ML13042A425
ML13042A425 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 01/29/2013 |
From: | Mcneil D Operations Branch III |
To: | Xcel Energy |
References | |
Download: ML13042A425 (122) | |
Text
2013 MNGP ILT NRC Written Exam QUESTION # 001 The plant was operating at 85% reactor power with all equipment operable when a trip of #12 Recirc Pump occurred. Three minutes later the following plant conditions exist:
- RPV level is +35 inches and stable
- Recirc Loop A indicates a total jet pump flow of 25 Mlbm/hr
- Recirc Loop B indicates a total jet pump flow of 5 Mlbm/hr
- APRM recorders are fluctuating between 56% and 57% reactor power
- C.2-06 Figure 1 (MNGP P-F Operating Map) is provided on the following page Given the above information; which one of the following identifies a correct action to take for the given conditions?
- a. Raise recirculation flow to exit the OPRM Enabled region.
- b. Control rods need to be inserted to exit ONLY Stability Region I.
- c. Control rods need to be inserted to exit Stability Regions I AND II.
- d. A manual scram needs to be inserted due to neutron flux oscillations.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 002 The plant was operating at rated conditions when a Main Generator over voltage condition occurred resulting in a Generator Lockout and a Station Blackout (SBO).
Which of the following strategies is used in a SBO for RPV pressure control?
- c. Maintain RPV pressure 900-1050 psig with turbine bypass valves.
- d. Maintain RPV pressure 900-1052 psig with Low-Low Set.
QUESTION # 003 The plant is at rated conditions with D-20 (DIV II 125 VDC CHARGER) out of service. Given the following:
- D-10 (DIV I 125 VDC CHARGER) is in service supplying the Division I loads
- D-40 (SPARE 125 VDC CHARGER) is in service supplying the Division II loads With the conditions above; what would be the impact if a LOCKOUT occurred on LC-103?
- a. Battery 11 would deplete, resulting in a loss of Division I 125 VDC ONLY.
- b. Battery 12 would deplete, resulting in a loss of Division II 125 VDC ONLY.
- c. Batteries 11 & 12 would deplete, resulting in a COMPLETE loss of 125 VDC.
- d. Batteries 11 & 12 would be unaffected as they BOTH would be charging from LC-104.
2013 MNGP ILT NRC Written Exam QUESTION # 004 The plant was operating at rated conditions when Moisture Separator high level caused annunciator 7-B-25 (TURBINE LOCKOUT) and a reactor scram. Given the following:
- RPV Pressure is 1025 psig and rising
- RPV Water Level is 20 inches and stable
- The lowest RPV Water Level was -12 inches
- The Main Generator Field Breaker is CLOSED
- The Main Turbine Stop Valves are all CLOSED
- Main Generator Output Breakers 8N7 and 8N8 are OPEN Based on the given conditions above and assuming NO operator actions have been taken; has the plant responded correctly and why?
- a. Yes; the Main Generator Field Breaker remains CLOSED on a turbine lockout.
- b. Yes; the LL-SET System is expected to control RPV pressure 900-1056 psig.
- c. No; the Main Generator Output Breakers should have remained CLOSED.
QUESTION # 005 The plant was operating at rated conditions when a scram occurred due to an RPS fault. The following conditions now exist:
- RPV Pressure is 900 psig and stable
- RPV water level lowered to -20 inches
- RPV water level is now +4 inches and slowly rising
- The DFWLC System status is shown pictorially on the next page Using the given conditions, approximately where will RPV water level stabilize out at? (Assume the Reactor Feed Pumps remain running)
- a. 5 inches.
- b. 15 inches.
- c. 35 inches.
- d. 38 inches.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 006 The plant was operating at rated conditions when a Control Room evacuation was required. An emergency depressurization was performed to restore RPV water level. RPV pressure is 70 psig and lowering with the ASDS Fuel Zone RPV level indicator reading as shown:
Based on the given conditions, complete the following statement concerning RPV water level and why?
Actual RPV water level is
- a. lower than indicated because this instrument is calibrated at 0 psig.
- b. lower than indicated because this instrument is calibrated at 1000 psig.
- c. higher than indicated because this instrument is calibrated at 0 psig.
- d. higher than indicated because this instrument is calibrated at 1000 psig.
2013 MNGP ILT NRC Written Exam QUESTION # 007 The plant is operating at rated conditions with the following RBCCW system status:
With the conditions above; If the running RBCCW pump trips on overload, which of the following actions must be taken in the control room?
- a. Trip the Recirc pumps and close the RBCCW drywell isolation valves.
- b. Verify the standby RBCCW pump automatically starts.
- c. Attempt to manually restart the tripped RBCCW pump.
- d. Attempt to manually start the standby RBCCW pump.
2013 MNGP ILT NRC Written Exam QUESTION # 008 On a complete loss of Instrument Air, which of the following components will fail CLOSED?
- a. SBGT valves.
- b. CRD flow control valves.
- d. RHR pump minimum flow valves.
QUESTION # 009 The reactor is shutdown for a scheduled refueling outage. The following conditions exist:
- RPV water level is 57 inches
- Reactor Coolant Temperature is 149°F
- The Reactor Mode switch is in SHUTDOWN
- ALL Reactor Vessel Head closure bolts are fully tensioned
- Division 2 RHR/RHRSW pumps are in Shutdown Cooling (SDC)
- Division 1 AC Busses are deenergized for a scheduled maintenance window Electricians wish to perform maintenance on the Bus 16 voltmeter. The clearance order requires the Bus 16 POT drawer to be tagged opened in order for this work to commence.
Which of the following SDC Technical Specification LCOs, if any, would be NOT MET if this clearance order is implemented?
- a. NONE; this maintenance will NOT affect SDC.
- b. LCO 3.4.7 (RHR Shutdown Cooling System - Hot Shutdown).
- c. LCO 3.4.8 (RHR Shutdown Cooling System - Cold Shutdown).
2013 MNGP ILT NRC Written Exam QUESTION # 010 The plant is in Mode 5 with a full core off-load in progress. A refueling error occurs resulting in inadvertent criticality in the Fuel Pool and the following conditions:
- 4-A-1 (REFUELING FL AREA HI RADIATION) is in alarm
- ALL other radiation monitors are reading below their alarm setpoints Which one of the following is the correct response to these conditions?
- a. Evacuate the Refuel Floor ONLY.
- b. Verify that SBGT has automatically initiated.
- c. Evacuate the Reactor Building AND the Refuel Floor.
- d. Refueling personnel should monitor and evaluate local ARM readings.
QUESTION # 011 The plant was operating at rated conditions when a Bus 14 Lockout resulted in the following:
- RPV water level is 20 and stable
- RPV pressure is 900 psig and stable
- Drywell pressure is 2.3 psig and rising
- 15 Bus is being supplied from 13 Bus
- 16 Bus is being supplied from 12 EDG Which one of the following correctly describes the load sheds received by 15 & 16 Busses?
15 BUS 16 BUS
- b. ECCS Load Shed ONLY EBT Load Shed ONLY
2013 MNGP ILT NRC Written Exam QUESTION # 012 The plant was at rated conditions with the RCIC Pump Flow Test in progress.
Annunciator 4-A-5 (RCIC STEAM LINE HI DIFF PRESSURE) was received and conditions are now as follows:
- All Control Rods are fully inserted
- Steam chase temperature is 210° F
- RPV pressure is 1045 psig and slowly rising
- RPV water level is +10 inches and slowly rising Which of the following can be used to control RPV pressure under these conditions?
- a. HPCI
- b. RCIC
- c. Main Steam Line Drains
- d. Main Turbine Bypass Valves
2013 MNGP ILT NRC Written Exam QUESTION # 013 The plant was operating at rated conditions when a severe ATWS condition occurred. The following indications were noted at 0800:
Of the times below, when will the Torus Heat Capacity Limit (Detail M) FIRST be exceeded?
(Assume Torus temperature rate of change, Torus water level and Reactor pressure remain constant. Detail M is on the following page).
- a. 0828
- b. 0831
- c. 0835
- d. 0838
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 014 The plant was operating at rated conditions when an event occurred resulting in a significant rise in Drywell temperature.
Which of the following completes the statement below concerning RPV Fuel Zone Level instrumentation for the given conditions?
Reference Leg Boil-off will result in a (1) indicated level because differential pressure (d/p) across the level detector will be (2) .
(1) (2)
- a. lower lower
- b. higher lower
- c. lower higher
- d. higher higher QUESTION # 015 The plant was operating at rated conditions when a severe accident occurred. HPCI is running in the Level Control Mode when the following timeline of indications occur:
TIME RPV Pressure Torus Water Level HPCI Pump HPCI Turbine Suction Pressure Exhaust pressure 1500 850 psig - 1.0 feet 20 psig 50 psig 1501 650 psig - 2.0 feet 18 psig 60 psig 1502 450 psig - 3.0 feet 16 psig 70 psig 1503 250 psig - 4.0 feet 14 psig 20 psig 1504 50 psig - 5.0 feet 12 psig 15 psig If HPCI fails to automatically trip; at what time above is a procedural OR automatic trip threshold FIRST EXCEEDED that will require operators to manually trip HPCI?
- a. 1501
- b. 1502
- c. 1503
- d. 1504
2013 MNGP ILT NRC Written Exam QUESTION # 016 The plant was operating at rated conditions when a LOCA occurred resulting in the following conditions:
- B RHR is in the Torus cooling Mode
- Torus water temperature is 145°F and rising
- Both Core Spray pumps are running with their inboard injection valves throttled Subsequently, a Loss of ALL Offsite Power occurred, 11 EDG failed to start and reactor water level is -130 inches and stable.
To ensure adequate core cooling AND continue to mitigate the Torus temperature rise; which combination of pumps must be kept in service by the operating crew?
- a. 1 RHR Pump, 1 RHRSW Pump and 1 Core Spray Pump.
- b. 2 RHR Pumps, 1 RHRSW pump, and 1 Core Spray Pump.
- c. 1 RHR Pumps, 2 RHRSW pumps, and 1 Core Spray Pump.
- d. 1 RHR Pump, 2 RHRSW pumps, and NO Core Spray Pump.
QUESTION # 017 The plant was operating at rated conditions when a scram condition occurred and reactor power remained above 3.5%. The ATWS RPV level instruments sensed the following levels for 10 seconds:
- LT-2-3-180A: - 46 inches
- LT-2-3-180B: - 48 inches
- LT-2-3-180C: - 48 inches
- LT-2-3-180D: - 49 inches Which of the following represents the ATWS system response for the above conditions?
2013 MNGP ILT NRC Written Exam QUESTION # 018 The plant is in a refueling outage with spent fuel being moved in the fuel pool. A spent fuel bundle is dropped resulting in the following radiation readings:
- Refueling Floor Radiation Monitors - 60 mrem/hr
- RB Exhaust Plenum Radiation Monitors - 21 mrem/hr
- Control Room Air Intake Radiation Monitors - 0.5 mrem/hr Complete the following statement that describes the CRV/EFT system response to the above conditions and why?
The CRV/EFT system will
- a. remain in Normal Mode because CRV/EFT is NOT affected by the above conditions.
- b. shift to Recirculation Mode isolating outside contaminated air from entering the Control Room atmosphere.
- c. shift to High Radiation Mode providing HVAC and pressurizing the Control Room with filtered air to prevent contamination.
- d. shift to High Radiation Mode isolating the Control Room and requiring the crew to utilize the Control Room Breathing Air Supply.
2013 MNGP ILT NRC Written Exam QUESTION # 019 The plant was operating at rated conditions when a lube oil rupture resulted in a fire in the Turbine Building (TB). The following timeline of events occurred:
Time Event 1300 The plant is manually scrammed 1303 Main condenser vacuum is broken 1305 07-B-11 (VACUUM 20 IN TRIP #1) is received 1310 V-AH-1/2 (TB AIR HANDLING UNITS) automatically start 1312 03-B-55 (REACTOR BLDG EXH PLENUM HI RAD) is received 1315 The Standby Gas Treatment (SBGT) System automatically starts.
Complete the following statement that describes the status of V-AH-1/2 at 1320 and why?
V-AH-1 & 2 will be
- a. tripped because of breaking main condenser vacuum.
- b. tripped because of the SBGT system automatic start signal.
- c. remain running because of the high TB temperature condition.
- d. remain running to prevent an unmonitored release from the TB.
QUESTION # 020 The plant was operating at rated conditions when an electric grid disturbance resulted in a Loss of ALL Offsite Power and ATWS condition. Given the following:
- 11 EDG responded as expected
- 12 EDG failed to start
- 13 DG failed to start Which of the following describes the availability of #11 and #12 SBLC Squib Valves based on available plant electrical power?
- a. ONLY #11 would actuate.
- b. ONLY #12 would actuate.
- c. BOTH #11 and #12 would actuate.
- d. NEITHER #11 nor #12 would actuate.
2013 MNGP ILT NRC Written Exam QUESTION # 021 The plant is operating at rated conditions with Breaker 52-908 (LC-102 TO LC-109 XTIE) open for maintenance.
An inadvertent local manipulation results in Breaker 152-301 (2R SUPPLY TO 13 BUS) being opened.
What effect, if any, will this event have on the Circulating Water (CW) System?
- a. No effect, the 1R Transformer will maintain power to the CW System.
- b. BOTH CW Pumps will be lost resulting in degrading condenser vacuum.
- c. 11 CW Pump is lost but 12 CW Pump will maintain adequate flow through the condenser.
- d. 12 CW Pump will pump water backwards through 11 CW Pump resulting in degrading condenser vacuum.
QUESTION # 022 The plant is operating in Mode 2 during a plant startup/heatup. Given the following:
- RPV pressure is 800 psig
- RPV water level is +35 inches
- The Low Flow FW Regulating valve is controlling RPV level in AUTO Which of the following is correct if an Inadvertent Group 1 isolation occurs?
- b. RPV water level will initially rise due to the reduction in steam flow.
- c. RPV water level will initially lower due to the collapse in core voids.
- d. DFCS will shift to single element control due to the reduction in steam flow.
2013 MNGP ILT NRC Written Exam QUESTION # 023 Given EOP Detail W:
Which of the following temperature limits are based on exceeding environmental qualification limits of accident mitigation equipment in those areas?
- a. 120°F MAX NORMAL
- b. 130°F MAX NORMAL
- c. 130°F MAX SAFE
- d. 212°F MAX SAFE
2013 MNGP ILT NRC Written Exam QUESTION # 024 The plant was operating at rated conditions when an event occurred resulting in the following:
- Drywell pressure is 1.6 psig
- Reactor water level is 7 inches
- Fuel Pool radiation monitors indicate 52 mrem/hr
- Reactor Building vent radiation monitors indicate 21 mrem/hr Which one of the following identifies an expected response to current plant conditions?
- a. RCIC will automatically initiate.
- b. SBGT will automatically initiate.
- c. RWCU will automatically isolate.
- d. LPCI Loop Select Logic will energize.
QUESTION # 025 The plant is operating at rated conditions. A plant worker calls the control room and reports that it is difficult to pull OPEN Door-63 (MAIN ACCESS TO RX BLDG - INNER DOOR). The manometer on C-24 is reading -1.30 inches of H2O.
Which of the following is a correct action to normalize the C-24 manometer reading?
- a. Manually place SBGT in service.
- b. Manually isolate Secondary Containment.
- c. Adjust the variable inlet vanes on V-EF-28 (SPENT FUEL POOL EXHAUST FAN).
- d. Adjust the variable inlet vanes on V-EF-24A or V-EF-24B (RX BLDG EXHAUST FAN).
2013 MNGP ILT NRC Written Exam QUESTION # 026 The plant was at rated conditions when an electrical malfunction occurred resulting in the loss of BOTH ECCS Sump Pumps in the A RHR ROOM. Both pumps have lost the ability to mitigate high water level in the room and have been declared INOPERABLE.
Based on these conditions; which of the following is correct concerning the operability of the ECCS Pumps?
- b. ONLY Division 1 RHR pumps are INOPERABLE.
- c. ONLY Division 1 ECCS pumps are INOPERABLE.
- d. BOTH Division 1 & 2 ECCS pumps are INOPERABLE.
QUESTION # 027 The plant has experienced a severe accident from rated power. Given the following:
- Drywell pressure is 27 psig
- Torus water level is +0.5 feet
- Both SBGT systems are unavailable
- High hydrogen levels exist in the Drywell
- Operators are executing C.5-3504 (PRIMARY CONTAINMENT VENT AND PURGE)
Based on the given conditions; where can the VENT portion(s) of C.5-3504 be performed?
- a. Control Room ONLY
- b. Alternate Shutdown Panel ONLY
- c. Control Room AND Cable Spreading Room
- d. Control Room AND Alternate Shutdown Panel
2013 MNGP ILT NRC Written Exam QUESTION # 028 Which of the following is the MAXIMUM amount of time allowed for the operator to establish ECCS room cooling following a DBA-LOCA?
- a. 2 minutes.
- b. 10 minutes.
- c. 13 minutes.
- d. 16 minutes.
QUESTION # 029 The reactor was operating at 100% power when an event occurred that resulted in the following conditions:
- RPV pressure is 410 psig
- HPCI automatically started
- 11 Recirc system riser pressure sensed by LPCI is 110 psig
- 12 Recirc system riser pressure sensed by LPCI is 410 psig Which of the following is correct concerning the RHR System response to the above conditions AND why?
- a. MO-2012 (RHR DIV 1 LPCI INJ OTBD) received an automatic OPEN signal due to the LPCI Loop selection logic.
- b. MO-2003 (RHR DIV 2 HX BYPASS) received an automatic OPEN signal to allow full LPCI bypass flow around the heat exchanger.
- c. MO-4085A/B (RHR INTERTIE VALVES) received automatic OPEN signals to allow full LPCI injection flow from ALL four RHR Pumps.
- d. MO-4086 (RHR SUCTION EQUALIZING VALVE) received an automatic CLOSE signal to prevent an inadvertent loss of LPCI injection flow due to a broken recirc loop.
2013 MNGP ILT NRC Written Exam QUESTION # 030 The plant is in Mode 4 with the following conditions:
- A RHR is in Shutdown Cooling with 11 RHR pump running
- B RHR is in Torus Cooling with 12 RHR pump running If a leak occurred resulting in RPV water level lowering to +5 inches, what would be the final status of the following RHR system components?
11 RHR Pump 12 RHR Pump MO-2014 MO-2029 (RHR DIV 1 (S/D COOL LPCI INJ INBD) ISO INBD)
- a. RUNNING RUNNING OPEN OPEN
- b. TRIPPED RUNNING OPEN CLOSED
- c. TRIPPED RUNNING CLOSED CLOSED
- d. TRIPPED TRIPPED CLOSED CLOSED QUESTION # 031 The reactor is operating in MODE 2 at approximately 3% Rated Thermal Power (RTP). HPCI is in operation for surveillance testing.
Which of the following is the HIGHEST Torus water temperature that if reached, would still allow the continuance of HPCI testing IAW Technical Specifications?
- a. 89°F
- b. 94°F
- c. 99°F
- d. 109°F
2013 MNGP ILT NRC Written Exam QUESTION # 032 The plant was at rated conditions with 11 Core Spray Pump operating in the Torus Mixing Mode. At 0800 a Loss of Offsite power and a LOCA occurred. Given the following:
- At 0801 Drywell pressure is 2 psig and slowly rising
- At 0802 Essential Bus and EDG status are shown pictorially on the next page If NO operator actions have yet been taken; what will be the status of the Core Spray pumps at 0803 AND what action, if any, should now be taken?
