ML13025A037

From kanterella
Jump to navigation Jump to search
Initial Exam 2012-302 Draft Administrative JPMs
ML13025A037
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 01/22/2013
From:
NRC/RGN-II
To:
Duke Energy Carolinas
References
Download: ML13025A037 (63)


Text

Admin-1 24 Page 1 of 9 P

REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-124 Determine if RO License requirements are met CANDIDATE EXAMINER

Adm in-i 24 Page 2 of 9 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Determine if RO License requirements are met per NSD 512 for minimum On-Shift Experience Alternate Path:

N/A Facility JPM #:

ADMIN-i 24 K/A Rating(s):

System: Gen K/A: 2.1.4 Rating: 3.3/3.8 Task Standard:

Completes Form 512-1 and determines requirements of NSD 512 are NOT met.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

NSD 512 (Maintenance of RO/SRO NRC Licenses)

Validation Time: 15 minutes Time Critical: NO Candidate: Time Start:

NAME Time Finish:_______

Performance Rating: SAT UNSAT Performance Time Examiner: /

NAME SIGNATURE DATE COMMENTS

Admin-124 Page 3 of 9 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

Admin-l 24 Page 4 of 9 Tools/Equipment/Procedures Needed:

NSD 512 (Maintenance of RO/SRO NRC Licenses)

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Todays date is 10/29/12. You are a Reactor Operator. Your work history for October of this year is as follows:

10/12/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as BOP on Unit 1 (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/13/12 Worked 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> as OATC on Unit 1 and 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> OATC doing crew JIT training on Simulator A (day shift). Took turnover at beginning and gave turnover at end of both of these assignments.

10/14/12 Worked 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> as BOP on Unit 1 (day shift). Took turnover at beginning of shift.

10/19/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as BOP on Unit 1 (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/20/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as OATC on Unit 3 (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/21/12 Worked 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> as OATC on Unit 3 and 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> as BOP on Unit 1 (night shift). Took turnover at beginning of shift and did NOT give turnover at end of shift.

10/27/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as NEC on Unit 3 (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

INITIATING CUES:

The OSM directs you to review your work history for October, complete Section 3 of form NSD 512-1 based on your fourth quarter work history, and determine if you satisfy the minimum fourth quarter requirements to maintain your active RO License.

Admin-1 24 Page 5 of 9 START TIME:

CRITICAL STEP STEP 1: Evaluate 10/12/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1.

Required position for 12 hrs. with Turnover at beginning and end of shift. SAT COMMENTS: UNSAT CRITICAL STEP STEP 2: Evaluate 10/13/12 work period STANDARD: Determines that requirement is not met because Simulator time does not count toward maintain RO license requirements SAT COMMENTS: UNSAT CRITICAL STEP STEP 3: Evaluate 10/14/12 work period STANDARD: Determines that requirement is not met. No turnover at end of shift, <l2hrs worked in position. SAT U N SAT COMMENTS:

CRITICAL STEP STEP 4: Evaluate 10/19/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1.

Required position for 12 hrs. with Turnover at beginning and end of shift. SAT COMMENTS: UNSAT

Admin-124 Page 6 of 9 CRITICAL STEP STEP 5 Evaluate 10/20/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1.

Required position for 12 hrs. with Turnover at beginning and end of shift. SAT COMMENTS: UNSAT CRITICAL STEP STEP 6: Evaluate 10/21/12 work period STANDARD: Determines that requirement is not met. No turnover at end of shift and position not filled for entire shift. SAT UN SAT COMMENTS:

CRITICAL STEP STEP 7: Evaluate 10/27/12 work period STANDARD: Determines that NEC is not a required position and cannot be credited toward maintenance of RD license SAT COMMENTS: UNSAT CRITICAL STEP STEP 8: Compares credited time vs minimum requirements STANDARD: Determines that there are only 3 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shifts that can be credited and therefore his minimum fourth quarter requirements to maintain his active SAT RD License are not met.

UN SAT COMMENTS:

END OF TASK TIME STOP:

Adm in-i 24 Page 7 of 9 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 1 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

2 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

3 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

4 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

5 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

6 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

7 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

8 This step makes the determination regarding minimum license requirment.

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Todays date is 10/29/12. You are a Reactor Operator. Your work history for October of this year is as follows:

10/12/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as BOP on Unit 1 (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/13/12 Worked 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> as OATC on Unit 1 and 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> OATC doing crew JIT training on Simulator A (day shift). Took turnover at beginning and gave turnover at end of both of these assignments.

