on Division III600V system.
Based on the team's review of the referenced deviation/event reports and calculation EC-151,
the team concluded that the loading and potential fault duties were within the Class 1E ac
power system equipment capabilities.
2.5
The team observed that a dedicated emergency diesel generator (EDG) is provided for each
Class 1E ac power system.
The ratings of the EDGs are as follows:
8760 hour0.101 days <br />2.433 hours <br />0.0145 weeks <br />0.00333 months <br /> (continuous) rating
2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> (short time) rating
2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating
Division I &II
4400 kW
4750 kw
4840 kw
Division III
2600 kw
2850 kw
2860 kw
NMPC identified, during their self-assessment,
that their calculation EC-032, Revision 7,
titled "Diesel Generator Loading," which was used to document the worst-case loading,
contained inconsistencies.
Namely, the calculation did not consider cable losses nor actual
motor power factors.
Further, the calculation did not address
the transient voltage and
frequency conditions encountered
during the EDG loading sequences.
To address
these
concerns, NMPC issued DER 2-92-Q-1782, dated April2, 1992, and DER 2-92-3628, dated
October 6, 1992.
In addition, NMPC determined that a scenario of a loss-of-offsite power
(LOOP) followed by a LOCA had not been analyzed.
To address
these concerns, NMPC
issued DER 2-92-Q-1461, dated April7, 1992.
Resolution of the steady-state
loading
concerns involved revising calculation EC-32 as Revision 8, dated January 4, 1993, which
did consider transformer and cable losses and, where known, actual motor brake horsepower
and power factor (otherwise nameplate horsepower and power factor).
This revision of the
calculation, based on the "ELMS-AC" program used in calculation EC-151, Revision 0,
determined the worst-case loading on Divisions I, II and IIIEDGs to be 4292 kW, 3875 kW
and 2540 kW, respectively, which is within the EDG continuous rating.
The resolution of the transient voltage and frequency concern involved the issuance of a new
calculation, EC-156, Revision 0, dated June 29, 1993, entitled "Diesel Generator Transient
Analysis," which was based on the electrical transient analyzer program "ETAP." The team
noted from the results of this calculation that, for Division I and Division II, generator output
frequency did not recover to 98 percent as implied by the calculation objective, and the
regulatory position given in USNRC Regulatory Guide 1.9, Revision 3, dated July 1993.
In
response to the team's concern, NMPC made a preliminary rerun of the "ETAP" program
using the known brake horsepower for motor loads when known rather than the rated
0
horsepower.
In addition, the EDG governor and exciter transfer function constants were
changed to better represent
the NMP2 EDG units.
The rerun of the program yielded an
acceptable frequency recovery.
NMPC advised that the next revision of calculation EC-156
willbe issued using this more realistic data.
In their self-assessment
inspection, NMPC also identified the lack of a EDG generator
neutral grounding resistor calculation.
This.was addressed
by DER 2-92-Q-1256, dated
March 31, 1992.
The concern was resolved by the issuance of calculation EC-153, which
addressed
the EDG generator neutral ground resistor, Revision 0, dated September 30, 1992.
Based on review of the referenced DERs and calculations EC-032 and EC-156, the team
concluded that the loadings on the EDGs were within their designed capabilities.
2.6
Degraded Voltage Protection Schemes for Class 1E Buses
2.6.1
First Level Voltage Protection
The team observed that the setting of the first level, or loss of voltage, protection scheme for
the Class 1E 4.16 kV buses was 3212 volts or about 77 percent of nominal.
Three relays
were provided for this function on each bus; i.e., one per phase,
and acted in two-out-of-
three logic to detect loss of the offsite power supply to the associated
bus.
Following a time
delay of about 3 seconds,
load shedding and EDG starting for that bus would have been
initiated.
The team did not identify any concerns in the review of this protection scheme,
2.6.2
Second Level Voltage Protection
The team observed that the setting of the second level, or degraded voltage protection
scheme for the Class 1E 4.16 kV buses was 3847 volts, or about 92.5 percent of nominal.
NMPC determined that with this setting, when considering relay tolerances,
the protection
scheme actuation could occur at 3770 volts or 90.6 percent of nominal.
NMPC had
determined, using their preliminary revision 4 to calculation EC-136, titled "Degraded
Voltage Relay Set Point," that the lower limitof the setting, i.e., 3770 volts, would still
provide sufficient voltages for the 600 volt safety-related motors (at least 90 percent of
nameplate rating for running conditions and at least 80 percent of nameplate rating for motor
starting).
The preliminary revision of calculation EC-136 was based on the "ELMS-AC"
program used in calculation EC-151, Revision 0.
The team noted that, as was the case for the first level protection, three relays were provided
on each bus, i.e., one per phase,
and acted in two-out-of-three logic to detect unacceptable
degraded voltage conditions on the associated
bus.
This scheme had two time delays.