- a. BOTH Core Spray pumps will be running; NO further action required.
- b. ONLY 11 Core Spray pump will be running; place 12 Core Spray Pump in PTL.
- c. ONLY 12 Core Spray pump will be running; place 11 Core Spray Pump in PTL.
- d. NEITHER Core Spray pump will be running; place BOTH Core Spray Pumps in PTL.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 033 During an ATWS condition, the CRS directed initiation of SBLC. The OATC successfully started and began injection with SBLC System 1. The OATC now observes the following:
- The MSIVs are open
- RCIC is injecting at 400 gpm
- RPV water level is -60 inches and intentionally being lowered
- A RWCU pump is running with 160 gpm total system flow Based on the above conditions which of the following actions are required?
- a. RCIC should be terminated.
- b. Manually Initiate SBLC System 2.
- c. Manually perform a Group 1 isolation.
- d. Manually perform a Group 3 isolation.
QUESTION # 034 The plant is in Mode 1 with two Recirc loops in operation. The APRM ODAs currently indicate that Total Recirc flow is 44%.
Which of the following approximates the current STP Scram setpoint?
- a. 78%
- b. 84%
- c. 89%
- d. 95%
2013 MNGP ILT NRC Written Exam QUESTION # 035 The plant is in Mode 2 with a Reactor Startup in progress.
What is the required number of operable IRM Neutron Flux High-High channels for the given conditions?
- a. 1 per TRIP SYSTEM.
- b. 2 per TRIP SYSTEM.
- c. 3 per TRIP SYSTEM.
- d. 4 per TRIP SYSTEM.
QUESTION # 036 A plant startup is in progress with the Mode Switch in STARTUP. Given the following:
- All SRM indicators are on-scale with detectors partially withdrawn
- All IRMs are on Range 1 reading between 10-50 on the 125 scale.
An event occurs that results in the following C-05 indication:
Which one of the following will cause the above conditions?
- a. An SRM reading lowers to 90 cps.
- b. An SRM reading rises to 60,000 cps.
- c. An SRM period shortens to 10 seconds.
- d. An IRM reading lowers to 4 on the 125 scale.
2013 MNGP ILT NRC Written Exam QUESTION # 037 The plant is operating at rated conditions when a RPS MG Set malfunction results in the following:
Which of the following PRNM components, if any, will lose power with the above condition?
- a. RBM A.
- b. APRMs 1 & 3.
- c. 2 of 4 Voters - 1 & 3.
- d. None, they are all auctioneered with RPS Bus B.
QUESTION # 038 The plant was operating at rated conditions with HPCI out of service when a Group I Isolation Occurred. Given the following:
- The RCIC pump flow signal was lost resulting in a constant ZERO gpm flow signal being sent to the flow controller.
Complete the following statement describing the RCIC system response if no operator action is taken?
The RCIC turbine will...
- a. remain at minimum speed.
- b. trip on high RPV water level.
- c. trip as soon as the signal is lost.
- d. trip on overspeed and remain shutdown.
2013 MNGP ILT NRC Written Exam QUESTION # 039 The plant was operating at rated conditions when the following events occurred:
0800:00 A LOCA & Loss of ALL Offsite Power occurs 0800:10 BOTH Essential AC Busses are re-energized 0800:15 3-A-41 (AC INTERLOCK) is received 0800:45 3-A-38 (REACTOR LOW LOW LEVEL) is received 0801:15 8-B-18 (NO. 15 4160V BUS LOCKOUT) is received 0802:00 3-A-38 (REACTOR LOW LOW LEVEL) clears.
Based on the above timeline, which one of the following describes the expected response of the ADS valves, and why?
- c. The ADS valves will REMAIN CLOSED due to the receipt of a 15 Bus LOCKOUT.
QUESTION # 040 During a surveillance test, LS-2-3-657C & D trip settings are found to be out of tolerance.
Given NH-36242 (P&ID VESSEL INSTRUMENTATION NUCLEAR BOILER SYSTEM), which of the following trip logics will be affected by the out of tolerance switches?
- a. Reactor Scram logic
- b. Group 1 Isolation logic
- c. Group 2 Isolation logic
- d. ATWS Recirc Pump trip logic
2013 MNGP ILT NRC Written Exam QUESTION # 041 The plant was at rated conditions when the following annunciator was received:
The Out Plant Operator reports that Alternate N2 Train B pressure is 195 psig and lowering.
Which of the following combinations of Safety Relief Valves (SRVs) will be affected by current plant conditions?
- a. A, B & G
- b. A, B & E
- c. C, H & F
- d. C, D & H
2013 MNGP ILT NRC Written Exam QUESTION # 042 The plant is operating at rated conditions with the following level inputs to the Digital Feedwater Level Control System (DFLC):
- LI-2-3-85A (REACTOR VESSEL WATER LEVEL) reads 34 inches
- LI-6-94A (FW REACTOR VESSEL A LEVEL CONTROL) reads 35 inches
- LI-6-94B (FW REACTOR VESSEL B LEVEL CONTROL) reads 36 inches Given the DFLC mode of operation in the picture, what will be the final status of DFLC if LI 94A instantaneously lowers to 23 inches due to a leak in its variable leg sensing line? (Assume the leak doesnt affect the indication of LI-2-3-85A or LI-6-94B.)
- a. DFLC will shift to 1EL and use LI-6-94B as its level input.
- b. DFLC will shift to 1EL and use LI-2-3-85A as its level input.
- c. DFLC will remain in 3EL and automatically use LI-6-94B as its level input.
- d. DFLC will remain in 3EL and automatically use LI-2-3-85A as its level input.
2013 MNGP ILT NRC Written Exam QUESTION # 043 The plant was at rated conditions when a valid SBGT initiation occurred. BOTH trains of SBGT have initiated. The following annunciators have been received on Panel C-24B for SBGT Train "B":
- 24-B-3A (NO DT)
With BOTH trains of SBGT running, which one of the following correctly states:
- 1) Whether the above annunciators are Anticipated or NOT Anticipated and
- 2) What procedural action would be taken to clear the alarm?
- a. 1) Anticipated.
- 2) Lower SBGT train "A" flow.
- b. 1) NOT Anticipated.
- 2) Lower SBGT train "A" flow.
- c. 1) Anticipated.
- 2) Raise SBGT train "B" flow.
- d. 1) NOT Anticipated.
- 2) Raise SBGT train "B" flow.
2013 MNGP ILT NRC Written Exam QUESTION # 044 The plant is at normal rated conditions when the following occurs on 15 and 16 Bus:
TIME 15 AND 16 BUS VOLTAGE 00:00:00 4300 volts 00:00:01 3950 volts 00:00:02 3913 volts 00:00:03 3009 volts 00:00:04 3011 volts 00:00:05 3015 volts 00:00:06 3010 volts 00:00:07 3012 volts 00:00:08 0 volts 00:00:11 0 volts 00:00:13 4260 volts Based on the above timeline, which of the following is correct?
- a. At 00:00:02 the EDGs automatically started.
- b. At 00:00:13 the EDGs loaded onto their respective bus.
- c. At 00:00:08 the degraded essential bus voltage logic is blocked and the loss of essential bus voltage logic is actuated.
- d. At 00:00:11 the degraded essential bus voltage logic trips OPEN 152-308 (13/15 Bus Tie) and 152-408 (14/16 Bus Tie).
2013 MNGP ILT NRC Written Exam QUESTION # 045 The plant was operating at rated conditions when 8-A-24 (DIV 1 INVERTER Y71 TROUBLE) was received in the Control Room. It was determined that Y-71 (DIVISION 1 UPS) experienced a low output voltage condition. Given the following:
- 8-A-24 (DIV 1 INVERTER Y71 TROUBLE) has RESET
- Y-71 (DIVISION 1 UPS) status is now as follows:
Based on the conditions above; which of the following is correct?
- a. Y71 is currently operating in the ZIP MODE.
- b. Y71 was manually transferred to the ALTERNATE source
- c. Y71 has automatically transferred to the ALTERNATE source.
- d. Y71 automatically transferred to the ALTERNATE and back to the PREFERRED source.
QUESTION # 046 A General Precaution in B.08.07-05 (HEATING AND VENTILATION) states that V-EF-34A or V-EF-34B (BATTERY ROOM EXHAUST FANS) should be operating at all times.
Complete the following statement that describes the reason for this precaution?
Exhaust fan operation
- a. prevents the buildup of hydrogen gas that is generated as the batteries are charged.
- b. maintains a flow of outside air across the Radiation Monitors for the CRV-EFT system.
- c. ensures Battery Room temperature is maintained above 50°F during the winter months.
- d. ensures Battery Rooms are maintained at -0.25 d/p for secondary containment integrity.
2013 MNGP ILT NRC Written Exam QUESTION # 047 With a complete loss of AC power to the 480 Volt UPS Y-91, how long will the No. 17 Battery maintain power to ALL of its connected loads?
- a. 10 Minutes.
- b. 30 Minutes.
- c. 60 Minutes.
- d. 90 Minutes.
QUESTION # 048 The plant is operating at rated conditions when a small fire starts in the #11 EDG Room.
Complete the following statement that describes the response of the EDG Room Preaction Sprinkler System?
If a thermal electric detector is activated
- a. the Wet Pipe system will spray when the fusible link melts.
- b. spray will NOT occur until a second EDG Room detector is activated.
- c. the sprinkler valve opens, immediately spraying water from the spray heads in the #11 EDG Room.
- d. the sprinkler valve opens admitting water to the sprinkler piping but doesnt spray until the fusible link melts.
2013 MNGP ILT NRC Written Exam QUESTION # 049 The plant is at rated conditions with the 1AR Transformer ISOLATED for modifications.
A LONOP then occurs coincident with an ECCS initiation signal.
Complete the following statement for the above conditions.
Nominally, #13 and #14 RHR Pumps will auto start _________ after the LONOP.
- a. 10 seconds
- b. 15 seconds
- c. 20 seconds
- d. 25 seconds QUESTION # 050 The plant was operating at rated conditions when a Loss of ALL Offsite Power occurred. Given the following conditions:
- 11 EDG Failed to start
- 12 EDG started and properly loaded
- 13 Diesel Generator started and properly loaded For the above conditions, which of the following is the expected power availability to the Instrument Air Compressors (A/C)?
POWER to 15 A/C POWER to 16 A/C POWER to 17 A/C
- a. UNAVAILABLE UNAVAILABLE UNAVAILABLE
- b. AVAILABLE UNAVAILABLE AVAILABLE
- c. AVAILABLE AVAILABLE UNAVAILABLE
- d. UNAVAILABLE AVAILABLE AVAILABLE
2013 MNGP ILT NRC Written Exam QUESTION # 051 The plant was operating at rated conditions when the following occurred:
- MSIV Main (Pallet) Air pressure indicates 165 psig and lowering With NO operator action, what effect will this have on the OUTBOARD MSIVs, and why?
- a. They will DRIFT CLOSED because outboard actuating air will be lost.
- b. They will DRIFT CLOSED because outboard solenoid pilot air will be lost.
- c. They will REMAIN OPEN because nitrogen supplies the actuating and pilot air.
- d. They will REMAIN OPEN because air intensifiers will automatically maintain air pressure.
2013 MNGP ILT NRC Written Exam QUESTION # 052 The plant startup is in progress with RPV level being controlled by RWCU Dump Flow to the Main Condenser. An RBCCW transient occurs resulting in the following conditions:
Based ONLY on the given conditions above, what would be the expected final positions of the RWCU valves listed below?
MO-2397 MO-2398 MO-2404 (INLET INBOARD) (INLET OUTBOARD) (DUMP TO HOTWELL)
- a. OPEN OPEN OPEN
- b. OPEN OPEN CLOSED
- c. CLOSED CLOSED OPEN
- d. CLOSED CLOSED CLOSED
2013 MNGP ILT NRC Written Exam QUESTION # 053 The plant was operating at rated conditions when a Loss of ALL Offsite Power and LOCA occurred.
Which of the following describes when the EDG-ESW pumps will auto start?
- a. When the EDGs reach 125 rpm.
- b. When Drywell pressure reaches 1.84 psig.
- c. When the EDG output breakers close onto their bus.
- d. When Service Water header pressure lowers to 40 psig.
QUESTION # 054 Complete the following statement that describes where displaced reactor water is sent during a control rod INSERTION:
Displaced reactor water is sent from the CRDM over-piston area
- a. back to the Reactor.
- b. to the Cooling Water header.
- c. back to the Drive water header.
- d. to the RB Floor and Equipment Drain Tanks.
2013 MNGP ILT NRC Written Exam QUESTION # 055 A reactor startup is in progress with the plant in Mode 2. Given the following:
- Control Rod (CR) 22-31 has been single-notch withdrawn to position 10
- The OATC attempts to withdraw CR 22-31 to its withdraw limit, position 12
- CR 22-31 is double-notched to position 14 causing a RWM Withdraw Error Which of the following identifies the RMCS control rod movement, if any, which will be allowed for the above conditions?
- a. The INSERTION of CR 22-31 only.
- b. The INSERTION of any withdrawn control rod.
- c. The INSERTION and WITHDRAWAL of CR 22-31 only.
- d. None, the RWM must be bypassed to allow control rod movement.
QUESTION # 056 The reactor is operating at rated conditions. A tachometer failure on the 11 Recirc MG Set results in the speed signal failing high.
Which of the following describes the Recirc Flow Control response to this failure?
- a. NO effect because the MG Set speed signal is for indication ONLY.
- b. A Scoop Tube Lock will occur LOCKING the actuator in its current position.
- d. A Drive Motor breaker TRIP will occur resulting in the LOSS of the 11 Recirc MG Set.
2013 MNGP ILT NRC Written Exam QUESTION # 057 The plant is in Mode 1 with control rod manipulations in progress. Control rod 06-31 is being repositioned when annunciator 5-A-11 (ROD OVERTRAVEL) is received.
Which one of the following would you expect to see on the full core display window for control rod 06-31?
- a. Green 00
- b. Blank indication
- c. Red double dashes
- d. Green double dashes QUESTION # 058 The plant is operating at rated conditions. Traversing In-core Probe (TIP) scans are in progress when a PCIS malfunction results in an inadvertent Group 2 isolation.
Which of the following is correct if the TIP detector didnt automatically retract from the core with the above conditions?
- a. The TIP Shear Valve must be manually actuated from panel C-13.
- b. The TIP Ball Valve will automatically close from the Group 2 isolation.
- c. The TIP Shear Valve will automatically actuate from the Group 2 isolation.
- d. The TIP detector must be manually retracted THEN the Ball Valve will automatically close.
2013 MNGP ILT NRC Written Exam QUESTION # 059 The plant was operating at rated conditions when a LOCA occurred in the Drywell (DW). Given the following:
- DW pressure is 11 psig and slowly lowering
- RPV pressure is 440 psig and slowly lowering
- RPV water level is -184 inches and slowly lowering
- B RHR System status is shown on the following page Based on the given conditions, complete the following statement concerning the Torus Spray valves?
The Torus Spray valves
- a. WILL automatically close when DW pressure is < 1.5 psig.
- b. WILL automatically close when RPV pressure is < 420 psig.
- c. SHOULD have automatically closed when RPV water level went < -174.
- d. SHOULD have automatically closed when RPV pressure went < 460 psig.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 060 Complete the following statement concerning system component temperatures on a loss of RBCCW from rated power?
The (1) system must be shutdown prior to the outlet temperature of the
_______(2) _exceeding 120°F to protect downstream piping from over temperature.
(1) (2)
- b. FPCC Fuel Pool Cooling Heat Exchanger
- c. Recirc Reactor Recirc Pump Seal Coolers
- d. RWCU Non-regenerative Heat Exchanger QUESTION # 061 The plant was operating at rated conditions when a station power transfer occurred from the 2R to the 1R transformer. A reactor scram was inserted and all systems responded as expected.
Which one of the following actions must be taken next to control Reactor Feedwater IAW procedure C.4-A (REACTOR SCRAM)?
- a. Prepare and restart #11 Reactor Feed Pump.
- b. Prepare and restart #12 Reactor Feed Pump.
- d. Control RPV water level with the Low Flow Reg valve.
2013 MNGP ILT NRC Written Exam QUESTION # 062 The plant is operating at rated conditions. Given the following:
- At 1800 RM-17-150A (OG Pretreatment Radiation Monitor) failed downscale
- At 1815 RM-17-150B (OG Pretreatment Radiation Monitor) failed upscale Which of the following, if any, will occur for the above conditions?
- a. At 1845, main condenser vacuum will begin to degrade.
- b. At 1830, AO-7557A/B (A & B RECMBINER CDSR OUT) will close.
- c. At 1830, AO-1085A/B (11 & 12 A/E 2ND STAGE SUCTION ISOLATIONS) will close.
- d. None, the trip logic requires 2 upscale OR 2 downscale trips to initiate an Off-Gas isolation.
QUESTION # 063 The plant was operating at rated conditions with an outside air temperature of 95°F. A loss of MCC-111 occurred resulting in a PCIS Group I Isolation.
Based on the loss of MCC-111, complete the following statement that describes a valid reason for the Group 1 Isolation?
A loss of
- a. RPS logic power directly caused this isolation.
- b. PCIS logic power directly caused this isolation.
- c. Drywell ventilation caused this isolation on high temperature.
- d. Reactor Building ventilation caused this isolation on high temperature
2013 MNGP ILT NRC Written Exam QUESTION # 064 What is the MINIMUM emergency event classification level in which the Emergency Response Organization (ERO) is required to be fully activated?
- a. NUE
- b. ALERT
- c. SITE AREA EMERGENCY
- d. GENERAL EMERGENCY QUESTION # 065 Complete the following statement concerning the IRM Detectors.
When FULLY INSERTED, IRM detectors are
- a. IN direct contact with water AND 24 inches ABOVE core centerline.
- b. IN direct contact with water AND 24 inches BELOW core centerline.
- c. NOT in direct contact with water AND 24 inches ABOVE core centerline.
- d. NOT in direct contact with water AND 24 inches BELOW core centerline.
QUESTION # 066 Which of the following will require a plant page announcement prior to a pre-planned start?
- a. Electric Fire Pump
- b. Mechanical Vacuum Pump
- c. Main Turbine Aux Oil Pump
- d. Emergency Bearing Oil Pump
2013 MNGP ILT NRC Written Exam QUESTION # 067 How and where can the deluges be initiated for the 1R, 2R and Main Transformers?
- a. A control switch on C-300 (Zonalert Control Room Panel).
- b. A deluge valve in the Northwest corner of the12 EDG Room.
- c. A deluge valve in the Southeast corner of the East Electrical Equipment Room.
- d. Arming collar pushbuttons on C-08 (Control Room Electrical Distribution Panel).
QUESTION # 068 Given the following timeline of Upstream River and Discharge Canal temperatures:
TIME UPSTREAM RIVER (°F) DISCHARGE CANAL (°F) 1800 53 84 1900 52 78 2000 51 72 2100 50 70 2200 49 69 2300 48 63 0000 48 62 0100 49 68 0200 49 69 0300 50 72 During which of the following times has a Discharge Canal temperature Rate of Change limit been exceeded?
