ML14181A982

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/98-03 on 980105-09.Violations Noted.Major Areas Inspected:Followup on Insp Findings from NRR Design Insp Performed from 970407-0523
ML14181A982
Person / Time
Site: Robinson 
Issue date: 02/06/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14181A980 List:
References
50-261-98-03, 50-261-98-3, NUDOCS 9802170041
Download: ML14181A982 (53)


See also: IR 05000261/1998003

Text

U. S. NUCLEAR REGULATORY COMMISSION

Report No:

50-261/98-03

Licensee: Carolina Power & Light (CP&L)

Facility:

H. B. Robinson Unit 2

Location:

3581 West Entrance Road

Hartsville, SC 29550

'Dates:

January 5 - 9, 1998

Inspectors:

J. Lenahan, Reactor Inspector

M: Miller, Reactor Inspector

Approved by:

H.

Christensen. Chief. Engineering Branch

Division of Reactor Safety

Enclosure 2

9802170041 980206

PDR ADOCK 05000261

Q

PDR

EXECUTIVE SUMMARY

H. B. Robinson Unit 2

NRC Inspection Report 50-261/98-03

This inspection was conducted to followup on the inspection findings from the

Office of Nuclear Reactor Regulation (NRR) design inspection performed from

April 7 through May 23, 1997. The inspection findings, documented in NRC

Inspection Report (IR)

number 50-261/97-201, were classified as 15 Unresolved

Items and 12 Inspector Followup Items

Results:

During the current inspection, three Inspector Followup items and 14

Unresolved items were closed. Four violations and two apparent violations

were identified. These violations were as follows:

A violation for inadequate corrective action to resolve instrument

line slope deficiencies.

A violation for failure to report peak cladding temperatures

changes as required by 10 CFR 50.46.

A violation of 10 CFR 50.59 for increasing the motor operator

stroke times for two valves in excess of the times specified in

the UFSAR.

A violation of 10 CFR 50.9 for providing inaccurate information to

NRC regarding cable separation for the safety injection pumps.

The two apparent violations were identified as follows:

An apparent violation for deficiencies .in

NPSH resulting in the

safety injection pumps failing to meet the operability

requirements of the Technical Specifications and the design bases

for the pumps.

An apparent violation for inadequate design control.

Enclosure 2

REPORT DETAILS

III.

Engineering

El

Conduct of Engineering

An inspection was performed by the NRC from April 7 through

May 23, 1997, on design activities associated with the safety injection

(SI) and auxiliary feedwater (AFW) systems. The results of the design

inspection were documented in NRC Inspection Report (IR)

number 50

261/97-201 and transmitted to the licensee by NRC letter dated

August 14, 1997. The licensee replied to the Inspection Report in a

letter to NRC dated November 3, 1997, Subject: Reply to NRC Design

Inspection. In their reply, the licensee discussed their planned

corrective actions and commitments to address the issues identified

during the design inspection. The corrective actions, some of which

were previously addressed in the licensee's February 11, 1997, response

to the NRC October 9, 1996, 10 CFR 50.54(f) letter, included the

following;

Performance of a self assessment on control of calculations and

personnel performance of individuals completing or reviewing

calculations.

Review the use of uncertainties in instrument setpoint

calculations.

Provide additional training on licensing and design basis to

engineering and technical personnel.

Perform self-assessments (Safety System Functional type

inspections) on the effectiveness of design basis translation into

procedures and configuration maintenance.

Implement the Improved Technical Specifications.

Complete the review of the Updated Final Safety Analysis Report

(UFSAR).

Completion of validations of the design basis documents.

Resolve discrepancies identified as part of the design basis

review reconstitution program.

Enclosure 2

2

E7

Quality Assurance in Engineering Activities

E7.1 Licensee Self Assessments

a. Inspection Scope

The inspectors reviewed the self assessment the licensee performed

in the engineering support area during 1997 as a followup to

issues identified during the April - May, 1997 design control

inspection. The licensee committed to perform this self

assessment-in the November 3, 1997 letter referenced above.

b. Observation and Findings

The inspectors.reviewed Self Assessment RESS 97-34. Control of

Calculations, dated November 17, 1997. Six issues, three

weaknesses, and three recommendations (items for management

consideration) were identified during the self assessment.

The issues identified by the self assessment were as follows: two

issues regarding administrative controls (procedures): the need to

prepare or revise calculations for instrumentation setpoints, an

issue involving'calculation errors, and one issue which concerned

cross-referencing calculations. The inspectors verified condition

reports (CRs) were initiated to evaluate the issues in accordance

with the licensee's self assessment procedure. The weaknesses

identified concerned lack of consistency in calculations, failure

to have procedures in place which require cross discipline reviews

on calculations, and lack of a database to identify relationship

between various calculations. The inspectors verified that CRs

were initiated to evaluate the weaknesses. The recommendations

from the self assessment concerned improvements to Procedure MOD

002, Design Calculations, recommended additional training, and a

change to the document control database to identify the

relationship between various calculations and various other

calculations.

c. Conclusions

The self assessment resulted in identification of numerous issues

and weaknesses, which when resolved by the licensee, would improve

completed calculations. However some areas not addressed in the

self assessment included availability of the original design

records for use by engineers when completing calculations, and

compliance with corporate design control procedures (EGR-NGGC

series).

Enclosure 2

3

E.8

Miscellaneous Engineering Issues

E8.1 (Closed) Unresolved Item 50-261/97-201-02, Single Failure of CST Level

Instrumentation.

The NRC design team questioned whether the instrumentation for the

condensate storage tank (CST) complied with Regulatory Guide (RG) 1.97,

Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess

Plant Conditions During and Following an Accident. The questions

concerned whether the level instrumentation which did not provide true

redundant power supplies for the two level-circuits complied with RG

1.97. During a loss of off-site power concurrent with a failure of EDG

A, the CST level instrumentation would be lost after one hour. Both

circuits were powered from A train. Instrumentation Loop AFW-LT-1454A

was powered from Bus 1 and backed by EDG A. Instrumentation Loop AFW

LT-1454B was powered from Bus 2 and backed by Battery A. Battery A

would provide power for one hour.

Both circuits were original plant design. The licensee's RG 1.97

submittal, Revision 1, dated June, 1985, identified the CST level

instrumentation design configuration as described above. This was

accepted by the NRC staff and a safety evaluation report was

issued.

Operating Procedure OP-402, "Auxiliary Feedwater System" contained

a precaution that informs the operator that if CST level decreases

to 10% during operation, a backup water supply should be placed in

service. The backup water supply for the AFW system is service

water.

The inspectors concluded there was no safety concern regarding the CST

level instrumentation and it was in compliance with the licensee's RG

1.97 submittal to NRC.

E8.2 (Closed) Unresolved Item 50-261/97-201-03, Design Verification for

Calculations.

The NRC design team identified numerous potential deficiencies in

engineering calculations. The calculations and deficiencies were

discussed in NRC inspection report IR 50-261/97-201 in Sections

E1.3.2.2.b. E1.3.4.2.c,.E1.3.4.2.e. E1.3.5.2.a. and E1.5.2.2.

The

inspectors reviewed the following calculation deficiencies:

Enclosure 2

4

Calculation Number RNP-I/INST-1023, "Refueling Water Storage Tank

(RWST) Level Indication Accuracies". Revision 0. dated June 28.

1991, did not consider potential vortexing for the RWST above the

level setpoint of 9 percent that was used in the End Path

Procedure EPP-9, "Transfer to Cold Leg Recirculation", Revision

20.

EPP-9 directed the operators to operate one safety injection

(SI) pump and, if required, one containment spray (CS) pump from

the RWST under accident conditions until the tank reached an

indicated level of 9 percent. The licensee initiated condition

report (CR) 97-00988 which was still being evaluated to address

.this concern. The vortexing effect was minor concerning -RWST

actual level. However, the vortexing affected the 9 percent level

setpoint for the net positive suction head (NPSH) for the SI

pumps. NPSH issues are discussed in Paragraph E8.7.

Calculation Number RNP-I/INST 1109, "Containment EOP Setpoint

Parameters", Revision 0, dated November 29, 1994, did not

determine the correct containment water level required for post

accident residual heat removal (RHR) pump recirculation operation

(EOP setpoint No. 20).

The EOP setpoint, No. 20, was calculated

to be 354 inches based on a required containment water level of 9

inches above the containment floor during normal operating

conditions. UFSAR Section 6.3.2.2.3 correctly stated that the RHR

NPSH analysis was based on a containment building water level of

1.5 feet above the containment floor. Calculation RNP-I/INST 1109

was updated using the correct containment water level to determine

level setpoint No. 20. This containment water level error was

applicable to Calculation RNP-I/INST-1058, discussed below. The

revised calculations did not effect the EOP setpoint of 354

inches.

Calculation Number RNP-I/INST-1058, "Containment Water Level

Instrument Uncertainty", Revision 0. dated April 4, 1994, used an

incorrect value for the containment water above the containment

floor. This error in the containment water level was similar as

discussed above for Calculation RNP-I/INST 1109. The licensee

revised Calculation RNP-I/INST-1058 using the correct containment

water level. The EOP setpoint was not effected.

Calculation Number RNP-I/INST.1040, "Main Steam Flow Accuracy and

Scaling Calculation", Revision 0. dated May 16, 1994, and

Calculation number RNP-I/INST-1043, "Main Steam Pressure Channel

Accuracy and Scaling Calculation", Revision 1, dated April 15,

1994, did not include seismic uncertainty factors. The design

requirements for the instruments covered by these calculations

required consideration of seismic uncertainty factors. Design

Enclosure 2

5

Guide DG-VIII.50. "Engineering Instrument Setpoints". Section 10,

Seismic Effects (SE), required that seismic effects be included in

the setpoint calculations for instrumentation which were required

to be operable during and after an earthquake. These calculations

were revised to include the seismic error uncertainty factors as

required by the design guide.

Calculation Number RNP-M/MECH-1620. "Evaluation of Effects of High

Energy Pipe Rupture on the CCWS", Revision 0, dated July 18. 1996,

did not document the break locations; the spatial relationship

between high energy line breaks (HELBs) and the componentcooling

water (CCW) piping; the possible jet impingement areas due to

cracks/breaks in CCW piping; and piping interactions due to the

HELB forces. Also, the calculation did not specifically address

the CCW piping between the containment penetrations and the

missile barrier. The licens6e determined that the design inputs

discussed above had not been included in the Calculation.

Calculation RNP-M/MECH-1620 was voided and ESR 97-00014 was

revised to include the information from the AE and NSSS vendors to

support that the CCW System inside containment is a closed system.

Calculation Number RNP-M/MECH-1362, "SW Screen Wash Piping Flow S

Analysis", Revision 1, dated September 5. 1991, was the

calculation (analysis) to demonstrate adequate performance of the

SW system with ruptures of non-seismic piping. The calculation did

not include rupture of the non-seismic piping that supply the

instrument and station air compressors. The licensee was in the

process of addressing the item.

Calculation Number RNP-E-6.020,"Load Profile and Battery Sizing

Calculation for Battery B", Revision 2, dated November 24, 1993,

incorrectly referenced a time period of "2 minutes to 59 minutes",

instead of "1 minute to 59 minutes. The calculation did not

consider some of the connected non-safety related loads and

referenced an incorrect battery cell type (MCT instead of MCX) in

Attachment U to the calculation. The licensee issued CR 97-00996

and CR 97-01082 to address these items. Evaluation of these items

was in progress.

Calculation Number RNP-E-6.23., "Minimum Inverter Voltage

Verification". Revision 2, dated December 1, 1993. did not

consider the increased inverter current at reduced battery

voltage. The licensee issued CR 97-01070. Corrective actions

included revision of the calculation to correct the above errors.

Enclosure 2

6

Calculation Number RNP-E-6.004, "DC Short Circuit Study", Revision

2, dated May 19, 1993, did not consider a small DC motor that was

connected to the system. The battery open circuit voltage used in

the calculation was less than voltage measured during testing.

This calculation along with calculation number RNP-E-018,

"Ampacity Evaluation of Safety Related 125VDC and 120VAC Power

Cables". Revision 4, dated March 16. 1994, analyzed cables rated

at 750C. whereas 600C rated cables were installed. The licensee

issued CR 97-01085 to have the calculation revised and corrected.

Calculation Number RNP-E-6.018, "DC Control Circuit Loop

Analysis". Revision 0, dated April 19, 1994, used incorrect

solenoid valve power values as a design input value. The licensee

issued CR 97-00996 to correct this item.

Calculation Number RNP-E-8.016, "Emergency Diesel Generator Static

and Dynamic Analysis", Revision 5, dated September 19, 1994, used

an incorrect reference and only modeled the "B"

SI pump motor.

The licensee issued CR-01074 to have the calculation corrected.

RNP-M/MECH-1460, "NPSH VS. CST Level for SDAFW Pump", Revision 0.

dated June 19. 1992, incorrectly assumed the CST water temperature

lto

be 1000F, instead of 115 0 F as in the Plant Parameter Document

for Cycle 18. The licensee was in the process of evaluating this

item.

RNP-M/MECH-1394, "AFW Pump Recirculation Flowrates for RNP-2",

Revision 2, dated August 21, 1995, used an incorrect specific

gravity for the CST water. The licensee was in the process of

evaluating this item.

The above examples of calculation errors were determined by the

inspectors to be (individually) minor discrepancies. The inspectors

concluded the safety significance of each individual calculation error

was minor and that none of the individual issues resulted in an

unreviewed safety question (USQ).

However, the large number of

calculation deficiencies identified a programmatic problem in the

licensee's design control program.

10 CFR 50, Appendix B, Criterion III. Design Control, requires that

design control measures verify the adequacy of design, such as by design

review, alternate calculational methods, or a suitable testing program.

Section 3.4.3 of CP&L Corporate Quality Assurance Manual, states that

"sufficient design verification shall be performed by one or more

methods to substantiate that final design documents meet the

Enclosure 2

7

appropriate design." It further states that a design verification

should confirm that the design is technically adequate with respect to

the design bases.

The calculation errors discussed above were examples where the

design verification process did not verify either the adequacy of

the design with respect to the design basis, or that correct

design inputs were utilized in the calculations. Failure to

implement the design control measures of 10 CFR 50, Appendix B.

Criterion III was identified to the licensee as apparent violation

item EEI 50-261/98-03-01, Inadequate Design Control.

The NRC design team identified an issue concerning Calculation

RNP-I/INST-1015, "Condensate Storage Tank Level Alarm Setpoints",

Revision 0. The issue concerned not referring to engineering

procedure, EGR-NGGC-0153, for scope and methodology of instrument

uncertainty and scaling. The inspectors verified that EGR-NGGC

0153, Revision 0 was not in effect at the time Revision 0 of

Calculation RNP-I/INST-1015 was completed. However, RNP-I/INST

1015 was in compliance with design guide DG-V111.50, "Instrument

Setpoints". which was in effect at that time.

Two additional issues were also identified by the NRC design team

as potential calculation errors in Section E1.5.2.2 of IR 50

261/97-201 which were reviewed and resolved by.the inspectors.

One concerned questions on Seimens calculati.on EMF-94-203(P). The

licensee issued ESR 9700487 to address the design team's

questions. The ESR concluded that the Seimens calculation was

correct. The other issue concerned calculation-number RNP-E-5.004

which will be addressed under IFI 50-261/97-201-22.

E8.3

(Closed) Unresolved Item 50-261/97-201-04, Instrument Sensing Line

Slope

During the design inspection, the NRC design team for identified

instrument lines for six instruments which had inadequate slope.

Inadequate slope permits trapping of air/gases in the instrument

lines which can result in erroneous instrument readings.

Previous

violations regarding inadequate instrument line slopes were

identified by NRC during the inspections documented in NRC

Inspection Report numbers 50-261/94-17 (VIO 94-17-02) and

50-261/95-30 (VIO 95-30-01). The licensee's actions to correct these

violations were documented in CP&L letters dated September 14, 1994, and

February 21, 1996,. Subject:.Reply to a Notice of Violation. The

licensee stated, in the violation responses, that other instrument

Enclosure 2

8

S

installations would be reviewed to identify any sensing lines that may

be improperly sloped and appropriate corrective actions would be

initiated. In response to the NRC design inspection, the licensee

determined that additional inspections of instrument sensing lines were

required. The instrument line inspections showed that additional

modifications were necessary to correct instrument line with inadequate

slope.

The failure to take adequate corrective actions to resolve the

instrument line slope deficiencies which-resulted in the previously

identified violations was identified to the licensee as Violation Item

50-261/98-03-02. Inadequate Corrective Actions to Resolve Instrument

Line Slope Deficiencies.

E8.4 (Closed) Unresolved Item 50-261/97-201-06, Notification of Changes

in Peak Cladding Temperature (PCT)

The NRC design team identified some examples where the licensee

may have failed to make annual reports of changes to the peak

cladding temperature required by 10 CFR 50.46. This URI is

discussed in paragraph E.8.5. below, in resolution of URI 50

261/97-201-07.

E8.5 (Closed) Unresolved Item 50-261/97-201-07, Reporting of

Significant Changes in PCT

The licensee initiated CR 97-01023 to document and evaluate

questions regarding notifications to NRC under 10 CFR 50.46 to

report changes in peak cladding temperatures. .The CR summarizes

the licensee's actions in reporting changes in PCT to NRC and

includes appropriate document references which submitted

information to NRC. From review of the submittal data, the

inspectors noted that on April 24, 1996, calculations showed the

PCT increased from 2006 0F to 20640F. On October 14, 1996,

calculations were completed which indicated the PCT increased from

2064oF to 21570F. Subsequently, the PCT was reduced to 2128oF

(based on calculations completed on October 25, 1996), which was

increased to 2163oF by a calculation completed on October 29.

1996. This value was reported to NRC on October 29. 1996.

10 CFR 50.46(a)(3)(ii) requires each significant change to or

error discovered in an acceptable evaluation model or in the

application of such a model that affect the peak cladding

temperature calculation, be reported to NRC within 30 days.

Significant change or error is defined in 10*CFR 50.46(a)(3)(I) as

one that results in a peak cladding temperature different by more

than 500F from the temperature calculated for the limiting tran

sient using the last acceptable model.

Enclosure 2

9

Review of the licensee's documentation showed that the licensee

failed to report the significant change to PCT (from 2006 0F to

20640F), as defined in 10 CFR 50.46, to.NRC from May 24, 1996, to

October 14, 1996. The failure to report the significant change in

PCT was identified to the licensee as violation item 50-261/98-03

03, Failure to Report PCT Changes.

The team also had additional questions on the licensee's reporting

of PCT changes for the cold leg switch over analysis. This will

be evaluated under IFI 50-261/97-201-08.

E8.6 (Open) Inspector Followup Item 50-261/97-201-08, Evaluation of

Transfer to Cold Leg Recirculation

By letter dated August 26, 1997, NRC requested additional

information concerning the analysis of the emergency core cooling

system switch over from the injection to recirculation phase. The

licensee provided the information requested in a letter to NRC

dated October 14, 1997. The information is currently under review

by the Office of Nuclear Reactor Regulation.

E8.7 (Closed) Unresolved Item 50-261-97-201-09. SI, RHR, and CS Pump

NPSH

The NRC design team questioned the licensee on.the adequacy of th.e

available net positive suction head (NPSH) for operation of the

safety injection (SI), residual heat removal (RHR), and

containment spray (CS) pumps operating under accident conditions.

In responses to the team's questions, the licensee retained a

consulting engineering company to perform an analysis to

demonstrate that the pumps had adequate NPSH.

The inspectors reviewed the following calculations which were

prepared to address NPSH questions:

Calculation RNP-M/MECH-1637, Determination of Available NPSH for

ECCS SI Pumps A, B, & C in the Injection Mode of Operation,

Revision 0 (Altran Calculation 97159-C-01, Revision 0, dated

July 11, 1997)

Calculation RNP-M/MECH-1638, Determination of Available NPSH for

ECCS RHR Pumps A & B in the Recirculation Mode of Operation,

Revision 0 (Altran Calculation 97159-C-02. Revision 0. dated

November 6, 1997).

Enclosure 2

10

Review of the calculations showed that the NPSH available for the

RHR and CS pumps exceeded the NPSH required for various pump

running combinations in the recirculation mode of operation.

However, the analysis for the SI pumps showed that the NPSH

required exceeded the NPSH available for both the B and C SI pumps

when only one pump was running for the water levels in the RWST at

the EOP low level and low-low level setpoints. Upon discovery of

the NPSH deficiency for the SI pumps, the licensee evaluated the

effects by performing additional analyses and implemented

modifications to raise the RWST level. The modifications were

completed under ESR 9700307 and included adjustments to

instrumentation and relocation of the RWST overflow line. The

water level in the RWST was raised approximately 37 inches, which

corresponds to an increase of approximately 11 percent from the

original water level in the RWST. The licensee reported this

issue to the NRC Operations Center on June 27, 1997, and submitted

LER 97-008 on July 28. 1997.

