ML15219A712

From kanterella
Jump to navigation Jump to search

State of Vermonts Reply in Support of Motion for Leave to File a New Contention and Add Bases and Support to Existing Contentions
ML15219A712
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 08/07/2015
From: Landis-Marinello K
State of VT, Office of the Attorney General
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-271-LA-3, ASLBP 15-940-03-LA-BD01, RAS 28127
Download: ML15219A712 (16)


Text

1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

)

)

ENTERGY NUCLEAR VERMONT

)

Docket No. 50-271-LA-3 YANKEE, LLC AND ENTERGY

)

NUCLEAR OPERATIONS, INC.

)

August 7, 2015

)

(Vermont Yankee Nuclear Power Station) )

STATE OF VERMONTS REPLY IN SUPPORT OF MOTION FOR LEAVE TO FILE A NEW CONTENTION AND ADD BASES AND SUPPORT TO EXISTING CONTENTIONS INTRODUCTION On July 6, 2015, the State of Vermont (State) moved for leave to file a new contention and to supplement the bases and support for existing Contentions I, III, and IV.1 The Atomic Safety and Licensing Board (Board) held oral argument in this matter on July 7, 2015. The U.S. Nuclear Regulatory Commission (NRC) Staff (Staff) and Entergy Nuclear Operations, Inc. (Entergy) filed Answers to the States motion on July 31, 2015.2 The State now submits this Reply.3 1 State of Vermonts Motion for Leave to File a New Contention Including the Proposed New Contention and to Add Additional Bases and Support to Existing Contentions I, III, and IV (July 6, 2015) (ADAMS Accession No. ML15187A350).

2 NRC Staffs Answer to the State of Vermonts Motion for Leave to File a New and Amended Contentions (July 31, 2015) (ADAMS Accession No. ML15212A281) (Staff Answer); Entergys Answer Opposing the State of Vermonts New Contention V and Additional Bases for Pending Contentions I, III, and IV (July 31, 2015) (ADAMS Accession No. ML15212A828) (Entergy Answer).

3 10 C.F.R. § 2.309(i)(2).

2 Entergy and Staff make two overarching arguments, both of which lack merit. First, they argue that the States motion is untimely. They assert that the granting of an exemption request does not present new facts relevant to this License Amendment Request (LAR) and therefore the State should have filed this contention before the granting of the exemption.4 Besides reducing the exemption decision to a ministerial non-event, contrary to the Commissions view that exemptions are an extraordinary equitable remedy,5 this argument makes no sense because it is difficult to imagine any factual development more relevant here than the granting of Entergys requested exemption.

Second, Entergy and Staff assert that the States motion should be denied because the States new contention is inadmissible.6 Repeatedly asserting that license amendments are separate, distinct, independent, and unrelated to exemption requests, Entergy and Staff ask this Board to turn a blind eye to an exemption that is directly relevant here. The position of Staff and Entergy is that this Board should intentionally disregard directly relevant information. That is not the Boards role. This Board has a legal duty to evaluate whether granting the LAR is consistent with the provisions of 10 C.F.R. § 50.75(h). Now that the exemption has been granted, the LAR is not consistent with 50.75(h) and should be denied.

4 Staff Answer at 15-19; Entergy Answer at 7-9.

5 In the Matter of Honeywell International, Inc. (Metropolis Works Uranium Conversion Facility), CLI-13-01, 77 N.R.C. 1, 9 (2013).

6 Staff Answer at 19-28; Entergy Answer at 9-20.

3 I.

The States Motion Is Timely Because the Granting of an Exemption Request Is New Information Entergy and Staffs argument on timeliness falls short. The request for an exemption is different from the granting of an exemption. When the State filed its initial Petition, Entergy had requested an exemption, but the exemption had not yet been granted. The granting of the exemption was not noticed in the Federal Register until June 23, 2015.7 On that date, the State had new information directly relevant to this proceeding and promptly filed a new contention. The States motion thus meets all three requirements of 10 C.F.R. § 2.309(c)(1).

Staffs Answer asserts that the granting of the exemption was not new information, but rather a confirmation of previously-available information.8 In other words, Staff presents Entergys January 6, 2015 exemption request as a fait accompli the day it was filed. According to Staff, the actual decision to grant the exemption request was apparently ministerial.