- a. 1800-1900 and 1900-2000 ONLY
- b. 1800-1900 and 1900-2000 and 2200-2300
- c. 2200-2300 ONLY
- d. 0000-0100 ONLY
2013 MNGP ILT NRC Written Exam QUESTION # 069 A plant startup is in progress with reactor power at 18%.
Complete the following statement regarding transfer from the FW LOW FLOW REG VALVE to the A MAIN FW REG VALVE.
Caution must be exercised during the manual operation of these valve controllers as
- a. the controller pushbuttons are two speed in the OPEN direction ONLY.
- b. the controller pushbuttons are two speed in the CLOSE direction ONLY.
- c. the controller pushbuttons are two speed in both the OPEN and CLOSE direction.
- d. the longer each pushbutton is held in the OPEN or CLOSE direction, the faster the signal changes.
QUESTION # 070 A plant startup is in progress with RPV pressure at 685 psig and both Recirc loops in service.
Which of the following would be a Safety Limit violation with the above conditions?
- a. MCPR lowered to 1.35
- b. Reactor power rose to 27%
- c. Rated core flow lowered to 8%
- d. RPV water level lowered to -50 inches
2013 MNGP ILT NRC Written Exam QUESTION # 071 While the plant is operating in Mode 1 a pressure regulator failure causes reactor pressure to rise and stabilize at 1030 psig.
Which of the following represents the Technical Specifications required time allowed to restore pressure to < 1025.3 psig?
- a. 15 minutes
- b. 20 minutes
- c. 30 minutes
- d. 60 minutes QUESTION # 072 During an abnormal evolution an operator receives a dose of 11 REM to the eye lenses. CRS approval was given to the operator to receive this dose.
In accordance with the 10CFR20 Federal Dose Limits and AWI 08.04.01 RADIATION PROTECTION PLAN, which, if any, dose limits have been exceeded?
- a. NEITHER limit has been exceeded
- b. ONLY the AWI limit has been exceeded
- c. ONLY the10CFR limit has been exceeded
- d. BOTH the 10CFR and AWI limits have been exceeded
2013 MNGP ILT NRC Written Exam QUESTION # 073 The following coolers are supplied by the Reactor Building (RB) Service Water header:
- 1. V-AC-6 (RCIC ROOM COOLER)
- 2. V-AC-7A/B (CRD ROOM COOLERS)
- 3. V-AC-8A/B (HPCI ROOM COOLERS)
- 4. V-AC-9 (RB 985 ELEVATION COOLER)
Which of the coolers listed above are monitored for Service Water outlet radiation prior to leaving the Reactor Building?
- a. 1 and 3 ONLY
- b. 1, 2 and 3 ONLY
- c. 2, 3 and 4 ONLY
QUESTION # 074 The plant is operating in Mode 1 on the weekend with ONE duty crew on-site. The control room receives a report of a fire in Warehouse 6.
Based on the conditions above, what action is required to be taken by the Fire Brigade IAW the A.3 (FIRE FIGHTING) procedures?
- a. All fire brigade members must report to Warehouse 6 and attempt to contain and/or extinguish the fire.
- b. Notify the Monticello Fire Department and provide them with isolation and direction to contain and/or extinguish the fire.
- c. Notify Security to direct fire fighting activities for the Monticello Fire Department because the fire is outside the Protected Area.
- d. The Duty Chemist and RP Technician must attempt to contain and/or extinguish the fire until additional fire brigade members report on-site.
2013 MNGP ILT NRC Written Exam QUESTION # 075 The plant is operating at rated conditions when a fire occurs in the control room requiring IMMEDIATE control room evacuation. Given the following conditions:
- 15 minutes later annunciator 292-A-3 (Loss of Voltage Bus No. 16) alarms.
- ALL appropriate C.4-C actions are taken AND Bus 16 voltage is restored from 1AR.
Which one of the following identifies automatic control features, if any, that have been DISABLED?
- d. None, ALL automatic control features associated with a loss of voltage are enabled.
QUESTION # 076 The plant is operating at rated conditions when an electrical transient occurs. While the panel operators are investigating the cause, you observe the following indications on the C-03 Mimic Bus (See Picture on following page).
Based on the indications, determine the extent of the electrical transient AND what Technical Specification Action is required as the CRS?
Direct the isolation of ONE penetration flow path within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
Direct the Isolation of ONE penetration flow path within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
Direct the Isolation of ONE penetration flow path within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
Direct the Isolation of THREE penetration flow paths within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 077 The plant is operating at rated conditions with 345KV Bus 1 ISOLATED for maintenance. Given the Subyard one-line diagram:
If a Main Generator LOCKOUT occurs with the above conditions, which of the following procedure(s) must be directed by the CRS, and why?
- a. C.4-B.09.06.A (LOSS OF BUS 12) ONLY, because a station power transfer has occurred.
- b. C.4-A (REACTOR SCRAM) ONLY, because station power was originally being supplied from the 1R transformer.
- c. C.4-A (REACTOR SCRAM) ONLY, because station power was originally being supplied from the 2R transformer.
- d. C.4-A (REACTOR SCRAM) AND C.4-B.09.06.A (LOSS OF BUS 12) because a station power transfer and a reactor scram have occurred.
2013 MNGP ILT NRC Written Exam QUESTION # 078 The plant is operating at rated conditions. A Loss of Instrument Air occurs resulting in the receipt of alarm 5-B-22 (SCRAM PILOT AIR HEADER HI/LO PRESS).
Based on the conditions above; which procedure must be entered/directed, and why?
- a. C.4-A (REACTOR SCRAM); the backup scram valves will open at this pressure and an automatic reactor scram will occur.
- b. C.4-B.01.03.C (CONTROL ROD DRIFTING); the CRD flow control valve will fail OPEN causing multiple control rods to drift in.
- c. C.5-2007 (FAILURE TO SCRAM); the potential exist for an ATWS condition due to a hydraulic lock in the Scram Discharge Volume.
- d. C.4-K (IMMEDIATE REACTOR SHUTDOWN); random control rods could begin inserting into the core resulting in uneven flux distribution.
QUESTION # 079 A normal plant cooldown is in progress with the following conditions:
- Rx Mode Switch in SHUTDOWN
- Reactor coolant temperature is 180°F
- Secondary Containment IS established A loss of all Shutdown Cooling occurs resulting in the following heatup:
TIME Reactor Coolant Temperature 00:00:00 180°F 00:15:00 210°F 00:30:00 225°F 00:45:00 235°F 01:00:00 245°F Based on the indications above, which of the following is a correct action?
- a. Declare a NUE
- b. Declare an ALERT
- c. Enter LCO 3.4.9 Condition A
- d. Enter LCO 3.4.9 Condition C
2013 MNGP ILT NRC Written Exam QUESTION # 080 Given the following sets of parameters:
Case1) Torus Water Temperature, stable at 170°F RPV Pressure, stable at 700 psig Drywell Pressure, stable at 20 psig Torus Water Level, stable at -3 ft Case 2) Torus Water Temperature, stable at 160°F RPV Pressure, stable at 800 psig Drywell Pressure, stable at 20 psig Torus Water Level, stable at -2 ft Assuming actions to restore and maintain the above parameters have NOT been successful; determine if an Emergency Depressurization (BLOWDOWN) is required/not required to be directed by the CRS for each of these cases?
- a. Case 1) BLOWDOWN NOT required.
Case 2) BLOWDOWN NOT required.
- b. Case 1) BLOWDOWN NOT required.
Case 2) BLOWDOWN required.
- c. Case 1) BLOWDOWN required.
Case 2) BLOWDOWN NOT required.
- d. Case 1) BLOWDOWN required.
Case 2) BLOWDOWN required.
2013 MNGP ILT NRC Written Exam QUESTION # 081 The plant was operating at rated conditions when a Group 1 Isolation and subsequent reactor scram occurred. Reactor power immediately following the scram was 7% but the following conditions now exist:
- RPV level is +20 inches and stable
- RPV pressure is 1030 psig and rising
- Reactor period is -80 seconds and steady
- Reactor power is now on IRM Range 5 and lowering
- Standby Liquid Control (boron) has NOT been injected
- Five (5) control rods are at position 08, all other rods have fully inserted Based on the conditions above, which of the following procedures must be selected/directed by the CRS and why?
- a. C.4-A (REACTOR SCRAM) to insert the remaining control rods.
- b. C.5-3101 (ALTERNATE ROD INSERTION) to insert the remaining control rods.
- c. C.5-3205 (TERMINATE AND PREVENT) to eliminate injection from Condensate &
- d. C.5-3302 (ALTERNATE PRESSURE CONTROL) to stabilize RPV pressure below 1056 psig using the main turbine bypass valves.
2013 MNGP ILT NRC Written Exam QUESTION # 082 The plant was operating at rated conditions when the control room receives a report of a fire in the Heating Boiler Room. Given the following:
00:00:00 Fire reported to control room 00:08:00 Fire Brigade began attacking the fire 00:16:00 Control Room notified the fire is extinguished Given the information above, complete the statement below by determining if an Emergency Plan classification is required? If SO, who assumes the responsibilities of the Shift Emergency Communicator (SEC)? If NOT, why?
Emergency Plan classification
- a. is required. Shift Security Supervisor
- b. is required. Shift Radiation Protection Technician
- c. is NOT required. The fire was only fought for 8 minutes.
- d. is NOT required. The Heating Boiler is not vital equipment.
2013 MNGP ILT NRC Written Exam QUESTION # 083 The plant is in Mode 2 with a reactor startup in progress. RPV pressure is 900 psig when a LOCA occurs resulting in the following:
- Drywell Pressure is 5.0 psig and rising
- Drywell Temperature is 282°F and rising
- All available drywell cooling is in service As the CRS, can Drywell sprays be directed at this time AND why?
- a. Yes; the structural integrity of the drywell is being challenged.
- b. No; Drywell Sprays cannot be initiated when operating in Mode 2.
- c. No; Torus Sprays are always placed in service prior to Drywell sprays.
- d. No; evaporative cooling may cause containment failure or Drywell de-inertion.
QUESTION # 084 The plant was operating at rated conditions when a steam leak occurred in the Steam Chase.
Given the following conditions:
- Steam Chase blowout panels ruptured on high D/P
- Turbine Building ventilation has been restarted
- The steam leak is unisolable Which of the following stable RB Vent Effluent readings would be the HIGHEST allowed that will NOT require the CRS to direct C.5-2002 (EMERGENCY DEPRESSURIZATION)?
- a. 7 x 105 uCi/sec
- b. 7 x 106 uCi/sec
- c. 7 x 107 uCi/sec
- d. 7 x 108 uCi/sec
2013 MNGP ILT NRC Written Exam QUESTION # 085 The plant was operating at rated conditions when a DBA LOCA occurred. All systems responded as expected and the following conditions now exist:
- RPV water level is +20 and stable
- Drywell pressure is 18 psig and stable
- Drywell temperature is 245°F and stable Based on the conditions above, which of the following procedures must be directed by the CRS in order to place the H2/O2 analyzers in service, AND why?
- 1. C.4-B.04.01.B (PRIMARY CONTAINMENT GROUP 2 ISOLATION)
- 2. C.5-3501 (H2/O2 ANALYZER OPERATION)
- 3. C.5-3502 (CONTAINMENT SPRAY)
- a. 2 ONLY This procedure will reset the Group 2 isolation for the H2/O2 Analyzer valves.
- b. 1 & 2 ONLY The entire Group 2 isolation must be reset to allow for H2/O2 Analyzer operation.
- c. 2 & 3 ONLY Drywell temperature must be lowered prior to placing the H2/O2 analyzers in service.
- d. 1, 2 & 3 The entire Group 2 isolation must be reset and drywell temperature must be lowered for H2/O2 Analyzer operation.
2013 MNGP ILT NRC Written Exam QUESTION # 086 The plant is at rated conditions with surveillance test 0255-03-IA-1-1 (CORE SPRAY LOOP A QUARTERLY PUMP AND VALVE TESTS) in progress. During the performance of STEP H.20, the BOP operator records an opening time for MO-1751 of 11.0 seconds. As the CRS, you direct the valve to be immediately retested.
Which of the following completes the statement below describing the requirements to maintain compliance with the Inservice Testing Program?
If the retest opening time is _____(1)_____ , then the CRS must _____(2)_____
- a. (1) 11.0 seconds (2) declare the valve INOPERABLE because the Limiting Stroke time has been exceeded.
- b. (1) 13.0 seconds (2) declare the valve OPERABLE because the average of the two stroke times is less than the Limiting Stroke Time.
c.. (1) 9.5 seconds (2) declare the valve INOPERABLE because the average of the two stroke times exceeds the IST acceptance band.
- d. (1) 10.5 seconds (2) ensure the data is analyzed within 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> to verify that the new stroke time represents acceptable operation OR the valve must be declared INOPERABLE.
QUESTION # 087 Complete the following statement that correctly describes the protection provided by the APRM HI Rod Block:
The APRM HI Rod Block setting will
- a. ensure PCIUTL is not exceeded.
- b. preclude a MCPR safety limit violation.
- c. ensure Peak Fuel Enthalpy is not exceeded.
- d. minimize the consequences of a Control Rod Drop Accident.
2013 MNGP ILT NRC Written Exam QUESTION # 088 The plant was operating at rated conditions when an inadvertent ADS initiation signal was received. The BOP operator placed the ADS Inhibit Switches to INHIBIT but the ADS SRVs still OPENED after 107 seconds. Given the following:
- C.4-B.03.03.A (STUCK OPEN RELIEF VALVE) has been completed
- Reactor power is currently stable at 60%
Which of the following is a correct Technical Specification ACTION to take?
- a. Enter LCO 3.0.3 IMMEDIATELY.
- b. Place the plant in Mode 3 within 12 HOURS.
- c. Place the plant in Mode 3 within 13 HOURS.
2013 MNGP ILT NRC Written Exam QUESTION # 089 The plant was operating in MODE 1 when a common mode failure was discovered to exist with the safety function on a number of Safety/Relief Valves. An extent of condition is being performed.
At this time; what is the minimum number of inoperable SRVs that will require a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Non-Emergency NRC notification?
- a. 2 of 8
- b. 3 of 8
- c. 4 of 8
- d. 5 of 8 QUESTION # 090 The plant is at rated conditions when several valid annunciators are received including the following:
- 3-A-49 (SBGT ANNUNCIATOR)
- 8-A-4 (Y-10/Y-70 INSTR AC LOSS OF VOLTAGE)
- 8-A-24 (DIV 1INVERTER Y71 TROUBLE)
Based on the given conditions, which one of the following procedures, if any, must be directed to mitigate the conditions above?
- a. C.4-B.05.07.A (LOSS OF REACTOR WATER LEVEL CONTROL)
- b. C.4-B.04.01.A (PRIMARY CONTAINMENT ISOLATION - GROUP 1)
- c. C.4-B.04.01.B (PRIMARY CONTAINMENT ISOLATION - GROUP 2)
- d. NONE would be directed without knowing what specific circuit was lost.
2013 MNGP ILT NRC Written Exam QUESTION # 091 The plant was operating at 95% with a down power in progress. While adjusting #11 Recirc Pump, the speed control failed causing a continuous lowering of pump speed. The #11 Recirc Pump scoop tube was locked and the following conditions exist:
- Reactor power is 90%
- A jet pump loop flow is 20 Mlb/hr
- B jet pump loop flow is 24 Mlb/hr Which of the following Technical Specification actions, if any, are correct for the above conditions and why?
- a. Be in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to satisfy 2/3 core height reflood analyses.
- b. Match Recirc loop jet pump flows within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to satisfy LOCA analyses.
- c. No action required as the jet pump loop flows are currently considered matched.
- d. No action required provided the limits of LCO 3.2.1, 3.2.2 and 3.3.1.1 are applied.
QUESTION # 092 The plant is at rated conditions with MO-2021 (RHR DIV 2 DRYWELL SPRAY OTBD) closed and its breaker open for maintenance activities. While conducting rounds, the Reactor Building Operator reports the following:
- PI-10-115B (B RHR HX DISHCHARGE PRESSURE) indicates 49 psig Which of the following Tech Spec REQUIRED ACTIONS and COMPLETION TIMES are required for the above conditions?
- c. Restore a RHR drywell spray subsystem to OPERABLE within 7 days AND Restore low pressure ECCS injection/spray subsystem to OPERABLE within 7 days.
- d. Restore a RHR drywell spray subsystem to OPERABLE within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> AND Restore low pressure ECCS injection/spray subsystem to OPERABLE within 7 days.
2013 MNGP ILT NRC Written Exam QUESTION # 093 The plant was operating at rated conditions when a transient occurred resulting in a reactor scram. All control rods fully inserted and conditions are now as follows:
- The MSIVs are OPEN
- SRVs CANNOT be opened
- Drywell pressure is 1.0 psig and slowly rising
- RPV pressure is 400 psig and lowering slowly
- It has been determined that RPV water level is UNKNOWN
- ONLY Division 1 RHR and Core Spray pumps are available for injection Complete the following statement based on the conditions above.
The CRS will / will NOT direct the MSIVs to be CLOSED because
- a. will; the RPV cooldown rate is being exceeded.
- b. will NOT; a flowpath must be maintained for minimum steam cooling.
- c. will; the pipe hangers are NOT designed for excessive water weight loading.
- d. will NOT; this will help depressurize the reactor vessel and raise injection flow.
QUESTION # 094 A reactor startup is in progress with the following conditions:
Time THERMAL POWER Steam Flow Chloride ion concentration RCS Conductivity
(%) (lbm/hr) (ppm) (mho/cm) 0100 0 0 0.0 1.0 0200 .30 20,000 0.1 1.2 0300 .75 85,000 0.1 5.2 0400 1.0 106,000 0.3 9.2 0500 2.0 250,000 0.3 12.5 Of the times below; when is the earliest that TLCO 3.0.3 ACTIONS are REQUIRED?
- a. 0200
- b. 0300
- c. 0400
- d. 0500
2013 MNGP ILT NRC Written Exam QUESTION # 095 The plant was operating at rated conditions when an event occurred resulting in the following plant computer readings:
Based on the given conditions, which one of the following parts of C.5-3203 must be directed by the CRS for Alternate RPV Injection?
- b. PART B - CONDENSATE SERVICE TO PRESSURIZATION STATION
- c. PART C - SERVICE WATER CROSS-TIE TO CONDENSATE/FEEDWATER
- d. PART D - FIRE WATER CROSS-TIE TO LPCI
2013 MNGP ILT NRC Written Exam QUESTION # 096 The plant has been operating at rated conditions for several months.
On August 6th at 1300 it is discovered that SR 3.1.3.2 had not been performed on control rod 26-19 since June 28th at 0800. Given the following:
- Control rod 26-19 is at position 12
- SR 3.0.3 is provided on the following page
- SR 3.1.3.2 has a FREQUENCY of 31 Days
- An assessment has been performed and the risk can be managed Determine if an extension is allowed, if so, when is the latest the surveillance can be completed and remain in compliance with Technical Specifications?
- a. Perform the surveillance prior to August 7th at 0200.
- b. Perform the surveillance prior to August 7th at 1300.