The
first time delay was set at 8 seconds and acted in the event of a LOCA; the second time
delay was set at 30 seconds without a LOCA. Following either time delay actuation, bus
stripping and EDG starting is to be initiated for the associated
bus.
9
The team did not identify any concerns with the design of this second level voltage protection
scheme.
2.7
Class 1E 120 VAC System
The team noted that the Class 1E 120 Vac system consisted of two uninterruptible power
supplies (UPS) which served the plants instrumentation and controls associated
with the
emergency core cooling system.
These UPS systems each had a rated output of 25 kVA at
120 volts, plus or minus 2 percent and 60 hertz, plus or minus 0.5 hertz.
The team noted
that for the kVAloading, these UPS systems were well within their capabilities.
Both the NMP2 FSAR and the UPS procurement specification identified the total harmonic
distortion (THD) of the output voltage to be not more than 5% of the fundamental,
It was
not clear to the team nor NMPC engineers whether the 5% applied to the loaded or unloaded
conditions.
Tests conducted by NMP2 plant personnel indicated that during the unloaded
condition, the THD was 3.9%, while during the loaded condition, the maximum THD was
9%.
In response
to the team's concern, NMPC performed a thorough analysis, which
indicated that all loads connected to the UPS were determined to be operable because
many
of these loads were immune to a higher THD. Subsequently,
NMPC issued DER 2-93-2905,
entitled, "UPS,with a THD Greater Than 5%," on December
15, 1993, to address
this issue.
This DER requires further analysis to determine the acceptance
criteria for the THD and to
establish control of future load addition.
This item is unresolved pending NRC review of the
resolution of DER 2-93-2905 (50-410/93-81-01).
2.8
Class 1E 125 VDC Systems
The team observed that the Class 1E 125 vdc systems consisted of three separate
systems;
one each for Division I, II and III. The Division I and Division II systems each consisted of
a 2550 AH (8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> rate), 60 cell, calcium grid, lead acid battery bank, two 300 A chargers
and associated
panelboards.
The Division IIIsystem consisted of a 100 AH (8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> rate), 60
cell, calcium grid, lead acid battery bank, two 50 A chargers
and associated
panelboards.
The second charger of each system was an installed spare which could be manually placed in
service when required.
The NMPC self-assessment
inspection identified two technical specifications concerns
involving these systems.
The first related to electrolyte temperature.
Both the FSAR,
Section 8.3.2.1.2, and design calculations considered 65'
to be the minimum electrolyte
temperature
whereas Technical Specification 4.8.2 specifies a surveillance requirement for a
minimum temperature of60'.
NMPC has requested,
by a letter to the NRC, dated
December
14, 1993, that the Technical Specification be changed to 65'.
10
The second NMPC-identifiied concern involved Division I and Division II systems.
Technical Specification Section 3.8.2.2 requires that both the primary and backup chargers
be in operation when the associated
UPS system is powered by its backup dc supply.
determined that, ifthe battery had been discharged prior to the connection of the second
charger, there was a potential for the bus supply breaker to trip when both chargers went to
their current limit. NMPC verified the adequacy of one charger to supply the normal dc
loads, including the dc requirements of the UPS, and recharge the battery within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
As a result, NMPC has requested,
by the same letter as above, that the Technical
Specification be changed to delete the requirement for the operation of the second charger.
NMPC identified a few minor concerns involving assumptions
used in the 125 Vdc system
calculations including battery design margin, battery temperature correction factor and
loading assumptions.
These concerns where addressed
and resolved by the deviation/event
report process.
The team did not identify any additional concerns with the Class 1E 125 Vdc
system design.
C
2.9
Class 1E AC Power System Equipment
The team reviewed NMPC licensee event report (LER) 93-10, dated December 8, 1993,
regarding the inoperability of the High Pressure
Core Spray (HPCS, Division IIIemergency
core cooling) system due to equipment deficiencies.
The LER reported a failure to operate
the HPCS system injection valve motor starter opening contactor during a test that was
performed on November 8, 1993, during the 1993 refueling outage.
The opening contactor,
located in motor control center 2EHS*MCC201, provides electrical power to the valve motor
to open the valve when that contactor picked up.
NMPC determined that the control voltage
applied to the contactor was insufficient for the starter coil to pickup, thus preventing the
HPCS system injection valve (2CSH*MOV107) from opening.
NMPC stated that the design
specifications had required the contactor to operate with 96 volts '(80 percent of 120 volts) or
less across the contactor coil.
NMPC determined that the inadequate coil voltage was due to two separate conditions,
One
of these conditions was that the tap setting on the 4160-600V transformer (2EJS*X2) was set
at +2.5% rather than -2.5% as specified in the design.
This resulted in a 5% voltage
reduction on the 600V motor control center bus.
The second condition was the inability of
the valve motor starter coil (GE size 2 contactor) to pickup at 96 volts (80% of the coil
rating) as determined by testing.