10/14/12 Worked 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> as BOP on Unit 1 (day shift). Took turnover at beginning of shift.

10/1 9/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as GOP on Unit 1 (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/20/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as OATC on Unit 3 (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/21/12 Worked 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> as OATC on Unit 3 and 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> as BOP on Unit 1 (night shift). Took turnover at beginning of shift and did NOT give turnover at end of shift.

10/27/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as NEO on Unit 3 (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

INITIATING CUES:

The OSM directs you to review your work history for October, complete Section 3 of form NSD 512-1 based on your fourth quarter work history, and determine if you satisfy the minimum fourth quarter requirements to maintain your active RO License.

Admin1 25 Page 1 of 9 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-125 Determine if SRO License Requirements are met CANDIDATE EXAMINER

Adm in-I 25 Page 2 of 9 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Determine if SRO License Requirements are met per NSD 512 for minimum On-Shift Experience Alternate Path:

N/A Facility JPM #:

ADMIN-125 KIA Rating(s):

System: Gen K/A: 2.1.4 Rating: 3.3/3.8 Task Standard:

Completes Form 512-1 and determines requirements of NSD 512 are met.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

NSD 512 (Maintenance of RO/SRO NRC Licenses)

Validation Time: 15 mm. Time Critical: NO Candidate: Time Start:

NAME Time Finish:

Performance Rating: SAT UNSAT Question Grade Performance Time Examiner:

NAME SIGNATURE DATE COMMENTS

Adm in-i 25 Page 3 of 9 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

Admin-1 25 Page 4 of 9 ToolslEciuipmentlProcedures Needed:

NSD 512 (Maintenance of RO/SRO NRC Licenses)

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Today is 10/29/12. You have just obtained your Senior Reactor Operator license and were assigned you first SRO watch on 10/13/12. Your work history for October of this year is as follows:

10/05/12 Worked 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> as Unit 3 BOP (day shift). Took turnover at beginning of shift and gave turnover at the end.

10/06/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 BOP (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/07/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 OATC (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/12/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit I BOP (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/13/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> (night shift). Worked 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> as the CR SRO and then 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> as WCC SRO. Took turnover at beginning and gave turnover at the end for his CR SRO position and his WCC SRO position.

10/14/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 1 CR SRO (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/20/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 OATC (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

INITIATING CUES:

The OSM directs you to review your work history for October, complete Section 3 of form NSD 512-1 based on your fourth quarter work history, and determine if you satisfy the minimum fourth quarter requirements to maintain your active SRO License.

Adm in-I 25 Page 5 of 9 START TIME:

CRITICAL STEP STEP 1: Evaluate 10/05/12 work period STANDARD: Determines that requirement is not met; <l2hrs worked in position.

SAT COMMENTS:

U N SAT CRITICAL STEP STEP 2: Evaluate 10/06/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1. Required position for 12 hrs. with Turnover at beginning and SAT end of shift.

U N SAT COMMENTS:

CRITICAL STEP STEP 3: Evaluate 10/07/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1. Required position for 12 hrs. with Turnover at beginning and SAT end of shift.

UNSAT COMMENTS:

Admin-1 25 Page 6 of 9 CRITICAL STEP STEP 4: Evaluate 10/12/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1. Required position for 12 hrs. with Turnover at beginning and SAT end of shift.

UNSAT COMMENTS:

CRITICAL STEP STEP 5: Evaluate 10/13/12 work period STANDARD: Determines that requirement is not met since 9 of the hours were not at a required position (VVCC SRO). SAT UNSAT COMMENTS:

CRITICAL STEP STEP 6: Evaluate 10/14/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1. Required position for 12 hrs. with Turnover at beginning and SAT end of shift.

U NSAT COMMENTS:

CRITICAL STEP STEP 7: Evaluate 10/20/12 work period STANDARD: Determines that requirement is met and adds this period to Form 512-1. Required position for 12 hrs. with Turnover at beginning and SAT end of shift.