This view of exemption requests cannot be reconciled with the requirement in 10 C.F.R. § 50.12 that exemption requests will not even be consider[ed]let alone grantedunless special circumstances are present.9 As the Commission has previously noted:

Although our regulations... authorize exemptions, we consider an exemption to be an extraordinary equitable remedy to be used only 7 80 Fed. Reg. 35992-35995 (June 23, 2015).

8 Staff Answer at 15; id. at 18 (same).

9 10 C.F.R. § 50.12(a)(2).

4 sparingly.

The reason for this high standard is simple. Every NRC regulation has gone through the rulemaking process, including public notice-and-comment, and its underlying rationale has been explained in our Statements of Consideration. Although our authority under the Atomic Energy Act of 1954, as amended (AEA), and other statutes to adopt rules of general application entails a concomitant authority to provide exemption procedures in order to allow for special circumstances, our rules presumably apply until an exemption requester has met the high burden we place upon such requests. Our exemption regulations are in place to provide equitable relief only when supported by compelling reasonsthey are not intended to serve as a vehicle for challenging the fundamental basis for the rule itself. Challenges to the rule itself are more appropriately lodged through a request for rulemaking.10 Far from a ministerial confirmation of the licensees application, the evaluation of an exemption request should be searching. And it should lead to denials of such requests in all instances where the licensee has failed to meet its high burden of demonstrating that it meets all of the requirements for an exemption.11 The Commissions directive that exemptions are extraordinary and are to be used sparingly12 belies Staffs position that the NRC review of an exemption request is essentially a ministerial confirmation of the licensees application. In addition, the State raised numerous arguments with the NRC for denying the exemption. Indeed, just weeks before this exemption was granted, the State and two utilities, the Vermont Yankee Nuclear Power Corporation and Green Mountain Power, formally request[ed] the opportunity for public participation on Entergys 10 Honeywell, CLI-13-01, 77 N.R.C. at 9.

11 Id.

12 Id.

5 January 6, 2015 exemption request before the NRC made a decision on the matter.13 The two utilities have an existing 55% interest in the alleged excess funds that Entergy is dipping into to fund spent fuel management. That request further noted a number of reasons why Entergys exemption request [was]

premature and should be denied.14 These and other arguments make clear that the granting of Entergys exemption request was not ministerial or merely confirmatory.

Further, it is the granting of a request here that constitutes the new and material information in this proceeding. Staff compares this situation to Powertech, which it describes as rejecting a contention as impermissibly late for its failure to explain how the information in a draft supplemental environmental impact statement is materially different from the information contained in the applicants previously-available environmental report.15 This comparison fails for three reasons.

First, Staff has ignored the relevant holding in Powertech. In that case, as here, Staff and Applicant opposed admission of a contention because it was 13 Letter from Vermont Attorney Generals Office, Vermont Department of Public Service, Vermont Yankee Nuclear Power Corporation, and Green Mountain Power to William Dean, Director, NRC Office of Nuclear Regulatory Regulation (June 5, 2015).

14 Id. at 2 (citing, among other things, the need for Entergy to amend the Master Trust Agreement before it can use the decommissioning trust fund for spent fuel management expenses, and further noting that 18 C.F.R. § 35.32(6) requires FERC authorization before the trust fund can be used for anything other than decommissioning expenses).

15 Staff Answer at 16 (citing Powertech USA, Inc. (Dewey-Burdock in Situ Uranium Recovery Facility), LBP-13-9, 78 NRC 37, 111-12 (2013)).

6 untimely based on the fact that the Petitioner should have filed the contention at the time the Applicant filed an allegedly flawed model of air emissions and not at the time Staff adopted that model for the Draft Supplemental Environmental Impact Statement (DSEIS). However, in language particularly relevant to the issue here, the Board held:

As to the air emissions model, the Oglala Sioux Tribes contention was timely because the revised mobile source inventory used to model air emissions first appeared in the DSEIS. It is irrelevant that it was based on data submitted to the Staff in July 2012. The use of the Powertech submission by the NRC Staff first occurred in the DSEIS.16 There is no requirement that a petitioner file a contention based on an Applicants filing. Under Powertech, a contention based on when Staff makes use of the data here, by granting Entergys exemption requestis timely.17 Second, the portion of Powertech that Staff cites relates to a contention that was deemed untimely due to specific NRC requirements for environmental contentions.18 NRC Regulations require that an environmental contention must be based on the Environmental Report and can only be based on the DSEIS to the extent the DSEIS differs from the Environmental Report.19 No such pleading requirement applies

here, particularly since Entergy has not filed an Environmental Report.