The cause of the NPSH deficiency was determined by the licensee to

have occurred as a result of a modification implemented to the SI

system in 1988. The licensee concluded that the personnel

involved in the design change, Modification M-951, implemented on

March 24, 1988, failed to adequately assess the impact of the

changes on NPSH. The failure to verify the adequacy of design

changes was contrary to the requirements of 10.CFR 50, Appendix B,

Criterion III.

The inspectors concluded'that SI pumps B & C were'

inoperable due to insufficient NPSH in some plant configurations.

This is contrary to the requirements of Technical Specification 3.3.1.1.c which required two pumps to be operable during normal

plant operations. This was identified to the licensee as Apparent

Violation item EEI 50-261/98-03-04, SI Pumps Inoperable Due to

Inadequate NPSH.

The design team also identified inconsistencies in the UFSAR concerning

design and operation of the emergency core cooling system (ECCS). The

effect of these changes on NPSH were not discussed in the UFSAR.

Resolution of these issues will be included as part of violation item

EEI 50-261/98-03-04.

E8.8 (Closed) Unresolved Item 50-261/97-201-10, SI Valve Testing

During review of the Inservice Inspection (ISI) Program, the

Design team questioned an apparent inconsistency for lack of

inservice testing (IST) of accumulator fill valve numbers SI-851A,

B, and C. The team questioned whether these valves met the

definition of active valves and therefore should have been

Enclosure 2

included in the IST program. Active' valves are defined as valves

which are required to change position to perform their safety

function. A passive valve is not required to change position to

perform its safety .function. IST is not required to be performed

on valves defined as passive. Section 2.4.2 of NUREG-1482.

Guidelines for Inservice Testing at Nuclear Power Plants, states

"If a valve is routinely operated during plant operations, or has

an active safety function, it is an active valve. A valve need

not be considered active if it is only temporarily removed from

service for a short period of time."

The inspectors determined

that operation of valve numbers SI-851A. B, and C occurs

infrequently, and then for only short periods of time

(approximately 5 seconds) during power operations for make up to

the accumulators. The last time the valves were operated was on

October 20, 1997. They had not been operated for more than six

months prior to that date. The inspectors concluded that the

valves were properly classified as passive valves and were not

required to be included in the IST program. Therefore, the

licensee's IST program was in compliance with NRC requirements for

these valves. However, the licensee decided that a prudent and

conservative action would be to include these valves in their IST

program. The licensee revised procedure TMM-004, Inservice

Inspection Testing, to reclassify the valves as active and include

them in the IST program. The inspectors reviewed Revision 49 of

procedure' TMM-004, and verified the valves were now included in

the IST program in accordance with the response in the November 3.

1997 letter.

E8.9 (Closed) Inspector Followup Item 50-261/.97-201-11, Classification

of Valves in IST

During review of procedure TMM-004, the Design team questioned

whether valve numbers SI-864 A & B and SI-856 A & B were properly

classified in the procedure regarding inservice testing

requirements. The concern was an inconsistency in documentation

since the licensee had periodically leak tested the valves under

procedure EST-140. The licensee initiated CR 97-01981 to document

and evaluate this concern. The licensee revised procedure TMM-004

to reclassify the valves as Category A for testing requirements

and revised the IST data base to reflect the correct testing

category.

The Design team also questioned the classification of manual

operated valve numbers CC-927, CC-928, SW-75, and SW-77. These

valves were identified as passive valves in procedure TMM-004.

The licensee initiated CR 97-01129 on May 14, 1997, to document

Enclosure 2

12

and evaluate this issue. The licensee determined that numbers SW

75 and SW-77 stated in IR

50-261/97-201 were incorrect. The

correct numbers were SW-906 and SW-907. The normal position for

these valves is open to provide cooling to the RHR pumps. However

in the event of a pump seal failure, or a pipebreak, it would be

necessary to close the valves to prevent flooding of the RHR pump

room (pit). This issue was previously addressed in LER 89-008

which was reported to NRC on May 4, 1989. Corrective actions to

resolve the potential flooding problem included implementation of

a modification, number MOD-1017, to relocate the valves outside

the RHR room so the valves would be accessible for manual

isolation during long term recirculation operation when radiation

level may preclude entry to the RHR room. Therefore these valves

should have been classified as active and subject to IST. The

licensee determined that they had tested valve numbers CC-927 and

-928. but not the other two. The licensee initiated CR-01354 and

performed IST on valve numbers SW-906 and -907. The licensee

revised procedures to reclassify the valves as active and require

IST. The inspectors determined that when the design change

(modification) was implemented, licensee engineers failed to

revise the ASME Section XI program to incorporate the effect of

the design change on the IST program. The inspectors identified

the failure to update the IST program to the licensee as another

example of Apparent Violation EEI 50-261/98-03-01.

E8.10 (Closed) Unresolved Item 50-261/97-201-12, 10 CFR 50.59 Screening

Deficiency

In March, 1996, the licensee initiated ESR 9600012 to evaluate

replacement of motor pinions and the worm shaft gear on valve

numbers RHR-744 A & B. The evaluation in the ESR showed that the

valve stroke times would be increased from ten seconds to

approximately 16 seconds. A 10 CFR 50.59 safety evaluation screen

was performed.to determine if the proposed modification required a

detailed unreviewed safety question determination. In performance

of the safety evaluation screen, the.responsible engineers

concluded that the ESR would not result in a change to the

facility as described in the FSAR. The NRC design team identified

that Section 6.3.2.2.12 of the UFSAR stated that these valves were

supplied with 10-second operators...Therefore, increasing the

stroke time to 16 seconds did result in a change to the facility

as described in the FSAR.

10 CFR 50.59 requires the performance of an evaluation to

determine if changes to the facility (sys-tems, structures, or

components) or facility operating procedures described in the

Enclosure 2

13

Safety Analysis Report (SAR) involves an unreviewed safety

question. The 50.59 Safety Evaluation Screen performed on

March 7, 1996, to address replacement of motor pinions and worm shaft

clutch gears for valve numbers RHR-744 A & B under Engineering Service

Request 9600012, was inadequate. The activity resulted in increasing

the motor operator valve stroke times beyond the ten seconds specified

in UFSAR Section 6.3.2.2.12. This was identified to the licensee as

Violation item 50-261/98-03-05, Failure to Comply with 10 CFR 50.59 for

Modification to Two Valves Under ESR 9600012.

The modifications to the valves which increased the stroke times

beyond ten seconds were implemented in 1996. However, during

review of IST data, the licensee's IST engineer identified the

UFSAR discrepancy. CR 97-00589 was initiated on March 7, 1997 to

document and disposition the problem. Closeout of the CR included

performance of a new 10 CFR 50.59 safety evaluation screen which

identified the conflict with the UFSAR statement. The licensee's

evaluation showed that the revised 16 second stroke time was still

less than the 21 to 28 second allowable stoke.times permitted by

the accident analysis. A pending UFSAR change was initiated to

revise the statement in the UFSAR regarding the type operators (10

second) on the valves. The inspectors concluded that the original

error in the safety screen did not result in an unreviewed safety

question.and had only minor significance since the licensee had

already resolved the technical issues resulting from the screening

error.

E8.11 (Closed) Unresolved Item 50-261/97-201-14, SI Cable Separation

Discrepancy

The SI system consists of three pumps, designated A. B, and C,

with pumps A and C receiving electrical power from the A and B

trains, respectively. The B pump is powered from either train and

is maintained in a standby status. The B pump is powered from the

same electrical source as the pump being taken out of service. In

response to a request from the team that the licensee verify that

the electrical cables were adequately separated, the licensee

performed a review of cable routing for the safety injection

pumps. After reviewing the cable routing, the licensee determined

that the cables did not have adequate separation. The review

disclosed that safety injection pump C autostart cable C2239C and

manual cable C2239D were in the same cable tray as the SI pump A

autostart cable C2237D and the SI pump B (train A line up)

autostart cable C2891C.

Enclosure 2

14

When the licensee discovered the cable separation problem, they

declared SI pump C inoperable per Technical Specification 3.3.1.2

and placed pump B in service. The licensee initiated a condition

report (CR 97-01177) on May 20, 1997, and issued ESR 9700274 to

reroute cables C2239C and C2239D to obtain the required cable

separation. The modification was implemented on May 24-25, 1997.

UFSAR Section 8.3.1.3 stated that control cables are separated into two

basic channels (cable trays) as.required for redundant circuits. Cables

assigned to these channels for separation are required to be in their

respective channels from the beginning of the cable to the final

termination.

10 CFR 50.9 requires information provided to NRC by licensees to

be complete and accurate in all material respects. The fact that

the licensee provided inaccurate information in the UFSAR

regarding cable separation was identified to the licensee as

Violation 50-261/98-03-06, Failure to Provide Accurate

Information to NRC on Cable Separation for the SI Pumps.

E8.12 (Closed) Inspector Followup Item 50-261/97-201-16. Seismic

Qualification of 480 V AC Circuit Breakers

The NRC design team questioned licensee engineers regarding

seismic qualification of circuit breakers when the breakers were

in the disconnect (racked out) and removed (physically out of the.

cabinets and supported on rails) positions. The licensee had

previously identified an outlier concerning seismic qualification

of the breakers in these positions when performing the review

required to respond to Generic Letter 87-02, Verification of

Seismic Adequacy of Mechanical and Electrical Equipment in

Operating Reactors, Unresolved Safety Issue (USI) A-46. The

licensee determined that the breakers were seismically qualified

in the racked out;position in Calculation number RNP-C/EQ-1137.

The inspectors reviewed the calculation and verified that the

breakers were seismically qualified in this position. The

licensee also determined that the breakers were not qualified in

the removed position. However, the breakers are only in this

position when they are undergoing maintenance and are attended by

maintenance personnel. If maintenance personnel are not

physically present when the breakers are in the removed position,

that is,

physically out of the cabinets and supported on the

rails, the breakers are removed from the cabinets (rails) and

stored on the floor or moved to the electrical workshop for

performance of maintenance. Therefore, the breakers are not

Enclosure 2

15

required to be seismically qualified in the removed position for

possible seismic interactions with the cabinets.

E8.13 (Closed) Unresolved Item 50-261/97-201-17, SI Accumulator Pressure

Alarm Setpoint

The NRC design team identified a potential concern that the accumulator

relief valves would actuate before the control room would be alerted by

the accumulator high pressure alarm. The relief valve setpoints were

680 psig with a tolerance of -10 psig. The high pressure alarm setpoint

was 700 psig with a tolerance of +/-21 psig. Therefore, there was a 1

psig overlap (680 vs 679) and there was the possibility that the relief

valves could actuate before the control room operators would be alerted

by the high pressure alarm .

The inspectors did not identify any safety

concern in this area since the valves would automatically perform their

function and would reset as soon as the pressure dropped below the

relief valve setpoint value.

To correct this problem, the licensee changed the accumulator high

pressure alarm setpoint from 680 psig to 646 psig. The inspectors

concluded this concern was satisfactorily addressed by the licensee.

E8.14 (Closed) Unresolved Item 50-261/97-201-18, RWST Level Instrument

Uncertainty

The concern was that the seismic uncertainty factor was not used in

calculation RNP-I/INST-1023, "Refueling Water Storage Tank Level

Indication Accuracies", Revision 0 as required in Engineering procedure

EGR-NGGC-0153. The inspectors verified EGR-NGGC-0153 was not in effect

at the time RNP-I/INST-1023 was issued and therefore not applicable.

The procedure in effect was design guide DG-V111.50, "Instrument

Setpoints" and it did not require the "uncertainty" factor.

E8.15 (Closed) Unresolved Item 50-261/97-201-21, Translation of Design

Bases into Drawings. Procedures, and Installed Components

The NRC design team -identified examples where the installation

drawings did not reflect the design basis specified in the

calculations.

Examples were also identified by the NRC design

team where maintenance and surveillance test procedures did not

incorporate or verify the design basis specified in the design

calculations.

These examples, which were discussed in Sections

E1.3.5.2(a), E1.4.2.3. and E1.4.2.5 of IR 50-261/97-201, were as

follows:

Enclosure 2

16

The design basis for CCW thermal relief valve numbers CC-747 A and

B, CC-774, and CC-791G were incorrectly translated into the

installation drawings. Consequently, the valves were installed in

locations which resulted in the 10 psig back pressure values

specified in Westinghouse E-spec No. 676257 being exceeded by 5

psig.

The design basis for performance of testing on station batteries

(IEEE Standard 450-1980, Recommended Practice for Maintenance.

Testing, and Replacement of Large Storage Batteries for Generating

Stations and Substations) was incorrectly translated into MST-920,

Station Battery Performance Capacity Test, Revision 6, dated

September 28. 1995, and MST-921, Station Battery Service Test,

Revision 7, dated April 20, 1995. Step 7.5.10 of procedure MST

921 accepted voltages less than the minimum value of 1.0 volt DC

specified in IEEE Standard 450-1980. The duration of capacity

testing of station battery B specified in MST-920.was different

from that used by the battery manufacturer. The minimum

acceptance criteria of 107 volts specified in MST-921 for the

station battery load profile test was less than the value of 109.8

volts evaluated in Calculation RNP-E-6.018.

The designbasis for performance of maintenance on station

batteries was incorrectly translated'into procedures PM-410,

Installation of Battery Bank and Cell Connections, Revision 6,

dated November 2, 1995, and PM-411, Disassembly, Cleaning,

Assembly, and Testing of A and B Station Battery Cell Connections,

Revision 6, dated October 6, 1995. The procedures stated the

acceptance criteria for measured resistance was 50 microohms,

whereas the vendor calculations specified that the resistance of B

station battery may not exceed 50 microohms and the A station bat

tery resistance may not exceed 34 microohms. The requirements for

installation (torque) of intercell connections and mechanical

cable connections and the thickness of the intercell connectors

specified in PM-411 conflicted with requirements specified in

vendor technical manuals.

The NRC design team and the inspectors concluded that none of the

above examples resulted in inoperable equipment or constituted an

unreviewed safety question. The above examples of failure to

correctly translate the design basis into specifications,

drawings, procedures and instructions was identified to the

licensee as additional examples of Apparent Violation item EEI

50-261/98-03-01.

Enclosure 2

17

E8.16 (Closed) Inspector Followup Item 50-261/97-201-24. Station Battery

B Rating

The NRC design team questioned an inconsistency in the station battery

"B"

discharge rates used in calculation number RNP-E-6.020. The

question concerned whether values on the manufacturer's published data

sheets was correct, or whether actual test data should be used as was

used in calculation number RNP-E-6.021 for sizing Battery"A". The

inspectors reviewed a letter from the vendor dated December 15, 1997,

that stated the published information was correct and verified by

testing. Therefore, the rating specified in calculation RNP-E-6.020 was

correct. The inspectors concluded that battery "B"

was sized correctly.

E8.17 (Closed) Unresolved Item 50-261/97-201-25, Field Flash Battery

Testing

The licensee performed a self-assessment January 3 - 6. 1996. for the

Station Blackout Program which was documented in Self Assessment Report

No. 96-04. The report~stated that the battery capacity testing and duty

cycle testing were not being performed on either DSDG (dedicated

shutdown diesel generator) battery. It recommended that testing be

developed. A self assessment followup. RESS Report No.96-04f, dated

March 4, 1997, noted that.the battery testing had not been developed.

The licensee had issued condition report CR 96-00188. dated January 24,

1996, to track the resolution of station blackout requirements for

technical, implementation and improvement items (including the

batteries). The followup report No. 96-.4f-stated the design basis

calculation for the DSDG field flash battery was in progress.

The NRC inspection conducted from April 7 through May 23, 1997,

identified from the licensee's followup report No.96-04f that the DSDG

battery testing had not been initiated. The DSDG was the alternate AC

source for the "station blackout". At that time, the NRC inspection

team concluded that the licensee could not verify the availability or

operability of either the DSDG or the battery because it was not

incorporated into a testing program.

The inspectors verified that the licensee had completed calculations

RNP-E-6.028. "DS Battery Sizing Calculation" and RNP-E-6.029, "DSDG

Battery Sizing Calculation" that demonstrated the adequacy of the

battery. The licensee was also performing a monthly surveillance test

per operation procedure OST-910, Dedicated Shutdown Diesel Generator

(Monthly), Revision 19, dated December 23, 1997. to verify operability

of the DSDG. Two new testing procedures had been developed to verify

operability of the batteries, PM-449, "Dedicated Shutdown Field Flash

Battery Service Test" and PM-452, "Dedicated Shutdown UPS Battery

Enclosure 2

18

Service Test". The inspectors concluded the licensee had initiated

appropriate corrective action for this concern.

E8.18 (Closed) Unresolved Item 50-261/97-201-27, Control of Calculations

During review of design calculations, the NRC design team

identified examples where calculations that performed the same

analysis used different input data and/or reached different

conclusions. These examples, which were documented in Section

E1.5.2.1 of IR 50-261/98-03, were as follows:

Discrepancies were identified in calculation numbers RNP-I/INST

1015, Revision 0, dated December 22, 1990, and 84065-M-06-F.

Revision 3, dated January 14, 1991. for the condensate storage

tank level at which to change the AFW pump suction supply to the

service water system. Calculation RNP-I/INST-1015 shows a 10

percent level, whereas calculation 84065-M-06-F shows a 15 percent

level.

Calculation numbers 789M-M-02, Revision 0, dated December 15,

1989. 789M-M-05,.Revision 0, dated December 18, 1989, and RNP-E

6.002, Revision 0, dated December 1, 1987, were not identified as

voided or superseded when replaced by other calculations.

A calculation in ESR-00474, Revision 0. dated August 19, 1996.

which evaluated whether failure of a non-seismic pipe would affect

water supply to the safety injection pumps was not design

verified.

None of the above examples resulted in equipment being inoperable

or outside the design basis. The examples were minor errors which

did not result in a USQ. The above discrepancies were determined

to be additional examples of failure to comply with the

requirements of 10 CFR 50, Appendix B, Criterion III, Design

Control.

These were identified to the licensee as additional

examples of Apparent Violation item EEI 50-261/98-03-01.

V. MANAGEMENT MEETINGS

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on January 9 and

January 30, 1998. The licensee acknowledged the findings presented.

Dissenting comments were not received from the licensee.

The licensee did not identify any materials used during the inspection

as proprietary information.

Enclosure 2

19

PARTIAL LIST OF PERSONS CONTACTED

Licensee

J. Boska, Manager, Operations

H. Chernoff, Supervisor, Licensing/Regulatory Programs

T. Cleary, Manager, Maintenance

T. Clements, Superintendent, Design Control Unit, Nuclear

Engineering Department

R. Duncan, Manager, Robinson Engineering Support Section (RESS)

W. Farmer, Supervisor, ECCS, RESS

J. Fletcher, Superintendent, Mechanical Systems, RESS

J. Keenan, Vice-President, Robinson Plant

J. Moyer, Plant General Manager

J. Snelson, I&C Supervisor, RESS

T. Wilkerson, Manager, Regulatory Affairs

Other licensee employees contacted included engineers, and

administrative personnel.