- c. Perform the surveillance prior to September 6th at 1300.
- d. An extension IS NOT allowed, immediately enter the ACTIONS of TS 3.1.3.
2013 MNGP ILT NRC Written Exam SR 3.0.3 If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery, up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the risk impact shall be managed.
If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
2013 MNGP ILT NRC Written Exam QUESTION # 097 Which of the following activities REQUIRE the use of the Bypass Control Process?
- a. Modifying a Control Room annunciator circuit by LIFTING an electrical lead.
- b. Installing a TEMPORARY hose to drain the Service Water System to the floor drains.
- c. Opening C-31 INSTALLED Knife Switch 16 with plant power fed from the 1R Transformer.
- d. Installing new Condensate Demineralizers that have NOT yet been RELEASED to the plant.
QUESTION # 098 The plant was at rated conditions when an event occurred. Twenty (20) minutes later the following conditions exist:
- A General Emergency has been declared
- 5790-401-01 (EMERGENCY EXPOSURE AUTHORIZATION FORM) has been initiated for Joe Radworker and is ready for your review
- Joe is assigned to manipulate several valves for protection of valuable property
- Radiation Protection estimates that Joe will receive the following exposure:
o Whole Body: 7 REM o Lens of the Eye: 35 REM o Hands and Forearms: 75 REM A.2-401 Figure 7.1 (EMERGENCY WORKER EXPOSURE LIMITS) is provided on the following page.
As the Emergency Director; which one of the following is correct, and why?
- a. Approve the 5790-401-01 as the estimated exposures are within limits.
- b. Do NOT approve the 5790-401-01 as the estimated exposure to the Whole Body exceeds the limit.
- c. Do NOT approve the 5790-401-01 as the estimated exposure to the Hands and Forearms exceeds the limit.
- d. Do NOT approve the 5790-401-01 as the estimated exposure to the Lens of the Eye exceeds the limit.
2013 MNGP ILT NRC Written Exam 2013 MNGP ILT NRC Written Exam QUESTION # 099 An event has occurred that has resulted in the declaration of a General Emergency and the following conditions:
- A Radioactive release is in progress
- State dose projections have NOT been received
- A severe winter storm is in progress with the wind from the North
- 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) TABLE 1 is provided on the following page Given the above conditions, determine the initial Protective Action Recommendations (PARS)?
__(1)__ Evacuate or Shelter.
__(2)__ sectors out to 2 miles.
__(3)__ sectors out to 5 miles.
__(4)__ sectors out to 10 miles.
(1) (2) (3) (4)
Evacuate or Shelter 2 miles 5 miles 10 miles
- a. Evacuate H, J, K 5S, 5W 10SE, 10S, 10SW
- b. Shelter R, A, B 5N 10NW, 10N, 10E
- c. Shelter All 5S, 5W None
- d. Evacuate All 5S, 5W None
2013 MNGP ILT NRC Written Exam TABLE 1 SECTOR/SUBAREA CONVERSION CHART Choose geopolitical subareas corresponding to the current wind direction (or affected downwind sectors) and the desired downwind distance one needs to apply the Protective Action Recommendations.
AFFECTED SUBAREAS WIND FROM DOWNWIND (DEGREES) SECTORS 2 MILES 5 MILES 10 MILES 348.75 - 11.25 H, J, K 2 5S, 5W 10SE, 10S, 10SW 11.25 - 33.75 J, K, L 2 5S, 5W 10S, 10SW, 10W 33.75 - 56.25 K, L, M 2 5S, 5W 10S, 10SW, 10W 56.25 - 78.75 L, M, N 2 5W, 5S 10SW, 10W 78.75 - 101.25 M, N, P 2 5W 10SW, 10W, 10NW 101.25 - 123.75 N, P, Q 2 5W, 5N 10W, 10NW 123.75 - 146.25 P, Q, R 2 5W, 5N 10W, 10NW, 10N 146.25 - 168.75 Q, R, A 2 5W, 5N 10NW, 10N 168.75 - 191.25 R, A, B 2 5N 10NW, 10N, 10E 191.25 - 213.75 A, B, C 2 5N, 5E 10N, 10E 213.75 - 236.25 B, C, D 2 5N, 5E 10N, 10E 236.25 - 258.75 C, D, E 2 5N, 5E 10E 258.75 - 281.25 D, E, F 2 5N, 5E, 5S 10E, 10SE 281.25 - 303.75 E, F, G 2 5E, 5S 10SE 303.75 - 326.25 F, G,H 2 5E, 5S 10SE, 10S 326.25 - 348.75 G, H, J 2 5S 10SE, 10S
2013 MNGP ILT NRC Written Exam QUESTION # 100 The plant is at rated conditions when annunciator 5-A-46 (SRV OPEN) is received along with the following indications:
Which of the following is a required TRM/Tech Spec REQUIRED ACTION and COMPLETION TIME for the above conditions?
- a. None; TRM/Tech Spec Actions are NOT required.
- c. Restore the instrument channel to OPERABLE status within 30 days
- d. Restore the instrument channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
2013 MNGP ILT NRC Written Exam ANSWER KEY 001 c. 021 d. 041 c. 061 d. 081 a.
002 d. 022 c. 042 d. 062 a. 082 a.
003 a. 023 d. 043 a. 063 d. 083 d.
004 d. 024 b. 044 c. 064 b. 084 c.
005 b. 025 d. 045 d. 065 c. 085 a.
006 b. 026 a. 046 a. 066 c. 086 d.
007 d. 027 b. 047 b. 067 b. 087 b.
008 b. 028 c. 048 d. 068 c. 088 a.
009 c. 029 b. 049 c. 069 c. 089 c.
010 c. 030 c. 050 d. 070 b. 090 c.
011 c. 031 c. 051 a. 071 a. 091 b.
012 a. 032 c. 052 b. 072 b. 092 d.
013 c. 033 d. 053 c. 073 c. 093 d.
014 b. 034 c. 054 a. 074 b. 094 c.
015 c. 035 c. 055 a. 075 a. 095 d.
016 a. 036 a. 056 b. 076 a. 096 c.
017 b. 037 c. 057 b. 077 b. 097 a.
018 c. 038 b. 058 d. 078 d. 098 d.
019 b. 039 d. 059 c. 079 b. 099 c.
020 a. 040 b. 060 b. 080 c. 100 c.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 001
REFERENCE:
C.4-B.05.01.02.A REFERENCE PROVIDED DURING EXAM: None BANK HIGHER K/A: 295001 2.1.25 Partial or Complete Loss of Forced Core Flow Circulation: Ability to interpret reference material, such as graphs, curves, tables, etc.
JUSTIFICATION: The examinee must determine that B jet pump flow must be subtracted from A jet pump flow. This results in a total core flow of 20 Mlbm/hr. With the current power this is an entry into Stability Region I. IF plant is operating in Stability Region I or in Stability Region II, THEN exit Stability Region by inserting rods or raising recirc flow.
A is incorrect: Although raising recirc flow is procedurally allowed in this condition, exiting the OPRM Enabled region is not required.
B is incorrect: Both Stability Region I & II must be exited.
D is incorrect: A reactor scram would not be required unless the OPRM was inoperable, there was difficulty inserting rods or neutron flux oscillations were occurring. By definition, neutron flux oscillations are a 10% peak-peak change in power. The fluctuations given in the stem would merely be considered normal instrument noise.
QUESTION # 002
REFERENCE:
C.4-B.09.02.A REFERENCE PROVIDED DURING EXAM: None NEW FUNDAMENTAL K/A: 295003K1.06 Partial or Complete Loss of A.C. Power: Knowledge of the operational implications of the following concepts as they apply to PARTIAL OR COMPLETE LOSS OF A.C. POWER: Station blackout.
JUSTIFICATION: An operational implication of a station blackout is the required use of HPCI and/or RCIC for level control. This was quite evident during the Japan events in 2011. The SBO procedure directs the operator to maintain pressure with the LL-Set valves (900-1052 psig) or with manual SRV operation 900-1050 psig.
A is incorrect: Depressurization is not desired in this event for reasons stated above. However, it is plausible to think decay heat must be removed rapidly in this situation.
B is incorrect: This is the normal post scram pressure band but wrong for this situation.
C is incorrect: The turbine bypass valves would not be available in this situation due the loss power.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 003
REFERENCE:
B.09.10-02 B.09.10-06 NEW HIGHER K/A: 295004K2.01 Partial or Complete Loss of D.C. Power Knowledge of the interrelations between PARTIAL OR COMPLETE LOSS OF D.C. POWER and the following:
Battery chargers JUSTIFICATION: LC-103 supplies power to MCC-133 which supplies power to D-10 (DIV I 125 VDC CHARGER). A loss of LC-103 would eventually result in the depletion of Battery 11 and a loss of Div I 125 VDC because the spare charger is not allowed to be connected to both divisions. The examinee must recognize that D-40 is powered from LC-104 and not affected by the given power loss.
B and C are incorrect: The spare charger (D-40) will not lose power. It receives power from MCC-142 which is fed from LC-104. Therefore Battery 12 will remain charging.
D is incorrect: Plausible misconception if examinee believes the spare charger is powered from LC-103.
QUESTION # 004
REFERENCE:
C.6-007-B-25 C.4-A B.05.09-02 REFERENCE PROVIDED DURING EXAM: None NEW HIGHER K/A: 295005K3.07 Main Turbine Generator Trip Knowledge of the reasons for the following responses as they apply to MAIN TURBINE GENERATOR TRIP: Bypass valve operation JUSTIFICATION: The examinee must realize that given the above conditions, the MSIVs will remain open since a Group 1 isolation has not occurred. Since all of the Turbine Stop Valves are closed, pressure should be controlled via the Bypass Valves on the Electronic Pressure Regulator (EPR) at its previous setpoint. This value is typically around 900 psig following a reactor scram from full power.
A is incorrect: The Main Generator Field Breaker will open on a turbine lockout.
B is incorrect: Low-Low Set System would maintain pressure 900-1056 psig but it is not expected since the MSIVs have not closed and bypass valve operation will maintain pressure.
C is incorrect: The Main Generator Output Breakers should open and remain open on a Turbine Lockout.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 005
REFERENCE:
B.05.07-02 REFERENCE PROVIDED DURING EXAM: None BANK HIGHER K/A: 259006A1.02 Reactor Water Level Control System Ability to operate and/or monitor the following as they apply to SCRAM: Reactor water level control system.
JUSTIFICATION: The picture shows both Main Feedwater Regulating valves (MFRV) in manual and closed which is a required action IAW the scram procedure. The Low Flow Regulating valve (LFRV) is in AUTO set at 5 inches. However, when the LFRV is in AUTO the setpoint is clamped between 15-40 inches. Therefore RPV water level should stabilize out at approximately 15 inches.
A is incorrect: Plausible for the current setting of the LFRV.
C is incorrect: Plausible for the current setting of the Master controller plus taking into account DFWLC programming which automatically lowers the setting by 3 inches. This programming is only in effect at high power.
D is incorrect: Plausible for the current setting of the Master controller.
QUESTION # 006
REFERENCE:
B.01.01-06 Figure 29 REFERENCE PROVIDED DURING EXAM: None NEW HIGHER K/A: 295016A2.02 Control Room Abandonment: Ability to determine and/or interpret the following as they apply to CONTROL ROOM ABANDONMENT: Reactor water level.
JUSTIFICATION: The examinee must determine that the fuel zone level indicator on the ASDS panel is calibrated for 1000 psig (HOT). With RPV pressure at 70 psig cold conditions are established. The colder water requires less inventory to provide the same level indication.
Therefore, actual water level is lower. As plotted on Figure 29 actual water level is approximately -65 inches.
A, C and D are incorrect: Plausible misconceptions of water level indications during off normal calibration conditions.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 007
REFERENCE:
C.4-B.02.05.A B.02.05-02 REFERENCE PROVIDED DURING EXAM: None NEW HIGHER K/A: 295018A1.01 Partial or Complete Loss of Component Cooling Water: Ability to operate and/or monitor the following as they apply to PARTIAL OR COMPETE LOSS OF COMPONENT COOLING WATER: Backup systems JUSTIFICATION: The provided picture shows that the backup (standby) RBCCW pump is not setup to automatically start. This can be determined because its white standby light is not on.
The first immediate operator actions for a loss of RBCCW is to verify a pump is running. In this case that would mean to manually start the standby pump.
A is incorrect: These are immediate actions to perform on a loss of RBCCW but the operator should attempt to start a pump first.
B is incorrect: The examinee must recognize that the standby pump will not start because it is not in standby setup.
C is incorrect: This could be an attempted immediate action but since it has tripped on overload the operators should know not to attempt a restart.
QUESTION # 008
REFERENCE:
C.4-B.08.04.01.A REFERENCE PROVIDED DURING EXAM: None BANK FUNDAMENTAL K/A: 295019A2.02: Partial or Total Loss of IA: Ability to determine and/or interpret the following as they apply to PARTIAL OR COMPLETE LOSS OF INSTRUMENT AIR: Status of safety-related instrument air system loads.
JUSTIFICATION: The CRD flow control valves fail closed.
A is incorrect: All valves on SBGT fail open to permit system operation.
C is incorrect: The EDG room ventilation dampers fail open on a loss of air.
D is incorrect: The RHR pump min flow valves will fail open.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 009
REFERENCE:
TS 3.4.8 TS Table 1.1-1 Steam Tables REFERENCE PROVIDED DURING EXAM: Steam Tables NEW HIGHER K/A: 295021 2.2.36: Loss of Shutdown Cooling: Ability to analyze the effects of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations.
JUSTIFICATION: Opening a Bus POT causes metering and relaying for the associated Bus to become de-energized. This will cause the main feeder breaker for Bus 16 to open resulting in loss of Bus 16 and all related loads. With this loss of power along with the Division 1 maintenance window, the examinee must determine that both shutdown cooling subsystems are inoperable. Then the examinee must determine that the plant is in Mode 4 and LCO 3.4.8 will be not met. This event occurred during the MNGP Loss of Bus 16 event during RFO-24.
A is incorrect: The examinee must recognize that bus pot removal will result in the loss of Bus 16 and a loss of SDC.
B is incorrect: This would be the correct answer if the plant was in Mode 3.
D is incorrect: 3.9.8 requires RHR SDC Mode to be operable and could be correct answers if the plant was in Mode 5 since water level is below 217 above the RPV flange. The water level given is normal level during shutdown cooling operations in Mode 4.
QUESTION # 010
REFERENCE:
D.2-05 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 295023K1.03 Refueling Accident: Knowledge of the operational implications of the following concepts as they apply to REFUELING ACCIDENTS: Inadvertent criticality.
JUSTIFICATION: If a loading error occurred causing criticality in the fuel pool, radiation alarms would be expected. ARM A-1 is the closest to the refuel floor and alarms at 20 mrem/hr. If a high radiation alarm or a high airborne alarm is sounded, all personnel in the Reactor Building will leave at once.
A is incorrect: IAW 4-A-1 this would be a minimum requirement during any plant condition.
However, during refueling operations D.2-05 states that the entire Reactor Building should be evacuated.
B is incorrect: SBGT would not be initiated automatically unless the RBV process radiation reading reached 26 mrem/hr or if the Refuel floor process radiation monitor reached 50 mrem/hr.
D is incorrect: This would only be the case if only the Refuel Bridge ARM alarmed. In this case the cause of the alarm would be investigated.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 011
REFERENCE:
B.09.06-01 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 295024K2.10 High Drywell PressureKnowledge of the interrelationships between HIGH DRYWELL PRESSURE and the following: A.C. distribution.
JUSTIFICATION: There are two independent ECCS Load Sheds, one for each essential bus.
The conditions required for an ECCS Load Shed to occur are:
- 3) ECCS Signal - Reactor Low Low Level (-47") for 20 minutes.
With the conditions above both 15 and 16 busses would have an ECCS load shed. 16 Bus would also have an EBT (Essential Bus Transfer) load shed but 15 bus would not because its still being supplied from its normal source (13 Bus).
A is incorrect: Plausible since only 15 bus remains on its normal power source.
B is incorrect: Plausible since 16 bus is on its alternate source and ONLY it would have an Essential Bus Transfer load shed.
D is incorrect: Plausible if examinee thinks that the EBT logic work similar to the ECCS logic in that one signal sheds both bussed of the EBT loads.
QUESTION # 012
REFERENCE:
C.6-004-A-05 B.05.06-02 B.02.03-01 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295025K3.03 High Reactor Pressure :Knowledge of the reasons for the following responses as they apply to HIGH REACTOR PRESSURE: HPCI operation.
JUSTIFICATION: With reactor pressure high HPCI is needed for pressure control. The only system of the above choices available for pressure control with the reactor isolated from the main condenser is HPCI. Therefore HPCI operation is required.
B is incorrect: The examinee must realize that RCIC would be isolated due to the steam line differential pressure signal (1 of 2 taken once).
C is incorrect: The examinee must realize that Main Steam line drains would isolate because they are part of the Group 1 isolation (195-200°F Steam Chase Temp).
D is incorrect: The examinee must realize that the Bypass valves will require the MSIVs to be opened. The MSIVs would isolate from the Group 1 isolation (195-200°F Steam Chase Temp).
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 013
REFERENCE:
C-5-1200 Detail M REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295026A1.03 Supp Pool High Water Temp Ability to operate and/or monitor the following as they apply to SUPPRESSION POOL HIGH WATER TEMPERATURE: Temperature monitoring JUSTIFICATION: At 0835 Torus temperature will have risen to (35 min x 2.9F/min + 88.1F =
189.6°F) With Rx Pressure at approximately 1000 psig and using the solid (-4 to +3.5) Torus level curve, Detail M will be exceeded.
A is incorrect: After 28 minutes Torus water temperature will be 169.3F. This would be the first to exceed Detail M only if using the dotted Torus Water level curve.
B is incorrect: After 31 minutes Torus water temperature will be 178F. This would exceed Detail M only if using the dotted Torus Water level curve.
D is incorrect: After 38 minutes Torus water temperature will be 198.3F. This exceeds Detail M but wouldnt be first.
QUESTION # 014
REFERENCE:
C.5.1-1000 Generic Fundamentals REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 295028A2.03 High Drywell Temperature Ability to determine and/or interpret the following as they apply to HIGH DRYWELL TEMPERATURE: Reactor water level.
JUSTIFICATION: The RPV Saturation Temperature given in Figure 1 is a plot of the saturation temperature of water as a function of pressure. If the temperature of the water in an RPV water level instrument run exceeds this temperature, the water may start to boil, resulting in errors in the indicated level. Boiling is of concern in all instrument runs; horizontal and vertical, reference and variable, drywell and reactor building. Boiloff from the reference leg reduces the height of water in the leg. This decreases the pressure on the reference leg side of the differential pressure transmitter and increases the indicated level.
A, C and D are incorrect: Plausible variations of drywell temperature effects on indicated RPV level.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 015
REFERENCE:
C.5.1-1200 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295030 2.2.44 Low Suppression Pool Wtr Lvl Ability to interpret control room indications to verify the status and operation of a system, and understand how operator actions and directives affect plant and system conditions.
JUSTIFICATION: EOPs require that HPCI be tripped if torus water level cannot be maintained above - 3.7 feet to prevent a pressurization of the torus air space. At time 1503 torus water level is - 4.0 feet and the examinee must understand that this is beyond the EOP procedural threshold and that operator action must be taken to trip HPCI in order to protect containment.
