Email from: Jonathan Bartley, to: John Boska, Cc: Kenneth Karwoski, Nancy Salgado, Patrick Hiland, Michael Cheok, Michele Evans, Allen Howe, Rick Croteau and William Jones Subject: Jld Presentation on 5/8/12-Oconee Slide
ML13066A761
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 05/04/2012
From: Bartley J
NRC/RGN-II
To: Boska J
Division of Operating Reactor Licensing
References
FOIA/PA-2012-0325
Download: ML13066A761 (1)


Text

Bartley, Jonathan From: Bartley, Jonathan Sent: Friday, May 04, 2012 9:48 AM To: Boska, John Cc: Karwoski, Kenneth; Salgado, Nancy; Hiland, Patrick; Cheok, Michael; Evans, Michele; Howe, Allen; Croteau, Rick; Jones, William

Subject:

RE: JLD presentation on 5/8/12- Oconee slides John, 2 comments from me:

1. It appears that options 1 and 2 are directly related, i.e., we need option 1 before we can do option 2.

Maybe combine them into 1 option.

2. Do we need more discussion and present options on the appropriate standards for the flood protection measures such as the flood wall?

I have forwarded to my management and will provide you any comments I receive from them.

Jonathan From: Boska, John Sent: Friday, May 04, 2012 8:38 AM To: Karwoski, Kenneth; Salgado, Nancy; Hiland, Patrick; Che.pk, Michael; Evans, Michele; Howe, Allen; Bartley, Jonathan

Subject:

JLD presentation on 5/8/12- Oconee slides (OC Attached is the draft of the Oconee slides. Please let me know if you have any comments. The reason I used the phrase "adequate protection of public health and safety," is because it will then require the use of the backfit rule to add additional requirements on Duke, which I believe is the level of assurance they desire before proceeding with construction of flood walls.

John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: iohn.boska(.nrc.pov 1.