NRC

J. Lenahan, Reactor Inspector

M. Miller, Reactor Inspector

B. Desai, Senior Resident Inspector

INSPECTION PROCEDURES USED

IP 37550:

Engineering

IP 92903:

Followup - Engineering

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

50-261/98-03-01

EEI

Inadequate Design Control (Paragraphs E8.2,

E8.9, E8.15 and E8.18)

50-261/98-03-02

VIO

Inadequate Corrective Actions to Resolve

Instrument Line Slope Deficiencies (Paragraph

E8.3)

50-261/98-03-03

VIO

Failure to Report PCT Changes (Paragraphs E8.5)

Enclosure 2

20

50-261/98-03-04

EEl

SI Pumps Inoperable Due to Inadequate NPSH

(Paragraphs E8.7)

50-261/98-03-05

VIO

Failure to Comply with 10 CFR 50.59 for

Modifications to Two Valves Under ESR 9600012

(Paragraph E8.10)

50-261/98-03-06

VIO

Failure to Provide Accurate Information NRC on

Cable Separation for SI Pumps (Paragraph E8.11)

Closed

50-261/97-201-02 URI

Single Failure of CST Level

Instrumentation (Paragraph E8.1)

50-261/97-201-03 URI

Design Verification for Calculations

(Paragraph E8.2)

50-261/97-201-04 URI

Instrument Sensing Line Slope.(Paragraph E8.3)

50-261/97-201-06 URI

Notification of Changes in PCI (Paragraph E8.4)

50-261/97-201-07 URI

Reporting of Significant Changes in PCT

0

(Paragraph E8.5)

50-261/97-201-09 URI

SI, RHR, and CS Pump NPSH (Paragraph E8.7

50-261/97-201-10 URI

SI Valve Testing (Paragraph E8.8)

50-261/97-201-11

IFI

Classification of Valves in IST (Paragraph E8.9)

50-261/97-201-12 URI

10 CFR 50.59 Screening Deficiency (Paragraph

E8. 10)

50-261/97-201-14 URI

SI Cable Separation Discrepancy (Paragraph

[8. 11)

50-261/97-201-16 IFI

Seismic Qualification of 480 V AC Circuit

Breakers (Paragraph E8.12)

20-261/97-201-17 URI

SI Accumulator Pressure Alarm Setpoint

(Paragraph E8.13)

50-261/97-201-18 URI

RWST Level Instrument Uncertainty (Paragraph

E8.14)

0lEnclosure

2

21

50-261/97-201-21 URI

Translation of Design Bases into

Drawings, Procedures, and Installed Components

(Paragraph E8.15)

50-261/97-201-24 IFI

Station Battery B Rating (Paragraph E8.16)

50-261/97-201-25 URI

Field Flash Battery Testing (Paragraph E8.17)

50-261/97-201-27 URI

Control of Calculations (Paragraph E8.18)

Discussed

50-261/97-201-08 IFI

Evaluation of Transfer to Cold Leg

Recirculation .(Paragraph E.8.6)

Enclosure 2

Enclosure 3

U.S. NUCLEAR REGULATORY COMMISSION

Enforcement Policy Statement

This document compiles the "General Statement of Policy and Procedures for NRC

Enforcement Actions," (Enforcement Policy), NUREG-1600, published June 30, 1995, and

the various amendments to the Enforcement Policy approved by the Commission through

September 10, 1997. It is the staffs inteht to republish NUREG-1600 later this year. Pending

that republication, the Office of Enforcement is issuing this interim compilation of all

amendments to the Policy since it was last published. This document is also accessible on the

Internet at: www.nrc.gov/OE.

The amendments to the Policy were published in the Federal Register as follows:

Federal

Subittl

Register

Dat=

Adjustment of Civil Monetary Penalties

61FR53553

10/11/96

Departures from FSAR

61FR54461

10/18/96

Commission consultation, Open Enforcement

Conferences; risk; NCVs

61FR65088

12/10/96

Part 20, Exceedance of dose constraints

61FR65128

12/10/96

Correction as to exercise of discretion

61FR68070

12/26/96

Gaseous Diffusion Plants; NRC organizational

changes; Commission consultation

62FR06677

02/12/97

Participation in enforcement conferences

involving discrimination

62FR13906

03/24/97

Part 34, Radiography, examples of

62FR28974

05/28/97

potential violations

Corrections to Part 34 examples

62FR33447

06/19/97

Enforcement conference clarification

62FR52577

10/08/97

The Enforcement Policy is a general statement of policy explaining the NRC's policies and

procedures in initiating enforcement actions, and of the presiding officers and the Commission

in reviewing these actions. This policy statement is applicable to enforcement in matters

involving the radiological health and safety of the public, includin employees' health and

safety, the common defense and security, and the environment. This statement of general

policy and procedures is published to provide widespread. dissemination of the Commission's

Enforcement Policy. However, this is a policy statement and not a regulation. The

Commission may deviate from this statement of policy and procedure as appropriate under the

S

circumstances of a particular case.

Compilation of NRC Enforcement Policy as of September 10, 1997

WN ERAL STATEMENT OF POLICY

XI. REFERRALS TO THE DEPARTMENT

Consistent with the purpose of this

AND PROCEDURE FOR NRC

OF JUSTICE

program, prompt and vigorous

ENFORCEMENT ACTIONS

XII. PUBLIC DISCLOSURE OF

enforcement action will be taken when

ENFORCEMENT ACTIONS

dealing with licensees, vendors,

Table of Contents

XI. REOPENING CLOSED

ENFORCEMENT ACTIONS

Preface

SUPPLEMENTS

do not achieve the necessary

meticulous attention to detail and the

I. INTRODUCTION AND PURPOSE

PREFACE

high standard of compliance which the

II. STATUTORY AUTHORITY

NRC expects.'

Each enforcement

A. Statutory Authority

The following statement of general

action is dependent on'the

B. Procedural Framework

policy and procedure explains the

circumstances of the case and requires

M. RESPONSIBILITIES

enforcement policy and procedures of the

the exercise of discretion after

IV. SEVERITY OF VIOLATIONS

A. Aggregation of Violations

U.S. Nuclear Regulatory Commission

consideration of this enforcement

B. Repetitive Violations

(NRC or Commission) and the NRC staff

policy. In no case, however, will

C. Willful Violations

(staff) in initiating enforcement actions,

licensees who cannot achieve and

D. Violations of Reporting Requirements

and of the presiding officers and the

maintain adequate levels of protection

V. PI8DECISIONAL ENFORCEMENT

Commission in reviewing these actions.

be permitted to conduct licensed

CONFERENCES

C

VI. ENFORCEMENT

This statement is applicable to

activities.

A. Notice

ation

enforcement in matters involving the

B. Civileolti

radiological health and safety of the

Pa.

STATUTORY AUTHORITY AND

B. B Civil Penalty

I. Base Civil Penalty

public, including employees' health and

PROCEDURAL FRAMEWORK.

2. Civil Penalty Assessment

safety, the common defense and security,

A. Stuory Authonly

Initial Escalated Action

and the environment.' This statement of

Credit for Actions Related to

general policy and procedure will be

Identification

published as NUREG-1600to provide

The NRC's enforcement jurisdiction

c. Credit for Prompt and Comprehensive

widespread dissemination of the

drawn from the Atomic Energy Act

Corrective Action

Commission's Enforcement Policy,

of 1954, as amended, and the Energy

d. Exercise of Discretion

However, this is a policy statement and

Reorganization Act (ERA) of 1974, as

C. Orders

D. Related Administrative Actions

not a regulation. The Commission may

VII. EXERCISE OF DISCRETION

deviate from this statement of policy and

A. Escalation of Enforcement Sanctions

procedure as appropriate under the

I. Civil Penalties

circumstances of a particular case.

The term "vendor" as used in

2. Orders

2.

Odersthis

policy means a supplier of

3. Daily Civil Penalties

1. INTRODUCTION AND PURPOSE

B. Mitigation of Enforcement Sanctions

1. Licensee-Identified Severity Level IV

The purpose of the'NRC enforcement

NRC-licensed faciity or activity.

Violations

2. Violations Identified During Extended

This policy primarily addresses

Shutdowns or Work Stoppages

safety mission in protecting the public and

the activities of NRC licensees and

3. Violations Involving Old Design Issues

the environment. Consistent with that

4. Violations Identified Due to Previous

purpose, enforcement action should be

apinfor

NRC

license

Escalated Enforcement Action

used:

used throughout the policy. However,

5. Violations Involving Discrimination

0 As a deterrent to emphasize the

6. Violations Involving Special

importance of compliance with

deteines hat t

r

Circumstances

requirements, and

C. Exercise of Discretion for an Operating

0 To encourage prompt identification and

take enforcement action against a

Facility

non-licensee or individual, the

VIII. ENFORCEMENT ACTIONS

, comprehensive correction of

guidance in this policy will be used,

INVOLVING INDIVIDUALS

violations.

IfkNACCURATE AND INCOMPLETE

a

plcbe

pcfcgiac

NACCRATEAND NCOMLETEregarding

enforcement action against

FORMATION

FORCEMENT

individuals and non-licensees is

ACTIONIAGAINST.

Antitrust enforcement matters will

addressed in Sections VIII and X,

be dealt with on a case-by-case basis.

respectively.

Thi

satmet

s ppicbl t

Questions concerning the Enforcement Policy should be directed to the NRC's Office of

Enforcement at (301) 415-2741.

James Lieberman, Director

Office of Enforcement

Compilation of NRC Enforcement Policy as of September 10, 1997

ction 161 of the Atomic Energy Act

the Act and regulations or orders issued

order may request a hearing. The

thorizes the NRC to conduct

under sections 65, 161(b), .161(i). or 161(o)

NRC is authorized to make orders

inspections and investigations and to

of the Act. Section 223 provides that

immediately effective if required to

issue orders as may be necessary or

criminal penalties may be imposed on

protect the public health, safety, or

desirable to promote the common

certain individuals employed by firms

interest, or if the violation is willful.

defense and security or to protect health

constructing or supplying basic components

Section 2.204 sets out the procedures

or to minimize danger to life or

of any utilization facility if the individual

for issuing a Demand for Information

property. Section 186 authorizes the

knowingly and willfully violates NRC

(Demand) to a licensee or other person

NRC to revoke licenses under certain

requirements such that a basic component

subject to the Commission's

circumstances (e~g., for material false

could be significantly impaired. Section

jurisdiction for the purpose of

statements, in response to conditions

235 provides that criminal penalties may be

determining whether an order or other

that would have warranted refusal of a

imposed on persons who interfere with

enforcement action should be issued.

license on an original application, for a

inspectors. Section 236 provides that

The Demand does not provide hearing

licensee's failure to build or operate a

criminal penalties may be imposed on

rights, as only information is being

facility in accordance with the terms of

persons who attempt to or cause sabotage at

sought. A licensee must answer a

the permit or license, and for violation

a nuclear facility or to nuclear fuel.

Demand. An unlicensed person may

of an NRC regulation). Section 234

Alleged or suspected criminal violations of

answer a Demand by either providing

autholzes the NRC to impose civil

the Atomic Energy Act are referred to the

the requested information or explaining

penalties not to exceed $100,000 per

Department of Justice for appropriate

why the Demand should not have been

violation per day for the violation of

action.

issued.

certain specified licensing provisions of

the Act, rules, orders, and license terms

B. Procedural Framework

M. RESPONSEBIMUS

implementing these provisions, and for

violations for which licenses can be

Subpart B of 10 CFR Part 2 of NRC's

The Executive Director for

e

ked. In addition to the enumerated

regulations sets forth the procedures the

Operations (EDO) and the principal

isions in section 234, sections 84

NRC uses in exercising its enforcement

enforcement officer of the NRC, the

and 147 authorize the imposition of civil

authority. 10 CFR 2.201 sets forth the

Deputy Executive Director for

penalties for violations of regulations

procedures for issuing notices of violation.

Regulatory Effectiveness; hereafter

implementing those provisions. Section

The procedure to be used in assessing

referred to as the Deputy Executive

232 authorizes the NRC to seek

civil penalties is set forth in 10 CFR 2.205.

Director, has been delegated the

injunctive or other equitable relief for

This regulation provides that the civil

authority to approve or issue a

violation of regulatory requirements.

penalty process is initiated by issuing a

escalated enforcement actions. 4 The

Section 206 of the Energy

Notice of Violation and Proposed

Deputy Executive Director is

Reorganization Act authorizes the NRC

Imposition of a Civil Penalty. The licensee

responsible to the EDO for the NRC

to impose civil penalties for knowing

or other person is provided an opportunity

enforcement program. The Office of

and conscious failures to provide certain

to contest in writing the proposed

Enforcement (QE) exercises oversight

safety information to the NRC.

imposition of a civil penalty. After

of and implements the NRC

Notwithstanding the $100,000 limit

evaluation of the response, the civil penalty

enforcement program. The Director,

stated in the Atomic Energy Act, the

may be mitigated, remitted, or imposed.

OE, acts for the Deputy Executive

Commission may impose higher civil

An opportunity is provided for a hearing if

Director in enforcement matters in his

penalties as provided by the Debt

a civil penalty is imposed. If a civil penalty

absence or as delegated.

Collection Improvement Act of 1996.

is not paid following a hearing or if a

Subject to the oversight and direction

Under the Act, the Commission is'

hearing is not requested, the matter may be

of OE, and with the approval of the

required to modify civil monetary

referred to the U.S. Department of Justice

Deputy Executive Director, where

penalties to reflect inflation. The

to institute a civil action in District Court.

adjusted maximum civil penalty amount

The procedure for issuing an order to

is reflected in 10 CFR 2.205 and this

institute a proceeding to modify, suspend,

The term "escalated enforcement

Policy Statement.

or revoke'a license or to take other action

action' as used in this policy means a

Chapter 18 of the Atomic Energy Act

against a licensee or other personsubject to

des for varying levels of criminal

the jurisdiction of the Commission is set

ies (i.e., monetary fines andI,

II, or I

th

n

rviolation

(or problem) or any order

imprisonment) for willful violations of

any other person adversely affected by the

based upon a violation.

-2 -

Compilation of NRC Enforcement Policy as of September 10, 1997

necessary, the regional offices normally

provided notice the first time that discretion

In considering the significance of a

issue Notices of Violation and proposed

is exercised for a plant meeting the criteria

violation, the staff considers the

0

civil penalties. However, subject to the

of Section VII.B.2. In addition, the

technical significance, i.e., actual and

same oversight as the regional offices,

Commission will be consulted prior to

potential consequences, and the

the Office of Nuclear Reactor

taking action in the following situations

regulatory significance. In evaluating

Regulation (NRR) and the Office of

(unless the urgency of the situation dictates

the technical significance, risk is an

Nuclear Material Safety and Safeguards

immediate action):

appropriate consideration.

I

(NMSS) may also issue Notices of

(1) An action affecting a licensee's

Consequently, for purposes of formal

Violation and proposed civil penalties

operation that requires balancing the public

enforcement action, violations are

for certain activities. Enforcement

health and safety or common defense and

normally categorized in terms of four

orders are normally issued by the

security implications of not operating with

levels of severity to show their relative

Deputy Executive Director or the

the potential radiological or other hazards

importance within each of the

Director, OE. However, orders may

associated with continued operation;

following eight activity areas:

also be issued by the EDO, especially

(2) Proposals to impose a civil penalty

those involving the more significant

for a single violation or problem that is

I.

Reactor Operations;

matters. The Directors of NRR and

greater than 3 times the Severity Level 1

11.

Facility Construction;

NMSS have also been delegated

value shown in Table 1A for that class of

III.

Safeguards;

authofity to issue orders, but it is

licensee;

IV.

Health Physics;

expected that normal use of this

(3) Any proposed enforcement action that

V.

Transportation;

authority by NRR and NMSS will be

involves a Severity Level I violation;

VI.

Fuel Cycle and Materials

confined to actions not associated with

(4) Any action the EDO believes

Operations;

compliance issues. The Director, Office

warrants Commission involvement;

VII. Miscellaneous Matters; and

of the Controller, has been delegated the

(5) Any proposed enforcement case

VIII. Emergency Preparedness.

authority to issue orders where licensees

involving an Office of Investigations (01)

violate Commission regulations by

report where the NRC staff (other than the

Licensed activities will be placed in

nonpayment of license and inspection

01 staff) does not arrive at the same

the activity area most suitable n light

fees.

conclusions as those in the 01 report

of the particular violation involved

In recognition that the regulation of

concerning issues of intent if the Director

including activities not directly covered

nuclear activities in many cases does not

of 01 concludes that Commission

by one of the above listed areas, e.g.,

lend itself to a mechanistic treatment,

consultation is warranted; and

export license activities. Within each

judgment and discretion must be

jugetan

iceio

utb

(6) Any proposed enforcement action on.

activity area, Severity Level I has been

exercised in determining the severity

which the Commission asks to be

assigned to violations that are the most

levels of the violations and the

consulted.

significant and Severity Level IV

appropriate enforcement sanctions,

violations are the least significant.

including the decision to issue a Notice

IV. SEVERITY OF VIOLATIONS

Severity Level I and II violations are of

of Violation, or to propose or impose a

very significant regulatory concern. In

civil penalty and the amount of this

Regulatory requirements' have varying

general, violations that are included in

penalty, after considering the general

degrees of safety, safeguards, or

these severity categories involve actual

principles of this statement of policy and

environmental significance. Therefore, the

or high potential impact on the public.

the technical significance of the

relative importance of each violation,

Severity Level III violations are cause

violations and the surrounding

including both the technical significance

for significant regulatory concern.

circumstances.

and the regulatory significance, is evaluated

Severity Level IV violations are less

Unless Commission consultation or

as the first step in the enforcement process.

serious but are of more than minor

notification is required by this policy,

concern; i.e., if left uncorrected, they

the NRC staff may depart, where

could lead to a more serious concern.

warranted in the public's interest, from

The Commission recognizes that there

this policy as provided in Section VII,

are other violations of minor safety or

"Exercise of Enforcement Discretion.

The term "requirement' as used in

environmental concern which are

The Commission will be provided

this policy means a legally binding

below the level of significance of

written notification of all enforcement

Severity Level IV violations. These

actions involving civil penalties or

rieent

suchn

a se

regulation,

minor violations are not the subject of

orders. The Commission will also be

econ

l

p

io

o

formal enforcement action and are not

odeah a

seurtyimliaton

f otoprain3wt

Compilation of NRC Enforcement Policy as of September 10, 1997

ly described in inspection reports.

contributed to or were unavoidable

licensees and their contractors,

the extent such violations are

consequences of the underlying problem.

employees, and agents acting with

described, they are noted as Non-Cited

Normally, Severity Level 11 and III

integrity and communicating with

Violations.'

violations are not aggregated into a higher

candor. Willful violations cannot be

Comparisons of significance between

severity level.

tolerated by either the Commission or a

activity areas are inappropriate. For

The purpose of aggregating violations is to

licensee. Licensees are expected to

example, the immediacy of any hazard

focus the licensee's attention on the

take significant remedial action in

to the public associated with Severity

fundamental underlying causes for which

responding to willful violations

Level I violations in Reactor Operations

enforcement action appears warranted and

commensurate with the circumstances

is not directly comparable to that

to reflect the fact that several violations

such that it demonstrates the

associated with Severity Level I

with a common cause may be more

seriousness of the violation thereby

violations in Facility Construction.

significant collectively than individually and

creating a deterrent effect within the

Supplements I through VIII provide

may therefore, warrant a more substantial

licensee's organization. Athough

examples and serve as guidance in

enforcement action.

removal of the person is not necessarily

determining the appropriate severity

required, substantial disciplinary action

level for violations in each of the eight

B. Repetitive Violations

is expected.

activity areas. However, the examples

Therefore, the severity level of a

are neither exhaustive nor controlling.

The severity level of a Severity Level IV

violation may be increased if the

In addition, these examples do not

violation may be increased to Severity

circumstances surrounding the matter

create new requirements. Each is

Level III, if the violation can be considered

involve careless disregard of

designed to illustrate the significance

a repetitive violation.' The purpose of

requirements, deception, or other

that the NRC places on a particular type

escalating the severity level of a repetitive

indications of willfulness. The term

of violation of NRC requirements.

violation is to acknowledge the added

.willfulness" as used in this policy

Each of the examples in the supplements

significance of the situation based on the

embraces a spectrum of violations

Aft redicated on a violation of a

licensee's failure to implement effective

ranging from deliberate intent to

llatory requirement.

.corrective

action for the previous violation

violate or falsify to and including

The NRC reviews each case being

The decision to escalate the severity level

careless disregard for requirements.

considered for enforcement action on its

of a repetitive violation will depend on the

Willfulness does not include acts which

own merits to ensure that the severity of

circumstances, such as, but not limited to,

do not rise to the level of careless

a violation is characterized at the level

the number of times the violation has

disregard, e.g., inadvertent clerical

best suited to the significance of the

occurred, the similarity of the violations

eors in a document submitted to the

particular violation. In some cases,

and their root causes, the adequacy of

NRC. In determining the specific

special circumstances may warrant an

previous corrective actions, the period of

severity level of a violation involving

adjustment to the severity level

time between the violations, and the

willfulness, consideration will be given

categorization.

significance of the violations,

to such factors as the position and

responsibilities of the person involved

A. Aggregation of Violations

C. Willful Violatrions

in the violation (e.g., licensee official'

A group of Severity Level IV

Willful violations are by definition of

violations may be evaluated in the

particular concer

to the Commission

The term "licensee official as

aggregate and assigned a single,

because its regulatory program is based on

~sdi hsplc ttmn

en

increased severity level, thereby

first-line supervisor or above, a

resulting in a Severity Level III

licensed individual, a radiation safety

problem, if the Violations have the same

The term "repetitive violation" or

officer, or an authorized user of

fundamental undelyin case forgrwhichi

underlying

cause or programmaticnfsimilar violation" as used in this policy

licensed material whether or not listed

deficiencies, or the violations

statement means a violation that reasonably

on a license. Notwithstanding an

____________________

could have been prevented by a licensee's

individual's job title, severity level

corrective action for a previous violation

categorization for willful acts involving

AsNon-Cited Violation (NCV) is a

normally occurring (1) within the past 2

individuals who can be considered

ation that has not been formalized

years of the inspection at issue, or (2) the

licensee officials will consider several

o'a 10 CFR 2.201 Notice of

period within the last two inspections,

factors, including the position of the

Violation.

whichever is longer,

individual relative to the licensee's

-4-

Compilation of NRC Enforcement Policy as of September 10, 1997

or non-supervisory employee), the

Whenever the NRC has learned of the

the regional offices and are normally

significance of any underlying violation,

existence of a potential violation for.which

open to public observation.

the intent of the violator (i.e., careless

escalated enforcement action appears to be

Conferences will not normally be open

disregard or deliberateness), and the

.

warranted, or recurring nonconformance on

to the public if the enforcement action

economic or other advantage, if any,

the part of a vendor, the NRC may provide

being contemplated.

gained as a result of the violation. The

an opportunity for a predecisional

(I) Would be taken against an

relative weight given to each of these

enforcement conference with the licensee,

individual, or if the action, though not

factors in arriving at the appropriate

vendor, or other person'before taking

taken against an individual, turns on

severity level will be dependent on the

enforcement action. The purpose of the

whether an individual has committed

circumstances of the violation.

conference is to obtain information that will

wrongdoing;

However, if a licensee refuses to correct

assist the NRC in determining the

(2) Involves significant personnel

a minor violation within a reasonable

appropriate enforcement action, such as:

failures where the NRC has requested

time such that it willfully continues, the

(1) a common understanding of facts, root

that the individual(s) involved be

violation should be categorized at least

causes and missed opportunities associated

present at the conference;

at a Severity Level IV.

with the apparent violations, (2) a common

(3) Is based on the findings of an

understanding of corrective actions taken or

NRC Office of Investigations report

D. Violations of Reporting

planned, and (3) a common understanding

that has not been publicly disclosed; or

Requifements

of the significance of issues and the need

(4) Involves safeguards information,

for lasting comprehensive corrective action.