Both conditions existed in the plant since initial startup
more than five years ago.
Further, NMPC determined that either condition alone would
have prevented valve actuation during degraded voltage conditions.
This problem was not
detected and corrected earlier because it was obscured by the ALTCs for the RSSTs being
operated in the manual mode as discussed in Section 2.1.
When the ALTCs were in the
manual mode, the 4.16 kV bus voltage was increased
about 2.6%, resulting higher control
voltage across the valve motor starter coil. NMPC made these ALTC features operational
'and set at auto-mode before startup from the 1992 refueling outage.
The 4160V bus voltage
was maintained at nominal voltage since then.
NMPC stated that the HPCS system injection valve passed all tests conducted prior to the
1993 refueling outage.
During the 1993 refueling outage, several tests were conducted for this'valve.
The first test
was a static test (stroking the valve with the HPCS pump stopped) that was conducted on
October 4, 1993, and passed.
The second test was a dynamic test (with the HPCS pump
running) and was conducted on October 5, 1993.
The valve opened successfully.
The third
test was also a dynamic test conducted on November 8, 1993.
The valve failed to open.
Subsequently,
DER 2-93-2622 was generated
and the valve was declared inoperable (LER
93-10 was issued later).
On November 10, 1993, after cleaning various contacts in the
control circuit, NMPC stroked the valve twice (HPCS pump not running), and the valve
opened successfully.
On November 15, 1993, NMPC attempted to stroke the valve, and the
motor contractor failed to pick up. Allof the above tests were conducted before the
deficiencies were corrected, which took place between November 17, 1993, and
November 21, 1993.
The offsite power supply was at normal voltage during the above tests.
However, specific voltages were not measured in each case.
After the motor contactor was
replaced and the transformer tap setting corrected,
a dynamic test was conducted on
November 21, 1993, and passed.
During this inspection, NMPC performed a preliminary calculation, which indicated that,
before the deficiencies were corrected,
and with the 4160V bus being at nominal voltage, the
valve motor control circuit had barely enough voltage for the contactor coil to pick up, with
no margin.
The corrective actions taken and completed by NMPC included:
a)
Replaced four GE size 2 contactors in the HPCS 600V motor control center with
Gould contactors, which have a pull-in voltage of'86V or less, and corrected the
transformer tap setting from +2.5% to -2,5%.
b)
Verified, by measuring the secondary voltage, that the Divisions I and II switchgear
transformer taps were set correctly.
c)
Reviewed the preoperation
test data for Divisions I k, IIcontactors and determined
that the contactors could pull in under degraded voltage conditions. It was found that
Divisions I and IIswitchgear use Gould contactors.
This type of contactor has a pull-
in voltage of 86V or less.
The above corrective actions were verified by the team during the inspection.
" For the contactors in the HPCS 600V motor control center that were not replaced, NMPC
provided the followingjustifications:
Pl
12
a)
Two GE size 2 contactors were not replaced because
they were used for equipment
which is required to function only when the HPCS pump was in the standby mode and
was not required to function during an accident.
In addition, the test data indicated
that these two contactors required pull-in voltage of 89V or less.
b)
GE size
1 and size 3 contactors were not replaced because the test data indicated that
these contacts would pull-in with less than 96 V.
The team considered this justification to be appropriate.
NMPC determined the root cause for the valve motor contactor deficiency to be an
equipment deficiency that was not identified during plant startup testing due to inadequate
methods used to evaluate startup test data.
NMPC also determined the root cause of the
incorrect transformer tap setting to be poor work practices during plant construction and
preoperational
testing.
The team reviewed NMPC's program for plant modification to
ascertain whether their current practices would preclude the above deficiencies.
For a typical
plant modification, the project engineer interfaces directly with the design engineers
and
procurement engineers
to assure that the design requirements are properly incorporated into
the purchasing requirements.
Upon receipt of the procured items, receipt inspection and
document reviews are performed by the procurement engineers
to ensure conformance with
the design requirements.
Post-modification tests are required to demonstrate proper
operation of the equipment.
Any nonconformances
identified are documented in a DER and
resolved through the DER program.
During this inspection, the team interviewed project
engineers,
procurement engineers,
design engineers,
QA engineers,
and testing personnel.
The team found them knowledgeable and familiar with the program procedures.
Within the
scope of this review, the team did not find a current problem with the programs that led to
the motor contactor deficiency.
The team determined that the HPCS system injection valve would not open during degraded
voltage conditions, which rendered the HPCS system inoperable from initial startup of the
plant until the deficiencies were corrected in November 1993.
This deficient condition
constitutes an apparent violation of NhIP2 Technical Specifications, Section 3.5.1, item C,
which requires that the HPCS system be operable during conditions 1, 2, and 3 (EEI 50-
410/93-81-04).
