MONTHYEARML13310A9171983-08-26026 August 1983 Notifies That Proposed Change to Tech Specs Re Battery Surveillance Requirements Will Be Submitted in Oct 1983. Results of Recent 60-month Battery Performance Test Will Also Be Delayed Due to Efforts Involved Project stage: Request ML13310B0951983-11-28028 November 1983 Application to Amend License DPR-13,consisting of Proposed Change 126 to Tech Specs,Revising Limiting Conditions for Operation & Corresponding Surveillance Requirements for Electrical Supplies Project stage: Request ML13310B0921983-11-30030 November 1983 Forwards Application to Amend License DPR-13,consisting of Proposed Change 126 to Tech Specs,Specifying Limiting Conditions for Operation & Surveillance Requirements for Electrical Supplies for Each Mode of Operation Project stage: Request ML13310B0971983-11-30030 November 1983 Existing & Proposed Tech Specs 3.7, Auxiliary Electrical Supply, & 4.4, Emergency Power Sys Periodic Testing Project stage: Other ML13316A5731983-12-22022 December 1983 Advises That Proposed Change 126 to Tech Specs to Delete Existing Auxiliary Feedwater Pump Requirements in Section 4.4.E Does Not Provide Adequate Justification for Deletion of Provisions of Spec Project stage: Other ML13310B1341983-12-30030 December 1983 Submits Addl Info to Support Util 831130 Proposed Change 126 to Delete Tech Spec 4.4.E Re Operability of Auxiliary Feedwater Sys.Surveillance Requirements in Tech Spec 4.4.E Superseded by Tech Spec 4.1.9 Issued in Amend 65 Project stage: Request ML13310B1421984-01-13013 January 1984 Requests No Addl Consideration Be Given to Removal of Tech Spec 4.5.E as Part of Proposed Change 126 Submitted on 831130.Removal of Surveillance Requirement for Auxiliary Feedwater Sys Will Be Handled in Future Proposed Change Project stage: Request ML13310B2891984-03-0909 March 1984 Forwards Request for Addl Info Re Proposed Changes 76 & 126 to Tech Specs.Info Requested within 30 Days of Ltr Date Project stage: RAI ML13310B3241984-04-12012 April 1984 Addl Info Re Proposed Changes 76 & 126 to License DPR-13. Response to NRC 840309 Request for Info Will Be Submitted in 45 Days,Following Replacement of Dc Battery Bank 1 Due to End of Svc Life Project stage: Request ML13310B6031984-07-27027 July 1984 Forwards Addl Info Re Proposed Changes 76 & 126 to Tech Specs,In Response to NRC 840309 Request.Calculation Sheets Encl.W/Three Oversize Drawings.Aperture Cards Available in PDR Project stage: Request ML13330A4461984-10-15015 October 1984 Application to Amend License DPR-13,revising Proposed Change 126,to Maintain Battery Charger Output Current Consistent W/Existing Tech Specs & to Omit Operability Contingency That Battery Parameters Must Be within Allowable Values Project stage: Request ML13316A7431984-11-14014 November 1984 Amend 84 to License DPR-13,approving Changes to Tech Specs & Bases to Incorporate Mods to Operability & Surveillance Requirements for Auxiliary Electric Supplies Project stage: Other ML13316A7461984-11-14014 November 1984 Safety Evaluation Supporting Amend 84 to License DPR-13 Project stage: Approval ML13316A7401984-11-14014 November 1984 Forwards Amend 84 to License DPR-13 & Safety Evaluation. Amend Approves Tech Spec Changes & Bases Incorporating Mods to Operability & Surveillance Requirements for Auxiliary Electric Supplies Project stage: Approval 1984-01-13
[Table View] |
Text
Southern California Edison Company P. 0.
BOX 800 2244 WALNUT GROVE AVENUE
- ROSEMEAD, CALIFORNIA 91770 M.O. MEDFORD TELEPHONE MANAGER, NUCLEAR LICENSING January 13, 1984 (213) 572-1749 Director, Office of Nuclear Reactor Regulation Attention: D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Gentlemen:
Subject:
Docket No. 50-206 Proposed Change No. 126 to the Technical Specifications San Onofre Nuclear Generating Station Unit 1 By [[letter::05000362/LER-1983-104-03, /03L-0:on 831205,high Auxiliary Feedwater (AFW) Flow Rate Erroneously Indicated When No Flow Existed.Steam Generator E-089 AFW Flow Rate Channel Declared Inoperable. Caused by Loose Voltage Converter Terminal|letter dated December 30, 1983]], we submitted a request for additional consideration of the removal of Technical Specification 4.4.E as part of Proposed Change No. 126 to the San Onofre Unit 1 Technical Specifications submitted on November 30, 1983. Subsequently, the NRC staff has identified potential inconsistencies regarding the requirements of 4.4.E.
It has been determined that the best way to resolve these concerns is to include the removal of 4.4.E in an upcoming proposed change to the Technical Specifications which will include all changes resulting from equipment modifications to the Auxiliary Feedwater System accomplished as a result of the TMI Lessons Learned requirements.
It is therefore requested that no additional consideration be given to the removal of Technical Specification 4.4.E as part of Proposed Change No. 126. The removal of this surveillance requirement will be handled as part of a future proposed change.
If you have any questions or desire additional information, please contact me.
Very truly yours, cc:
J. 0. Ward, California Department of Health Services 8401170200 8413 PDR Ab0CK 05000206~