Privacy Act information, or

The NRC expects licensees to provide

If the NRC concludes that it has sufficient

information which could be considered

complete, accurate; and timely

information to make an informed

proprietary;

information and reports. Accordingly,

enforcement decision, a conference will not

In addition, conferences will not

unless otherwise categorized in the

normally be held unless the licensee

normally be open to the public if:

Supplements, the severity level of a

requests it. However, an opportunity for a

(5) The conference involves medical

violation involving the failure to make a

conference will normally be provided

misadministrations or overexposures

required report to the NRC will be

before issuing an order based on a violation

and the conference cannot be conductedO

based upon the significance of and the

of the rule on Deliberate Misconduct or a

without disclosing the exposed

circumstances surrounding the matter

civil penalty to an unlicensed person. If a

individual's name; or

that should have been reported.

conference is not held, the licensee will

(6) The conference will be conducted

However, the severity level of an

normally be requested to provide a written

by telephone or the conference will be

untimely report, in contrast to no report,

response to an inspection report, if issued,

conducted at a relatively small

may be reduced depending on the

as to the licensee's views on the apparent

licensee's facility.

circumstances surrounding the matter.

violations and their root causes and a

Notwithstanding meeting any of these

A licensee will not normally be cited for

description of planned or implemented

criteria, a conference may still be open

a failure to report a condition or event

corrective actions.

if the conference involves issues related

unless the licensee was actually aware of

During the predecisional enforcement

to an ongoing adjudicatory proceeding

the condition or event that it failed to

conference, the licensee, vendor, or other

with one or more intervenors or where

report. A licensee will, on the other

persons will be given an opportunity to

the evidentiary basis for the conference

hand, normally be cited for a failure to

provide information consistent with the

is a matter of public record, such as an

report a condition or event if the

purpose of the conference, including an

adjudicatory decision by the

licensee knew of the information to be

explanation to the NRC of the immediate

Department of Labor. In addition,

reported, but did not recognize that it

corrective actions (if any) that were taken

notwithstanding the above normal

was required to make a report.

following identification of the potential

criteria for opening or closing

violation or nonconformance and the long-

conferences,- with the approval of the

V. PREDECISIONAL ENFORCEMENT

term comprehensive actions that were taken

Executive Director for Operations,

CONFERENCES

or will be taken to prevent recurrence.

conferences may either be open or

Licensees, vendors, or other persons will

closed to the public after balancing the

be told when a meeting is a predecisional

benefit of the public's observation

organizational structure and the

enforcement conference.

against the potential impact on the

indvidal'

reponiblites elaiveto

A predecisional enforcement conference is

agency's decision-making process in a

individual's responsibilities relative to

a meeting between the NRC and the

particular case.

thermally

held in

The NRC will notify the licensee that

the use of licensed materiale

ofen

re n

an pprtniy ora reecsina

Compilation of NRC Enforcement Policy as of September 10, 1997

conference will be open to public

For a case in which an NRC Office of-

there is a full adjudicatory record

observation. Consistent with the

Investigations (01) report finds that

befote the Department of Labor. If a

agency's policy on open meetings,

discrimination as defied under 10 CFR

conference is held in such cases,

"Staff Meetings Open to Public,"

50.7 (or similar provisions in Parts 30, 40,

generally the conference will focus on

published September 20, 1994 (59 FR

60, 70, or 72) has occurred, the 01 report

the licensee's corrective action. As

48340), the NRC intends to announce

may be made public, subject to withholding

with discrimination cases based on 01

open conferences normally at least 10

certain information (i.e., after appropriate

investigations, the complainant may be

working days in advance of conferences

redaction), in which case the associated

allowed to participate.

through (1) notices posted in the Public

predecisional enforcement conference will

Members of the public attending open

Document Room, (2) a toll-free

normally be open to public observation. In

conferences will be reminded that (1)

telephone recording at 800-952-9674,

a conference where a particular individual

the apparent violations discussed at

(3) a toll-free electronic bulletin board

is being considered potentially responsible

predecisional enforcement conferences

at 800-952-9676, and on the Worlo

for the discrimination, the conference will

are subject to further review and may

Wide Web at the NRC Office of

remain closed. In either case (i.e., whether

be subject to change prior to any

Enforcement homepage

the conference is open or closed), the

resulting enforcement action and (2)

(www.nrc.gov/OE). In addition, the

employee or former employee who was the

the statements of views or expressions

NRC pill also issue a press release and

subject of the alleged discrimination

of opinion made by NRC employees at

notify appropriate State liaison officers

(hereafter referred to as "complainant")

predecisional enforcement conferences,

that a predecisional enforcement

will normally be provided an opportunity to

or the lack thereof, are not intended to

conference has been scheduled and that

participate in the predecisional enforcement

represent final determinations or

it is open to public observation.

conference with the licensee/employer,

beliefs.

The public attending open conferences

This participation will normally be in the

When needed to protect the public

may observe but may not participate in

form of a complainant statement and

health and safety or common defense

e confetence. It is noted that the

comment on the licensee's presentation,

and security, escalated enforcement

inpo se of conducting open conferences

followed in turn by an opportunity for the

action, such as the issuance of an

W

ot to maximize public attendance,

licensee to respond to the complainant's

immediately effective order, will be

but rather to provide the public with

presentation. In cases where the

taken before the conference. In these

opportunities to be informed of NRC

complainant is unable to attend in person,

cases, a conference maybe held after

activities consistent with the NRC's

arrangements will be made for the

the escalated enforcement action is

ability to exercise its regulatory and

complainant's participation by telephone or

taken.

safety responsibilities. Therefore,

an opportunity given for the complainant to

members of the public will be allowed

submit a written response to the licensee's

VI. ENFORCEMENT ACTIONS

access to the NRC regional offices to

presentation. If the licensee chooses to

attend open enforcement conferences in

forego an enforcement conference and,

This section describes the

accordance with the "Standard

instead, responds to the NRC's findings in

enforcement sanctions available to the

Operating Procedures for Providing

writing, the complainant will be provided

NRC and specifies the conditions under

Security Support For NRC Hearings and

the opportunity to submit written comments

which each may be used. The basic

Meetings," published November 1, 1991

on the licensee's response. For cases

enforcement sanctions are Notices of

(56 FR 56251). These procedures

involving potential discrimination by a

Violation, civil penalties, and orders of

provide that visitors may be subject to

contractor or vendor to the licensee, any

various types. As discussed further i

personnel screening, that signs, banners,

associated predecisional enforcement

Section VID related administrative

posters, etc., not larger than 18" be

conference with the contractor or vendor

actions such as Notices of

permitted, and that disruptive persons

would be handled similarly. These

Nonconformance, Notices of

may be removed. The open conference

arrangements for complainant participation

Deviation, Confirmatory Action

will be terminated if disruption

in the predecisional enforcement conference

Letters, Letters of Reprimand, and

interferes with a successful conference.

are not to be conducted or viewed in any

Demands for Information are used to

NRC's Predecisional Enforcement

respect as an adjudicatory hearing. The

supplement the enforcement program.

Conferences (whether open or closed)

purpose of the complainant's participation

In selecting the enforcement sanctions

ally will be held at the NRC's

is to provide information to the NRC to

or administrative actions, the NRC will

onal offices or in NRC Headquarters

assist it in its enforcement deliberations,

consider enforcement actions taken by

ces and not'in the vicinity of the

A predecisional enforcement conference

other Federal or State regulatory

licensee's facility.

may not need to be held in cases where

bodies having concurrent jurisdiction,

.6-

Compilation of NRC Enforcement Policy as of September 10, 1997

such as in transportation matters.

violations resulting from matters not within

1. Base Civil Penalty

Usually, whenever a violation of NRC

their control, such as equipment failures

requirements of more than a minor

that were not avoidable by reasonable

The NRC imposes different levels of

concern is identified, enforcement action

licensee quality assurance measures or

penalties for different severity level

is taken. The nature and extent of the

management controls. Generally, however,

violations and different classes of

enforcement action is intended to reflect

licensees are held responsible for the acts of

licensees, vendors, and other persons.

the seriousness of the violation involved.

their employees. Accordingly, this policy

Tables IA and lB show the base civil

For the vast majority of violations, a

should not be construed to excuse personnel

penalties for various reactor, fuel

Notice of Violation or a Notice of

errors.

cycle, materials, and vendor programs.

Nonconformance is the normal action.

(Civil penalties issued to individuals

B. Civil Penalty

are determined on a case-by-case

A. Notice of Violation

basis.) The structure of these tables

A civil penalty is a monetary penalty that

generally takes into account the gravity

A Notice of Violation is a written

may be imposed for violation of (I) certain

of the violation as a primary

notice setting forth one or more

specified licensing provisions of the Atomic

consideration and the ability to pay as a

violations of a legally binding

Energy Act or supplementary NRC rules or

secondary consideration. Generally,

requirement. The Notice of Violation

orders; (2) any requirement for which a

operations involving greate r nuclear

nornlly requires the recipient to

license may be revoked; or (3) reporting

material inventories and greater

provide a written statement describing

requirements under section 206 of the

potential consequences to the public

(1) the reasons for the violation or, if

Energy Reorganization Act. Civil penalties

and licensee employees receive higher

contested, the basis for disputing the

are designed to deter future violations both

civil penalties. Regarding the

violation; (2) corrective steps that have

by the involved licensee as well as by other

secondary factor of ability of various

been taken and the results achieved;

licensees conducting similar activities and

classes of licensees to pay the civil

(3) corrective steps that will be taken to

to emphasize the need for licensees to

penalties, it is not the NRCs intention

prevent recurrence; and (4) the date

identify violations and take prompt

that the economic impact of a civil

when full compliance will be achieved.

comprehensive corrective action.

penalty be so severe that it puts a

The NRC may waive all or portions of a

Civil penalties are considered for Severity

licensee out of business (orders, rather

written response to the extent relevant

Level III violations. In addition, civil

than civil penalties, are used when the

information has already been provided

penalties will normally be assessed for

intent is to suspend or terminate

to the NRC in writing or documented in

Severity Level I and 11 violations and

licensed activities) or adversely affects

an NRC inspection report.

The NRC

knowing and conscious violations of the

a licensee's ability to safely conduct

may require responses to Notices of

reporting requirements of section 206 of the

licensed activities. The deterrent effect

Violation to be under oath. Normally,

Energy Reorganization Act.

of civil penalties is best served when

responses under oath will be required

Civil penalties are used to encourage

the amounts of the penalties take into

only in connection with Severity Level

prompt identification and prompt and

account a licensee's ability to pay. In

I, II, or III violations or orders.

comprehensive correction of violations, to

determining the amount of civil

The NRC uses the Notice of Violation

emphasize compliance in a manner that

penalties for licensees for whom the

as the usual method for formalizing the

deters future violations, and to serve to

tables do not reflect the ability to pay

existence of a violation. Issuance of a

focus licensees' attention on violations of

or the gravity of the violation, the NRC

Notice of Violation is normally the only

significant regulatory concem.

will consider as necessary an increase

enforcement action taken, except in

Although management involvement, direct

or decrease on a case-by-case basis.

cases where the criteria for issuance of

or indirect, in a violation may lead to an

Normally, if a licensee can

civil penalties and orders, as set forth in

increase in the civil penalty, the lack of

demonstrate financial hardship, the

Sections VI.B and VI.C, respectively,

management involvement may not be used

NRC will consider payments over

are met. However, special

to mitigate a civil penalty. Allowing

time, including interest, rather than

circumstances regarding the violation

mitigation in the latter case could encourage

reducing the amount of the civil

findings may warrant discretion being

the lack of management involvement in

penalty. However, where a licensee

exercised such that the NRC refrains

licensed activities and a decrease in

claims financial hardship, the licensee

from issuing a Notice of Violation. (See

protection of the public health and safety.

will normally be required to address

Section VII.B, "Mitigation of

why it has sufficient resources to safely

Enforcement Sanctions.") In addition,

conduct licensed activities and pay

licensees'are not ordinarily cited for

license and inspection fees.

-7-

Compilation of NRC Enforcement Policy as of September 10, 1997

The civil penalty assessment process

associated considerations for any given

  • Wcivil Penalty Assessment

considers four decisional points: (a)

case, the outcome of the assessment

whether the licensee has had any Previous

process for each violation or problem,

In an effort to (1) emphasize the

escalated enforcement action (regardless of

absent the exercise of discretion, is

importance of adherence to requirements

the activity area) during the past 2 years or

limited to one of the following three

and (2) reinforce prompt self-

past 2 inspections, whichever is longer;

results: no civil penalty, a base civil

identification of problems and root

(b) whether the licensee should be given

penalty, or a base civil penalty

causes and prompt and comprehensive

credit for actions related to identification;

escalated by 100%. The flow chart

correction of violations, the NRC

(c) whether the licensee's corrective actions

presented below is a graphic

reviews each proposed civil penalty on

are prompt and comprehensive; and (d)

representation of the civil penalty

its own merits and, after considering all

whether, in view of all the circumstances,

assessment process.

relevant circumstances, may adjust the

the matter in question requires the exercise

base civil penalties shown in Table 1A

of discretion. Although each of these

and lB for Severity Level I, II, and Ill

decisional points may have several

violations as described below.

  • Stiouwhether thelcensee

behas

rei

had

acnyrviu

reatdto

eito

cin

eae t

dniiain

(~)Disreion ~:(c) when e the

v

licnsesl norriea

ction

resul

n a

aref

pena ty ads cofprehnsie

Cand(d

0i

--

ES

the atte in ueston

rquirs th execis

ofS diceinCAtog

Ahohs

decisiona

pont may-have-severa

asoitdcnsdrtosfo

ntie

caeNheotomNfth-sesmn

prcesfoLacLioaioFrUrblm

aben the exrieoNisrtoi

limte tooeYfthEoloig;he

reut:Yocvi1eaty21as

ii

pnlyoraBASEcilpeat

NO

?

YES

YES

CA

CREDIT

NON-AS

1st

WILLFUL

IDuf

CPacvlpnat

eades

fI

n

A

CREDIT*-

Compilation of NRC Enforcement Policy as of September 10, 1997

a. Initial Escalated Action.

consider the factor of identification in

those opportunities;

addition to corrective action (see the

(iii) Whether the problem was

W

When the NRC determines that a non-

discussion under Section VI.B.2.c, below).

revealed as the result of a licensee self

willful Severity Level III violation or

As to identification, the NRC should

monitoring effort, such as conducting

problem has occurred, and the licensee

consider whether the licensee should be

an audit, a test, a surveillance, a design

has not had my previous escalated

given credit for actions related to

review, or troubleshooting;

actions (regardless of the activity area)

identification.

(iv) For a problem revealed through

during the past 2 years or 2 inspections,

In each case, the decision should be

an event, the ease of discovery, and the

whichever is longer, the NRC will

focused on identification of the problem

degree of licensee initiative in

consider whether the licensee's

requiring corrective action. In other

identifying the root cause of the

corrective action for the present

words, although giving credit for

problem and any associated violations;

violation or problem is reasonably

Identfication and Corrective Action should

(v) For NRC-identified issues,

prompt and comprehensive (see the

be separate decisions, the concept of

whether the licensee would likely have

discussion under Section VI.B.2.c,

Identfication presumes that the identifier

identified the issue in the same time

below). Using 2 years as the basis for

recognizes the existence of a problem, and

period if the NRC had not been

assessment is expected to cover most

understands that corrective action is

involved;

situations, but considering a slightly

needed. The decision on Identification

(vi), For NRC-identified issues,

long&i or shorter period might be

requires considering all the circumstances

whether the licensee should have

warranted based on the circumstances of

of identification including:

identified the issue (and taken action)

a particular case. The starting point of

(i) Whether the problem requiring

earlier; and

this period should be considered the date

corrective action was NRC-identified,

(vii) For cases in which the NRC

when the licensee was put on notice of

licensee-identified, or revealed through an

identifies the overall problem requiring

the need to take corrective action. For a

event9;

corrective action (e.g., a programmatic

licensee-identified violation or an event,

(ii) Whether prior opportunities existed to

issue), the degree of licensee initiative

this would be when the licensee is aware

identify the problem requiring corrective

or lack of initiative in identifying the

that a problem or violation exists

action, and if so, the age and number of

problem or problems requiring

requiring corrective action. For an

corrective action.

NRC-identified violation, the starting

(2) Although some cases may

point would be when the NRC puts the

An event," as used here, means (1)

consider a of the above factors, the

licensee on notice, which could be

liceseeon

ntic, wich oul bean

event characterized by an active adverse

importance of each factor will vary

during the inspection, at the inspection

duigteisetontteiseto

impact on equipment or personnel, readily

based on the type of case as discussed

exit meeting, or as part of post-

obvious by human observation or

in the following general guidance:

inspection communication.