2.10
Conclusion
The team concluded that the ac and dc systems were generally well designed and conformed
to the Technical Specifications and NMP2 FSAR with the exception of the two items (battery
minimum electrolyte temperature
and the battery backup charger) for which NMPC has
requested Technical Specification revisions (discussed in Section 2.8).
The team also
concluded that the EDS components were adequately
sized and configured, and that the
actions taken by NMPC in response
to the HPCS system injection valve issue were
13
appropriate.
One apparent violation (identified by NMPC) and one unresolved item were
identified in this area.
The apparent violation pertains to the inoperability of the HPCS
system, while the unresolved item pertains to the total harmonic distortion of the UPS output
voltage.
3.0
MECHANICALSYSTEMS
To verify the loading on the emergency diesel generators,
the team reviewed the power
demands of major loads for selected pumps and the translation of mechanical into electrical
loads as input into the design basis calculations.
The team also conducted a walkdown of the
supporting mechanical systems, including the diesel generator cooling water system, the
starting air system, the lube oil system, and the heating, ventilation and air conditioning
(HVAC) systems for the emergency diesel generators
(EDG) rooms, the ac and dc
switchgear areas and battery rooms.
3.1
Power Demands for Major Loads
The team reviewed the power demands for the major pump motors on the EDGs following a
loss of coolant accident (LOCA) plus a loss of offsite power (LOOP) condition.
Other
combination of LOCA and LOOP conditions discussed in the Nine Mile Point 2 (NMP 2)
Updated Safety Analysis Report (USAR) were also reviewed.
This review was based on the
information provided in the NMPC self-assessment
report and review of the design
calculations, procedures
and memoranda.
The majority of the break horse power (BHP)
curves, for the large pumps, exhibited peak values.
For these pumps, maximum BHP values
were conservatively assumed
to be in excess of the peak values indicated on the BHP vendor
certified curves.
For the pumps which had an increasing BHP characteristic (e.g., service
water pump) NMPC used very conservative assumptions
to maximize the flow rates.
These
flow rates were utilized to determine the corresponding BHP values for input into the EDG
loading calculation.
Based on this review, the team has determined that the power demands
for the major pump motors on the EDG were conservatively established in the Diesel
Generator Loading Calculation No. EC-32, Rev. 8.
'he team also reviewed a resolution of a concern related to a potential for EDG overloading
due to a lack of the administrative controls in the operating procedures,
which was identified
during the NMPC's self-assessment.
The existing procedures did not restrict the restart of
the tripped low pressure core spray or residual heat removal pump motor during a
LOCA/LOOP condition with a nearly fully loaded diesel.
The team found the NMPC's
corrective actions (a revision of the appropriate procedures)
undertaken to resolve this
concern, to be appropriate.
, ~
14
3.2
Diesel Generator and Auxiliary Systems
The team reviewed the NMPC's calculations, procedures,
and drawings to determine the
design adequacy of the diesel generators
and auxiliary systems.
A summary of the team's
findings is given below.
Two EDGs are rated at 4,400 kW each and supply power to
Divisions I and II emergency loads.
The third EDG is rated at 2,600 kW and is supplying
power to high pressure core spray (HPCS - Division III) system.
Each EDG has its own day
tank and (7 day) storage tank.
Two fuel oil transfer pumps per EDG are used to transfer
fuel oil to day tank from its respective storage tank.
The FSAR, Section 9.5.4.2.1, stated that each storage tank (approximately 52,664 gal. for
each of the standby diesel generator fuel oil storage tanks, and 36,173 gal. for the HPCS
diesel generator fuel oil storage tank) is sized to store sufficient oil for continuous operation
of its respective diesel engine at rated capacity for 7 days.
The FSAR, Section 9.5.4.2.3,
stated that based on a fuel consumption of 5.472 gpm at a rated 4,480 kW for the Division I
and II diesels, and 3.361 gpm at a rated 2,850 kW for the Division IIIdiesel, the 1-hr
running time volumes, including the dead volume in the tanks are 409 gal and 282 gal,
respectively.
To verify these commitments the team reviewed nine related mechanical and
~
~
~
~
~
electrical calculations.
The team's review of these documents generated
some concerns related to the NMPC's
ability to meet its FSAR commitments.
The discussion presented below provides basis for
the team's concerns and the NMPC's response.
a)
The fuel oil consumption rate changes
and the variation in the fuel oil properties were
not considered in the above calculations.
The committed fuel oil tank (both day and
storage) capacities were established
based on the results of the EDG tests for the
Division I &II diesels and on a vendor manual data for the HPCS diesel.
The team
expressed
concern with using the data as a basis for the tank volume calculation
without addition of any margin to allow for changes in the diesel conditions and/or
acceptable, variation of the fuel properties,
This is especially true for the HPCS
diesel,'since the calculation was based on a typical consumption
rate.
concurred with the team's concerns and performed a preliminary engineering
evaluation of the impact of these assumptions.