16 Powertech, 78 NRC at 93 (emphasis added).

17 Id.

18 Id. at 111-12.

19 10 C.F.R. § 2.309(f)(2); see e.g., L.P Louisiana Energy Services (National Enrichment Facility), CLI-05-20, 62 N.R.C. 523, 532-33 (2005).

7 Third, Staff leaves out a crucial fact in Powertech: there, the intervenors were putting forth a contention that had previously been litigated and rejected by the Board... because it lacked support.20 Here, by contrast, the Board has yet to rule on any of the States existing contentions. Powertech stands for nothing more than general law-of-the-case principles that preclude relitigation of matters that have already been decided.

II.

The States New Contention Is Admissible All three partiesEntergy, Staff, and the Stateare in agreement that the Boards decision here must comply with 10 C.F.R. § 50.75(h)(5). That provision provides directly applicable requirements to this precise situationwhere a licensee with existing license conditions relating to decommissioning trust agreements elects to amend those conditions.21 The regulations require that the license amendment shall be in accordance with the provisions of paragraph (h) of this section.22 Paragraph (h) specifically requires, among other things, that trust fund disbursements be restricted to decommissioning expenses and that the 30-day notice requirement is eliminated only for those expenses.23 The parties further agree that this Board has a legal duty to determine whether Entergys LAR is in 20 Powertech, LBP-13-9, 78 NRC at 111.

21 10 C.F.R. § 50.75(h)(5).

22 Id. (emphasis added).

23 Id. § 50.75(h)(1)(iv).

8 fact in accordance with the provisions of paragraph (h) of this section.24 A LAR that fails to comply with the provisions of 50.75(h) must be denied.

When it comes to a determination of whether a LAR is in accordance with the provisions of 50.75(h), the parties positions diverge. The States position is simple: look at what regulatory regime actually applies if the LAR is granted.

Entergy and Staff, by contrast, ask this Board to evaluate not what regulatory regime actually applies, but what regulations the LAR says will apply, ignoring reality. In essence, Entergy and Staff urge the Board to trust what the LAR says, not what it does. However, all parties to this proceeding know full well what happens if the Board grants this LARthe current license conditions will not be replaced with requirements from 50.75(h). Entergy explicitly describes its LAR as replacing existing license conditions with regulations that are substantially similar.25 This is empirically false. If this LAR is granted, Entergys current license conditions will not be replaced with similar provisions because Entergy has been exempted from them. This Board cannot allow form to trump substance by accepting Entergy and Staffs strained argument that the Boards inquiry should be so limited as to wholly ignore what actually happens if the LAR is approved.

In its Answer, Entergy attempts to back away from the representation in its LAR that it was replacing its license conditions with substantially similar 24 Id. § 50.75(h)(5).

25 LAR at Attachment 1, p.2.

9 regulatory requirements.26 Entergy asserts that it did not identify a standard that would only allow the NRC to grant the LAR when the license condition and regulations are substantially similar and that [n]o such standard exists.27 This strategic retreat rings hollow for two reasons.

The LAR is incomplete and inaccurate.

First, Entergy cannot deny that its LAR explicitly represents that [t]he provisions in 10 CFR 50.75(h) include substantially similar decommissioning trust requirements as those found in VY OL License Condition 3.J.28 Far from an off-hand remark, that is the entire thrust of this LAR. The explicit statement about 50.75(h) being substantially similar is followed by multiple references to where specific license conditions are addressed by the regulations.29 This culminates in a three-and-a-half page table illustrating where each specific license condition is addressed by a specific regulation.30 Entergy asserted that the LAR involved only administrative changes to the license that will be consistent with the NRCs regulations at 10 CFR 50.75(h) and that [t]he proposed amendment is confined to administrative changes for providing consistency with existing regulations.31 As 26 Entergy Answer at 13 n.50.