If te crreciveactin

i juded o b

instrumentation, or (2) a radiological(iLces-Intfd.W

na

If the corrective action is judged to be

problem requiring corrective action is

prompt and comprehensive, a Notice of

Violation normally should be issued

excess of regulatory limits, such as an

licensee-identified (i.e., identified

Vioatonnoraly hold e ssed

overexposure, a release of radioactive

before the problem has resulted in an

with no associated civil penalty. If the

material above NRC limits, or a loss of

event), the NRC should normally give

corrective action is judged to be less

the licensee credit for actions related to

than prompt and comprehensive, the

Noticemof

an ormally sh

e

equipment failure discovered through a spill

identification, regardless of whether

Notce f Volaionnorall shuldbe

of liquid, a loud noise, the failure to have a

prior opportunities existed to identify

issued with a base civil penalty.

system respond properly, or an annunciator

the problem.

alarm would be considered an event; a

(ii) Identified Through an Event.

b. Credit for Actions Related to

system discovered to be inoperable through

When a problem requiring corrective

Identification.

a document review would not. Similarly, if

action is identified through an event,

a liense dicovredthrugh uanrly

the decision on whether to give the

(1) If a Severity Level I or I1 i

licesedis

, throh q

a

licensee credit for actions related to

or a willful Severity Level III violation

been inadequately monitored for radiation

identification normally should consider

has occurred--or if, during the past 2

the issue would normally be considered

the ease of discovery, whether the

years or 2 inspections, whichever is

licensee-identified; however, if the same

event occurred as the result of a

longer, the licensee has been issued at

licensee self-monitoring effort (i.e.,

least one other escalated action--the civil

dosietr ran

disclose

an

V

overexposure, the issue would beh

penalty assessment should

et

the problem"), the degree of licensee

normallygnieredi for

event

identifcation

Compilation of NRC Enforcement Policy as of September 10, 1997

iative in identifying the problem or

matter would be treated as licensee-

employees and contractors, and failure

4Woblems requiring corrective action,

identified for purposes of assessing the civil

to take effective corrective steps. It

and whether prior opportunities existed

penalty. In such cases, the question of

may include findings of the NRC, the

to identify the problem.

identification credit shifts to whether the

licensee, or industry made at .other

Any of these considerations may be

licensee should be penalized for NRC's

facilities operated by the licensee

overriding if particularly noteworthy or

identification of the problem.

where it is reasonable to expect the

particularly egregious. For example, if

(iv) Mixed Identification. For "mixed"

licensee to take action to identify or

the event occurred as the result of

identification situations (i.e., where

prevent similar problems at the facility

conducting a surveillance or similar self-

multiple violations exist, some NRC-

subject to the enforcement action at

monitoring effort (i.e., the licensee was

identified, some licensee-identified, or

issue. In assessing this factor,

looking for the problem), the licensee

where the NRC prompted the licensee to

consideration will be given to, among

should normally be given credit for

take action that resulted in the identification

other things, the opportunities available

identification. As a second instance,

of the violation), the NRC's evaluation

to discoverthe violation, the ease of

even if the problem was easily

should normay determine whether the

discovery, the similarity between the

discovered (e.g., revealed by a large

licensee could reasonably have been

violation and the notification, the

spill of liquid), the NRC may choose to

expected to identify the violation in the

period of time between when the

give credit because noteworthy licensee

NRC's absence. This determination should

violation occurred and when the

effort (vas exerted in ferreting out the

consider, among other things, the timing of

notification was issued, the action

root cause and associated violations, or

the NRC's discovery, the information

taken (or planned) by the licensee in

simply because no prior opportunities

available to the licensee that caused the

response to the notification, and the

(e.g., procedural cautions, post-

NRC concern, the specificity of the NRC's

level of management review that the

maintenance testing, quality control

concern, the scope of the licensee's efforts,

notification received (or should have

failures, readily observable parameter

the level of licensee resources given to the

received).

trends, or repeated or locked-in

investigation, and whether the NRC's path

The evaluation of missed

Adb~inciator warnings) existed to identify

of analysis had been dismissed or was being

opportunities should normally depend

Wproblem.

pursued in parallel by the licensee,

on whether the information available to

(iii) NRC-Identified. When a

In some cases, the licensee may have

the licensee should reasonably have

problem requiring corrective action is

addressed the isolated symptoms of each

caused action that would have

NRC-identified, the decision on whether

violation (and may have identified the

prevented the violation. Missed

to give the licensee credit for actions

violations), but failed to recognize the

opportunities is normally not applied

related to identification should normally

common root cause and taken the necessary

where the licensee appropriately

be based on an additional question:

comprehensive action. Where this is true,

reviewed the opportunity for

should the licensee have reasonably

the decision on whether to give licensee

application to its activities and

identified the problem (and taken action)

credit for actions related to Identification

reasonable action was either taken or

earlier?

should focus on identification of the

planned to be taken within a reasonable

In most cases, this reasoning may be

problem requiring corrective action (e.g.,

tune.

based simply on the ease of the NRC

the programmatic breakdown). As such,

In some situations the missed

inspector's discovery (e.g., conducting a

depending on the chronology of the various

opportunity is a violation in itself. In

walkdown, observing in the control

violations, the earliest of the individual

these cases, unless the missed

room, performing a confirmatory NRC

violations might be considered missed

opportunity is a Severity Level III

radiation survey, hearing a cavitating

opportunities for the licensee to have

violation in itself, the missed

pump, or finding a valve obviously out

identified the larger problem.

opportunity violationmay be grouped

of position). In some cases, the

(v) Missed Oppornitiesto Identify.

with the other violations into a single

licensee's missed opportunities to

Missed opportunities include prior

Severity Level III "problem.'

identify the problem might include a

notifications or missed opportunities to

However, if the missed opportunity is

similar previous violation, NRC or

identify or prevent violations such as (1)

the only violation, then it should not

industry notices, internal audits, or

through normal surveillances, audits, or

normally be counted twice (i.e., both

readily observable trends.

quality assurance (QA) activities; (2)

as the violation and as a missed

fthe NRC identifies the violation but

through prior notice i.e., specific NRCor

opportunity--"double counting") unless

ludes that, under the circumstances,

industry notification; or (3) through other

the number of opportunities missed was

l icensee's actions related to

reasonable indication of a potential problem

particularly significant.

Identification were not unreasonable, the

or violation, such as observations of

The timing of the missed opportunity

-10-

Compilation of NRC Enforcement Policy as of September 10, 1997

should also be considered. While a rigid

In assessing this factor, consideration will

action that (1) addresses the broader

time-frame is unnecessary, a 2-year

be given to the timeliness of the corrective

environent for raising safety conceri

period should generally be considered

action (including the promptness in

in the workplace, and (2) provides a

for consistency in implementation, as

developing the schedule for long term

remedy for the particular

the period reflecting relatively current

corrective action), the adequacy of the

discrimination at issue.

performance.

licensees root cause analysis for the

In response to violations of 10 CFR

(3) When the NRC determines that the

violation, and, given the significance and

50.59, corrective action should

licensee should receive credit for actions

complexity of the issue, the

normally be considered prompt and

related to Identification, the civil penalty

comprehensiveness of the corrective action

comprehensive only if the licensee

assessment should normally result in

(i.e., whether the action is focused

(i) Makes a prompt decision on

either no civil penalty or a base civil

narrowly to the specific violation or broadly

operability; and either

penalty, based on whether Corrective

to the general area of concern). Even in

(ii) Makes a prompt evaluation under

Action is judged to be reasonably

cases when the NRC, at the time of the

10 CFR 50.59 if the licensee intends to

prompt and comprehensive. When the

enforcement conference, identifies

maintain the facility or procedure in the

licensee is not given credit for actions

additional peripheral or minor corrective

as found condition; or

related to Identification, the civil penalty

action still to be taken, the licensee may be

(iii) Promptly initiates corrective

assessment should normally result in a

given credit in this area, as long as the

action consistent with Criterion XVI of

Notice of Violation with.either a base

licensee's actions addressed the underlying

10 CFR 50, Appendix B, if it intends

civil penalty or a base civil penalty

root cause and are considered sufficient to

to restore the facility or procedure io

escalated by 100%, depending on the

prevent recurrence of the violation and

the FSAR description.

quality of Corrective Action, because the

similar violations.

licensee's performance is clearly not

Normally, the judgment of the adequacy

d. Exercise of Discretion.

acceptable.

of corrective actions will hinge on whether

the NRC had to take action to focus the

As provided in Section VII, "Eercise

c. Credit for Prompt and

licensee's evaluative and corrective process

of Discretion," discretion may b

Comprehensive Corrective Action.

in order to obtain comprehensive corrective

exercised by either escalating or

action. This will normally be judged at th~e

mitigating the amount of the civil

The purpose of the Corrective Action

time of the enforcement conference (e.g.,

penalty determined after applying the

factor is to encourage licensees to (1)

by outlining substantive additional areas

civil penalty adjustment factors to

take the immediate actions necessary

where corrective action is needed). Earlier

ensure that the proposed civil penalty

upon discovery of a violation that will

informal discussions between the licensee

reflects the NRC's concern regarding

restore safety and compliance with the

and NRC inspectors or management may

the violation at issue and that it

license, regulation(s), or other

result in improved corrective action, but

conveys the appropriate message to the

requirement(s); and (2) develop and

should not normally be a basis to deny

licensee. However, in no instance will

implement (in a timely manner) the

credit for Corrective Action. For cases in

a civil penalty for any one violation

lasting actions that will not only prevent

which the licensee does not get credit for

exceed SI 10,000 per day.

recurrence of the violation at issue, but

actions related to Identification because the

will be appropriately comprehensive,

NRC identified the problem, the assessment

TABLE IA-BASE CIVIL PENALTIES

given the significance and complexity of

of the licensee's corrective action should

the violation, to prevent occurrence of

begin from the time when the NRC put the

violations with similar root causes.

licensee on notice of the problem.

aePowerireactorsan

Regardless of other circumstances

Notwithstanding eventual good

b. Fuel fabricators, industrial

(e.g., past enforcement history,

comprehensive corrective 'ction, if

processors, and independent

identification), the licensee's corrective

immediate corrective action was not taken

s

fuel and monitored

actions should always be evaluated as

to restore safety and compliance once the

retrievable storage

wa ietiiecoretveacin

.installations...................

27,500

part of the civil penalty assessment

violation

Test reactors, mills and

process. As a reflection of the

Would not be considered prompt and

uranium conversion facilities.

importance given to this factor, an NRC

comprehensive,

contractors, vendors, waste

judmen tat he

icnse's orectve

orectve cton orviolations involving

disposal licensees, and

judgment that the licensee's correctiveradiographers..000

action has not been prompt and

discrimination should normally only be

d. Research reactors, academic.

comprehensive will always result in

considered comprehensive if the licensee

medical, or other material

issuing at least a base civil penalty.

takes prompt, comprehensive corrective

licensee

............... S5.500

be give to

th

tieineso

hcretv

Compilation of NRC Enforcement Policy as of September 10, 1997

This

legally authorized.

oppornity for a hearing on the order

othewis caeoie.nti almbl

ula

Suspensions may apply to al or part of

is afforded. -For cases in which the

otherwise categorized in this table, mobile nuclear

services, nuclear pharmacies, and physician

the licensed activity. Ordinarily, a licensed

NRC believes a basis could reasonably

offices.

activity is not suspended (nor is a

exist for not taking the action as

suspension prolonged) for failure to comply

proposed, the licensee will ordinarily

TABLE 1B-BASE CVL PENALTIES

with requirements where such failure is not

be afforded an opportunity to show

willful and adequate corrective action has

why the order should not be issued in

been taken.

the proposed manner by way of a *

Severity Level

Base Civil Penalty

3. Revocation Orders may be used:

Demand for Information. (See 10 CFR

Amount (Percent of amount

(a) When a licensee is unable or

2.204)

listed in Table IA)

___________________

unwilling to comply with NRC

I.......

..........

100%

requirements;

D. Related Administratve Actions

II.................. 80%

(b) When a licensee refuses to correct a

M ........................ 50%

m.........50%violation;

In addition to the formal enforcement

(c) When licensee does not respond to a

actions, Notices of Violation, civil

C. Orders

Notice of Violation where a response was

penalties, and orders, the NRC also

required;.

uses administrative actions, such as

An 6rder is a written NRC directive to

(d) When a licensee refuses to pay an

Notices of Deviation, Notices of

modify, suspend, or revoke a license; to

applicable fee under the Commission's

Nonconformance, Confirmatory Action

cease and desist from a given practice or

regulations; or

Letters, Letters of Reprimand, and

activity; or to take such other action as

(e) For any other reason for which

Demands for Information to

may be proper (see 10 CFR 2.202).

revocation is authorized under section 186

supplement its enforcement program.

Orders may also be issued in lieu of, or

of the Atomic Energy Act (e.g., any

The NRC expects licensees and

in addition to, civil penalties, as

condition which would warrant refusal of a

vendors to adhere to any obligations

opriate for Severity Level I, II, or

license on an original application).

and commitments resulting from these

iolations. Orders may be issued as

4. Cease and Desist Orders may be used

actions and will not hesitate toissue

oows:

to stop an unauthorized activity that has

'-

appropriate orders to ensure that these

1. License Modification orders are

continued after notification by the NRC that

obligations and commitments are met.

issued when some change in licensee

the activity is unauthorized.

1. Notices of Deviation are written

equipment, procedures, personnel, or

5. Orders to unlicensed persons,

notices describing a licensee's failure

management controls is necessary.

including vendors and contractors, and

to satisfy a commitment where the

2. Suspension Orders may be used:

employees of any of them, are used when

commitment involved has not been

(a) To remove a threat to the public

the NRC has identified deliberate

made a legally binding requirement. A

health and safety, common defense and

misconduct that may cause a licensee to be

Notice of Deviation requests a licensee

security, or the environment;

in violation of an NRC requirement or

to provide a written explanation or

(b) To stop facility construction when,

where incomplete or inaccurate information

statement describing corrective steps

(i) Further work could preclude or

is deliberately submitted or where the NRC

taken (or planned), the results

significantly hinder the identification or

loses its reasonable assurance that the

achieved, and the date when corrective

correction of an improperly constructed

licensee will meet NRC requirements with

action will be completed.

safety-related system or component; or

that person involved in licensed activities.

2. Notices of Nonconformance are

(ii) The licensee's quality assurance

Unless a separate response is warranted

written notices describing vendor's

program implementation is not adequate

pursuant to 10 CFR 2.201, a Notice of

failures to meet commitments which

to provide confidence that construction

Violation need not be issued where an order

have not been made legally binding

activities are being properly carried out;

is based on violations described in the

requirements by NRC. An example is

(c) When the licensee has not

order. The violations described in an order

a commitment made in a procurement

responded adequately to other

need not be categorized by severity level,

contract with a licensee as required by

enforcement action;

Orders are made effective immediately,

10 CFR Part 50, Appendix B. Notices

(d) When the licensee interferes with

without prior opportunity for hearing,

e onduct of an inspection or

whe never it is determined that the public

stigation; or

health, interest, or safety. so requires, or

For any reason not mentioned

when the order is responding to a violation

above for which license revocation is

involving willfulness. Otherwise, a prior

- 12

Compilation of NRC Enforcement Policy as of September 10, 1997

of Nonconformances request

may apply its fall enforcement authority

identifies and reports the loss to the

non-licensees to provide written

where the action is warranted. NRC action

NRC, these cases should normally

0

explanations or statements describing

may include (1) escalating civil penalties,

result in a civil penalty in an amount at

corrective steps (taken or planned), the

(2) issuing appropriate orders, and

least in the order of the cost of an

results achieved, the dates when

(3) assessing civil penalties for continuing

authorized disposal of the material or

corrective actions will be completed,

violations on a per day basis, up to the

of the transfer of the material to an

and measures taken to preclude

statutory limit of $I 10,000 per violation,

authorized recipient; or

recurrence.

per day.

(h) Severity Level II or II violations

3. Confirmatory Action Letters are

1. Civil penalties. Notwithstanding the

associated with departures from the

letters confirming a licensee's or

outcome of the normal civil penalty

Final Safety Analysis Report identified

vendor's agreement to take certain

assessment process addressed in Section

after two years from October 18, 1996.

actions to remove significant concerns

VI.B, the NRC may exercise discretion by

Such a violation or problem would

about health and safety, safeguards, or

either proposing a civil penalty where

consider the number and nature of the

the environment.

application of the factors would otherwise

violations, the severity of the

4. Letters of Reprimand are letters

result in zero penalty or by escalating the

violations, whether the violations were

addressed to individuals subject to

amount of the resulting civil penalty (i.e.,

continuing, and who identified the

Commission jurisdiction identifying a

base or twice the base civil penalty) to

violations (and if the licensee identified

signifitant deficiency in their

ensure that the proposed civil penalty

the violation, whether exercise of

performance of licensed activities.

reflects the significance of the

Section VII.B.3 enforcement discretion

5. Demands for Information are

circumstances and conveys the appropriate

is warranted).

demands for information from licensees

regulatory message to the licensee.

The

2. Orders. The NRC may, where

or other persons for the purpose of

Commission will be notified if the deviation

necessary or desirable, issues orders in

enabling the NRC to determine whether

in the amount of the civil penalty proposed

conjunction with or in lieu of civil

an order or other enforcement action

under this discretion from the amount of the

penalties to achieve or formalize

should be issued.

civil penalty assessed under the normal

corrective actions and to deter further

process is more than two times the base

recurrence of serious violations.

VII. EXERCISE OF DISCRETION

civil penalty shown in Tables 1A and 1B.-

3. Daily civil penalties. In order to

Examples when this discretion should be

recognize the added technical safety

Notwithstanding the normal guidance

considered include, but are not limited to

significance or regulatory significance

contained in this policy, as provided in

the following:

for those cases where a very strong

Section III, "Responsibilities," the NRC

(a) Problems categorized at Severity

message is warranted for a significant

may choose to exercise discretion and

Level I or 11,

violation that continues for more than

either escalate or mitigate enforcement

(b) Overexposures, or releases of

one day, the NRC may exercise

sanctions within the Commission's

radiological material in excess of NRC

discretion and assess a separate

statutory authority to ensure that the

requirements;

violation and attendant civil penalty up

resulting enforcement action

(c) Situations involving particularly poor

to the statutory limit of S110,000 for

appropriately reflects the level of NRC

licensee performance, or involving

each day the violation continues. The

concern regarding the violation at issue

willfulness;

NRC may exercise this discretion if a

and conveys the appropriate message to

(d) Situations when the licensee's

licensee was aware or clearly should

the licensee,

previous enforcement history has been

have been aware of a violation, or if

paticularly poor, or when the current

the licensee had an opportunity to

A. Escalation of Enforcement Sanctions

violation is directly repetitive of an earlier

identify and correct the violation but

violation;

-failed

to do so.

The NRC considers violations

(e) Situations when the violation results

categorized at Severity Level I, II, or III

in a substantial increase in risk, including

B. Mitigation of Enforcement Sanctions

to be of significant regulatory concern.

cases in which the duration of the violation

If the application of the normal guidance

has contributed to the substantial increase;

The NRC may exercise discretion and

in this policy does not result in an

(f) Situations when the licensee made a

refrain from issuing a civil penalty

appropriate sanction, with the approval

conscious decision to be in noncompliance

and/or a Notice of Violation, if the

of the Deputy Executive Director and

in order to obtain an economic benefit;

outcome of the normal process

consultation with the EDO and

(a) Cases involving the loss of a source.

described in Section VI.B does not

Commission, as warranted, the NRC

In addition, unless the licensee self-

result in a sanction consistent with an

- 13

Compilation of NRC Enforcement Policy as of September 10, 1997

propriate regulatory message.

action committed to by the licensee by the

result of a comprehensive program for

owever, even if the NRC exercises

end of the inspection, including immediate

problem identification and correction

this discretion, when the licensee failed

corrective action and comprehensive

that was developed in response to the

to make a required report to the NRC, a

corrective action to prevent recurrence;

shutdown or identified as a result of an

separate enforcement action will

(d) It was not a willful violation or if it

employee allegation to the licensee; (If

normally be issued for the licensee's

was a willful violation;

the NRC dentifies the violation and all

failure to make a required report. The

(i) The information concering the

of the other criteria are met, the NRC

approval of the Director, Office of -

violation, if not required to be reported,

should determine whether enforcement

Enforcement, with consultation with the

was promptly provided to appropriate NRC

action is necessary to achieve remedial

Deputy Executive Director as

personnel, such as a resident ispector or

action, or if discretion may still be

warranted, is required for exercising

regional section or branch chief;

appropriate.)

discretion of the type described in

(ii) The violation involved the acts of a.

(b) It is based upon activities of the

Section VII.B. 1.b where a willful

low-level individual (and not a licensee

licensee prior to the events leading to

violation is involved, and of the types

official as defned in Section IV.C;

the shutdown;

described in Sections VII.B.2 through

(iii) The violation appears to be the

(c) It would not be categorized at a

VII.B.6.. Commission notification is

isolated action of the employee without

severity level higher than Severity

required for exercising discretion of the

management involvement and the violation

Level 11;

type ascribed in: (1)Section VII.B.2

was not caused by lack of management

(d) It was not willful; and

the first time discretion is exercised

oversight as evidenced by either a history

(e) The licensee's decision to restart

during that plant shutdown, and (2)

of isolated willful violations or a lack of

the plant requires NRC concurrence.

Section VII.B.6 where appropriate

adequate audits or supervision of

3. Violations Involving Old Design

based on the uniqueness or significance

employees; and

Issues. The NRC may refrain from

of the issue. Examples when discretion

(iv) Significant remedial action

proposing a civil penalty for a Severity

should be considered for departing from

commensurate with the circumstances was

Level II or III violation involving a

nlormal approach in Section VI.B

taken by the licensee such that it

past problem, such as in engineeng,

ude but are not limited to the

demonstrated the seriousness of the

design, or installation, provided that

Ilowing:

violationtoother employees and

the violation is documented in an

1. Licensee-Identified Severity Level

contractors, thereby creating a deterrent

inspection report (or official field notes

IV Violations. The NRC, with the

effect within the licensee's organization.

for some material cases) that includes a

approval of the Regional Administrator

Although removal of the employee from

description of the corrective action and

or his or her designee, may refrain from

licensed activities is not necessarily

that it meets all of the following

issuing a Notice of Violation for a

required, substantial disciplinary action is

criteria:

Severity Level IV violation that is

expected.