This evaluation indicated a potential
for a small shortfall (within a couple of percentage
points) from the committed
volumes.
However, at this time, the team could not make a final determination
regarding the NMPC's compliance with the FSAR commitments, since NMPC did not
have vendor's input required to complete the evaluation.
b)
15
The effects of the temperature
changes were not considered in the above calculations.
The fuel oil tank capacities were established
based on constant fuel oil temperature.
Although this assumption is true for the underground storage tanks, it is not always
true for the day tanks.
The day tanks are located in their respective EDG rooms and
see wide temperature variations.
This is further compounded by the use of volume-
based instruments for tank level monitoring.
(Unlike a differential pressure type, this
type indicates level based on a constant volume and not constant mass.
The vendor
consumption rates are mass-based.)
NMPC concurred with the team's concerns and
evaluated its impact as part of the preliminary engineering evaluation discussed in
item a) above.
Pending completion of this evaluation, the team deferred its
assessment of the impact of the temperature
changes on the FSAR commitments.
This is an unresolved item pending NRC's review of the completed evaluations discussed
in
items a) and b) above (50-410/93-81-02).
The team reviewed issues related to the EDG cooling identified in the self-assessment.
The
team agreed with NMPC's conclusion that the safety-related
service water (SW) system
provides adequate cooling to the EDGs.
The team noted that the process
safety limits, established in mechanical set point calculations,
were incorrectly incorporated into electrical calculations.
The error in the incorporation of
the process safety limits was originally discovered by NMPC during the self-assessment.
The team agrees with NMPC's assessment
that this error did not affect Technical
Specification limits. NMPC reconciled all of the affected calculations prior to completion of
this inspection.
However, this error appears
to be a part of the wider set point programmatic
issue, which has been recognized by NMPC. The set point issue is tracked (internally) by
NMPC. The NMPC's resolution of this issue encompasses
a variety of far reaching and
broad corrective actions which are scheduled for completion by December 31, 1995.
In the
interim, NMPC assessed
the accuracy of the NhP2 set point calculations for NSSS (nuclear
steam supply system) and BOP (balance of plant) positions of the Technical Specifications for
reactor protection.
The preliminary results of this review indicate that these calculations will
not require any changes.
3.3
Heating, Ventilation, and AirConditioning (HVAC) Systems
The team reviewed the design of the HVAC systems which provide services to the electrical
equipment within the scope of the EDSFI review, namely:
Division I, II&IIIbattery
rooms, switchgear rooms, diesel generator rooms, and diesel generator control rooms.
The
documents
used for this review were the NMPC's calculations, procedures,
drawings, and
the findings of the self-assessment.
16
The team reviewed related issues identified in the self-assessment.
These issues were:
1) the EDS equipment cooling;
2) hydrogen concentration;
and 3) EDG room exhaust fan
protection.
The team concurred with the NMPC's resolutions of these issues, which were as
follows:
1) the safety-related SW system provides adequate cooling of the EDS equipment;
2) the design of the HVAC system provides adequate hydrogen removal and complies with
the FSAR, Section 9.4.1.2.4, commitment that each battery room is maintained at a negative
pressure with regard to the surrounding areas;
and 3) the set point for the EDG room exhaust
fan low flow condition willprovide an adequate protection to the exhaust fan operation.
Additionally, NMPC had verified operation of tornado dampers during this inspection.
The team also reviewed issues related to tornado and missile protection of the HVAC
'ystems
and found that the afforded means of protection were adequate.
3.4
Conclusions
The team, based on the review of the design attributes within the scope of this inspection,
concluded that the mechanical systems supporting the EDG and other electrical equipment are
capable of performing their design functions.
The team also observed that the
mechanical'ystems,
within the scope of this inspection, had ample margin based on generally
conservative design.
One unresolved item was identified:
there was no evidence that the
capacity of the day tank and the fuel storage tank meets the FSAR commitments.
4.0
ELECTRICALDISTRIBUTIONSYSTEM EQUIPMENT
The scope of this inspection element was to assess
effectiveness of the controls established
to
ensure that the design bases for the electrical system was properly tested and maintained.
This effort was accomplished
through the review of the results of the NMPC's self-
assessment,
field walkdown and verification of the as-built configuration of electrical
equipment as specified in the electrical single-line diagrams, modification packages,
and site
procedures.
In addition, the maintenance
and test programs developed for electrical system
components were also reviewed to determine their technical adequacy.
l
4..1
Equipment Walkdowns
The team inspected various areas of the plant to verify the as-built configuration of the
installed equipment.
Areas inspected included the EDGs, EDG control rooms, 4 kV
switchgears,
batteries, inverters, and 480V load centers.
Class 1E transformers were also
examined.