27 Id.

28 LAR at Attachment 1 p.2.

29 Id.; accord id. at Attachment 1, p.3.

30 Id. at Attachment 1, pp.3-6.

31 Id. at Attachment 1, pp.7-8.

10 the States motion explains, now that the exemption has been granted, these representations are inaccurate. Entergys license conditions will not be replaced by substantially similar decommissioning trust requirements.32 This is precisely why Entergys LAR does not comply with the requirement in 10 C.F.R. § 50.9(a) that an application for a license amendment shall be complete and accurate in all material respects and the similar requirement in § 50.90 that an application for a license amendment fully describ[e] the changes desired. Given the granting of the exemption, the LAR now on file in this proceeding is inaccurate and does not fully describe the changes desired.

This is material. Were Entergy to submit an accurate LAR fully describing the changes desiredas it is legally required to dothe LAR would reflect the now-granted exemption. It would thus be missing the provisions of 50.75(h)(1)(iv) that restrict disbursements to decommissioning expenses and that allow elimination of the 30-day notice requirement only for those expenses. Such a LAR does not comply with the requirement in 50.75(h)(5) that the license amendment shall be in accordance with the provisions of paragraph (h) of this section.33 Further, Entergy is incorrect that the States identification of inaccuracies and omissions in Entergys LAR seeks to elevate form over substance.34 According 32 Id. at Attachment 1, p.2.

33 10 C.F.R. § 50.75(h)(5) (emphasis added). Notably, that language does not say shall be in accordance with the provisions of (h) from which Applicant has not been exempted.

34 Entergy Answer at 12 n.47.

11 to Entergy, [t]he NRC is well aware of the issuance of the exemptions, whether that action is discussed in the LAR or not.35 To begin, simply because someone at the NRC might know about Entergys exemption request does not relieve Entergy of its legal obligation to the NRC, to this Board, and to the public to present complete and accurate information. More importantly, Entergy ignores the fact that it was the State who informed the NRC that Entergys LAR must be evaluated in light of its exemption request. When Staff acted on this LAR on February 17, 2015, it gave no indication it was aware of Entergys January 6, 2015 exemption request.36 Had the State not filed comments and intervened in this matter, Staff may have granted the LAR without ever even considering the matters at issue in this proceeding.

The 2002 rule requires substantially similar regulatory provisions before deletion of licensing conditions.

Second, Entergy is incorrect in its claim that there is [n]o... standard requiring that its license conditions be replaced with substantially similar requirements from 50.75(h)(5).37 This gets at the heart of the 2002 rule, as clarified by the 2003 rule. The only reason the NRC was willing to allow applicants to delete license conditions governing trust funds was because any such amendment would have to be in accordance with the provisions of paragraph (h),38 which includes the 35 Id.

36 80 Fed. Reg. 8355-03 (Feb. 17, 2015).

37 Entergy Answer at 12 n.50.

38 10 C.F.R. § 50.75(h)(5).

12 explicit restriction on trust fund disbursements to decommissioning expenses and only eliminates the 30-day notice requirement for those expenses.39 When those restrictions are not in placeas is the case now that Entergys exemption request has been grantedthe 2002 rule prohibits a LAR from being granted.40 That is why Entergy and Staff are forced to argue here that the Board must turn a blind eye to the exemption decision: Entergy and Staffs only argument for granting this LAR is that the Board should ignore the on-the-ground legal reality and instead evaluate a fictional scenario in which Entergy has never applied for, nor was granted, an exemption.41 When the exemption was granted, the situation presented in Entergys LARa one-for-one swap of its license conditions for regulationsmoved from being hypothetical to being counterfactual.

The reality is that Entergy is now exempted from the 50.75(h) provision that all disbursements must be restricted to decommissioning expenses and from the 50.75(h) provision that allows elimination of the 30-day notice requirement only for those expenses.42 The LAR is thus not in accordance with the provisions of 50.75(h) and must be denied.

39 Id. § 50.75(h)(1)(iv).

40 Id. § 50.75(h)(5).

41 For instance, despite the fact that all of the parties and this Board are well aware that only the exempted version of 50.75(h) now applies to Entergy, not the entirety of 50.75(h), Staff nevertheless explicitly asks this Board to only evaluate the exchange of the VY decommissioning trust license condition provisions for the decommissioning trust regulations, in their entirety. Staff Answer at 21 (emphasis in original).