(a) It was a licensee-identified as a

documented in an inspection report (or

2. Violations Identified During Extended

result of its voluntary initiative;

official field notes for some material

Shutdowns or Work Stoppages. The NRC

(b) It was or will be corrected,

cases) and described therein as a Non-

may refrain from issuing a Notice of

including immediate corrective action

Cited Violation (NCV) provided that the

Violation or a proposed civil penalty for a

and long term comprehensive

inspection report includes a brief

violation that is identified after (i) the NRC

corrective action to prevent recurrence,

description of the corrective action and

has taken significant enforcement action

within a reasonable time following

that the violation meets all of the

based upon a major safety event

identification (this action should

following criteria:

contributing to an extended shutdown of an

involve expandingthe initiative, as

(a) It was identified by the licensee;

operating reactor or a material licensee (or

necessary, to identify other failures

(b) It was not a violation that could

a work stoppage at a construction site), or

caused by similar root causes); and

reasonably be expected to have been

(ii) the licensee enters an extended

(c) It was not likely tobe identified

prevented by the licensee's corrective

shutdown or work stoppage related to

(after the violation occurred) by routine

action for a previous violation or a

generally poor performance over a long

licensee efforts such as normal

previous licensee finding that occurred

period of time, provided that the violation

surveillance or quality assurance (QA)

within the past 2 years of the inspection

is documented in an inspection report (or

activities.

at issue, or the period within the last

official field notes for some material cases)

In addition, the NRC may refrain

inspections, whichever is longer;

and that it meets a of the following

from issuing a Notice of Violation for

It was or will be corrected within

criteria:

cases that meet the above criteria

a reasonable time, by specific corrective

(a) It was either licensee-identified as a

provided the violation was caused by

- 14-

Compilation of NRC Enforcement Policy as of September 10, 1997

conduct that is not reasonably linked to

after the NRC has taken escalated

that the matter was settled to the

present performance (normally,

enforcement action for a Severity Level 11

satisfaction of the employee (the terms*

violations that are at least 3 years old or

or III violation, provided that the violation

of the specific settement agreement

violations occurring during plant

is documented in an inspection report (or

need not be posted), and that, if the

construction) and there had not been

official field notes for some material cases)

DOL Area Office found

prior notice so that the licensee should

that includes a description of the corrective

discrimination, the licensee has taken

have reasonably identified the violation

action and that it meets all of the following

action to positively reemphasize that

earlier. This exercise of discretion is to

criteria:

discrimination will not be tolerated.

place a premium on licensees initiating

(a) It was licensee-identified as part of

Similarly, the NRC may refrain from

efforts to identify and correct subtle

the corrective action for the previous

taking enforcement action if a licensee

violations that are not likely to be

escalated enforcement action;

settles a matter promptly after a person

identified by routine efforts before

(b) It has the same or similar root cause

comes to the NRC without going to the

degraded safety systems are called upon

as the violation for which escalated

DOL. Such discretion would normally

to work.

enforcement action was issued;

not be exercised in cases in which the

Section VII.B.3 discretion would not

(c) It does not substantially change the

licensee does not appropriately address

normally.be applied to departures from

safety significance or the character of the

the overall work environment (

by

the FSAR if:

regulatory concern arising out of the initial

using training, postings, revised

(a)

T4he NRC identifies the violation

violation; and.

policies or procedures, any necessary

unless it was likely in the staff's view

(d) It was or will be corrected, including

disciplinary action, etc., to

that the licensee would have identified

immediate corrective action and long term

communicate its policy against

the violation in light of the defined

comprehensive corrective action to prevent

discrimination) or in cases that involve:

scope, thoroughness, and schedule of

recurrence, within a reasonable time

allegations of discrimination as a result

the licensee's initiative (provided the

following identification.

of providing information directly to the

schedule provides for completion of the

5. Violations Involving Certain

NRC, alegations of discrimination

licensee's initiative within two years

Discrimination Issues. Enforcement

caused by a manager above first-line

after October 18, 1996;

discretion may be exercised for

supervisor (consistent with current

(b) The licensee identifies the

discrimination cases when a licensee who,"-

Enforcement Policy classification of

violation as a result of an event or

without the need for government

Severity Level I or 11 violations),

surveillance or other required testing

intervention, identifies an issue of

allegations of discrimination where a

where required corrective action

discrimination and takes prompt,

history of findings of discrimination

identifies the FSAR issue;

comprehensive, and effective corrective

(by the DOL or the NRC) or

(c) The licensee identifies the

action to address both the particular

settlements suggests a programmatic

violation but had prior opporunities to

situation and the overall work environment

rather than an isolated discrimination

do so (was aware of the departure from

for raising safety concerns. Similarly,

problem, or allegations of

the FSAR) and failed to correct it

enforcement may not be warranted where a

discrimination which appear

earlier;

complaint is filed with the Department of

particularly blatant or egregious.

(d) There is willfulness associated

Labor (DOL) under Section 211 of the

6. Violations Involving Special

with the violation;

Energy Reorganization Act of 1974, as

Circumstances. Notwithstanding the

(e) The licensee fails to make a report

amended, but the licensee settles the matter

outcome of the normal civil penalty

required by the identification of the

before the DOL makes an initial finding of

assessment process addressed in

departure from the FSAR; or

discrimination and addresses the overall

Section VI.B, as provided in Section

(f) The licensee either fails to take

work environment. Alternatively, if a

III, "Responsibilities," the NRC may

comprehensive corrective action or fails

finding of discrimination i§ made, the

reduce or refrain from issuing a civil

to appropriately expand the corrective

licensee may choose to settle the case

penalty or a Notice of Violation for a

action program. The corrective action

before the evidentiary hearing begins. In

Severity Level II or III violation based

should be broad with a defined scope

such cases, the NRC may exercise its

on the merits of the case after

and schedule.

discretion not to take enforcement action

considering the guidance in this

4. Violations Identified Due to

when the licensee has addressed the overall

statement of policy and such factors as

Previous Escalated Enforcement Action.

work environment for raising safety

the age of the violation, the safety

The NRC may refrain from issuing a

concerns and has publicized that a

significance of the violation, the overall

Notice of Violation or a proposed civil

complaint of discrimination for engaging in

sustained performance of the licensee

penalty for a violation that is identified

protected activity was made to the DOL,

has been particularly good, and other

- 15 -

Compilation of NRC Enforcement Policy as of September 10, 1997

vant circumstances, including any

emergency or exigent license amendment

NRC staff has chosen to issue a

I may have changed since the

under the provisions of 10 CFR 50.91(a)(5)

NOED, enforcement action will

violation. This discretion is expected to

  • r (6). The person exercising enforcement

normally be taken for the root causes,

be exercised only where application of

discretion will document the decision.

to the extent violations were involved,

the normal guidance in the policy is

For an operating plant, this exercise of

that led to the noncompliance for which

unwarranted.

enforcement discretion is intended to

enforcement discretion was used. The

minimize the potential safety consequences

enforcement action is intended to

C. Exercise of Discretion for an

of unnecessary plant transients with the

emphasize that licensees should not

Operating Facility

accompanying operational risks and impacts

rely on the NRC's authority to exercise

or to eliminate testing, inspection, or

enforcement discretion as a routine

On occasion, circumstances may arise

system realignment which is inappropriate

substitute for compliance or for

where a licensee's compliance with a

for the particular plant conditions. For

requesting a license amendment.

Technical Specification (TS) Limiting

plants in a shutdown condition, exercising

Finally, it is expected that the NRC

Condition for Operation or with other

enforcement discretion is intended to reduce

staff will exercise enforcement

license conditions would involve an

shutdown risk by, again, avoiding testing,

discretion in this area infrequently.

unnecessary plant transient or

inspection or system realignment which is

Although a plant must shut down,

performance of testing, inspection, or

inappropriate for the particular plant

refueling activities may be suspended,

systenrrealignment that is inappropriate

conditions, in that, it does not provide a

or plant startup may be delayed, absent

with the specific plant conditions, or

safety benefit or may, in fact, be

the exercise of enforcement discretion,

unnecessary delays in plant startup

detrimental to safety in the particular plant

the NRC staff is under no obligation to

without a corresponding health and

condition. Exercising enforcement

take such a step merely because it has

safety benefit. In these circumstances,

discretion for plants attempting to staup is

been requested. The decision to forego

the NRC staff may choose not to

less likely than exercising it for an

enforcement is discretionary. When

enforce the applicable TS or other

operating plant, as simply delaying startup

enforcement discretion is to be

rs e condition. This enforcement

does not usually leave the plant in.a

exercised, it is to be exercised only if

etion, designated as a Notice. of

condition in which it could experience

the NRC staff is clearly satisfied that

forcement Discretion (NOED), will

undesirable transients. In such cases, the

such action is warranted from a health

only be exercised if the NRC staff is

Commission would expect that discretion

and safety perspective.

clearly satisfied that the action is

would be exercised with respect to

consistent with protecting the public

equipment or systems only when it has at

VIII. ENFORCEMENT ACTIONS

health and safety. A licensee seeking

least concluded that, notwithstanding the

INVOLVING INDIVIDUALS

the issuance of a NOED must provide a

conditions of the license: (1) The equipment

written justification, or in circumstances

or system does not perform a safety

Enforcement actions involving

where good cause is shown, oral

function in the mode in which operation is

individuals, including licensed

justification followed as soon as possible

to occur; (2) the safety function performed

operators, are significant personnel

by written justification, which

by the equipment or system is of only

actions, which will be closely

documents the safety basis for the

marginal safety benefit, provided remaining

controlled and judiciously applied. An

request and provides whatever other

in the current mode increases the likelihood

enforcement action involving an

information the NRC staff deems

of an unnecessary plant transient; or (3) the

individual will normally be taken only

necessary in making a decision on

TS or other license condition requires a

when the NRC is satisfied that the

whether or not to issue a NOED.

test, inspection or system realignment that

individual fully understood, or should

The appropriate Regional

is inappropriate for the particular plant

have understood, his or her

Administrator, or his or her designee,

conditions, in that it does not provide a

responsibility; knew, or should have

may issue a NOED where the

safety benefit, or may, in fact, be

known, the required actions; and

noncompliance is temporary and

detrimental to safety in the particular plant

knowingly, or with careless disregard

nonrecurring when an amendment is not

condition.

(i.e., with more than mere negligence)

practical. The Director, Office of

The decision to exercise enforcement

failed to take required actions which

Nuclear Reactor Regulation, or his or

discretion does not change the fact that a

have actual or potential safety

esignee, may issue a NOED if the

violation will ocur nor does it imply that

significance. Most transgressions of

ted noncompliance will occur

enforcement discretion is being exercised

individuals at the level of Severity

g the brief period of time it

for any violation that may have led to the

Level III or IV violations will be

requires the NRC staff to process an

violation at issue. In each case where the

handled by citing only the facility

  • 16-

Compilation of NRC Enforcement. Policy as of September 10, 1997

licensee.

conduct not amounting to deliberate action

e Willfully taking actions that viola

More serious violations, including

by an unlicensed individual in these

Technical Specification Limiting

those involving the integrity of an

situations may result in enforcement action

Conditions for Operation or other

individual (e.g., lying to the NRC)

against a licensee that may impact an

license conditions (enforcement action

concerning matters within the scope of

individual. The situations include, but are

for a willful violation will not be taken

the individual's responsibilities, will be

not limited to, violations that involve:

if that violation is the result of action

considered for enforcement action

Willfully causing a licensee to be in

taken following the NRC's decision to

against the individual as well as against

violation of NRC requirements.

forego enforcement of the Technical

the facility licensee. Action against the

0 Willfully taking action that would have

Specification or other license condition

individual, however, will not be taken if

caused a licensee to be in violation of NRC

or if the operator meets the

the improper action by the individual

requirements but the action did not do so

requirements of 10 CFR 50.54 (x),

was caused by management failures.

because it was detected and corrective

(i.e., unless the operator acted

The following examples of situations

action was taken.

unreasonably considering all the

illustrate this concept:

  • Recognizing a violation of procedural

relevant circumstances surrounding the

  • Inadvertent individual mistakes

requirements and willfully not taking

emergency.)

resulting from inadequate training or

corrective action.

Normally, some enforcement action is

guidance provided by the facility

Willfully defeating alarms which have

taken against a licensee for violations

license.

safety significance.

caused by significant acts of

  • Inadvertently missing an

Unauthorized abandoning of reactor

wrongdoing by its employees,

insignificant procedural requirement

controls.

contractors, or contractors' employees.

when the action is routine, fairly

0 Dereliction of duty.

In deciding whether to issue an

uncomplicated, and there is no unusual

0 Falsifying records required by NRC

enforcement action to an unlicensed

circumstance indicating that the

regulations or by the facility license,

person as well as to the licensee, the

procedures should be referred to and

  • Willfully providing, or causing a

NRC recognizes that judgments will

foll6wed step-by-step.

licensee to provide, an NRC inspector or

have to be made on a case by case

  • Compliance with an express

investigator with inaccurate or incomplete

basis. In making these decisions, the

direction of management, such as the

information on a matter material to the

NRC will consider factors such as the

Shift Supervisor or Plant Manager,

NRC.

following:

resulted in a violation unless the

0 Willfully withholding safety significant

1. The level of the individual within

individual did not express his or her

information rather than making such

the organization.

concern or objection to the direction.

information known to appropriate

2. The individual's training and

  • Individual error directly resulting

supervisory or technical personnel in the

experience as well as knowledge of the

from following the technical advice of

licensee's organization.

potential consequences of the

an expert unless the advise was clearly

e Submitting false information and as a

Wrongdoing.

unreasonable and the licensed individual

result gaining unescorted access to a

3. The safety consequences of the

should have recognized it as such.

nuclear power plant.

misconduct.

  • Violations resulting from

Willfully Providing false data to a

4. The benefit to the wrongdoer,

inadequate procedures unless the

licensee by a contractor or other person

e.g., personal or corporate gain.

individual used a faulty procedure

who provides test or other services, when

5. The degree of supervision of the

knowing it was faulty and had not

the data affects the licensee's compliance

individual, i.e., how closely is the

attempted to get the procedure

with 10 CER part 50, appendix B, or other

individual monitored or audited, and

corrected.

regulatory requirement.

the likelihood of detection (such as a

Listed below are examples of

  • Willfully providing false certification

radiographer working independently in

situations which could result in

that components meet the requirements of

the field as contrasted with a team

enforcement actions involving

their intended use, such as ASME Code.

activity at a power plant).

individuals, licensed or unlicensed. If

0 Willfully supplying, by vendors of

6. The employer's response, e.g.,

the actions described in these examples

equipment for transportation of radioactive

disciplinary action taken.

are taken by a licensed operator or taken

material, casks that do not comply with

7. The attitude of the wrongdoer,

deliberately by an unlicensed individual,

their certificates of compliance.

e.g., admission of wrongdoing,

enforcement action may be taken

e Willfully performing unauthorized

acceptance of responsibility.

directly against the individual.

bypassing of required reactor or other

8. The degree of management

However, violations involving willful

facility safety systems.

responsibility or culpability.

. 17 -

Compilation of NRC Enforcement.Policy as of September 10, 1997

Who identified the misconduct.

activities,

integrity, competence, fitness-for-duty,

Any proposed enforcement action

0 Require the person to tell a prospective

or other matters that may not

involving individuals must be issued

employer or customer engaged in licensed

necessarily be a violation of specific

with the concurrence of the Deputy

activities that the person has been subject to

Commission requirements.

Executive Director. The particular

an NRC order.

In the case of an unlicensed person,

sanction to be used should be

In the case of a licensed operator's failure

whether a firm or an individual, an

determined on a case-by-case basis. 0

to meet applicable fitness-for-duty

order modifying the facility license

Notices of Violation and Orders are

requirements (10 CFR 55.530)), the NRC

may be issued to require (1) the

examples of enforcement actions that

may issue a Notice of Violation or a civil

removal of the person from all licensed

may be appropriate against individuals.

penalty to the Part 55 licensee, or an order

activities for a specified period of time

The administrative action of a Letter of

to suspend, modify, or revoke the Part 55

or indefnitely, (2) prior notice to the

Reprimand may also be considered. In

license. These actions may be taken the

NRC before utilizing the person in

addition, the NRC may issue Demands

first time a licensed operator fails a drug or

licensed activities, or (3) the licensee to

for Information to gather information to

alcohol test, that is, receives a confirmed

provide notice of the issuance of such

enable it to determine whether an order

positive test that exceeds the cutoff levels of

an order to other persons involved in

or other enforcement action should be

10 CFR Part 26 or the facility licensees

licensed activities making reference

issued.

cutoff levels, if lower. However, normally

inquiries. In addition, orders to

Orders to NRC-licensed reactor

only a Notice of Violation will be issued for

employers might require retraining,

operators may involve suspension for a

the first confirmed positive test in the

additional oversight, or independent

specified period, modification, or

absence of aggravating circumstances such

verification of activities performed by

revocation of their individual licenses.

as errors in the performance of licensed

the person, if the person is to be

Orders to unlicensed individuals might

duties or evidence of prolonged use. In

involved in licensed activities.

include provisions that would:

addition, the NRC intends to issue an order

  • Prohibit involvement in NRC

to suspend the Part 55 license for up to 3

IX. INACCURATE AND

sed activities for a specified period

years the second time a licensed operator

INCOMPLETE INFORMATION

W in e (normally the period of

exceeds those cutoff levels. In the event

suspension would not exceed 5 years) or

there are less than 3 years remaining in the

A violation of the regulations

until certain conditions are satisfied,

term of the individuals license, the NRC

involving submittal of incomplete

e.g., completing specified training or

may consider not renewing the individuals

and/or inaccurate information, whether

meeting certain qualifications.

license or not issuing a new license after

or not considered a material false

  • Require notification to the NRC

the three year period is completed. The

statement, can result in the full range

before resuming work in licensed

NRC intends to issue an order to revoke the

of enforcement sanctions. The labeling

Part 55 license the third time a licensed

of a communication failure as a

operator exceeds those cutoff levels. A

material false statement will be made

'o Except for individuals subject to

licensed operator or applicant who refuses

on a case-by-case basis and will be

civil penalties under section 206 of the

to participate in the drug and alcohol testing

reserved for egregious Violations.

Energy Reorganization Act of 1974, as

programs established by the facility licensee

Violations involving inaccurate or

amended,or

who is involved in the sale, use, or

incomplete information or the failure to

amended

NR wiil

nlt notinormal

possession of an illegal drug is also subject

provide significant information

impose a civil penalty against an

inivdul.Hweer scto 24 f h

to license suspension, revocation, or denial,

identified by a licensee normally will

individual. However, section 234 of the

In addition, the NRC may take

be categorized based on the guidance

Atomic Energy Act (AEA) gives the

Commission authority to impose civil

enforcement action against a licensee that

herein, in Section IV, Severity of

penalties on "any person." "Person" is

may impact an individual, where the

Violations, and in Supplement VII.

broadly defined in Section

"so th

conduct of the individual places in question

The Commission recognizes that oral

AEA to include individuals, a variety of

the NRCs reasonable assurance that

information may in some situations be

AE t icldeinivduls avaiey f

licensed activities will be properly

inherently less reliable than written

organizations, and any representatives

.Iztns

conducted. The NRC may take

submittals because oi the absence of an

or agents. This gives the Commission

0enforcement

action for reasons that would

opportunity for reflection and

authority to impose civil penalties on

management review. However, the

loyees of licensees or on separate

  • lov es

o licnsee orrnisenaat

application. Accordingly,

Commission must be able to rely on

ies when a violation of a

o

a

quirement directly imposed on them is

appropriate enforcement actions may be

oral communications from licensee

taken regarding matters that raise issues of

officials concering

18-

Compilation of NRC Enforcement Policy as of September 10, 1997

information. Therefore, in determining

promptly identified and corrected by the

X. ENFORCEMENT ACTION

whether to take enforcement action for

licensee prior to reliance by the NRC, or

AGAINST NON-LICENSEES

an oral statement, consideration may be

before the NRC raised a question about the

given to factors such as (1) the degree of

information, no enforcement action will be

The Commission's enforcement

knowledge that the communicator

taken for the initial inaccurate or

policy is also applicable to

should have had, regarding the matter,

incomplete information. On the other

non-licensees, including employees of

in view of his or her position, training,

hand, if the misinformation is identified

licensees, to contractors and

and experience; (2) the opportunity and

after the NRC relies on it, or after some

subcontractors, and to employqes-of

time available prior to the

question is raised regarding the accuracy of

contractors and subcontractors, who

communication to assure the accuracy or

the information, then some enforcement

knowingly provide components,

completeness of the information; (3) the

action normally will be taken even if it is in

equipment, or other goods or services

degree of intent or negligence, if any,

fact corrected. However, if the initial

that relate to a licensee's activities

involved; (4) the formality of the

submittal was accurate when made but later

subject to NRC regulation. The

communication; (5) the reasonableness

turns out to be erroneous because of newly

prohibitions and sanctions for any of

of NRC reliance on the information;

discovered information or advance in

these persons who engage in deliberate

(6) the importance of the information

technology, a citation normally would not

misconduct or submission of

which was wrong or not provided; and

be appropriate if, when the new

incomplete or inaccurate information

(7) thi reasonableness of the explanation

information became available or the

are provided in the rule on deliberate

for not providing complete and accurate

advancement in technology was made, the

misconduct, e.g., 10 CFR 30.10 and

information.

initial submittal was corrected.

50.5.