The walkdown indicated that adequate
measures
were in place to control system
configuration. Allelectrical equipment was found to be generally well maintained with
surrounding areas clear of the safety hazards.
In general, the electrical equipment installed
adhered to the design requirements.
17
The team reviewed issues identified in the self-assessment
related to housekeeping
and
potential safety hazards.'uring
the walkdown, the team observed that all housekeeping
potential safety hazard issues were satisfactory resolved.
The general plant condition gave
the impression of good housekeeping
practices, especially considering that the unit was being
returned to service after an outage at the time of the walkdown.
4.2
Electrical Equipment Maintenance and Testing
The team reviewed the results of the NMPC's self-assessment,
various maintenance
and
testing procedures for equipment such as the emergency diesel generator,
batteries, battery
chargers,
4 kV switchgear, molded case circuit breakers,
and protective relays.
personnel were interviewed to assess
their understanding of the testing and maintenance
programs.
The team observations
are described below.
4.2.1
Emergency Diesel Generator Testing
Periodic surveillance testing of the EDGs was conducted to assure their operational
availability and capacity to perform their shutdown functions.
The Technical Specifications
(TS) for NMP2, Section 4.8.1.1.2, provided monthly and 18-month test requirements for
each EDG to demonstrate operational readiness.
These requirements
were implemented by
the monthly surveillance tests and by the 18-month endurance
tests.
The team reviewed monthly surveillance test procedures
and 18-month test procedures
and
several completed monthly and 18-month records test.
The team concluded that the test
procedures included adequate
acceptance
criteria that were consistent with the TS
requirements.
Review of completed test records indicated that the tests were conducted in
accordance with the test procedures.
The 18-month test procedure specified an EDG load equal to or greater than its 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating
of 4840 kW (Division I &II EDGs) and 2860 kW (Division IIIEDG) for the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
without specifying the upper limit. During the remaining 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />, this test procedure
specified an EDG load equal to or greater than its continues rating (also without the upper
limitvalue) of 4400 kW (Division I &IIEDGs) and 2600 kW (Division IIIEDG). The
team reviewed the test data of past two 18-month tests for all three EDGs.
The test data indicated the following:
1) Division I &IIEDGs were loaded consistently
between 4850 and 4910 kW for first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and between 4400 and 4500 kW for the
remaining 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> in each test; and 2) Division IIIEDG was loaded consistently between
2900 and 2910 kW for first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and between 2600 and 2700 kW for the remaining 22
hours in each test.
18
NMPC's position on this issue was as follows:
1) the temperature
and other variables
observed during these tests were well within the normal operating range; and 2) the
maintenance inspections, which took place 18 months after each endurance
test, did not
reveal any unexpected wear to the diesel engine parts that would be expected to indicate
wear.
Additionally, NMPC contacted both EDG vendors concerning the consequences
of
these tests.
The vendors'esponses
indicated that testing with slightly above rated load
would not damage the EDGs.
Also, NMPC revised appropriate procedures by addition of
caution statements which identified maximum load not to be exceeded.
The team agreed with NMPC that the current condition does not present an immediate
operability concern.
The long term concern, associated with the continuing operation of the
diesels above their rating, requires further resolution.
Pending NRC's review of the
provided information and/or corrective actions by NMPC, this item is unresolved (50-
410/93-81-03).
The team also reviewed issues related to a potential for fuel exposure below the cloud point
(formation of paraffin due to a low temperature exposure) before the fuel was transferred to
the storage tank from the delivery truck, identified in the self-assessment.
NMPC has an
operation procedure in place which requires the delivery truck to be stored in a heated
enclosure during the winter. The team agreed with the NMPC's conclusion, that this
operation procedure provided an adequate protection against fuel exposure below cloud point.
4.2.2
Station Batteries
The team reviewed the testing program'of the station batteries to assure that adequate dc
power was available to operate the dc equipment.
There were three 125 Vdc batteries - one
for each division. The team reviewed 18-month and 60-month test procedures
and their test
results to assure that they, meet the surveillance requirements
stated in the TS, Section 4.8.2.1.
The team noted that the test procedures included adequate acceptance
criteria that were consistent with the TS requirements.
Review of completed test records
indicated that these tests were conducted in accordance with the test procedures.
The team
concluded that the 18-month and 60-month tests for 125 Vdc batteries at NMP 2 were
properly implemented.
The team reviewed related issues identified in the self-assessment.
These issues were as
follows:
1) the battery charger output voltage regulation commitment; and 2) electrolyte
minimum temperature requirements of 60'F vs. 65 F. NMPC's resolutions of these issues
were as follows:
1) NMPC contacted the battery charger vendor and obtained the results of
the original charger test, which confirmed the voltage regulation commitment; and 2) NMPC
had submitted a TS change request, requesting changing the minimum temperature in TS 4.8.2.1.b.3 from 60'F to a more conservative value of 65'F (this issue was also discussed in
paragraph" 2.8 of this report).