A is incorrect: Plausible for confusion with the RCIC high exhaust trip of 50 psig for 5 seconds.
B is incorrect: Plausible for confusion between psig and vacuum. HPCI low suction trip is 16.5 Hg Vacuum.
D is incorrect: Plausible for being below the low RPV pressure Group 4 isolation trip of 100 psig but this isnt when the trip is first required.
QUESTION # 016
REFERENCE:
C.5.1-1000 B.03.04-05 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 295031K1.01 Reactor Low Water Level Knowledge of the operational implications of the following concepts as they apply to REACTOR LOW WATER LEVEL: Adequate core cooling.
JUSTIFICATION: With the loss of all offsite power and 11 EDG failing to start LPCI injection is lost and only 12 EDG is available to provide power to the division 2 ECCS pumps. For proper EDG loading only 3 large pumps should be loaded on the EDG. One Core spray pump at 2800 gpm is sufficient for adequate core cooling and in order to mitigate the torus temperature rise an RHRSW pump should be in service along with an RHR pump.
B and C are incorrect: These are each 4 large pumps which is too much for one EDG.
D is incorrect: The Core Spray pump would be required to ensure adequate core cooling.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 017
REFERENCE:
B.05.06-01 B.05.06-02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 295037K2.09 SCRAM Condition Present and Reactor Power Above APRM Downscale or Unknown Knowledge of the interrelations between SCRAM CONDITION PRESENT AND REACTOR POWER ABOVE APRM DOWNSCALE OR UNKNOWN and the following: Reactor water level.
JUSTIFICATION: A trip occurring in both sub-channels of logic channel A (A & C) or channel B (B & D) will cause an ATWS trip which opens both Recirc MG set generator field breakers and causes control rod insertion by venting the scram air header. LT-2-3-180B and D sensing < -
47 for greater that 7.3 seconds satisfies the B ATWS logic. Each field breaker is equipped with two trip coils, one connected to logic channel A and the other to channel B. Either trip coil can trip the breaker. Two solenoid valves, SV-3-142A(B), are installed in the scram air header. A trip of the B ATWS will only energize the B solenoid valve.
A is incorrect: Both ARI valves will not vent in this case, only the B solenoid valve will vent.
C is incorrect: Both Recirc MG field breakers will open and only the B solenoid valve will vent.
D is incorrect: The logic is a two-out-of-two-once type. Plausible for confusion between channels and subchannels.
QUESTION # 018
REFERENCE:
B.08.13-01 B.08.13-02 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295038K3.03 High Off-site Release Rate Knowledge of the reasons for the following responses as they apply to HIGH OFF-SITE RELEASE RATE: Control room ventilation isolation.
JUSTIFICATION: CRV/EFT will shift to the High Rad mode when either Refueling Floor Radiation Monitors reach 50 mrem/hr or RB Exhaust Plenum Radiation Monitors reach 26 mrem/hr or Control Room Air Intake Radiation Monitors reach 1 mrem/hr. The CRV-EFT System will automatically shift into the High Radiation Mode to provide HEPA/charcoal filtered outside air to the Control Room and EFT Building 1st and 2nd floors to pressurize them. This will prevent any leakage into the Control Room from adjacent spaces.
A is incorrect: Prior to the modification during the 2007 RFO this would have been correct because the only signal that would cause entry into this mode was the 1 mrem/hr at the CR intake.
B is incorrect: The Recirc Mode is initiated manually and is used for total isolation during a toxic gas event.
D is incorrect: This is the correct mode but the control room wont be isolated. When isolated in the recirc mode control room breathing air may be required during a toxic gas event.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 019
REFERENCE:
B.08.07-02 B.08.07-03 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 600000 A1.05 Plant Fire On Site Ability to operate and/or monitor the following as they apply to PLANT FIRE ON SITE: Plant and/or control room ventilation systems JUSTIFICATION: The controls of the Turbine Building air handling units V-AH-1 and V-AH-2 are interlocked with a differential pressure switch (dPS-9299), so that when the Plenum Room pressure increases to -.2 inch WC the air handling units will shut off and the Plenum Room ceiling dampers will close. A time delay of one minute is provided before an isolation associated with this pressure increase takes place (62-9299 located in Panel N-9302). Automatic initiation of SBGT on high radiation in the exhaust plenum (26 mrem/hr) and the associated trip of V-EF-20, V-EF-21 and V-EF-22 will cause the Plenum Room pressure to become slightly positive and therefore trip V-AH-1 and V-AH-2.
A is incorrect: Although TB air pressure will change when vacuum is broken, this will not trip V-AH-1 & 2.
C is incorrect: These units auto start on 250°F in the TB but they will trip approximately 1 minute after SBGT starts.
D is incorrect: Plausible to remain running for release purposes but they will trip.
QUESTION # 020
REFERENCE:
B.03.05-02 B.03.05-05 MNGP USAR 6.6 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 700000 A2.07 Generator Voltage and Electric Grid Disturbances Ability to determine and/or interpret the following as they apply to GENERATOR VOLTAGE AND ELECTRIC GRID DISTURBANCES: Operational status of engineered safety features.
JUSTIFICATION: A loss of ALL offsite power means that the feed from the emergency transformer (1AR) is also lost.
SBLC Pump #11 and its explosive Squib valve are powered from MCC-133 via LC-103 via 15 Bus which in this case would be powered from 11 EDG. Therefore, #11 Squib valve would actuate.
SBLC Pump #12 and its explosive Squib valve are powered from MCC-142 via LC-104 via 16 Bus which in this case would not be powered because 12 EDG failed to start. Therefore #12 Squib valve would not actuate.
B, C and D are incorrect: Plausible combinations for misinterpretation of the given conditions and/or failure to recall the SBLC Squib power supplies.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 021
REFERENCE:
C.4-B.09.06.B REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 295002K1.03 Loss of Main Condenser Vacuum Knowledge of the operational implications of the following concepts as they apply to LOSS OF MAIN CONDENSER VACUUM: Loss of heat sink.
JUSTIFICATION: Both MO-1850 (11 CWP Discharge Valve) and MO-1851 (12 CWP Discharge Valve) are powered from Load Centers which are powered from Bus 13. Loss of Bus 13 would result in loss of 11 CW Pump and loss of LC-109 (Because the XTIE breaker is open) which would result in MO-1850 (11 CW Pump discharge valve) not being able to close due to loss of power. 12 CW Pump would pump water backwards through 11 CW Pump and not to the condenser and a scram could occur on a rapid loss of vacuum.
A is incorrect: This manipulation will not result in 1R assuming the load.
B is incorrect: Plausible if the examinee thinks a station power transfer will occur in which case both CW pumps will be lost.
C is incorrect: 12 CW pump will not maintain adequate flow due to the bypass path as discussed in the justification.
QUESTION # 022
REFERENCE:
C.4-A REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 295020K3.05 Inadvertent Containment Isolation Knowledge of the reasons for the following responses as they apply to INADVERTANT CONTAINMENT ISOLATION: Reactor water level response.
JUSTIFICATION: The increase in pressure will cause voids to collapse and a reduction of indicated level. Additionally this causes a full RPS trip from MSIV closure which will cause level to lower even more due to the collapse in voids following the scram A is incorrect: RPS will not remain energized as the MSIV closure scram is in effect > 600 psig.
Plausible confusion between the < 840 in RUN Group 1 isolation.
B is incorrect: Plausible as steam flow will be reduced, but water level will lower from the scram.
D is incorrect: With the Low flow FW reg. valve in service the loss of the steam flow input will have no effect on water level since DFCS is already in single element.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 023
REFERENCE:
C.5.1-1300 EOP Detail W REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295032K1.04 High Secondary Containment Area Temperature Knowledge of the operational implications of the following concepts as they apply to HIGH SECONDARY CONTAINMENT AREA TEMP: Impact of operating environment on components.
JUSTIFICATION: The maximum safe temperatures for all areas (excluding the 130°F for 935 East & West CRD, and 962 East) are based on the temperature profiles used for environmental qualification of accident mitigation equipment.
A is incorrect: These are indications of a fire OR high energy line break, but not a definite primary system break.
B is incorrect: Up to 130°F Max Safe, operation of equipment may be required (935 East &
West CRD, and 962 East) and the 130°F values are based on personnel entry and habitability concerns.
C is incorrect: Temperatures greater than 200°F at Reactor Bldg. 962 East will result in unusable level indications.
QUESTION # 024
REFERENCE:
B.04.02-01 B.05.11-02 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 295033K2.04 High Secondary Containment Area Radiation Levels Knowledge of the interrelations between HIGH SECONDARY CONTAINMENT AREA RADIATION LEVELS and the following: Standby gas treatment system.
JUSTIFICATION: Fuel Pool activity levels have reached the Partial Group 2 isolation and SBGT initiation setpoint. The Fuel Pool monitors upscale initiation setpoint is 50 mrem/hr. (the Reactor Building vent plenum monitors have a high trip of 26 mrem/hr)
A is incorrect: Although a 9 Low level Group 2 isolation and reactor scram signal is present, RCIC does not automatically initiate until Low-Low Level (-47) is reached.
C is incorrect: RWCU doesnt automatically isolate until 1.84 psig in the Drywell or -47 RPV water level. Plausible, however, because RWCU previously did automatically isolate at 9.
D is incorrect: LPCI loop select logic will not energize until 1.84 psig in the drywell or -47 RPV water level.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 025
REFERENCE:
B.04.02-05 B.08.07-02 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 295035A1.01 Secondary Containment High Differential Pressure Ability to operate and/or monitor the following as they apply to SECONDARY CONTAINMENT HIGH DIFFERENTIAL PRESSURE: Secondary containment ventilation system JUSTIFICATION: Abnormally low pressure will cause airlock doors to be more difficult to open and cause the doors to close with more force. If the manometer is reading -1.25 inches of H2O, then adjust the variable inlet vanes (VIVs) on V-EF-24A or V-EF-24B in accordance with the applicable B-manual procedure.
A is incorrect: Manually starting SBGT will not isolate secondary containment, which will not correct the problem.
B is incorrect: Procedural direction to perform this procedure is only allowed when the RB is inaccessible. Since the RB is accessible, this procedure would not be performed.
C is incorrect: V-EF-28 takes suction from the Dryer Separator area and discharges into the exhaust plenum, which is plausible for a negative pressure inside secondary containment; however, this fan does not have variable inlet vanes (VIVs).
QUESTION # 026
REFERENCE:
B.07.01-02 B.03.04-05 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 295036A2.01 Secondary Containment High Sump/Area Water Level Ability to determine and/or interpret the following as they apply to SECONDARY CONTAINMENT HIGH SUMP/AREA WATER LEVEL: Operability of components within the affected area.
JUSTIFICATION: The ECCS pumps provide a method to remove water from the floor in the A and B RHR Pump rooms. The sumps in both rooms are cross connected therefore only one of the four sump pumps needs to be operable for the ECCS Pumps to be operable. The A ECCS Sump pumps are both powered from MCC-133 which can explain the common cause electrical malfunction..
B, C and D are incorrect: For reasons stated in the justification these are plausible misconceptions of the sump layout, ECCS pump location and the sump pump operability requirements.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 027
REFERENCE:
C.5-3504 C.5-3505 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 500000 2.1.30 High CTMT Hydrogen Conc. Ability to locate and operate components, including local controls.
JUSTIFICATION: C.5-3504 directs the performance of C.5-3505 (VENTING PRIMARY CONTAINMENT) for the venting portions. C.5-3505 has three parts (A-B-C). Parts B and C require the use of SBGT to vent the containment. Part A uses the Hard Pipe Vent and this method can be used for the given conditions. The Hard Pipe Vent can only be manually operated from the Alternate Shutdown Panel (ASDS).
A and D are incorrect: Venting could only be performed from the control room if SBGT is available.
C is incorrect: Venting operations cannot be performed from the cable spreading room. This is plausible; however, because some vital equipment can be manually operated from this room.
QUESTION # 028
REFERENCE:
OWI-03.07 B.03.04-05 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 203000K4.04 RHR/LPCI Injection Mode Knowledge of RHR/LPCI INJECTION MODE design features and/or interlocks which provide for the following: Pump motor cooling.
JUSTIFICATION: Each of the RHR (ECCS) rooms contains 2 RHR pumps and 1 Core Spray pump. Only 2 RHR pumps are designed with service water motor cooling. The other 4 pumps rely on air cooling from the room coolers. These room coolers have no automatic start interlocks associated with them. Therefore, it is assumed the operators start the room coolers within 13 minutes of a DBA LOCA to protect the pumps from over heating.
A is incorrect: This is the TCOA time for donning breathing protection during a toxic gas event.
B is incorrect: This is the TCOA time for transferring control to the ASDS panel during a CR or CSR fire.
D is incorrect: This is the TCOA time for performing an ED from the ASDS panel.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 029
REFERENCE:
B.03.04-02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 203000K5.02 LPCI Injection Mode Knowledge of the operational implications of the following concepts as they apply to the LPCI INJECTION MODE: Core Cooling Methods.
JUSTIFICATION: MO-2003 (B RHR) receives an automatic OPEN signal from the LPCI Initiation Logic to allow full bypass of LPCI flow around the heat exchanger and maximize core cooling. Candidate must determine an ECCS initiation has occurred from HPCI automatically initiating. Then they must determine which LPCI loop is selected based on riser pressures.
With the lower pressure on the A loop, LPCI loop select will default to the B RHR loop.
A is incorrect: This valve will be on the Non-selected loop and will receive a CLOSE signal.
Plausible if the candidate thinks A RHR is the default LPCI loop C is incorrect: These valves receive an automatic close signal to prevent a loss of LPCI flow from the selected loop to a potentially broken loop.
D is incorrect: MO-4086 is a RHR to Recirc Intertie line; however this valve does not receive a closed signal.
MO-4085A and B, which are on the intertie lines, receive close signals from the LPCI Loop Select logic to prevent inadvertent loss or bypass of RHR LPCI flow.
QUESTION # 030
REFERENCE:
B.03.04-02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 205000K6.04 Shutdown Cooling Knowledge of the effect that a loss or malfunction of the following will have on Shutdown Cooling: Reactor water level.
JUSTIFICATION: With water level lowering to less than + 9 inches a Group 2 isolation will occur. If RHR is in the S/D Cooling mode this will result in the S/D Cooling suction valves (MO-2029 and MO-2030) going closed. Additionally, the LPCI Injection valve (MO-2013 or MO-2014) will close depending on which division of RHR is in S/D cooling.
A is incorrect: Plausible if examinee confuses the Low Level isolation (+9) for the Low-Low Level (-47) LPCI signal.
B is incorrect: Plausible if examinee fails to recall that the LPCI injection valve also closes.
D is incorrect: The 12 RHR pump that is providing torus cooling from the division 2 side will be unaffected.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 031
REFERENCE:
TS 3.6.2.1 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 206000A1.05 HPCI Ability to predict and/or monitor changes in parameters associated with operating the HPCI SYSTEM controls including: Suppression pool temperature.
JUSTIFICATION: While monitoring torus temperature the examinee must determine that with torus temperature >100°F and performance of testing that adds heat to the torus, all testing that adds heat to the suppression pool must be immediately suspended.
A is incorrect: This is plausible as it is approaching the EOP entry temperature limit (90°F) and the highest allowed limit if no testing were in progress.
B is incorrect: This is plausible if the candidate believes that the limit is to suspend testing above 95°F.
D is incorrect: This is plausible as it is approaching the scram limit for torus water temperature (110°F).
QUESTION # 032
REFERENCE:
B.03.01-01 B.03.01-05 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 209001A2.03 LPCS Ability to (a) predict the impacts of the following on the LOW PRESSURE CORE SPRAY SYSTEM; and (b) based on those predictions, use procedures to correct, control or mitigate the consequences of those abnormal conditions or operations: AC failures.
JUSTIFICATION: With the loss of offsite power given in the stem an essential bus transfer will occur transferring essential bus power to 1AR. However, the picture shows that 1AR is also deenergized so essential bus power should transfer to the EDGs. 25 seconds after DW pressure reached 1.84 psig the Core Spray pumps should start and load onto the EDGs. The picture shows that 12 EDG started and loaded onto 16 bus supplying power to 12 Core Spray pump, however, 11 EDG started but didnt load onto 15 bus so 11 Core spray pump would be without power. IAW the abnormal procedure for a loss of Bus 15; if a Core Spray Pump was running prior to the loss of power it should be placed in PTL to prevent it from restarting in a potentially drained system.
A and B are incorrect: Plausible if the examinee doesnt recognize that 11 EDG is running but not loaded.
D is incorrect: 12 Core Spray pump will be running as it has a 1.84 psig DW start signal and power available from 16 bus.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 033
REFERENCE:
B.03.05-05.G.1 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 211000A3.06 SLC Ability to monitor automatic operations of the STANDBY LIQUID CONTROL SYSTEM including: RWCU system isolation.
JUSTIFICATION: The operator is required to verify that the RWCU pumps have tripped and Group 3 RWCU Isolation valves MO-2397, 2398, and 2399 close when SBLC is initiated from the control room.
A is incorrect: With RPV level lowering, the use of RCIC is warranted to maintain RPV water level.
B is incorrect: The same Group 3 circuitry is used for SYS 1 or 2, this would have no effect on RWCU C is incorrect: The MSIVs are kept open by bypassing the RPV lo-lo water level isolation.
QUESTION # 034
REFERENCE:
ARP 5-A-22 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER JUSTIFICATION: This number represents the APRM STP two loop scram setpoint 0.66W +
59.6%. W is equal to percent total recirc flow which in this case is 44%. Calculated answer is 88.64%.
K/A: 212000A4.05 RPS Ability to manually operate and/or monitor in the control room:
Reactor power.
A is Incorrect: This number is the STP APRM HI Alarm/Rod Block setpoint using the equation 0.66W + 48.6%.
B is Incorrect: This number is the STP Flow Biased Scram setpoint in single loop. This equation is 0.66W + 54.6.
D is Incorrect: This number represents the OLD flow biased scram setpoint prior to the PRNM installation. The equation was 0.66W +65.6.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 035
REFERENCE:
B.05.01.01-05 TS LCO 3.3.1.1 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 215003 2.2.38 IRM Knowledge of conditions and limitations in the facility license.
JUSTIFICATION: The IRM system is divided into two groups of IRM channels, with four IRM channels inputting to each RPS trip system. Six channels, with three channels in each trip system, are required for IRM Operability.
A is incorrect: This is the SRM rod block requirement from the TRM B is incorrect: This is the IRM rod block requirement from the TRM.
D is incorrect: Plausible as the majority of RPS instrumentation requires all channels to be operable.
QUESTION # 036
REFERENCE:
B.05.01.01-02 ARP 5-A-3 ARP 5-A-28 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A:215004K1.02 Source Range Monitor Knowledge of the physical connections and/or cause-effect relationships between the SOURCE RANGE MONITOR SYSTEM and the following: Reactor manual control JUSTIFICATION: This will cause annunciator 5-A-28 (SRM RETRACT NOT PERMITTED) and the white RETRACT PERMIT indicating light on C-05 to go off AND will cause a rod block if IRMs are < Range 3. The rod block will result in annunciator 5-A-3 (ROD WITHDRAWAL BLOCK) and the rod out permit light to go out as shown in the picture.