Absent at least careless disregard, an

The failure to correct inaccurate or

Vendors of products or services

incomplete or inaccurate unsworn oral

incomplete information which the licensee

provided for use in nuclear activities

statement normally will not be subject to

does not identify as significant normally

are subject to certain requirements

enforcement action unless it involves

will not constitute a separate violation.

designed to ensure that the products or

significant information provided by a

However, the circumstances surrounding

services supplied that could affect

licensee official. However,

the failure to correct may be considered

safety are of high quality. Through

enforcement action may be taken for an

relevant to the determination of

procurement contracts with reactor

unintentionally incomplete or inaccurate

enforcement action for the initial inaccurate

licensees, vendors may be required to

oral statement provided to the NRC by a

or incomplete statement. For example, an

have quality assurance programs that

licensee official or others on behalf of a

unintentionally inaccurate or incomplete

meet applicable requirements including

licensee, if a record was made of the

submission may be treated as a more severe

10 CFR Part 50, Appendix B, and 10

oral information and provided to the

matter if the licensee later determines that

CFR Part 71, Subpart H. Vendors

licensee thereby permitting an

the initial submittal was in error and does

supplying products or services to

opportunity to correct the oral

not .correct it or if there were clear

reactor, materials, and 10 CFR Par 71

information, such as if a transcript of

opportunities to identify the error. If

licensees are subject to the

the communication or meeting summary

information not corrected was recognized

requirements of 10 CFR Part 21

containing the error was made available

by a licensee as significant, a separate

regarding reporting of defects in basic

to the licensee and was not subsequently

citation may be made for the failure to

components.

corrected in a timely manner.

provide significant information. In any

When inspections determine that

When a licensee has corrected

event, in serious cases where the licensee's

violations of NRC requirements have

inaccurate or incomplete information,

actions in not correcting or providing

occurred, or that vendors have failed to

the decision to issue a Notice of

information raise questions about its

fulfill contractual commitments (e.g.,

Violation for the initial inaccurate or

commitment to safety or itsfndamental

10 CFR Part 50, Appendix B) that

incomplete information normally will be

trustworthiness, the Commission may

could adversely affect the quality of a

dependent on the circumstances,

exercise its authority to issue orders

safety significant product or service,

including the ease of detection of the

modifying, suspending, or revoking the

enforcement action will be taken.

error, the timeliness of the correction,

license. The Commission recognizes that

Notices of Violation and civil penalties

whether the NRC or the licensee

enforcement determinations must be made

will be used, as appropriate, for

identified the problem with the

on a case-by-case basis, taking into

licensee failures to ensure that their

communication, and whether the NRC

consideration the issues described in this

vendors have programs that meet

relied on the information prior to the

section.

applicable requirements. Notices of

correction. Generally, if the matter was

Violation will be issued for vendors

- 19-

Compilation of NRC Enforcement Policy as of September 10, 1997

violate 10 CFR Part 21. Civil

was incorrectly applied, consideration may

1. A system designed to prevent or

W nalties will be imposed against

be given, dependent on the circumstances,

mitigate serious safety events not being

individual directors or responsible

to reopening a closed enforcement action to

able to perform its intended safety

officers of a vendor organization who

increase or decrease the severity of a

function;

knowingly and consciously fail to

sanction or to correct the record.

2. A licensed operator involved in

provide the notice required by 10 CFR

Reopening decisions will be made on a

the use, sale, or possession of illegal

21.21(b)(1). Notices of

case-by-case basis, are expected to occur

drugs or the consumption of alcoholic

Nonconformance will be used for

rarely, and require the specific approval of

beverages, within the protected area;

vendors which fail to meet commitments

the Deputy Executive Director.

3. A licensed operator at the control

related to NRC activities.

of a nuclear reactor, or a senior

SUPPLEMENT I- REACTOR

operator directing licensed activities,

XI. REFERRALS TO THE

OPERATIONS

involved in procedural errors and who,

DEPARTMENT OF JUSTICE

as a result of subsequent testing,

This supplement provides examples of

receives a confirmed positive test result

Alleged or suspected criminal

violations in each of the four severity levels

for drugs or alcohol; or

violations of the Atomic Energy Act

as guidance in determining the appropriate

4. Failures to meet 10 CFR 50.59

(and of other relevant Federal laws) are

severity level for violations in the area of

including several unreviewed safety

referred to the Department of Justice

reactor operations,

questions, or conflicts with technical

(DOJ) for investigation. Referral to the

A. Severity Level I - Violations involving

specifications, involving a broad

DOJ does not preclude the NRC from

for example:

spectrum of problems affecting

taking other enforcement action under

1. A Safety Limit, as defined in 10 CFR

multiple areas, some of which impact

this policy. However, enforcement

50.36 and the Technical Specifications

the operability of required equipment.

actions will be coordinated with the DOJ

being exceeded;

C. Severity Level III - Violations

in accordance with the Memorandum of

2. A system" designed to prevent or

involving for example:

erstanding between the NRC and the

mitigate a serious safety event not being

1. A significant failure to comply

9

, 53 FR 50317 (December 14,

able to perform its intended safety

with the Action Statement for a.

8)

funiction' 2 when actually called upon to

technical Specification Limiting

work;

Condition for Operation where the

XII. PUBLIC DISCLOSURE OF

3. An accidental criticality; or

appropriate action was not taken within

ENFORCEMENT ACTIONS

4. A licensed operator at the controls of a

the required time, such as:

nuclear reactor, or a senior operator

(a) In a pressurized water reactor, in

Enforcement actions and licensees'

directing licensed activities, involved in

the applicable modes, having one

responses, in accordance with

procedural errors which result in, or

high-pressure safety injection pump

10 CFR 2.790, are publicly available for

exacerbate the consequences of, an alert or

inoperable for a period in excess of

inspection. In addition, press releases

higher level emergency and who, as a result

that allowed by the action statement; or

are generally issued for orders and civil

of subsequent testing, receives a confirmed

(b) In a boiling water reactor, one

penalties and are issued at the same time

positive test result for drugs or alcohol,

primary containment isolation valve

the order or proposed imposition of the

B. Severity Level II - Violations

inoperable for a period in excess of

civil penalty is issued. In addition,

involving for example:

that allowed by the action statement.

press releases are usually issued when a

2. A system designed to prevent or

proposed civil penalty is withdrawn or

substantially mitigated by some amount.

Press releases are not normally issued

The term "system" as used in these

(a) Not being able to perform its

for Notices of Violation that are not

supplements, includes administrative and

intended function under certain

accompanied by orders or proposed civil

managerial control systems, as well as

conditions (e.g., safety system not

b

hivenoperable

unless offsite power is

Sse

s

eavailable;

materials or components not

X11I. REOPENINGCLOSED

12 "Intended safety function" means the

environmentally qualified); or

ENFORCEMENT ACTIONS

total safety function, and is not directed

(b) Being degraded to the extent that

toward a loss of redundancy. A loss of one

a detailed evaluation would be required

i~nifccant new information is

subsystem doesnot defeat the intended

to determine its operability (e.g.,

ed or obtained by NRC which

safety function as long as the other

component parameters outside

indicates that an enforcement sanction

subsystem is operable.

approved limits such as pump flow

- 20 -

Compilation of NRC Enforcement Policy as of September 10, 1997

rates, heat exchanger transfer

accuracy of the FSAR or a concern that 10

6. A relatively isolated failure to

characteristics, safety valve lift

CFR 50.59 requirements are not being met.

document an evaluation where there is

serpoints, or valve stroke times);

Application of this example requires

evidence that an adequate evaluation

3. Inattentiveness to duty on the part

weighing factors such as: a) the time period

was performed prior to the change in

of licensed personnel;

over which the violations occurred and

the facility or procedures, or the

4. Changes in reactor parameters that

existed, b) the number. of failures, c)

conduct of an experiment or test;

cause unanticipated reductions in

whether one or more systems, functions, or

7. A failure to update the FSAR as

margins of safety;

pieces of equipment were involved and the

required by 10 CFR 50.71(e) where an

5. [Reserved]

importance of such equipment, functions,

adequate evaluation under 10 CFR

6. A licensee failure to conduct

or systems, and d) the potential significance

50.59 had been performed and

adequate oversight of vendors resulting

of the failures;

documented; or

in the use of products or services that

13. The failure to update the FSAR as

8 A past programmatic failure to

are of defective or indeterminate quality

required by 10 CFR 50.71(e) where the

meet 10 CFR 50.59 and/or 10 CFR

and that have safety significance;

unupdated FSAR was used in performing a

50.71(e) requirements not involving

7. A breakdown in the control of

10 CFR 50.59 evaluation and as a result, an

Severity Level I1 or III violations that

licensed activities involving a number of

inadequate decision was made

does not reflect a current safety or

violatjons that are related (or, if

demonstrating a significant regulatory

regulatory concern about the accuracy

isolated, that are recurring violations)

concern; or

of the FSAR or a concern that 10 CFR

that collectively represent a potentially

14. The failure to make a report required

50.59 requirements are not being met.

significant lack of attention or

by 10 CFR 50.72 or 50.73 associated with

E. Minor Violations

carelessness toward licensed

(a) an unreviewed safety question, (b) a

A failure to meet 10 CFR 50.59

responsibilities;

conflict with a technical specification, or

requirements that involves a change to

8. A licensed operator's confirmed

(c) any other Severity Level III violation,

the ESAR description or procedure, or

positive test for drugs or alcohol that

D. Severity Level V-Violations

involves a test or experiment not

does not result in a Severity Level I or

involving for example:

described in the FSAR, where there

II violation;

1. A less significant failure to comply

was not a reasonable likelihood that thee

9. Equipment failures caused by

with the Action Statement for a Technical

change to the facility or procedure or

inadequate or improper maintenance that

Specification Limiting Condition for

the conduct of the test or experiment

substantially complicates recovery from

Operation where the appropriate action was

would ever be an unreviewed safety

a plant transient;

not taken within the required time, such as:

question. In the case of a 10 CFR

10. The failure to meet 10 CFR 50.59

(a) In a pressurized water reactor, a 5%

50.71(e) violation, where a failure to

where an unreviewed safety question is

deficiency in the required volume of the

update the FSAR would not have a

involved, or a conflict with a technical

condensate storage tank: or

material impact on safety or licensed

specification, such that a license

(b) In a boiling water reactor, one

activities. The focus of the minor

amendment is required;

subsystem of the two independent MSIV

violation is not on the actual change,

11. The failure to perform the

leakage control subsystems inoperable;

test, or experiment, but on the potential

required evaluation under 10 CFR 50.59

2. [Reserved]

safety role of the system, equipment,

prior to implementation of the change in

3. A failure to meet regulatory

etc., that is being changed, tested, or

those situations in which no unreviewed

requirements that have more than minor

experimented on.

safety question existed, but an extensive

safety or environmental significance;

evaluation would be needed before a

4. A failure to make a required Licensee

SUPPLEMENT Il-PART 50 FACILITY

licensee would have had a reasonable

Event Report;

CONSTRUCTION

expectation that an unreviewed safety

5. Relatively isolated violations of 10

question did not exist;

CFR 50*59 not involving severity level 11

This supplement provides examples of

12. Programmatic failures (i.e.,

or III violations that do not suggest a

violations in each of the four severity

multiple or recurring failures) to meet

programmatic failure to meet 10 CFR

levels as guidance in determining the

the requirements of 10 CFR 50.59

50:59. Relatively isolated violations or

appropriate severity level for violations

and/or 50.71(e) that show a significant

failures would include a number of recently

in the area of Par 50 facility

lack of attention to detail, whether or

discovered violations that occurred over a

construction.

not such failures involve an unreviewed

period of years and are not indicative of a

A. Severity Level I.- Violations

safety question, resulting in a current

programmatic safety concern with meeting

involving structures or systems that are

safety or regulatory concern about the

10 CFR 50.59 or 50.7 1(e);

-21 -

Compilation of NRC Enforcement Policy as of September 10, 1997

pleted" in such a manner that they

involving failure to meet regulatory

2. The theft, loss or diversion of

ouuld not have satisfied their intended

requirements including one or more Quality

SNM of moderate strategic

safety related purpose.

Assurance Criterion not amounting to

significance" in which the security

B. Severity Level II - Violations

Severity Level 1, 11, or III violations that

system did not function as required: or

involving for example:

have more than minor safety or

3. Actual unauthorized production of

1. A breakdown in the Quality

environmental significance.

SNM.

Assurance (QA) program as exemplified

C. Severity Level III - Violations

by deficiencies in construction QA

SUPPLEMENT II-SAFEGUARDS

involving for example:

related to more than one work activity

1. A failure or inability to control

(e.g., structural, piping, electrical,

This supplement provides examples of

access through established systems or

foundations). These deficiencies

violations in each of the four severity levels

procedures, such that an unauthorized

normally involve the licensee's failure to

as guidance in determining the appropriate.

individual (i.e., not authorized

conduct adequate audits or to take

severity level for violations in the area of

unescorted access to protected area)

prompt corrective action on the basis of

safeguards.

could easily gain undetected access'

such audits and normally involve

A. Severity Level I - Violations involving

into a vital area from outside the

multiple examples of deficient

for example:

protected area;

construction or construction of unknown

1. An act of radiological sabotage in

2. A failure to conduct any search at

qualitf due to inadequate program

which the security system did not function

the access control point or conducting

implementation; or

as required and, as a result of the failure,

an inadequate search that resulted in

2. A structure or system that is

there was a significant event, such as:

the introduction to the protected area of

completed in such a manner that it could

(a) A Safety Limit, as defined in 10 CFR

firearms, explosives, or incendiary

have an adverse effect on the safety of

50.36 and the Technical Specifications, was

devices and reasonable facsimiles

operations.

exceeded;

thereof that could significantly assist

. Severity Level III - Violations

(b) A system designed to prevent or

radiological sabotage or theft of

lving for example:

mitigate a serious safety event was not able

strategic SNM;

A deficiency in a licensee QA

to perform its intended safety function

3. A failure, degradation, or.other

program for construction related to a

when actually called upon to work; or

deficiency of the protected area

single work activity (e.g., structural,

(c) An accidental criticality occurred;

intrusion detection or alarm assessment

piping, electrical or foundations). This

2. The theft, loss, or diversion of a

systems such that an unauthorized

significant deficiency normally involves

formula quantity" of special nuclear

individual who represents a threat

the licensee's failure to conduct

material (SNM); or

could predictably circumvent the

adequate audits or to take prompt

3. Actual unauthorized production of a

system or defeat a specific zone with a

corrective action on the basis of such

formula quantity of SNM

high degree of confidence without

audits, and normally involves multiple

B. Severity Level II - Violations

insider knowledge, or other significant

examples of deficient construction or

involving for example:

degradation of overall system

construction of unknown quality due to

1. The entry of an unauthorized

capability;

inadequate program implementation;

individual' who represents a threat into a

4. A significant failure of the

2. A failure to confirm the design

vital area' from outside the protected area;

safeguards systems designed or used to

safety requirements of a structure or

Prevent or detect the theft, loss, or

system as a result of inadequate

diversion of strategic SNM;

preoperational test program

See 10 CFR 73.2 for the definition

5. A failure to protect or control

implementation; or

of "formula quantity."

classified or safeguards information

3. A failure to make a required 10

CFR 50.55(e) report.

" The term unauthorized individual

D. Severity Level IV - Violations

D. evriy

evl V Voltins

as used ini this supplement means someone 1

1 See 10 CFR 73.2 for the

who was not authorized for entrance into

definition of "special nuclear material

the area in question, or not authorized to

of moderate strategic significance."

a The term "completed" as used in

enter in the manner entered.

e

supplement means completion of

In determining whether access

truction including review and

The phrase "vital area" as used in

can be easily gained, factors such as

qW ceptance by the construction QA

this supplement includes vital areas and

predictability, identifiability, and ease

organization.

material access areas.

of passage should be considered.

22-

Compilation of NRC Enforcement Policy as of September 10, 1997

considered to be significant while the

5. A failure to conduct a proper search at

reis total effective dose equivalent;

information is outside the protected area

the access control point;

3. A radiation exposure during any

and accessible to those not authorized

6. A failure to properly secure or protect

year of a minor in excess of 2.5 rems

access to the protected area;

classified or, safeguards information inside

total effective dose equivalent, 7.5

6. A significant failure to respond to

the protected area which could assist an

reis to the lens of the eye, or 25 reis

an event either in sufficient time to

individual in an act of radiological sabotage

to the skin of the whole body, or to the

provide protection to vital equipment or

or theft of strategic SNM where the

feet, ankles, hands or forearms, or to

strategic SNM, or with an adequate

information was not removed from the

any other organ or tissue;

response force;

protected area;

4. An annual exposure of a member

7. A failure to perform an appropriate

7. A failure to control access such that an

of the public in excess of 1.0 rem total

evaluation or background investigation

opportunity exists that could allow

effective dose equivalent;

so that information relevant to the

unauthorized and undetected access into the

5. A release of radioactive material

access determination was not obtained

protected area but which was neither easily

to an unrestricted area at

or considered and as a result a person,

or likely to be exploitable;

concentrations in excess of 50 times the

who would likely not have been granted

8. A failure to conduct an adequate

limits for members of the public as

access by the licensee, if the required

search at the exit from a material access

described in 10 CFR 20.1302(b)(2)(i);

investigation or evaluation had been

area;

or

perfofined, was granted access; or

9. A theft or loss of SNM of low

6. Disposal of licensed material in

8. A breakdown in the security

strategic significance that was not detected

quantities or concentrations in excess

program involving a number of

within the time period specified inthe

of 10 times the limits of 10 CFR

violations that are related (or, if

security plan, other relevant document, or

20.2003.

isolated, that are recurring violations)

regulation; or

B. Severity Level 11 - Violations

that collectively reflect a potentially

10. Other violations that have more than

involving for example:

significant lack of attention or

minor safeguards significance.

1. A radiation exposure during any

carelessness toward licensed

year of a worker in excess of 10 reis

responsibilities.

SUPPLEMENT T-HEALTH PHYSICS (10

total effective dose equivalent, 30 reisW

D. Severity Level IV - Violations

CFR PART 20)

to the lens of the eye, or 100 reis to

involving for example:

inovnCoreape

the skin of the whole body, or to the

1. A failure or inability to control

.

This supplement provides examples of

feet, ankles, hands or forearms, or to

access such that an unauthorized

violations in each of the four severity levels

any other organ or tissue;

individual (i.e., authorized to protected

as guidance in determining the appropriate

2. A radiation exposure over the

area but not to vital area) could easily

severity level for violations in the area of

gestation period of the embryo/fetus of

gain undetected access into a vital area

health physics, 10 CFR Part 20.19

a declared pregnant woman in excess

from inside the protected area or into a.

A. Severity Level I - Violations involving

of 1.0 rem total effective dose

controlled access area;

for example:

equivalent;

1. A radiation exposure during any year

3. A radiation exposure during any

2. A failure to respond to a suspected

of a worker in excess of 25 rems total

year of a minor in excess of I rem total

event in either a timely manner or with

effective dose equivalent, 75 reis to the

effective dose equivalent, 3.0 reis to

an adequate response force;

lens of the eye, or 250 rads to the skin of

the lens of the eye, or 10 reis to the

3. A failure to implement 10 CFR

the whole body, or to the feet, ankles,

skin of the whole body, or to the feet,

Parts 25 and 95 with respect to the

hands or forearms, or to any other organ or

ankles, hands or forearms, or to any

information addressed under Section 142

tissue;

other organ or tissue;

of the Act, and the NRC approved

2. A radiation exposure over the

4. An annual exposure of a member

security plan relevant to those parts;

gestation period of the embryo/fetus of a

of the public in excess of 0.5 rem total

4. A failure to make, maintain, or

declared pregnant woman in excess of 2.5

effective dose equivalent;

provide log entries in accordance with

5. A release of radioactive material

10 CFR 73.71 (c) and (d), where the

to an unrestricted area at

omitted information (i) is not otherwise

Personnel overexposures and

concentrations in excess of 10 times the

available in easily retrievable records,

associated violations incurred during a

limits for members of the public as

and (ii) significantly contributes to the

described in 10 CFR 20.1302(b)

ability of either the NRC or the licensee

or other emergency response

(

effort will be treated on a case-by-case

at

to identify a programmatic breakdown;.

year has been approved by the

-23 -

Compilation of NRC Enforcement Policy as of September 10, 1997

ission under Section 20.1301(c));

CFR 20.2202(b) or an immediate

environmental radiation standards, such

Disposal of licensed material in

notification required by

as 40 CFR Part 190;

quantities or concentrations in excess of

10 CFR 20.2201(a)(1)(i);

6. A failure to make the 30-day

five times the limits of 10 CFR

8. A substantial potential for exposures

notification required by 10 CFR

20.2003; or

or releases in excess of the applicable limits

20.2201(a)(1)(ii) or 20.2203(a);

7. A failure to make an immediate

in 10 CFR Part 20 Sections

7. A failure to make a timely written

notification as required by

20.1001-20.2401 whether or not an

report as required by 10 CFR

10 CFR 20.2202 (a)(1) or (a)(2).

exposure or release occurs;

20.2201(b), 20.2204, or 20.2206;

C. Severity Level III - Violations

9. Disposal of licensed material not

8. A failure to report an exceedance

involving for example:

covered in Severity Levels I or II;

of the dose constraint established in 10

1. A radiation exposure during any

10. A release for unrestricted use of

CFR 20.1101(d) or a failure to take

year of a worker in excess of 5 rems

contaminated or radioactive material or

corrective action for an exceedance, as

total effective dose equivalent, 15 rems

equipment that poses a realistic potential for

required by 10 CFR 20.1101(d); or

to the lens of the eye, or 50 rems to the

exposure of the public to levels or doses

9. Any other matter that has more

skin of the whole body or to the feet,

exceeding the annual dose limits for

than a minor safety, health, or

ankles, hands or forearms, or to any

members of the public, or that reflects a

environmental significance.

other prgan or tissue;

programmatic (rather than an isolated)

2. A radiation exposure over the

weakness in the radiation control program;

SUPPLEMENT V

gestation period of the embryo/fetus of a

11. Conduct of licensee activities by a

TRANSPORTATION

declared pregnant woman in excess of

technically unqualified person;

0.5 rem total effective dose equivalent

12. A significant failure to control

This supplement provides examples of

(except when doses are in accordance

licensed material; or

violations in each of the four severity

with the provisions of

13. A breakdown in the radiation safety

levels as guidance in determining the

ion 20.1208(d));

program involving a number of violations

appropriate severity level for violations

A radiation exposure during any

that are related (or, if isolated, that are

in the area of NRC transportation

of a minor in excess of 0.5 tem

recurring) that collectively represent a

requirements20 .

total effective dose equivalent; 1.5 rems

potentially significant lack of attention or

A. Severity Level I - Violations

to the lens of the eye, or,5 rems to the

carelessness toward licensed

involving for example:

skin of the whole body, or to the feet,

responsibilities.