42 10 C.F.R. § 50.75(h)(1)(iv).

13 III.

The States Motion Raises Legitimate Additional Bases for Its Existing Contentions, Most Particularly the Request in Contention III for Consolidating This Matter with the Exemption Request At a minimum, the States new contention meets the requirements for admission. Further, the States new contention and its additional bases and support for existing contentions highlight the basis for consolidating this matter with an evaluation of Entergys exemption request, as the States existing Contention III specifically requests. When an exemption request is directly related to a LAR, the State is entitled to a hearing on the exemption request.43 That is the case here.

Staff nevertheless attempts to replace the Commissions testwhether matters are directly relatedwith an entirely different test in which matters must remain separate if the approval of one would accomplish something independent of the approval of the other.44 Staff cites no support for this argument.

And there is no support: that is simply not the test set forth in PFS.

Finally, Entergy is incorrect in its argument that now that the NRC has granted the Exemption Request, the States arguments about hearing rights connected with that Exemption Request are moot and should be rejected.45 The Commission squarely held in PFS that exemption grants do not supersede hearing 43 In the Matter of Private Fuel Storage, LLC (PFS), CLI-01-12, 53 NRC 459, 476; see also, e.g., Honeywell, CLI-13-01, 77 NRC at 7 (But when a licensee requests an exemption in a related license amendment application, we consider the hearing rights of the amendment application to encompass the exemption request as well.).

44 Staff Answer at 23.

45 Entergy Answer at 19.

14 rights in licensing proceedings.46 It is still well within this Boards authorityand indeed is the Boards dutyto consolidate these directly related matters for a hearing. To keep these matters improperly siloed, without analyzing how they relate to each other, would be precisely the type of inadequate attention to decommissioning financial assurance that the Commission has warned could result in significant adverse health, safety and environmental impacts.47 To the extent there is any doubt as to the Boards authority, the Board can certify the question of consolidation to the Commission.

CONCLUSION For the reasons stated above and in the States previous filings, the Board should grant the States Motion for Leave, admit new Contention V, and allow amendment of the Bases and Support for Contentions I, III, and IV.

Respectfully submitted,

/Signed (electronically) by/

Kyle H. Landis-Marinello Counsel for the State of Vermont Assistant Attorney General 46 PFS, CLI-01-12, 53 NRC at 469 (emphasis added); see also id. at 474 ([T]he Commissions rulemaking powers should not place the exemption itself beyond questioning in an otherwise litigable contention.); id. at 467 n.3 (We are aware of no licensing case where we have declared exemption-related safety issues outside the scope of the hearing process altogether.).

47 Honeywell, CLI-13-01, 77 NRC at 7 (citing Final Rule: General Requirements for Decommissioning Nuclear Facilities, 53 Fed. Reg. 24018, 24019 (June 27, 1988)); see id. at 7 n.17 (noting that delays from inadequate funding may cause potential health and safety problems (quoting 53 Fed. Reg. at 24033)).

15 Environmental Protection Division Vermont Attorney General's Office 109 State Street Montpelier, VT 05609 (802) 828-1361 kyle.landis-marinello@vermont.gov Dated at Montpelier, Vermont this Seventh day of August 2015

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of

)

)

ENTERGY NUCLEAR VERMONT

)

Docket No. 50-271-LA-3 YANKEE, LLC AND ENTERGY

)

NUCLEAR OPERATIONS, INC.

)

August 7, 2015

)

(Vermont Yankee Nuclear Power Station) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305, I hereby certify that copies of the State of Vermonts Reply in Support of Motion for Leave to File a New Contention and Add Bases and Support to Existing Contentions have been served upon the Electronic Information Exchange, the NRCs e-filing system, in the above-captioned proceeding, this Seventh day of August 2015.

/Signed (electronically) by/

Kyle H. Landis-Marinello Counsel for the State of Vermont Assistant Attorney General Environmental Protection Division Vermont Attorney General's Office 109 State Street Montpelier, VT 05609 (802) 828-1361 kyle.landis-marinello@vermont.gov Dated at Montpelier, Vermont this Seventh day of August 2015