B is incorrect: The SRM upscale rod block is set at 9.07 x 104 or 90,700 cps (Nominal 1 x 105).
60,000 cps would be 6 x 104 and not above the HI (rod block).
C is incorrect: If the period is shorter than 12 seconds a period alarm is received but this doesn't cause a rod block.
D is incorrect: An IRM reading lowering to <5 will result in a rod block only if IRMs are on range 2 or higher.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 037
REFERENCE:
B.5.1.2-05 B.09.12-05 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 215005K2.02 APRM/LPRM Knowledge of electrical power supplies to the following:
APRM Channels JUSTIFICATION: Primary power (120 VAC) for the PRNM system is provided from bus A and bus B of the RPS Power Distribution System. The 2 of 4 Voters are powered from the associated RPS bus; RPS A powers 2 of 4 Voters 1 and 3, RPS B powers 2 of 4 Voters 2 and 4.
A and B are incorrect: APRM and RBM drawers are powered from both RPS A and RPS B through LVPS and auctioneering circuits.
D is incorrect: The 2 of 4 voters do not receive auctioneered power.
QUESTION # 038
REFERENCE:
B.02.03-02 B.03.02-06 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 217000K3.01 RCIC Knowledge of the effect that a loss or malfunction of the REACTOR CORE ISOLATION COOLING SYSTEM (RCIC) will have on the following: Reactor water level JUSTIFICATION: In automatic flow control mode, the RCIC system flow controller compares the pump flow with the controller-setpoint and generates a signal proportional to the difference.
Controller output of 4 mA to 20 mA corresponds to turbine speeds of 2000 rpm to 4500 rpm, respectively. On an RCIC initiation, the ramp generator output is the most limiting and turbine speed is increased at a rate determined by the ramp slope. The flow controller output will drop from 20 mA as the RCIC flow approaches the setpoint value. At some point the controller output becomes the most limiting signal as the ramp generator output approaches saturation, and turbine speed is controlled by the flow controller. Therefore, in this situation, the RCIC turbine speed would increase due to the loss of flow signal and continue to operate at 4500 rpm until the turbine tripped on high water level.
A and C are incorrect: As described above, these conditions will not occur.
D is incorrect: The overspeed trip mechanism operates at approximately 5535-5715 rpm.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 039
REFERENCE:
B.03.03-01 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 218000K4.01 ADS Knowledge of ADS SYSTEM design feature(s) and/or interlock(s) which provide for the following: Prevent inadvertent initiator of ADS logic.
JUSTIFICATION: In order for the ADS System to initiate, the following two signals are required.
- RPV level below -47 (This causes the Reactor Low-Low Level alarm).
The above conditions are present at time 0800:45. If the AC interlock clears at any time the ADS timer stops or the valves will close. However, the Low-Low level signal clearing can only stop the timer (107 seconds or 1 minute 47 seconds). Since the timer had not timed out (75 seconds) before the Reactor Low-Low Level cleared, the ADS SRVs will not get an open signal and thus prevent an inadvertent initiation.
A is incorrect: This only would be 67 seconds on the timer. Commonly performed calculation error to incorrectly transpose 107 seconds with 1 minute 7 seconds.
B is incorrect: This would be the full 107 seconds, but since the low level condition cleared the valves wont open.
C is incorrect: This would keep the valves close if it were the only source of power left.
However, 16 Bus is still energized and the Division 2 low pressure ECCS pumps will be running.
QUESTION # 040
REFERENCE:
NH-36242 REFERENCE PROVIDED DURING EXAM:
NH-36242 NEW HIGHER K/A: 223002K6.04 PCIS Knowledge of the effect that a loss or malfunction of the following will have on the PRIMARY CONTAINMENT ISOLATION SYSTEM: Nuclear boiler instrumentation JUSTIFICATION: The print identifies that these two level switches feed into the following logic strings; Trip of Recirc Pump, Initiate Closure of Main Steam Line (Group 1) & RWCU Isolation Valves (Group 3). The Recirc Pump trip is based on the -47 inch RPV level drive motor breaker trip and NOT the ATWS field breaker trip.
A and C are incorrect: This logic does not provide a Low level Scram signal or Group 2 Isolation signal, this is fed from LIS-2-3-657A and B respectively.
D is incorrect: ATWS Recirc Pump Trip logic is fed from LIS-2-3-680A and C respectively. The Recirc Pump trip shown for LS-2-3-657C and D is based on the -47 inch RPV level drive motor breaker trip and NOT the ATWS field breaker trip.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 041
REFERENCE:
B.8.4.3-05 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 239002K6.02 SRVs Knowledge of the effect that a loss or malfunction of the following will have on the SRV System: Air (Nitrogen) supply.
JUSTIFICATION: 3-A-46, alarms setpoint is at 200 psig from PS-4237 on Alt Nitrogen System Train B bottle rack.
- Train A supplies one ADS SRV (A), one Lo-Lo Set SRV (E), and B SRV. It also supplies the INBD T-Rings.
- Train B supplies one ADS SRV (C) one Lo-Lo Set SRV (H) and F SRV. It also supplies the INBD MSIVs, OTBD T-rings and the HPV.
The candidate must recognize which train is affected by systems affected on the annunciator.
Additionally losing the Alt N2 supply to SRVs renders them inoperable.
A is incorrect: SRV A is supplied by Train A and SRV G doesnt have Alt N2 backup.
B is incorrect: These are supplied by Train A.
D is incorrect: SRV H doesnt have Alt N2 backup.
QUESTION # 042
REFERENCE:
B.05.07-02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 259002A1.01 Reactor Water Level Control Ability to predict and/or monitor changes in parameters associated with operating the REACTOR WATER LEVEL CONTROL SYSTEM controls including: Reactor water level.
JUSTIFICATION: A 10 inch deviation of any of the three level signals from the median (middle) value will result in annunciator 5-B-48 (FW CONTROL SIGNAL FAILURE) alarm but either A, Median, or B may still be selected. An attempt to choose a failed (out of range, high or low) signal results in a Median Selection. In this case with Median control selected and the A (median) instrument drifting low out of range, DFLC will use Median control and select the middle level input which is from LI-2-3-85A at 34 inches.
A is incorrect: DFLC will not shift to single element and not use the B FW level instrument.
B is incorrect: DFLC will not shift to single element.
C is incorrect: DFLC will shift to Median control and use the safeguards level instrument for an input.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 043
REFERENCE:
B.04.02-05 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 261000A2.01 SGTS Ability to (a) predict the impacts of the following on the SBGT SYSTEM; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal operations: Low system flow.
JUSTIFICATION:
IF FILTER HEATER E-34B-1 is OFF, THEN lower the flow through SBGT A Train by:
- a. Verify that FIC-2943 is in MANUAL.
- b. Manually control CV-2943 until annunciators 24-B-2A (LOW FLOW 3000 cfm) and 24-B-3A (NO DT) have RESET, AND DTI-2954 is rising above 6F.
On Auto start of SBGT system, both SBGT Trains may start and system flow should divide with approximately 50% of the total flow going through each train. However, SBGT A Train tends to dominate and the setting of FS-2950, SBGT B LOOP LOW FLOW ALARM, which provides the low flow interlock for operation of the E-34B-1, SBGT SYSTEM B ELECTRIC HEATER, has been too high for such unbalanced dual train operation. To operate E-34B-1 and, therefore, to operate both trains together, the flow through B Train must be raised (to close FS-2950) by lowering the flow through A Train. Total system flow will lower only slightly as B Train develops more flow and A Train flow is lowered.
B, C and D are incorrect: Plausible for misunderstanding dual train operation.
QUESTION # 044
REFERENCE:
B.09.06-01 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 262001A3.02 AC Electrical Distribution Ability to monitor automatic operations of the AC DISTRIBUTION SYSTEM including: Automatic bus transfer.
JUSTIFICATION: If at any time loss of voltage (2345-2905 volts) occurs while the degraded (3913-3927 volts) voltage logic timer (8.8 to 9.2 sec.) is actuated, the degraded logic is locked out and the 5 and 10 second time delay relays are actuated.
A is incorrect. EDGs do not start when the degraded logic is actuated. The EDGs will start when the degraded voltage timers time out or immediately when loss of voltage logic is actuated.
B is incorrect. 1AR accepted load, Diesel would not load bus until 00:00:18 D is incorrect. Loss of voltage initiated the essential bus transfer.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 045
REFERENCE:
B.09.13.01 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 262002A4.01 Uninterruptible Power Supply Ability to manually operate and/or monitor in the control room: Transfer from alternative source to preferred source.
JUSTIFICATION: If there is a fault on the system resulting in a low output voltage (108), the static switch will transfer the load to the alternate source (MCC) until the fault is clear. When the fault is cleared, the NORMAL SEEKING static switch will then transfer the load back to the preferred source (Inverter)
A is incorrect: During the ZIP mode the inverter will supply the out put voltage; however, the static switch will only enter the ZIP mode if the alternate source is not available. With the CB2 light lit the alternate source is available.
B is incorrect: On a low voltage condition the switch will auto transfer and doesnt require a manual transfer.
C is incorrect: Being on the alternate source is plausible for an undervoltage condition, but if this were the case 8-A-24 would not reset.
QUESTION # 046
REFERENCE:
B.08.07-05 B.08.07-02 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 263000K1.03 DC Electrical Distribution Knowledge of the physical connections and/or cause-effect relationships between the DC ELECTRICAL DISTRIBUTION SYSTEM and the following: Battery ventilation.
JUSTIFICATION: The Division 1 250 VDC Battery room contains a battery, DC distribution panels and charging equipment. One of the Battery Room exhaust fans should be operating at all times to prevent hydrogen from building up in these rooms.
B is incorrect: This is the function of V-EF-40A/B which ventilate the Div II 250 VDC Battery Room C is incorrect: This is not a requirement for the operation of these fans.
D is incorrect: This differential pressure is not required as this Battery room is outside secondary containment.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 047
REFERENCE:
B.09.13-05 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 263000 2.1.28 DC Electrical Distribution Knowledge of the purpose and function of major system components and controls JUSTIFICATION: The length of time available for operating Y-91 from the battery is as follows:
- 1) All connected loads for the first thirty minutes of a loss of AC power.
- 2) At the end of thirty minutes from the time both LC-107 and LC-108 lost power, the N0. 13 DG Load Shed logic will trip the three feeds to the computer distribution panels.
- 3) The capacity of No. 17 battery is sufficient to provide power to the UPS for sixty minutes after the three feeds to the computer distribution panels have been tripped.
A, C and D are incorrect: Plausible options for the given conditions as discussed above.
QUESTION # 048
REFERENCE:
B.08.05-01 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 264000K1.03 EDGs Knowledge of the physical connections and/or cause-effect relationships between the EDG SYSTEM and the following: Fire protection system.
JUSTIFICATION: When ambient temperatures reach a high setpoint, the thermal electric detectors actuate opening the sprinkler valve and admitting water to the sprinkler piping. If the temperature in the area of a sprinkler head reaches higher setpoint, the fusible link on that head melts allowing water to flow.
A is incorrect: This is not a wet pipe system.
B is incorrect: A second detector isnt required to activate the system C is incorrect: Immediate spray will not occur until 160°F when the fusible link melts.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 049
REFERENCE:
B.03.04-02 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 264000K5.06 EDGs Knowledge of the operational implications of the following concepts as they apply to the EDG SYSTEM: Load sequencing JUSTIFICATION: If normal auxiliary electrical power is not available at the time of an ECCS automatic initiation, a 10 second delay is added to allow the two Emergency Diesel Generators to start, come up to speed and for their respective breakers to CLOSE. This will be followed by a 10 second delay before starting 13 & 14 RHR Pumps.
Electrical Power Interlocks:
If normal auxiliary electrical power is available at the time of an ECCS automatic initiation, the starting of the RHR and Core Spray pumps will be delayed to limit the maximum motor starting load. The time delays employed are as follows:
Time Essential Bus 15 Essential Bus 16 5 seconds 11 RHR Pump 12 RHR Pump 10 seconds 13 RHR Pump 14 RHR Pump 15 seconds 11 Core Spray Pump 12 Core Spray Pump A is incorrect: Plausible time for the EDG start time.
B is incorrect: Plausible start time for 11 and 12 RHR pumps D is incorrect: Plausible start times for Core Spray pumps based on the power loss.
QUESTION # 050
REFERENCE:
B.08.04.01-05 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 300000K2.01 Instrument Air Knowledge of electrical power supplies to the following:
Instrument air compressor.
JUSTIFICATION:
15 A/C Power - LC-103 via 15 Bus from 13 bus or 1AR or 11 EDG 15 A/C load sheds on a loss of power. It does require operator actions to restart the compressor but in this case where 11 EDG failed to start LC-103 will be without power.
16 A/C Power - LC-107 via 13 Bus or from 13 DG No 16 A/C does not load shed and does not automatically restart but power will be available since 13 DG started and loaded on to LC-107.
17 A/C Power - LC-108 via 14 Bus No 17 A/C does not load shed and automatically restarts either to run as the lead to supply plant loads or should another compressor supply plant loads, it will go to standby. In this case LC-108 will cross connect with LC-107 and be supplied by 13 DG.
A, B and C Incorrect: Plausible IA Compressor power availability for Pre-Modification of the IA System and for the above conditions.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 051
REFERENCE:
B.02.04-01 B.02.04-02 B.02.04-05 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 300000K3.02 Instrument Air Knowledge of the effect that a loss or malfunction of the INSTRUMENT AIR SYSTEM will have on the following: Systems having pneumatic valves and controls.
JUSTIFICATION: The main actuator air supply for the outboards is from bottled air pallets.
This air is used to open and maintain open the outboard MSIVs. If this pressure lowers the MSIVs will eventually drift closed.
B is incorrect: The solenoid pilot air comes directly from instrument air which would cause the valve to close under spring pressure ONLY if instrument air was lost.
C is incorrect: Instrument nitrogen ONLY supplies air for the inboard MSIVs.
D is incorrect: Air intensifiers only supply a backup for outboard MSIV actuating air. Air intensifiers are supplied from instrument air but they normally do NOT supply main air and must be valved in.
QUESTION # 052
REFERENCE:
B.02.02-01 C.4-B.02.05.A REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 400000K3.01 Component Cooling Water Knowledge of the effect that a loss of malfunction of the COMPONENT COOLING WATER SYSTEM will have on the following: Loads cooled by CCW.
JUSTIFICATION: An RBCCW malfunction, specifically a loss, will cause RWCU filter Demin temps to rise. If Inlet Filter Demineralizer water temperature is >140°F then the following valves will receive an auto close signal: MO-2399 (RWCU RETURN ISOL), MO-2404 (DUMP TO HOTWELL) AND MO-2405 (DUMP TO WCT OR WST).
A is Incorrect: Plausible to think these valves are only affected by the Group 3 high room temperature isolation and or only the dump valves close on high water temperature.
C is Incorrect: MO-2397/98 would not close. MO-2399 would close. Plausible for confusion between the high room temperature isolation and high water temperature isolation.
D is Incorrect: MO-2397/98 would not close. Plausible to think all would close for a high temperature condition.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 053
REFERENCE:
B.08.01.02-01 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 400000K4.01 Component Cooling Water Knowledge of Component Cooling Water System design feature(s) and/or interlock(s) which provide for the following: Automatic start of standby pump.
JUSTIFICATION: With a loss of all offsite power these pumps will not have power to auto start until the respective EDG output breaker close onto their bus. The EDGs will auto start on the Loss of all offsite power but their standby cooling water pumps will not start until the output breakers close.
A is incorrect: This is when the pumps normally auto start if power is available on the EDG start.
B is incorrect: 1.84 psig is an EDG fast start signal, but without power the cooling water pumps will not auto start.
D is incorrect: Service water normally supplies cooling to the EDG cooling header. 40 psig is the auto start pressure for a standby SWP.
QUESTION # 054
REFERENCE:
B.01.03-01 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 201003K1.02 Control Rod and Drive Mechanism Knowledge of the physical connections and/or cause-effect relationships between the CONTROL ROD AND DRIVE MECHANISM and the following: Reactor water.
JUSTIFICATION: Water displaced by the upward movement of the piston flows through the over-piston water port, through directional control valve SV-121, through the exhaust header and into the reactor (through the other CRDs). Water displaced by the piston also flows past the control rod drive seals of the drive being inserted and into the reactor.
B is incorrect: Although the cooling water header does have relief valves that equalize pressure with the exhaust header, their function is to equalize pressure post scram to minimize differential pressure across the drive piston.
C is incorrect: Plausible option to think water is recycled back to the drive header during rod movement.
D is incorrect: This is the correct location for draining displaced reactor water from the result of a reactor scram after the SDV is drained but not for a rod insertion.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 055
REFERENCE:
B.05.02-02 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 201006K3.01 RWM Knowledge of the effect that a loss or malfunction of the ROD WORTH MINIMIZER SYSTEM will have on the following: Reactor manual control.
JUSTIFICATION: The RWM should not allow errors under normal drive speeds. The physics calculations allow a tolerance of 1 notch for these conditions. The only Reactor Manual Control (RMCS) rod movement the RWM will allow is to correct the Withdraw Error that was created when rod 22-31 went past its Withdraw Limit. The Operator must insert rod 22-31 to its Withdraw Limit, position 12, before any other rod movements are permitted by the RWM.
B is incorrect: Plausible if examinee believes these conditions will only result in a withdrawal block.
C is incorrect: Plausible for correction of the error, but a withdraw error will only allow the rod to be inserted.
D is incorrect: Plausible required action with a control rod out of sequence because anything other than a one notch error would require this.
QUESTION # 056
REFERENCE:
B.05.08-01/06 B.01.04-01 ARP 4-C-5 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 202002K4.03 Recirculation Flow Control Knowledge of RECIRCULATION FLOW CONTROL SYSTEM design feature(s) and/or interlock(s) which provide for the following: Signal failure detection.
JUSTIFICATION: Protective logic functions monitor the flow control loop and lock the actuator in position if abnormal conditions exist. This protective circuit will generate a scoop tube lock upon sensing a change in MG set actuator position or MG set speed which was not called for by the control room operator. This failure is MNGP site specific OE (AR 01008012).
A is incorrect: The speed indication is feed from the MG set tachometer but it is also sent to the PLC where the lock will be generated.
C is incorrect: This is a function provided by the PLC but in this case it wont compensate for the change since it wasnt called for. Prior to the PLC upgrade this type of speed feedback was utilized.
D is incorrect: Many failures will result in both a scoop tube lock and a drive motor breaker trip but this failure is not one of them.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 057
REFERENCE:
B.05.04-02 ARP 5-A-11 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 214000K5.01 RPIS Knowledge of the operational implications of the following concepts as they apply to ROD POSITION INFORMATION SYSTEM: Reed switches.
JUSTIFICATION: The rod overtravel annunciator is received when control rod notch position 49 (reed switch 50) is closed. This is an indication of the control rod becoming uncoupled from the CRDM. When Reed switch 50 is closed the window will indicate blank (black and shows no position indication).
A is incorrect: This is the normal indication for a fully inserted rod.
C is incorrect: It is not possible to get red double dashes, however plausible because double dashes are display for the insert overtravel.