19
4.2.3
Relay Testing
~
~
The team reviewed the NMPC calibration and testing program for protective relays used in
the safety-related portions of the EDS.
The team noted in the procedures
that safety-related
relays, such as loss of voltage and degraded voltage relays, reactor coolant pump drive motor
overcurrent relays and safety-related pump drive motor auto start time delay relays are
calibrated and tested every 18 months to conform with the technical specifications.
Other
safety-related protective relays are calibrated and tested on a less frequent schedule of either
every 30 months or 42 months depending on relay model and style number.
Auxiliary relays
are tested every 6 years.
The team did not identify any concerns with the program.
4.3
Conclusions
Based on the review of the documents,
the team concluded that NMPC had an acceptable
maintenance
and testing program for the electrical distribution system equipment at NMP 2.
One unresolved items was identified in these areas:
the EDGs were tested at a power output
greater than the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating of 4840 kW (Division I &IIEDGs) and 2860 kW (Division III
EDG).
5.0
REVIEW OF NMPC's SELF-ASSESSMFAT OF THE ELECTRICAL
DISTRIBUTIONSYSTEM
The team reviewed the NMPC's self-assessment
report and selected questions to determine
the adequacy of their review.
The self-assessment
was performed by NMPC from mid 1991,
'o
October 10, 1993.
In addition, NMPC contracted with Ogden Environmental and Energy
Services (Ogden) to perform an independent review.
The Ogden team consisted of six team
members:
one team leader, two electrical design reviewers, two mechanical design
reviewers, and one operations and testing reviewer.
The NMPC's self-assessment
covered electrical system design, mechanical system design,
electrical equipment testing and maintenance,
and engineering and technical support (E&TS)
areas.
The electrical system design covered offsite and onsite systems, including offsite grid
stability, bus alignments, voltage studies, emergency diesel generator (EDG) load
calculations, and station batteries and battery chargers.
The mechanical system design
covered EDG auxiliary systems (fuel oil, cooling water, lubrication oil, and starting air
systems), HVAC for switchgear room, EDG rooms, and battery rooms. It also covered
service water system performance in support of the EDS equipment, tornado and missile
protection, and hydrogen accumulation in the battery rooms.
The electrical equipment
testing and maintenance included maintenance
and testing of EDGs, protective relays, circuit
breakers and fuses, batteries and battery chargers.
20
The NMPC's self-assessment
team identified 57 open items and 43 observations.
Based on
these findings, 52 deviation event reports (DERs) were generated.
Out of these 52 DERs, 44
were closed and the required corrective actions implemented by NMPC prior to completion
of the NRC inspection.
The team was impressed not just by the number of questions, but
also by their quality and depth.
The team concluded that the self-assessment
findings had
been appropriately reviewed and prioritized by the NMPC.
Based on this review, the team concluded that the NMPC's self-assessment
was
comprehensive.
It covered sufficient areas for a normal EDSFI.
The number and
significance of their findings indicated an excellent level of detailed review.
Examples of
significant findings are:
1) incorrect operational mode for the reserve station service
transformers'utomatic
load tap changers
as discussed in Section 2.1, and 2) non-
conservative considerations
and the lack of transient voltage and transient frequency analyses
in the emergency diesel generator loading studies as discussed in Section 2.5.
Certain issues
were not identified.
These included:
1) there was insufficient evidence that the capacity of
the day tanks and storage fuel oil tanks met the final safety analysis report commitment; 2)
the emergency diesel generators were tested with power output greater than their two-hour
rating; and 3) lack of an analysis of the impact of the uninterruptible power supplies output
voltage total harmonic distortion (THD) in excess of 5% of the fundamental.
In addition,
there were two significant deficiencies that were also missed by the NMPC self-assessment,
but were later identified and corrected by NMPC:
1) incorrect tap setting on the 4160-600V
transformer which served the HPCS system auxiliaries; and 2) inadequate pickup voltage
characteristics of motor starter contactors for the HPCS system motor-operated valves
(MOVs). However, these additional findings and the deficiencies that were identified later
were, in the team's opinion, a rare exception, rather than the lack of indepth and
comprehensive review by the NMPC self-assessment
team.
6.0
UNRI<SOI VED ITEMS
Unresolved items are matters about which more information is required in order to ascertain
whether they are acceptable items, deviations, or violations.
Unresolved items are identified
in the Executive Summary of this report.
7.0
EXITMEETING
The licensee's
management
was informed of the scope and purpose of this inspection at the
entrance meeting on November 29, 1993.
The findings of this inspection were discussed
with the licensee's
representatives
during the course of the inspection and presented
to
licensee management during the exit meetings on December 17, 1993, and January 28, 1994.
The licensee did not dispute the inspection findings during the exit meeting.
A list of
attendees
is presented in Attachment 1.