1. Failure to meet transportation

ankles, hands or forearms, or to any

D. Severity Level IV - Violations

requirements that resulted in loss of

other organ or tissue;

involving forexample:

control of radioactive material with a

4. A worker exposure above

1. Exposures in excess of the limits of 10

breach in package integrity such that

regulatory limits when such exposure

CFR 20.1201, 20.1207, or 20.1208 not

the material caused a radiation

reflects a programmatic (rather than an

constituting Severity Level I, Il. or I

exposure to a member of the public and

isolated) weakness in the radiation

violations;

there was clear potential for the public

control program;

2. A release of radioactive material to an

to receive more than . 1 rem to the

5. An annual exposure of a member

unrestricted area at concentrations in excess

whole body;

of the public in excess of 0.1 rem total

of the limits for members of the public a

2. Surface contamination in excess of

effective dose equivalent (except when

referenced in 10 CFR 20.1302(b)(2)(i)

50 times the NRC limit; or

operation up to 0.5 rem a year has been

(except when operation up to 0.5 rem a

3. External radiation levels in excess

approved by the Commission under

year has been approved by the Commission

Section 20.1301(c));

under Section 20.1301(c));

6. A release of radioactive material to

3. A radiation dose rate in an unrestricted

20

an unrestricted area at concentrations in

or controlled area in excess of 0.002 rem in

reurmensra

iom

excess of two times the effluent

any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> (2 millirem/bour) or 50

one licensee involved in the same

concentration limits referenced in 10

millirems in a year;

activity such as a shipper and a carrier.

CFR 20.1302(b)(2)(i) (except when

4. Failure to maintain and implement

When a violation of such a requirement

operation up to 0.5 rem a year has been

radiation programs to keep radiation

roved by the Commission under

exposures as low as is reasonably

directed against the responsible

ion 20.1301(c));

achievable;

licensee which, under the

A failure to make a 24-hour

5. Doses to a member of the public in

circumstances of the case, may be one

notification required by 10

excess of any EPA generally applicable

or more of the licensees involved.

- 24 -

Compilation of NRC Enforcement Policy as of September 10, 1997

of 10 times the NRC limit.

D. Severity Level IV - Violations

activities, including chemical process

B. Severity Level II - Violations

involving for example:

that are integral to the licensed or

involving for example:

1. A breach of package integrity without

certified activity, whether radioactive

1. Failure to meet transportation

external radiation levels exceeding the NRC

material is released or not.

requirements that resulted in loss of

limit or Without contamination levels

B. Severity Level II - Violations

control of radioactive material with a

exceeding five times the NRC limits;

involving for example:

breach in package integrity such that

2. Surface contamination in excess of but

1. Radiation levels, contamination

there was a clear potential for the

not more than five times the NRC limit;

levels, or releases that exceed five

member of the public to receive more

3. A failure to register as an authorized

times the limits specified in the license;

than .1 rem to the whole body;

user of an NRC-Certified Transport

2. A system designed to prevent or

2. Surface contamination in excess of

package;

mitigate a serious safety event being

10, but not more than 50 times the NRC

4. A noncompliance with shipping

inoperable;

limit;

papers, marking, labeling, placarding,

3. A substantial programmatic failure

3. External radiation levels in excess

packaging or loading not amounting to a

in the implementation of the quality

of five, but not more than 10 times the

Severity Level 1, Il,'or III violation;

management program required by 10

NRC limit; or

5. A failure to demonstrate that packages

CFR 35.32 that results in a

4. A failure to make required initial

for special form radioactive material meets

misadministration;

notifications associated with Severity

applicable regulatory requirements;

4. A failure to establish, implement,

Level I or II violations.

6. A failure to demonstrate that packages

or maintain all criticality controls (or

C. Severity Level III - Violations

meet DOT Specifications for 7A Type A

control systems) for a single nuclear

involving for example:

packages; or

criticality scenario when a critical mass

1. Surface contamination in excess of

7. Other violations that have more than

of fissile material was present or

five but not more than 10 times the

minor safety or environmental significance.

reasonably available, such that a

NRC limit;

nuclear criticality accident was

2. External radiation in excess of one

SUPPLEMENT VI-FUEL CYCLE AND

possible; or

but not more than five times the NRC

MATERIALS OPERATIONS

5. The potential for a significant

limit;

injury or loss of life due to a loss of

3. Any'noncompliance with labeling,

This supplement provides examples of

control over licensed or cerified

placarding, shipping paper, packaging,

violations in each of the four severity levels

activities, including chemical processes

loading, or other requirements that

as guidance in determining the appropriate

could reasonably result in the following:

severity level for violations in the area of

certified activity, whether radioactive

(a) A significant failure to identify the

fuel cycle and materials operations.

material is released or not (e.g.,

type, quantity, or form of material;

A. Severity Level I - Violations involving

movement of liquid UF 6 cylinder by

(b) A failure of the carrier or

for example:

unapproved methods).

recipient to exercise adequate controls;

1. Radiation levels, contamination levels,

C. Severity Level III - Violations

or

or releases that exceed 10 times the limits

involving for example:

(c) A substantial potential for either

specified in the license;

1. A failure to control access to

personnel exposure or contamination

2. A system designed to prevent or

licensed materials for radiation

above regulatory limits or improper

mitigate a serious safety event not being

protection purposes as specified by

transfer of material;

operable when actually required to perform

NRC requirements;

4. A failure to make required initial

its design function;

2. Possession or use of unauthorized

notification associated with Severity

3. A nuclear criticality accident;

equipment or materials in the conduct

Level III violations; or

4. A failure to follow the procedures of

of licensee activities which degrades

5. A breakdown in the licensee's

the quality management program, required

safety;

program for the transportation of

by 10 CFR 35.32, that results in a death or

3. Use of radioactive material on

licensed material involving a number of

serious injury (e.g., substantial organ

humans where such use is not

violations that are related (or, if

impairment) to a patient;

authorized;

isolated, that are recurring violations)

5. A safety limit, as defined in 10 CFR

4. Conduct of licensed activities by a

that collectively reflect a potentially

76.4, the Technical Safety Requirements,

technically unqualified or uncertified

significant lack of attention or

or the application being exceeded, or

carelessness toward licensed

6. Significant injury or loss of life due to

5. A substantial potential for

responsibilities,

a loss of control over licensed or certified

exposures, radiation levels,

- 25 -

Compilation of NRC Enforcement Policy as of September 10, 1997

tamination levels, or releases,

conduct and/or complete decommissioning

available, such that a nuclear criticality

cluding releases of toxic material

activities in accordance with regulation or

accident was possible; or

caused by a failure to comply with NRC

license condition, or failure to meet

19. A failure, during radiographic

regulations, from licensed or certified

required schedules without adequate

operations, to stop work after a pocket

activities in excess of regulatory limits;

justification;

dosimeter is found to have gone off

6. Substantial failure to implement the

12. A significant failure to comply with

scale, or after an electronic dosimeter

quality management program as

the action statement for a Technical Safety

reads greater than 200 mrem, and

required by 10 CFR 35.32 that does not

Requirement Limiting Condition for

before a determination is made of the

result in a misadministration; failure to

Operation where the appropriate action was

individual's actual radiation exposure.

report a misadministration; or

not taken within the required time, such as:

D. Severity.Level IV - Violations

programmatic weakness in the

(a) In an autoclave, where a containment

involving for example:

implementation of the quality

isolation valve is inoperable for a period in

1. A failure to maintain patients

management program that results in a

excess of that allowed by the action

hospitalized who have cobalt-60,

misadministration;

statement; or

cesium-137, or iridium-192 implants or

7. A breakdown in the control of

(b) Cranes or other lifting devices

to conduct required leakage or

licensed activities involving a number of

engaged in the movement of cylinders

contamination tests, or to use properly

violations that are related (or, if

having inoperable safety components, such

calibrated equipment;

isolatet, that are recurring violations)

as redundant braking systems, or other

2. Other violations that have more

that collectively represent a potentially

safety devices for a period in excess of that

than minor safety or environmental

significant lack of attention or

allowed by the action statement;

significance;

carelessness toward licensed

13. A system designed to prevent or

3. Failure to follow the quality

responsibilities;

mitigate a serious safety event:

management QM) program, including

8. A failure, during radiographic

(a) Not being able to perform its intended

procedures, whether or not a

,

rations, to have present at least two.. function under certain conditions (e.g.,

misadmiristration occurs, provided the

fled individuals or to use

safety system not operable unless utilities

failures are isolated, do not

graphic equipment, radiation

available, materials or components not

demonstrate a programmatic weakness

survey instruments, and/or personnel

accordin to specifications); or

iii the implementation of the QM

monitoring devices as required by 10

(b) Being degraded to the extent that a

program, and have limited

CFR Part 34;

detailed evaluation would be required to

consequences if a misadministration is

9. A failure to submit an NRC Form

determine its operability;

involved; failure to conduct the

241 as required by 10 CFR 150.20;

14. Changes in parameters that cause

required program review; or failure to

10. A failure to receive required NRC

unanticipated reductions in margins of

take corrective actions as required by

approval prior to the implementation of

safety;

10 CFR 35.32;

a change in licensed activities that has

15. A significant failure to meet the

4. A failure to keep the records

radiological or programmatic

requirements of 10 CFR 76.68, including a

required by 10 CFR 35.32 or 35.33;

significance, such as, a change in

failure such that a required certificate

5. A less significant failure to

ownership; lack of an RSO or

amendment was not sought;

comply with the Action Statement for a

replacement of an RSO with an

16. A failure of the certificate holder to

Technical Safety Requirement Limiting

unqualified individual; a change in the

conduct adequate oversight of vendors or

Condition for Operation when the

location where licensed activities are

contractors resulting in the use of products

appropriate action was not taken within

being conducted, or where licensed

or services that are of defective or

the required time;

material is being stored where the new

indeterminate quality and that have safety

6. A failure to meet the requirements

facilities do not meet safety guidelines;

significance;

of 10 CER 76.68 that does not result in

or a change in the quantity or type of

17. Equipment failures caused by

a Severity Level 1, 11, or III violation;

radioactive material being processed or

inadequate or improper maintenance that

7. A failure to make a required

used that has radiological significance;

substantially complicates recovery from a

written event report, as required by

11. A significant failure to meet

plant transient;

10 CFR 76.120(d)(2); or

decommissioning requirements including

18. A failure to establish, maintain, or

8. A failure to establish, implement,

gailure to notify the NRC as required

implement all but one criticality control (or

or maintain a criticality control (or

gulation or license condition,

control systems) for a single nuclear

control system) for a single nuclear

,41W

antial failure to meet

criticality scenario when a critical mass of

criticality scenario when the amount of

decommissioning standards, failure to

fissile material was present or reasonably

fissile material available was not, but

-26 -

Compilation of NRC Enforcement Policy as of September 10, 1997

could have been sufficient to result in a

4. Action by senior corporate

7. A failure to take reasonableacti

nuclear criticality.

management in violation of 10 CFR 50.7 or

when observed behavior within the

O

similar regulations against an employee;

protected area or credible information

SUPPLEMENT VII-MISCELLANEOUS

5. A knowin and intentional failure to

concerning activities within the

MATTERS

provide the notice required by 10 CFR Part

protected area indicates possible

21; or

unfitness for duty based on drug or

This supplement provides examples of

6. A failure to substantially implement

alcohol use;

violations in each of the four severity

the required fitness-for-duty program.

8. A deliberate failure of the

levels as guidance in determining the

B. Severity Level H - Violations

licensee's Employee Assistance

appropriate severity level for violations

involving for example:

Program (EAP) to notify licensee's

involving miscellaneous matters.

1. Inaccurate or incomplete information

management when EAP's staff is

A. Severity Level I - Violations

that is provided to the NRC (a) by a

aware that an individual's condition

involving for example:

licensee official because of careless

may adversely affect safety related

1. Inaccurate or incomplete

disregard for the completeness or accuracy

activities; or

information' that is provided to the

of the information, or (b) if the

9. The failure of licensee

NRC (a) deliberately with the

information, had it been complete and

management to take effective action in

knowledge of a licensee official that the

accurate at the time provided, likely would

correcting a hostile work environment.

inforrrtion is incomplete or inaccurate,

have resulted in regulatory action such as a

C. Severity Level III - Violations

or (b) if the information, had it been

show cause order or a different regulatory

involving for example:

complete and accurate at the time

position;

I. Incomplete or inaccurate

provided, likely would have resulted in

2. Incomplete or inaccurate information

information that is provided to the

regulatory action such as an immediate

that the NRC requires be kept by a. licensee

NRC (a) because of inadequate actions

order required by the public health and

which is (a) incomplete or inaccurate

on the part of licensee officials but not

safety;

because of careless disregard for the

amounting to a Severity Level I or II

2. Incomplete or inaccurate

accuracy of the information on the part of a

violation, or (b) if the information, ha

information that the NRC requires be

licensee official, or (b) if the

it been complete and accurate at the

kept by a licensee that is (a) incomplete

had it been complete and accurate when.

time provided, likely would have

or inaccurate because of falsification by

reviewed by the NRC, likely would have

resulted in a reconsideration of a

or with the knowledge of a licensee

resulted in regulatory action such as a show

regulatory position or substantial

official, or (b) if the information, had it

cause order or a different regulatory

further inquiry such as an additional

been complete and accurate when

position;

inspection or a formal request for

reviewed by the NRC, likely would

3. "Significant information identified by a

information;

have resulted in regulatory action such

licensee" and not provided to the

2. Incomplete or inaccurate

as an immediate order required by

Commission because of careless disregard

information that the NRC requires be

public health and safety considerations;

on the part of a licensee official;

kept by a licensee that is (a) incomplete

3. Information that the licensee has

4. An action by plant management above

or inaccurate because of inadequate

identified as having significant

first-line supervision in violation of 10 CFR

actions on the part of licensee officials

implications for public health and safety

50.7 or similar regulations against an

but not amounting to a Severity Level I

or the common defense and security

employee;

or 11 violation, or (b) if the

("significant information identified.by

5. A failure to provide the notice

information, had it been complete and

a licensee") and is deliberately withheld

required by 10 CFR Part 21;

accurate when reviewed by the NRC,

from the Commission;

6. A failure to remove an individual from

likely would have resulted in a

unescorted access who has been involved in

reconsideration of a regulatory position

the sale, use, or possession of illegal drugs

or substantial further inquiry such as an

1 In applying the examples in this

within the protected area or take action for

additional inspection or a formal

supplement regarding inaccurate or

on duty misuse of alcohol, prescription

request for information;

incomplete information and records,

drugs, or over-the-counter drugs;

3. A failure to provide "sigificant

reference should also be made to the

information identified by a licensee" to

guidance in Section IX, "Inaccurate and

t Comm Io an noating

Incomplete Information," and to the

The example for violations for

S

r

Lv ior by

ilat

ion

definition of "licensee official"

fitness-for-duty relate to violations of 10

4n

ation

firt-

.7 srisiol

contained in Section

1.C0

CFR Part 26.

-27-

Compilation of NRC Enforcement Policy as of September 10, 1997

lations against an employee;

CFR Part 21 with more than minor safety

2. A licensee failure to meet or

. An inadequate review or failure to

significance;

implement more than one emergency

review such that, if an appropriate

4. Violations of the requirements of Part

planning standard involving assessment

review had been made as required, a 10

26 of more than minor significance;

or notification.

CFR Part 21 report would have been

A failure to report acts of licensed

C. Severity Level III - Violations

made;

operators or supervisors pursuant to 10

involving for example:

6. A failure to complete a suitable

CFR 26.73; or

1. In an alert, licensee failure to

inquiry on the basis of 10 CFR Part 26,

6. Discrimination cases which, in

promptly (1) correctly classify the

keep records concerning the denial of

themselves, do not warrant a Severity Level

event, (2) make required notifications

access, or respond to inquiries

III categorization,

to responsible Federal, State, and local

concerning denials of access so that, as

agencies, or (3) respond to the event

a result of the failure, a person

SUPPLEMENT VIII-EMERGENCY

(e.g., assess actual or potential offsite

previously denied access for

PREPAREDNESS

consequences, actiyate emergency

fitness-for-duty reasons was improperly

response facilities, and augment shift

granted access;

This supplement provides examples of

staff);

7. A failure to take the required action

violations in each of the four severity levels

2. A licensee failure to meet or

for a person confirmed to have been

as guidance in determining the appropriate

implement one emergency planning

testecFpositive for illegal drug use or

severity level for violations in the area of

standard involving assessment or

take action for onsite alcohol use; not

emergency preparedness. It should be

notification; or

amounting.to a Severity Level II

noted that citations are not normally made

3. A breakdown in the control of

violation;

for violations involving emergency

licensed activities involving a number

8. A failure to assure, as required,

preparedness occurring during emergency

of violations that are related (or, if

that contractors or vendors have an

exercises. However, where exercises

isolated, that are recurring violations)

five fitness-for-duty program;

reveal (i) training, procedural, or repetitive

that collectively represent a potentially

A breakdown in the fitness-for-duty

failures for which corrective actions have

significant lack of attention or

ram involving a number of

not been taken, (ii) an overall concern

carelessness toward licensed

violations of the basic elements of the

regarding the licensee's ability to

fitness-for-duty program that

implement its plan in a manner that

D. Severity Level IV - Violations

collectively reflect a significant lack of

adequately protects public health and

attention or carelessness towards

safety, or (iii) poor self critiques of the

A licensee failure to meet or

meeting the objectives of 10 CFR 26.10;

licensee's exercises, enforcement action

or

may be appropriate,

standard or requirement not directly

10. Threats of discrimination or

A. Severity Level I - Violations involving

related to assessment and notification.

restrictive agreements which are

for example:

violations under NRC regulations such

In a general emergency, licensee failure to

as 10 CFR 50.7(f).

promptly (1) correctly classify the event,

D. Severity Level IV - Violations

(2) make required notifications to

involving for example:

responsible Federal, State, and local

1. Incomplete or inaccurate

agencies, or (3) respond to the event (e.g.,

information of more than minor

assess actual or potential offsite

significance that is provided to the NRC

consequences, activate emergency response

but not amounting to a Severity Level 1,

facilities, and augment shift staff.)

11, or III violation;

B. Severity Level II - Violations

2. Information that the NRC requires

involving for example:

be kept by a licensee and that is

L' In a site emergency, licensee failure to

incomplete or inaccurate and of more

promptly (1) correctly classify the event,

than minor significance but not

(2) make required notifications to

amounting to a Severity Level I, II, or

responsible Federal, State, and local

e

violation;

agencies, or (3) respond to the event (e.g.,

An inadequate review or failure to

assess actual or potential offsite

ew under 10 CFR Part 21 or other

consequences, activate emergency response

procedural violations associated v4ith 10

facilities, and augment shift staff); or

-C28