D is incorrect: This is the indication for insert overtravel and 5-A-11 is not received for this overtravel.
QUESTION # 058
REFERENCE:
B.05.03-05.H.1 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 215001K6.04 Traversing In-core Probe Knowledge of the effect that a loss or malfunction of the following will have on the TRAVERSING IN-CORE PROBE SYSTEM: PCIS.
JUSTIFICATION: When a Group 2 isolation is received, the PCIS logic should retract the cable in fast speed and close the TIP Ball Valve. If the PCIS logic failed to retract the detector then it can be manually retracted from panel C-13 or locally using the hand crank to manually retract the probe, A is incorrect: This would be a correct action to take if containment isolation was imperative due to an actual Group 2 isolation with elevated fission product releases.
B is incorrect: With no scans in progress the Ball Valve does receive a close signal. However, in this case, the ball valve wont close until the cable retracts. The cable is suppose to auto retract if a Group 2 isolation is received.
C is incorrect: The TIP shear valve doesnt auto actuate; it must be manually fired from the control room.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 059
REFERENCE:
B.03.04-02 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 230000K6.08 RHR/LPCI Torus Spray Mode Knowledge of the effect that a loss or malfunction of the following will have on RHR/LPCI TORUS SPRAY MODE: Nuclear boiler instrumentation JUSTIFICATION: Based on the given conditions, the examinee must determine that the torus spray valves failed to automatically close when RPV level went below -174 (2/3 Core Height).
This would be indicative of an instrumentation failure. Keylocked switch (NEUTRAL-MAN OVERRIDE) 10A-S18B will override the 2/3 core height permissive but the picture shows that this hasnt been overridden. These valves are all interlocked to be automatically closed when a LPCI automatic initiation signal is received. Interlocks are designed to prevent diverting LPCI flow to areas other than the Vessel unless it is necessary or unless the LPCI requirements are satisfied. The Torus spray valves (MO-2006 through MO-2011) cannot be opened when a LPCI initiation signal is present except under the following conditions:
- a. Reactor water level is greater than 2/3 core height and
- b. Drywell pressure is greater than 1 psig.
A is incorrect: The torus spray valve (MO-2011) will automatically close if DW pressure lowers to <.75 psig.
B is incorrect: This would be true, however the LPCI signal is currently bypassed as indicated by the LPCI Initiation Bypass light being out.
D is incorrect: The LPCI initiation signal pressure used to be 460 psig. Plausible to think these valves have already closed on RPV pressure.
QUESTION # 060
REFERENCE:
C.4-B.02.05.A REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 233000A1.07 Fuel Pool Cooling/Cleanup Ability to predict and/or monitor changes in parameters associated with operating the FUEL POOL COOLING/CLEANUP SYSTEM: System temperature.
JUSTIFICATION: The FPCC heat exchanger outlet temp must be monitored and FPCC system removed from service before the heat exchanger outlet temp reaches 120 F. The FPCC Heat Exchanger outlet piping is not analyzed for temps above 120°F.
A, C and D are incorrect: Plausible RBCCW cooled components, however, these systems dont have temperature concerns for downstream piping.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 061
REFERENCE:
B.09.06-01 C.4-A REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 259001A2.06 Reactor Feedwater Ability to (a) predict the impacts of the following on the REACTOR FEEDWATER SYSTEM; and (b) based on those predictions, use procedures to correct, control or mitigate the consequences of those abnormal conditions or operations: Loss of AC electrical power.
JUSTIFICATION: On a station power transfer, all plant busses will transfer to the 1R transformer with the exception of 12 bus. This is to prevent a second feed pump from starting and complicating the electrical situation. 12 Reactor Feed pump is powered from 12 bus so it will not be running. 11 Reactor Feed pump will remain running and will be sufficient to maintain level post scram. Therefore RPV level will be maintained on the low flow feedwater regulating valve.
A is incorrect: Assuming the power transfer occurs correctly, 11 RFP will remain running.
B is incorrect: This pump can not be used as 12 Bus will be de-energized. If 11 Bus didnt re-power correctly then 12 Bus would get re-powered and 12 RFP would start.
C is incorrect: Plausible C.4-A action to take if the RFPs arent available.
QUESTION # 062
REFERENCE:
B.07.02.01-02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 271000A3.07 Offgas Ability to monitor automatic operations of the OFFGAS SYSTEM including: Process radiation monitoring system indications.
JUSTIFICATION: With one radiation monitor upscale and one downscale a 30 minute timer will start. After 30 minutes AO-1085 A/B will close and AO-7557 A/B will close. The Main Condenser Off-Gas isolation will occur at 1845. Condenser vacuum will lower to the point that results in a reactor scram and turbine trip.
B is incorrect: These valves will not automatically close until 1845 C is incorrect: AO-1085 A/B will not automatically close until 1845.
D is incorrect: One upscale and one downscale will result in an actuation of the off gas timers and condenser isolation in 30 minutes.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 063
REFERENCE:
C.4-B.04.01.B B.05.06-02/05 B.05.11-05 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 288000A4.02 Plant Ventilation Ability to manually operate and/or monitor in the control room: Area temperature.
JUSTIFICATION: A loss of MCC-111 will cause A RB Vent and A Fuel Pool radiation monitors to loose power. This causes these monitors to fail upscale which results in a Partial Group 2 isolation. This isolation will result in the loss of Reactor Building ventilation (V-AC-10A&B) which will cause temperatures to rise in the Main Steam Chase. At temperatures of 195°F-200°F, a PCIS Group 1 isolation will occur. Based on the high outside air temperature, procedural precautions remind the operators to monitor steam chase temperatures from the control room because an isolation would be possible.
A is incorrect: Although half of the RPS logic power is lost and power to Group 1 instruments is lost, this will not directly cause a Group 1 isolation.
B is incorrect: Although half of the PCIS logic power is lost and power to Group 1 instruments is lost, this will not directly cause a Group 1 isolation.
C is incorrect: Although it is plausible that Drywell temperature will isolate MSIV due to the inboard valves being inside the Drywell, this is not an input to this isolation logic.
QUESTION # 064
REFERENCE:
A.2-001 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 290003 2.4.41 Control Room HVAC Knowledge of the emergency action level thresholds and classifications.
JUSTIFICATION: The site ERO is activated and staffed in an emergency condition corresponding to an ALERT classification or higher.
A is incorrect: ERO is not activated for an NUE.
C and D are incorrect: The ERO would be activated for the levels but they are not the minimum.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 065
REFERENCE:
B.05.01.01-01/06 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 290002K1.20 Reactor Vessel Internals Knowledge of the physical connections and/or cause-effect relationships between the REACTOR VESSEL INTERNALS and the following:
Nuclear instrumentation JUSTIFICATION: IRM detectors are located in a dry tube and can be vertically positioned from 2 ft. above the core centerline (fully inserted) to 2 ft. below the core (fully withdrawn).
A is incorrect: IRMs are in a dry tube and not in direct contact with water. Plausible for confusion between IRMs and LPRMs.
B is incorrect: IRMs are in a dry tube and not in direct contact with water. Plausible for confusion between IRMs and LPRMs. Additionally, when fully inserted the detectors are 24 inches above core centerline. This is plausible as when IRMs are fully withdrawn they are 24 inches below core bottom.
D is incorrect: When fully inserted the detectors are 24 inches above core centerline. This is plausible as when IRMs are fully withdrawn they are 24 inches below core bottom.
QUESTION # 066
REFERENCE:
OWI-01.01 B.06.01-05 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 2.1.14 Knowledge of criteria or conditions that require plant-wide announcements, such as pump starts, reactor trips, mode changes, etc.
JUSTIFICATION: All crew members should ensure that appropriate announcement of pre-planned 4 KV breaker operations occurs in a timely manner. The plant page system should be used for the announcement. Make the announcement twice. In the choices provided, the Main Turbine Aux Oil pump is the only 4 KV breaker (152-510) which is powered from Bus 15.
A and B are incorrect: Page announcement not required, these are 480 V pumps.
D is incorrect: Page announcement not required, this is a 250 VDC Pump.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 067
REFERENCE:
B.08.05-01/03 A.3-37 A.3-15-A REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 2.1.30 Ability to locate and operate components, including local controls.
JUSTIFICATION: Initiation for these transformers is manual and may be accomplished from C-20 (Control Room Fire Panel), or locally at the deluge valve in the 12 EDG Room or from a control switch on the outside of the 12 EDG Building.
A is incorrect: This is a Control Room fire alarm panel only.
C is incorrect: The deluge valves in this area are only for the 13 Diesel Generator Room.
D is incorrect: These can be initiated from arming collar pushbuttons in the control room but they are on panel C-20.
QUESTION # 068
REFERENCE:
B.06.04-05 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 2.1.32 Ability to explain or apply system limits and precautions.
JUSTIFICATION: Below 50°F, the Discharge Canal Temperature may NOT decrease more than 5°F/hr (2200-2300). Whenever the upstream river water temperature is ABOVE 50 F, the Discharge Canal Temperature may increase or decrease at any rate. Additionally, discharge canal temperature must remain below 85°F during the month of November.
A and B are incorrect: Plausible distracter for the 5°F/hr lowering limit but upstream river temp is
>50°F.
D is incorrect: Plausible for confusion between a rising temperature limit and lowering temperature limit.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 069
REFERENCE:
B.05.07-05.D.1 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 2.2.2 Ability to manipulate the console controls as required to operate the facility between shutdown and designated power levels.
JUSTIFICATION: Feedwater controllers have a two speed controlling function, depressing the open or close pushbuttons halfway will cause slower response than depressing the buttons fully.
A, B and D are incorrect: These represent plausible but incorrect variations on the operation of these controllers during operation from shutdown and designated power levels.
QUESTION # 070
REFERENCE:
TS LCO 2.1.1.1 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 2.2.22 Knowledge of limiting conditions for operations and safety limits.
JUSTIFICATION: With reactor steam dome pressure <785 psig OR <10% rated core flow then THERMAL POWER shall be < 25% RTP.
A is incorrect: This is below the COLR limit but during two loop operation MCPR must remain >
1.15 for the safety limit.
C is incorrect: Being < 10% rated core flow by itself is not a safety limit violation.
D is incorrect: Although this level is below the Low-Low Level trip and initiation setpoint it is not a safety limit violation until level goes below - 126
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 071
REFERENCE:
TS 3.4.10 REFERENCE PROVIDED DURING EXAM:
None BANK FUNDAMENTAL K/A: 2.2.38 Knowledge of conditions and limitations in the facility license.
JUSTIFICATION: If Reactor Steam Dome pressure is exceeded it must be restored within 15 minutes. Operation above this limit will not ensure RPV integrity during an overpressure transient.
B is incorrect: Plausible time for inoperable control rod scram accumulators.
C is incorrect: Plausible time for violation of RPV heatup and cooldown rate.
D is incorrect: Plausible time for various < 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> TS action times.
QUESTION # 072
REFERENCE:
AWI-08.04.01 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 2.3.4 Knowledge of radiation exposure limits under normal or emergency situations.
JUSTIFICATION:
The 10CFR 20 Limit for Lens of the Eye is 15 Rem.
Without 1st line supervisor approval the AWI limit is up to 40% of 15 Rem, or 6 Rem.
With 1st line supervisor approval the AWI limit is 40-60% or 6-9 Rem.
11 Rem exceeds the AWI limits A, C, and D are incorrect: Plausible choices for lack of knowledge on radiation limits and/or approval allowances and/or miscalculation.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 073
REFERENCE:
B.08.01.01-01 NH-36664 (P&ID M-112 REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 2.3.15 Knowledge of radiation monitoring systems, such as fixed radiation monitors and alarm, portable survey instruments, personnel monitoring equipment, etc.
JUSTIFICATION: All service water from the reactor building, except the discharge from V-AC-6 RCIC Room Air Cooling Unit, is monitored for radiation before it leaves the plant. Discharge from the V-AC-6 is monitored by the discharge canal sample radiation monitoring system. For the service water discharge pipe a signal proportional to the radiation level is transmitted to an indicating recorder located on Panel C-10 in the Control Room. The recorder is equipped with a switch to alarm annunciator 4-A-23 (LIQUID PROCESS HI RADIATION) when a high radiation level is reached or exceeded.
A is incorrect: Plausible choice for RB Steam Systems.
B is incorrect: Plausible choice as all 3 are specific room coolers.
D is incorrect: Plausible choice to monitor all discharges leaving the RB.
QUESTION # 074
REFERENCE:
A.3-002 AWI-08.06.01 FIG 5.2 REFERENCE PROVIDED DURING EXAM:
None MODIFIED FUNDAMENTAL K/A: 2.4.27 Knowledge of fire in the plant procedures.
JUSTIFICATION: The examinee must first determine that warehouse 6 is outside the protected area then determine the fire fighting requirements. In the case of a fire outside the protected area, when only one fire brigade is available, that brigade shall provide isolation and direction for the Monticello fire department and its surrounding departments.
A is incorrect: This action is not taken unless 2 or more brigades are on-site.
C is incorrect: Although the fire is outside the protected area, security personnel are not qualified in fire fighting strategies.
D is incorrect: Although the Duty Chemist and RP Technician are not operators, they are fire brigade members and would not be dispatched for this fire.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 075
REFERENCE:
B.05.17-01 B.05.17-02 C.4-C REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 2.4.34 Knowledge of RO tasks performed outside the main control room during an emergency and the resultant operational effects.
JUSTIFICATION: Based on the initiating conditions, C.4-C has been entered and Part A of C.4-C has been completed, transferring 12 EDG control to the ASDS panel. When the normal voltage is lost C.4-C directs that the operator transfer control of the bus and restore power. This transfer at the ASDS Panel will disable the following automatic control features:
Auto start of #12 Core Spray Pump, Auto start of #14 ESW Pump, Auto start of #12 EDG, Auto start of #12 RHR Pump, Automatic load sequencing of ECCS pumps onto #12 EDG B is incorrect: Auto start features are not disabled form 14 RHR Pump C is incorrect: Although LO-LO Set SRVs are controlled from the ASDS Panel their auto function is not disabled.
D is incorrect: Plausible if examinee doesnt realize that the required actions for loss of voltage are to transfer control of bus 16 to the ASDS Panel. This will disable the control features listed above.
QUESTION # 076
REFERENCE:
C.4-B.09.09.A TS 3.6.1.3 REFERENCE PROVIDED DURING EXAM:
TS 3.6.1.3 BANK HIGHER K/A: 295004A2.02 Ability to determine and/or interpret the following as they apply to PARTIAL OR COMPLETE LOSS OF D.C. POWER: Extent of partial or complete loss of D.C power.
JUSTIFICATION: The following valves are shown with no power:
MO-2035 HPCI Outboard which is powered by D312 MO-2029 RHR S/D Cooling Inboard which is AC powered and normally de-energized at power MO-2032 RHR/Radwaste Drain Inboard which is AC powered and normally de-energized at power.
The picture only depicts a loss of power to the HPCI Outboard therefore the electrical transient has only affected ONE (HPCI) penetration flow path. This affected flow path must be isolated within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> IAW TS 3.6.1.3 Condition A B is incorrect: This is the correct transient but the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> completion time only applies to MSIVs C is incorrect: If D313 was lost, there would be no power to MO-2030.
D is incorrect: Only one penetration flow path is affected.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 077
REFERENCE:
NF-36298-1 B.09.06-01 C.6-008-A-01 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 295005A2.08 Main Turbine Generator Trip Ability to determine and/or interpret the following as they apply to MAIN TURBINE GENERATOR TRIP: Electrical distribution status JUSTIFICATION: With 345KV Bus No. 1 isolated, the examinee must determine that plant power is from the 1R transformer. If a generator lockout is received, the 286G relays will actuate and trip 8N7 and 8N8 and will also actuate the 286T relays to trip the main turbine. The trip of the main turbine will cause a scram from the load reject circuitry. Additionally, based on the electrical lineup, the examinee must determine that the electrical distribution status will remain unaffected by the turbine generator trip.
A is incorrect: The loss of bus 12 procedure is normally entered on a station power transfer.
C and D are incorrect: The 345KV Bus No. 1 is isolated; therefore, station power would have already been supplied from the 1R transformer. A 2R to 1R station power transfer will not occur.
QUESTION # 078
REFERENCE:
C.4-B.08.04.01 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 295019 2.1.20 Partial or Total Loss of Instrument Air Ability to interpret and execute procedure steps.
JUSTIFICATION: When air pressure lowers to 60 psig, the CRD HCU scram valves may begin to open causing controls to insert into the core. If the rods begin to insert or alarm 5-B-22 is received, the reactor should be scrammed. The scram prevents uneven flux distribution from random control rod insertion and minimizes the challenges to the CRD system through flooding of the SDV.
A is incorrect: Following a manual scram this procedure will be entered, but an automatic scram will not occur.
B is incorrect: This procedure is plausible as control rods will initially appear to drift in due to the lowering scram air header pressure. The CRD flow control valve fails closed on a loss of air and if multiple rods drift though the operators are instructed to execute C.4-K.
C is incorrect: SDV challenges may exist under these conditions; however this procedure wouldnt be entered preemptively.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 079
REFERENCE:
EAL Matrix TS 3.4.9 REFERENCE PROVIDED DURING EXAM:
Steam Tables, EAL Matrix, TS 3.4.9 NEW HIGHER K/A: 295021A2.04 Loss of Shutdown Cooling Ability to determine and/or interpret the following as they apply to LOSS OF SHUTDOWN COOLING: Reactor water temperature JUSTIFICATION: The examinee must be able to correctly correlate the given Reactor Coolant Temperature into an equivalent Reactor Pressure. According to the steam tables, 212°F correlates to 14.709 PSIA and 244°F correlates to 26.844 PSIA, a pressure difference of greater than 10 PSIG should be inferred by the candidate and these two numbers. An ALERT should be declared in accordance with CA4.3 due to the fact that an unplanned event resulted in an RCS pressure increase greater than 10 PSIG.
A is incorrect: The conditions ARE met for CU4.1, however, the higher EAL should be declared since conditions for an ALERT are also met.
C is incorrect: Based on reactor coolant temperature and the mode switch position, the reactor can only be in modes 4 or 5. LCO 3.4.9 condition A is only applicable in Modes 1, 2 and 3.
D is incorrect: LCO 3.4.9 condition C was not violated based on the information provided due to the fact that reactor coolant temperature did not heat-up greater than 100°F in a one hour period.
QUESTION # 080
REFERENCE:
C.5.1-1200 C.5-1200 REFERENCE PROVIDED DURING EXAM:
EOP Flowchart C.5-1200 BANK HIGHER K/A:295026A2.03 Suppression Pool High Water Temperature Ability to determine and/or interpret the following as they apply to SUPPRESSION POOL HIGH WATER TEMPERATURE:
Reactor pressure.
JUSTIFICATION: EOP-1200 (PRIMARY CONTAINMENT CONTROL) directs a blowdown based on High/Low Torus water level, high Drywell temperature/pressure, Heat Capacity limit or Pressure Suppression Pressure. Based on the conditions above, only Case 1 would require a blowdown. The SRO examinee can determine this by plotting Drywell pressure vs. Torus level on the Pressure Suppression Pressure Curve Detail O. In Case 1 Detail O is being exceeded and an Emergency Blowdown is required.