ATTACHMENT1
Persons Contacted
Nia ara M hawk Power
o
oration
T. Aiken
A. Anderson
W. Baker
M. Bullis
U. Buiva
J. Bunyan
J. Conway
R. Dean
C, Deban
R. Deuvall
S. Doty
G. Eldridge
P. Flint
D. Greene
J. Guariglia
J. Halusic
A. Issa
J. Jirusek
A. Julka
N. Kabarwal
K. Korcz
H. Lockwood
R. Main
L. Mott
J. Mueller
R. Orcutt
A. Pinter
A. Raju
L. Schiavone
C. Terry
K. Ward
A. Zallnick Jr.
Electrical Engineer, Unit 2 Design
Operations Department Specialist
Licensing Program Dir'ector
Supervisor, Administrative Service
Lead Engineer, Electrical Design
Senior Project Engineer
Acting Plant Manager, Unit 2
Manager, Technical Support, Unit 2
Manager, Information Management
Supervisor, Mechanical Design
General Supervisor, Electrical Maintenance
EQ Program Manager
Steno., Administrative Service
Manager, Licensing
Specialist, Mechanical Maintenance
Lead Engineer, Mechanical Design
SQ Program Manager
Lead Engineer, Special Programs
Supervisor, Unit 2 Electrical Engineering
Lead Electrical Design Engineer
Licensing, Unit 2
Supervisor, Relay and Control
Maintenance Engineer
Project Designer, Unit 2
Plant Manager, Unit 2
Superintendent,
Power Dept.
Site Licensing Engineer
Electrical Engineer, NMPC EDSPI Team Leader
Mechanical Design Engineer
Vice President, Nuclear Engineering
Manager, Engineering, Unit 2
Supervisor, Unit 2 Licensing
Attachment
1
~Con rect r
R. Das
G. Morris
ASTA Engineering
Ogden Engineering
Nucl
r Re
lat
ommission
W. Mattingly
J. Menning
B. Norris
W. Ruland
NRC Resident Inspector
Project Manager, NRR
Senior Resident Inspector
Chief, Electrical Section, DRS
ATTACEQCENT 2
Abbreviations
A or Amp
ac
BHP or bhp
BIL
CB
CFR
dc
GDC
, gpm
IEEE
kA
kv
kVA
kW
, LOOP
PSI or psi
rms
TS
UST
V
Vac
Vdc
Amperes
Alternating Current
Brake Horsepower
Basic Insulation Level
Balance of Plant
Circuit Breaker
Code of Federal Regulations
Direct Current
Final Safety Analysis Report
General Design Criteria
Gallons Per Minute
High Pressure
Heating Ventilation and Air Conditioning
Institute of Electrical and Electronics Engineers
Kiloamperes
Kilovolts
Kilovolt-amperes
Kilowatts
Load Center
Loss of Coolant Accident
Motor Control Center
Motor-Operated Valve
Nuclear Steam Supply System
Pounds per Square Inch
USNRC Regulatory Guide
Root Mean Square
Reserve Station Service Transformer
Total Harmonic Distortion
Technical Specifications
Uninterruptible Power Supply
United States Nuclear Regulatory Commission
Unit Service Transformer(s)
Volt(s)
Volts Alternating Current
Volts Direct Current
0*
345KV TO
ATION (LIME 23)
42/56/78HYA
RESERYE
BANK
'A'5/+5k
'45/25KV
Scu~g
4./PI&+
RBSHVA EACH
~ gag
xQ(R
ttskv/i3 gk.v/~J6kv
J
L
UNIT
25KY~
~NORHAL ST4
TRANSF,
24. Y6V/IXSKV
I88-58/58HYA
I154
13,tgvqi
a+ils~I/
8'puA6~ B
LMI8 ~
42/56/78HVA
RESERVE
BAN( 8
AVX BOILER
NO
CVL ONLY .
2%'S-SVGNI
13.8KV
NORHAL
AVX. TRANSF.
CUB. 0%.Y
20%-SMG883
AUX. TR4NSF.
NC
I3JRV
AUX.BOILER
BUS
2M%-SMG882
NORHAL 4.168KY
205-S'MGBH
NC
AS-SkeIS
ZNNS-SVGSII
~-SNGB13
4.16KV
NO
STUB BVS
STUB BUS
CUB.
ONLY
i.16~V OIV.I -I
EHERGENCT
BUS
ZENS~SWGIBI
NO
2ENS SVGI82
NO
~ 4.168KV OIV.3
El+RGENCY
BVS
ZENS'SNGI83
4.168KV GIVE
Ek%RGENCY
- BVS
EGI OIV.I
44NKN
ATTACHMENT 3
Nine Mile 2 Electrical Distribution S stem
EG2 OIV.3
~6%~ Y
m&4/z
zsHS4<cc zo I
EG3 GIVE
4INKN
SKASZ.nrM
0