MONTHYEARIR 05000445/20240032024-10-30030 October 2024 Integrated Inspection Report 05000445/2024003 and 05000446/2024003 IR 05000445/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000445/2024404 and 05000446/2024404 (Public) IR 07200074/20244012024-10-10010 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200074/2024401 Public 05000445/LER-2024-002-01, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-10-0303 October 2024 Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions 05000446/LER-2024-001-01, Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-09-30030 September 2024 Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications CP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024 License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel ML24031A6322024-09-11011 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4), Final Safety Analysis Report Update Schedule (EPID L-2023-LLE-0023) - Letter ML24243A0152024-09-0303 September 2024 – Notification of Comprehensive Engineering Team Inspection (05000445/2025012 and 05000446/2025012) and Request for Information ML24194A1332024-08-28028 August 2024 Issuance of Amendment Nos. 190 and 190, Respectively, Revision to Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24228A2252024-08-22022 August 2024 Relief to Use Later Code Edition for Inservice Inspection Program ML24179A0772024-08-20020 August 2024 Issuance of Amendment Nos. 189 and 189, Respectively, Extension of Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24232A2262024-08-19019 August 2024 Information Request, Security IR 2024404 ML24232A2412024-08-19019 August 2024 Information Request, ISFSI Security IR 2024401 CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000445/20240052024-08-15015 August 2024 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2024005 and 05000446/2024005) CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality IR 05000445/20240022024-07-31031 July 2024 Units 1 and 2 - Integrated Inspection Report 05000445/2024002 and 05000446/2024002,and Independent Spent Fuel Storage Installation Inspection Report 07200074/2024001 IR 05000445/20244032024-07-16016 July 2024 Security Baseline Inspection Report 05000445/2024403 and 05000446/2024403 (Full Report) ML24187A0372024-07-15015 July 2024 Withdrawal of Requested Licensing Action Exemption from Select Requirements of 10 CFR Part 55, Operators Licenses ML24192A1862024-07-10010 July 2024 Notification of Inspection (NRC Inspection Report 05000445/2024003 and 05000446/2024003) and Request for Information ML24185A1382024-07-0202 July 2024 Inservice Inspection Request for Information CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 IR 05000445/20244012024-06-26026 June 2024 MC&A Program Inspection Report 05000445-2024401 and 05000446-2024401 Public-Final CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 IR 05000445/20240122024-06-17017 June 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2024012 and 05000446/2024012 ML24120A3632024-06-10010 June 2024 Issuance of Amendment Nos. 187 and 187, Respectively Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants 05000445/LER-1924-002, (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-06-0303 June 2024 (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator 05000446/LER-2024-001, (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-05-13013 May 2024 (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications 05000445/LER-2024-001, Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning2024-05-0606 May 2024 Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning ML24120A3042024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Sylestine, R, Alabama-Coushatta Tribe of Texas ML24120A2902024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Bunch, J, United Keetoowah Band of Cherokee Indians ML24120A2912024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cooper, D, Apache Tribe of Oklahoma ML24120A3032024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-SpottedBird, L, Kiowa Indian Tribe ML24107B1012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cernek, J, Coushatta Tribe of Louisiana ML24120A3022024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Pierite, M, Tunica-Biloxi Tribe of Louisiana ML24120A2922024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Dotson, Delaware Nation ML24120A2952024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Johnson, L.J., Seminole Nation of Oklahoma CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters ML24120A3052024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Woommavovah, M, Comanche Nation ML24120A3072024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Yargee, W, Alabama-Quassarte Tribal Town ML24120A2932024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Garza, Jr, Juan, Kickapoo Traditional Tribe of Texas ML24120A3002024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Morrow, R K, Thlopthlocco Tribal Town ML24120A2942024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Gonzalez, B, Caddo Nation ML24120A3012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Parton, T, Wichita and Affiliated Tribes ML24120A2972024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Martin, R, Tonkawa Tribe of Oklahoma ML24120A2962024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Kaskaske, D, Kickapoo Tribe of Oklahoma 2024-09-30
[Table view] |
See also: IR 05000445/2015302
Text
R. UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E LAMAR BLVD
ARLINGTON, TX 76011-4511
October 30, 2014
Rafael Flores, Senior Vice President
and Chief Nuclear Officer
Attention: Regulatory Affairs
Luminant Generation Company LLC
Comanche Peak Nuclear Power Plant
P.O. Box 1002
Glen Rose, TX 76043
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -
NOTIFICATION OF NRC INITIAL OPERATOR LICENSING
EXAMINATION 05000445/2015302; 05000446/2015302
Dear Mr. Flores:
In a telephone conversation on October 29, 2014, between Messrs. G. Struble, Licensing Exam
Manager, and C. Osterholtz, Chief Examiner, arrangements were made for the administration of
licensing examinations at Comanche Peak Nuclear Power Plant during the week of June 1,
2015.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for
Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will
discuss with your staff any changes that might be necessary before the examinations are
administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by March 23, 2015. The written examinations, operating tests, and supporting
reference materials identified in Attachment 3 to ES-201 will be due by April 20, 2015. Pursuant
to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an
authorized representative of the facility licensee shall approve the outlines, examinations, and
tests before they are submitted to the NRC for review and approval. All materials shall be
complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or
safeguards information in your response be contained in a separate enclosure and appropriately
marked. Any delay in receiving the required examinations and reference materials, or the
R. Flores -2-
submittal of inadequate or incomplete materials, may cause the examinations to be
rescheduled. In addition, your support for on-site validation of the examinations is required
during the week of May 4, 2015.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402 and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary operator and
senior operator license applications (Office of Management and Budget (OMB) approval
number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver
requests (if any) (OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on April 30, 2016. The public reporting burden for
this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time
for reviewing instructions, gathering and maintaining the data needed, and completing and
reviewing the collection of information. Send comments regarding this burden estimate or any
other aspect of these information collections, including suggestions for reducing the burden, to
the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, or by Internet electronic mail to
INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRCs Public Document Room or from the
Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access
and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room
page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
R. Flores -3-
Thank you for your cooperation in this matter. Mr. Struble has been advised of the policies and
guidelines referenced in this letter. If you have any questions regarding the NRCs examination
procedures and guidelines, please contact Mr. Osterholtz at 817-200-1269 or myself at
817-200-1159.
Sincerely,
/RA/
Vincent G. Gaddy, Chief
Operations Branch
Division of Reactor Safety
Dockets: 50-445; 50-446
Licenses: NPF-87; NPF-89
cc: Electronic Distribution
ML14304A383
SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:
By: V. Gaddy Yes No Non-Publicly Available Sensitive RGN-002
OFFICE SOE:OB OE:OB
NAME COsterholtz VGaddy
SIGNATURE /RA/ /RA/
DATE 10/30/14 10/30/14
Letter to Rafael Flores from Vincent G. Gaddy, dated October 30, 2014
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -
NOTIFICATION OF NRC INITIAL OPERATOR LICENSING
EXAMINATION 05000445/2015302; 05000446/2015302
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
Acting DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Jason.Kozal@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (John.Kramer@nrc.gov)
Resident Inspector (Rayomand.Kumana@nrc.gov)
Administrative Assistant (Rhonda.Smith@nrc.gov)
Branch Chief, DRP/A (Wayne.Walker@nrc.gov)
Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)
Project Engineer, DRP/A (Thomas.Sullivan@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Stephen.Monarque@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (John.Jandovitz@nrc.gov)