A, B and D are incorrect: Torus water level, Drywell pressure, Heat Capacity limit Pressure Suppression Pressure are all within limits for Case 2 and a blowdown is not required.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 081
REFERENCE:
C.5-1100 Flowchart C.5-2007 Flowchart C.4-A REFERENCE PROVIDED DURING EXAM:
EOP-1100 & 2007 Flowcharts BANK HIGHER K/A: 295037 2.4.8 SCRAM Condition Present and Reactor Power Above APRM Downscale or Unknown. Knowledge of how abnormal operating procedures are used in conjunction with EOPs.
JUSTIFICATION: Based on the given conditions the examinee must interpret control rod position to determine which EOP procedures must be entered. With more than one rod out beyond position 04 the failure to scram EOP must be entered. Once that is entered the examinee must use reactor power and period to determine that the reactor is NOT critical. If the reactor is not critical the Failure to Scram EOP (C.5-2007) directs the exit of the Power Leg and entry into AOP C.4-A. This procedure will direct the insertion of the remaining control rods.
B is incorrect: If the reactor was critical this would be performed.
C is incorrect: This action would be performed if reactor power was >3.5%.
D is incorrect: This action would be directed from EOP-1100 or 2007. However, the MPR would not be available for pressure control because RPV pressure dropped to 820 psig causing an MSIV isolation on <840 in RUN and subsequent reactor scram.
QUESTION # 082
REFERENCE:
EAL Matrix 4AWI-08.02.02 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 600000A2.16 Plant Fire On Site Ability to determine and interpret the following as they apply to PLANT FIRE ON SITE: Vital equipment and control systems to be maintained and operated during a fire.
JUSTIFICATION: The SRO examinee must determine that the Heating Boiler room is contiguous to vital equipment as defined by EAL Table H-1(Turbine Building & Control and Administration building). The SRO examinee must then determine that E-Plan classification HU2.1 applies because the fire is burning longer than 15 minutes. In the case of a fire, the Shift Chemist and Shift RPT are required to report as part of the fire brigade resulting in the Security Shift Supervisor as the only available SEC.
B is incorrect: Although the Shift RPT is qualified SEC they must report as a fire brigade members.
C is incorrect: An E-Plan classification is required because the fire burned longer than 15 minutes.
D is incorrect: Plausible if examinee doesnt recognize the Heating Boiler is located contiguous to H-1 areas.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 083
REFERENCE:
C.5-1200 C.5.1-1000 REFERENCE PROVIDED DURING EXAM:
EOP Flowchart, C.5-1200 NEW HIGHER K/A: 295012 2.1.25 High Drywell Temperature Ability to interpret reference materials, such as graphs, curves, tables, etc.
JUSTIFICATION: According to C.5.1-1000, evaporative cooling refers to spray droplet heat and mass transfer which occurs when water is sprayed into a superheated atmosphere. This could result in a negative drywell pressure large enough to challenge the negative pressure capability of the primary containment. This is determined through the use of Detail N (Drywell Spray Limit). The SRO examinee must evaluate EOP Figure N to determine that Drywell sprays CANNOT be initiated at this time.
A is incorrect: Drywell integrity is being challenged at this temperature, however, according to Detail N (Drywell Spray Limit), the examinee must determine that conditions are not met to spray the drywell.
B is incorrect: This distracter is plausible because EOPs are only applicable in modes 1, 2 and 3.
Since there are modes that EOPs would not be applicable, the examinee may choose this option.
C is incorrect: This would be true if Figure N was met and the examinee only chose to spray the drywell based on Drywell pressure leg; however, Drywell sprays would only be required if the CRS determines that Drywell pressure cannot be maintained below 12 psig. Additionally, in this case the CRS should be executing the Drywell temperature leg which will allow drywell sprays prior to torus sprays.
QUESTION # 084
REFERENCE:
C.5-1400 EAL Matrix REFERENCE PROVIDED DURING EXAM:
C.5-1400 EOP flowchart and EAL Matrix NEW HIGHER K/A: 295035A2.02 Secondary Containment High D/P Ability to determine and/or interpret the following as they apply to SECONDARY CONTAINMENT HIGH DIFFERENTIAL PRESSURE: Off-site release rate.
JUSTIFICATION: The SRO examinee must recognize the high d/p and ruptured blowout panels will result in entry into EOP C.5-1400 (OFFSITE RELEASE). This EOP requires that the CRS perform an emergency depressurization prior to reaching the General Emergency release limits. From the EAL Matrix the SRO examinee can determine that the RB Vent Effluent GE limit is 1.5 x 108 uCi/sec. Therefore 7 x107 uCi/sec would be the highest reading before exceeding the limit.
A is incorrect: At this level an ED would be allowed but it isnt the highest. Plausible if examinee misreads EOPs and thinks the ED has to be performed before the ALERT level.
B is incorrect: At this level an ED would be allowed but it isnt the highest. Plausible if examinee misreads EOPs and thinks the ED has to be performed before the SITE AREA level.
D is incorrect: This level is above the GE release limit. Plausible if examinee believes the limit has to be exceeded prior to directing the ED.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 085
REFERENCE:
C.5-3501 C.5-1200 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 500000A2.01 High CTMT Hydrogen Concentration Ability to determine and/or interpret the following as they apply to HIGH PRIMARY CONTAINMENT HYDROGEN CONCENTRATION: Hydrogen monitoring system availability.
JUSTIFICATION: Under current plant conditions EOP C.5-1200 (Primary Containment Control) would be entered and would direct the H2/O2 analyzers to be placed in service IAW C.5-3501.
The H2/O2 sample and return valves will be isolated from the Group 2 isolation; however, the H2/O2 system has separate reset logic that allows the valves to be opened under Group 2 Conditions. This can be done using the 3501 procedure. Additionally, the 3501 requires that drywell temperature be < 280°F in order for the H2/O2 system to be placed in service. The SRO examinee must recognize under the current plant conditions the H2/O2 system is available and only the 3501 procedure must be directed.
B and D are incorrect: The Group 2 isolation can be reset using the 3501 procedure.
C and D are incorrect: Drywell pressure is low enough to allow the 3501 procedure to be performed.
QUESTION # 086
REFERENCE:
0255-03-IA-1-1 REFERENCE PROVIDED DURING EXAM:
0255-03-IA-1-1 BANK HIGHER K/A: 209001A2.08 LPCS Ability to (a) predict the impacts of the following on the LPCS system; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations: Valve openings JUSTIFICATION:
Valves with measured stroke times in their safety related direction which fall outside of the IST acceptance band but do not exceed the LST SHALL be immediately retested or declared inoperable. If retested and the second set of data also does not meet the acceptance criteria, the data SHALL be analyzed within 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> to verify that the new stroke time represents acceptable valve operation or the valve SHALL be declared inoperable. OPEN________Sec (6.0 - 10.0 Sec) (LST 12.0 Sec)
A is incorrect: The LST has not been exceeded.
B is incorrect: The valve would be inoperable because of exceeding LST.
C is incorrect: The valve would not be inoperable with this retest time.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 087
REFERENCE:
TRM T LCO 3.3.2.1 Bases REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 215005 2.2.22 APRM / LPRM Knowledge of limiting conditions for operations and safety limits.
JUSTIFICATION: The APRM control rod block function is provided to prevent excessive control rod withdrawal so that MCPR remains above the Safety Limit A is incorrect: Although PCIUTL does protect the fuel from plastic strain of the cladding, it is a conservative administrative preconditioning limit that isnt maintained by the APRM rod block.
C and D are incorrect: The RWM rod block ensures peak fuel enthalpy (280cal/gm) is not exceeded and that fuel damage does not occur during a control rod drop accident.
QUESTION # 088
REFERENCE:
TRM TLCO 3.5.1 TS LCO 3.5.1 B.03.03-01 REFERENCE PROVIDED DURING EXAM:
TRM: TLCO 3.5.1 TS 3.3.5.1 TS 3.4.3 TS 3.5.1 NEW HIGHER; K/A: 218000A2.06 ADS Ability to (a) predict the impacts of the following on the AUTOMATIC DEPRESSURIZATION SYSTEM; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations: ADS initiations signals present.
JUSTIFICATION: The SRO examinee must determine that the fuses were removed (Green light off) IAW the stuck open relief valve procedure. Then the examinee must determine that all 3 ADS valves are now inoperable because with the fuses removed, the ADS function is lost.
A is incorrect: Plausible for confusion with TLCO 3.0.3 as it would be entered for the failed Inhibit switches.
C is incorrect: If there was a ADS timer malfunction, TSs would allow an additionally hour to declare the ADS valves inoperable but not for inhibit switches and the fuses removed.
D is incorrect: This would only apply if the Safety Function of the SRVs was inoperable
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 089
REFERENCE:
TS LCO 3.4.3 AWI-04.08.02 Quad Cities LER REFERENCE PROVIDED DURING EXAM:
TS 3.4.3 and AWI-04.08.02 Figures 5.1-5.3 BANK HIGHER K/A: 239002 2.4.30 SRVs Knowledge of events related to system operations/status that must be reported to internal organizations or external agencies, such as State, the NRC, or the transmission system operator.
JUSTIFICATION: 7 of the 8 SRVs are required to be operable to meet the LCO. If 3 or more required SRVs are inoperable (4 OF 8), then the plant must be in MODE 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. This meets the criteria of 10CFR50.72(b)(2)(i), 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> notification for plant shutdown required by technical specifications.
A, B and D are incorrect: Plausible misinterpretations of the TS requirements and/or the notification requirements.
QUESTION # 090
REFERENCE:
C.4-B.09.13.F C.4-B.09.13.F Bases REFERENCE PROVIDED DURING EXAM:
None NEW FUNDAMENTAL K/A: 262002A2.01 UPS Ability to (a) predict the impacts of the following on UNINTERRUPTABLE POWER SUPPLY (AC/DC); and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations: Under voltage JUSTIFICATION: The examinee must recall that 8-A-4 will not be received unless a complete loss of Y-10 and/or Y-70 has occurred. Additionally, the examinee must recall that a loss of Y-70 has occurred and will result in a loss of power to some of the Group 2 Isolation Logic. A Partial Group 2 isolation will occur and that this procedure must be entered.
A is incorrect: Y-10 and Y-30 auctioneer power to DFWLC; however, control will not be lost as Y-10 and Y-30 will maintain power.
B is incorrect: Y-70 does supply power to the inboard solenoids for the MSIVs; however, this power is backed up by 125 VDC and entry into this procedure would not be required.
D is incorrect: Plausible for not understanding the implications of annunciator 8-A-4.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 091
REFERENCE:
TS 3.4.1 and Bases B.01.04-01 pg 3 REFERENCE PROVIDED DURING EXAM:
TS 3.4.1 and TS 3.4.2 BANK HIGHER K/A: 202001A2.06 Recirculation Ability to (a) predict the impacts of the following on the RECIRCULATION SYSTEM: and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations: Inadvertent recirculation flow decrease.
JUSTIFICATION: With two recirc loops in operation above 70% reactor power recirc loop flows must be matched within 5% of rated core flow (57.6 Mlb/hr). Based on the given jet pump flows the current mismatch is 7%. This makes LCO 3.4.1 not met with Condition A applicable. This condition requires flows to be matched within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The bases for this action is to ensure that during a LOCA caused by a break of the piping of one recirc loop the assumptions of the LOCA analysis are satisfied.
A is incorrect: Plausible action requirement and reason for a failed jet pump.
C is incorrect: Plausible and correct if reactor power was below 70%
D is incorrect: Plausible misinterpretation of the LCO action statement.
QUESTION 092
REFERENCE:
TS 3.6.1.8 TS 3.5.1 B.03.04-05 REFERENCE PROVIDED DURING EXAM:
TS 3.5.1 & TS 3.6.1.8 NEW HIGHER K/A: 226001 2.2.36 RHR/LPCI: Containment Spray System Mode Ability to analyze the effect of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations.
JUSTIFICATION: With B4339 (MO-2021, RHR DIV 2 DW SPRAY-INBOARD 480V SUPPLY) being OPEN, the Division II DW sprays must be declared inoperable. Also, since Division I keep fill system is not maintaining a minimum of 40 psig in the system, all Division I RHR functions must be declared INOPERABLE. This requires entry of the specified tech spec conditions and required actions.
A is incorrect: Plausible if examinee believes that no tech spec entry for Drywell Spray is required.
B is incorrect: Plausible if examinee fails to recognize that Div I RHR subsystem is INOPERABLE based on keep fill system pressure.
C is incorrect: Plausible if examinee fails to recognize that based on the maintenance occurring, BOTH divisions of DW sprays are INOPERABLE
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 093
REFERENCE:
C.5.1-2006 C.5-2006 REFERENCE PROVIDED DURING EXAM:
EOP flowchart C.5-2006 BANK HIGHER K/A: 239001A2.13 Main and Reheat Steam Ability to (a) predict the impacts of the following on the MAIN AND REHEAT STEAM SYSTEM: and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations: High reactor water level.
JUSTIFICATION: If no SRV can be opened, RPV pressure may remain high and flooding may not be possible with low pressure systems. If no high pressure motor-driven system is available, the steam lines are then left open to help depressurize the RPV and increase injection flow.
A is incorrect: Although RPV cooldown rate is approaching 100°F/hr, MSIVs should remain open because the SRVs cant be open.
B is incorrect: MSIVs will remain open but adequate core cooling at this point should be by RPV Flooding core submergence.
C is incorrect: Pipe hangar loading stress will occur but MSIVs should remain open because the SRVs cant be open.
QUESTION # 094
REFERENCE:
TLCO 3.4.1 REFERENCE PROVIDED DURING EXAM:
TLCO 3.4.1 NEW HIGHER K/A: 2.1.34 Conduct of Operations Knowledge of primary and secondary plant chemistry limits JUSTIFICATION: According to table 3.4.1-1 of TLCO 3.4.1, with steam flow greater than 100,000 lbm/hr, the maximum allowed chloride ion concentration would be less than or equal to 0.5 ppm. The maximum allowed RCS conductivity would be less than or equal to 10 mho/cm, based on note (a) that states upon commencing a reactor startup until 24 hrs after THERMAL POWER is >1% RTP, the conductivity shall be less than or equal to 10 mho/cm and the chloride ion concentration shall be less than or equal to 0.1 ppm.
A, B and D are incorrect: Plausible distracters due to misinterpretation of Table 3.4.1-1.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 095
REFERENCE:
C.5-3203 C.5-1100 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 2.1.19 Ability to use plant computers to evaluate system or component status.
JUSTIFICATION: This part can be used as long as the Screen Wash, Electric or Diesel Fire pump is available. The Screen Wash FP is deenergized as it is powered from LC-101. The Electric FP is deenergized as it is powered from LC-104. The Diesel Fire Pump would be available.
A is incorrect: ONLY RHRSW A can be used to cross-tie with LPCI. Since all other busses are deenergized (15 Bus), the A pumps would not have power. This part cannot be used because 11 and/or 13 RHRSW pumps must be available.
B is incorrect: In order to use this part the condensate service pumps must have power. 11 CSP is powered from MCC-111 which doesnt have power because LC-101 is deenergized. 12 CSP is powered from MCC-141 which does come off of LC-104 but is non-essential so it also doesnt have power.
C is incorrect: In order for this part to be used a condensate pump must be running. With the SBO both condensate pumps would not have power.
QUESTION # 096
REFERENCE:
TS 3.1.3 TS SR 3.0.3 REFERENCE PROVIDED DURING EXAM:
None BANK HIGHER K/A: 2.2.12 Knowledge of surveillance procedures.
JUSTIFICATION: SR 3.1.3.2 has a 31 day frequency with a 1.25 times grace period which would require the SR to have been performed by 0200 on August 6th. SR 3.0.3 allows from time of discovery, 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the length of the specified frequency which ever is greater to perform the surveillance. Note: 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> can only be exceeded if a risk evaluation has been performed. 31 days past time of discovery is equal to September 6th at 1300.
A is Incorrect: Plausible for miscalculation of days.
B is Incorrect: Plausible if a risk assessment wasnt performed.
D is Incorrect: SR 3.0.3 allows delay of entering actions.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 097
REFERENCE:
AWI-04.04.03 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 2.2.43 Knowledge of the process used to track inoperable alarms.
JUSTIFICATION: AWI-04.04.03 BYPASS CONTROL is the process used for this and states When alarm circuitry is modified directly (annunciator card removal, lifted lead, jumper or shutting off computer alarm points), a Bypass Tag or TMod Tag SHALL be used to identify the circuit modification and a Temporary Information Tag SHALL be placed on the alarm stating it is disabled.
B, C and D are incorrect: These are all examples of when this process is not required to be used.
QUESTION # 098
REFERENCE:
A.2-401 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 2.3.13 Knowledge of radiological safety procedures pertaining to licensed operator duties, such as response to radiation monitor alarms, containment entry requirements, fuel handling responsibilities, access to locked high radiation areas, aligning filters, etc.
JUSTIFICATION: The allowed Emergency Worker Exposure Limits for an emergency activity to protect valuable equipment is 10 REM. NOTE 3 on Figure 7.1 allows 3 times this number for lens of the eye and 10 times this number for the skin and/or extremities. Based on that the limits are as follows:
Lens of the eye: 30 REM Hands and forearms: 100 REM Whole Body: 10 REM A, B and C are incorrect: Plausible for incorrect application of Figure 7.1.
2013 MNGP ILT NRC Written Exam - REFERENCES QUESTION # 099
REFERENCE:
A.2-204 5790-102-02 REFERENCE PROVIDED DURING EXAM:
None NEW HIGHER K/A: 2.4.44 Knowledge of emergency plan protective actions recommendations.
JUSTIFICATION: Wind is from 0°. This will require all sectors within 2 miles sheltered and the 5S & 5W sectors sheltered. The 10-mile sectors are based on dose projection and are only evacuated with state recommendation. Since dose projections have not been received None would be entered.
A is incorrect: Evacuation would not be recommended based on weather conditions, all 2 mile sectors would be sheltered and 10 mile sectors are based on dose projections.
B is incorrect: All 2 mile sectors should be sheltered and plausible for opposite wind direction.
D is incorrect: This would be correct but evacuation would not be performed based on weather conditions.
QUESTION # 100
REFERENCE:
TRM TLCO 3.3.3.1 REFERENCE PROVIDED DURING EXAM:
TLCO 3.3.3.1, & TS 3.3.6.3, 3.4.3, 3.5.1, 3.6.1.5 NEW HIGHER K/A: 2.4.46 Ability to verify that the alarms are consistent with the plant conditions JUSTIFICATION: The SRO examinee must determine if the SRV OPEN alarm is consistent with conditions shown in the pictures. The amber light lit means pressure switch has activated (30#), which would indicate that an S/RV is open; however, the associated MSL flow does not reflect that the S/RV is open. This is indicative of a pressure switch instrument failure which requires entry into condition A.
A is incorrect: Plausible if the examinee does not think a TS or TRM is applicable to this pressure switch.
B is incorrect: Plausible if the examinee believes that the associated ADS valve in INOPERABLE, however, since no indication exists that anything is wrong with the valve itself, it should not be assumed INOPERABLE.
D is incorrect: Plausible if the examinee believes that the associated S/RV is a Low-Low Set valve.