U N SAT COMMENTS:

Admin-1 25 Page 7of9 CRITICAL STEP STEP 8: Compares credited time vs minimum requirements STANDARD: Determines that 5 12-hr shifts at a required position meets one of the SRO position requirements and that the NSD-512 requirement SAT of at least 1 shift/qtr at an SRO position is also met; so he meets the requirements to maintain his active SRO License.

UNSAT COMMENTS:

END OF TASK TIME STOP:

Admin-1 25 Page 8 of 9 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 1 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

2 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

3 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

4 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

5 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

6 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

7 Required to determine if minimum On Shift Experience requirements of NSD 512 have been met.

8 This step makes the determination regarding minimum license requirment.

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Today is 10/29/12. You have just obtained your Senior Reactor Operator license and were assigned you first SRO watch on 10/13/12. Your work history for October of this year is as follows:

10/05/12 Worked 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> as Unit 3 BOP (day shift). Took turnover at beginning of shift and gave turnover at the end.

10/06/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 BOP (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/07/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 OATC (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/12/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 1 BOP (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/13/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> (night shift). Worked 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> as the CR SRO and then 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> as WCC SRO. Took turnover at beginning and gave turnover at the end for his CR SRO position and his WCC SRO position 10/14/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 1 CR SRO (night shift). Took turnover at beginning of shift and gave turnover at end of shift.

10/20/12 Worked 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> as Unit 3 OATC (day shift). Took turnover at beginning of shift and gave turnover at end of shift.

INITIATING CUES:

The OSM directs you to review your work history for October, complete Section 3 of form NSD 512-1 based on your fourth quarter work history, and determine if you satisfy the minimum fourth quarter requirements to maintain your active SRO License.

Adm in-i 32 Page 1 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Adm in-i 32 Determine makeup requirements for Hotwell and minimum UST level.

CANDIDATE EXAMINER

Admin-132 Page 2 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Determine the Volume of DW Required to Raise Hotwell Inventory to 60 and the Minimum UST Level required to Meet EFDW Requirements Alternate Path:

N/A Facility JPM #:

NEW K/A Rating(s):

System: Gen K/A: 2.1.25 Rating: 3.9/4.2 Task Standard:

Determine that 22,500 gal of DW is required to Raise Hotwell level to 60 and the minimum UST level required to Meet EFDW Requirements is 6 feet.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

OP/0/A/1 108/001 (Curves and General Information)

Tech Spec 3.7.6 (Upper Surge Tank and Hotwell)

PT/i /AJO600/001 (Periodic Instrument Surveillance)

PT/i/AJO600/OOi B (Instrument Surveillance Prior to Mode change)

Validation Time: 12 minutes Time Critical: NO Candidate: Time Start:

NAME Time Finish:

Performance Rating: SAT UNSAT Performance Time Examiner: /

NAME SIGNATURE DATE COMMENTS

Admin-1 32 Page 3 of 8 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

Admin-i 32 Page 4 of 8 Tools/Equipment/Procedures Needed:

OP/0/A/1 108/001 (Curves and General Information)

Tech Spec 3.7.6 (Upper Surge Tank and Hotwell)

PT/i /A/0600/001 (Periodic Instrument Surveillance)

PT/1/A/0600/00i B (instrument Surveillance Prior to Mode change)

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 RCS temperature is 205°F Startup following refueling is in progress Upper Surge Tank Level = 8.5 feet Hotwell level = 50 inches INITIATING CUES:

The CRS directs you to determine the following:

1. The volume (in gallons) of water required to increase Hotwell level to 60 inches?
2. The minimum Upper Surge Tank level allowed by plant procedures to meet UST level Tech Spec requirements prior to the transfer of core decay heat removal from LPI to the Steam Generators.

Admin-132 Page 5 of 8 START TIME:

CRITICAL STEP STEP 1: Candidate refers to OP/0/A/l 108/001 (Curves and General Information) Enclosure 4.9 to determine the number of gallons required to raise the level in the hotwell from 50 inches to 60 inches. SAT STANDARD: Candidate determines the following:

UNSAT Volume associated with 50 inches in the hotwell =

127,500 gallons +/- 500 gallons COMMENTS:

CRITICAL STEP STEP 2: Candidate refers to OP/0/A/1 108/001 (Curves and General Information) Enclosure 4.9 to determine the number of gallons required to raise the level in the hotwell from 50 inches to 60 inches. SAT STANDARD: Candidate determines the following:

UNSAT Volume associated with 60 inches in the hotwell =

150,000 gallons +/- 500 gallons COMMENTS:

CRITICAL STEP STEP 3: Candidate refers to OP/0/AI1 108/001 (Curves and General Information) Enclosure 4.9 to determine the number of gallons required to raise the level in the hotwell from 50 inches to 60 inches. SAT STANDARD: Candidate determines the following:

UNSAT 150,000 127,500 = 22,500 +/- 1000 gallons (volume (in gallons) of UST water required to raise Hotwell level to 60 inches)

COMMENTS:

Admin-1 32 Page 6 of 8 CRITICAL STEP STEP 4: Candidate determines the minimum level required by plant procedures to allow transfer of core decay heat removal from LPI to the Steam Generators. SAT STANDARD: Referring to either PT/1/A10600/001 (Periodic Instrument Surveillance) Enclosure 3.3 (Mode 4) or PT/1/A/0600/OO1 B UNSAT (Instrument Surveillance Prior to Mode change) Enclosure 13.16 (Surveillances Prior to SGs Required for Heat Removal), the applicant determines that the minimum UST level is >6 feet EXAMINER NOTE: A common error would be to look at the TS 3.7.6 requirement of> 30,000 gallons and converting that to level based on the UST Volume Vs. Level Curve in OP/0/A/1 108/00 1. That course of action would result in determining that approximately 5.2 feet as the minimum level requirment.

COMMENTS:

END TASK TIME STOP:

Admin-1 32 Page 7 of 8 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 1 Required to determine the DW volume 2 Required to determine the DW volume 3 Required to determine the DW volume 4 Required to ensure Tech Spec compliance

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Unit 1 RCS temperature is 205°F Startup following refueling is in progress Upper Surge Tank Level = 8.5 feet Hotwell level = 50 inches INITIATING CUES:

The CRS directs you to determine the following:

1. The volume (in gallons) of water required to increase Hotwell level to 60 inches?
2. The minimum Upper Surge Tank level allowed by plant procedures to meet UST level Tech Spec requirements prior to the transfer of core decay heat removal from LPI to the Steam Generators.

Admin-238 Page 1 of 9 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-238 Perform NI Surveillance and Determine Any Required Actions CANDIDATE EXAMINER

Ad ml n-238 Page 2 of 9 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Perform NI Surveillance and Determine Any Required Actions Alternate Path:

N/A Facility JPM #:

NEW K/A Rating(s):

System: Gen K/A: 2.2.12 Rating: 3.7/4.1 Task Standard:

Perform SR 3.3.1.2 in accordance with PT/1/A/0600/O0i (Periodic Instrument Surveillance) and determine that the power increase must be stopped and actions taken to correct NI calibration.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

PT/i 1A106001001 (Periodic Instrument Surveillance)

OP/i/Ni 102/004 (Operation at Power)

Validation Time: 14 minutes Time Critical: NO Candidate: Time Start:

NAME Time Finish:

Performance Rating: SAT UNSAT Performance Time Examiner: /

NAME SIGNATURE DATE COMMENTS

Admin-238 Page 3 of 9 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

Admin-238 Page 4 of 9 Tools/Equipment/Procedures Needed:

PT/i/A10600/00i (Periodic Instrument Surveillance)

OP/i/Ni 102/004 (Operation at Power)

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Power escalation to 100% RTP is in progress.

Current Time is 0730 Reactor Power = 91.7%

Power history is attached INITIATING CUES:

Using the attached power history, you are to perform the Day Shift RPS Instrumentation Heat Balance Check Power Range Amplifiers Surveillance (SR 3.3.1.2) on Page 8 of 27 of PT/1/N0600/001 (Periodic Instrument Surveillance) Enclosure 13.1 (Mode 1&2) and determine the minimum actions required (if any).

Admin-238 Page 5 of 9 START TIME:

STEP 1: Determine if the unit is at Steady State NOTE: Steady State is defined as being +/-2% of a steady power SAT level for >4 hours STANDARD: Using the NOTE above and the attached power history, UNSAT determine that the unit is NOT at Steady State as defined by this surveillance. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 15 minutes ago power was 89.462%.

Current power level is 91 .737%. Power has changed by more than 2% within the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

Note: there are several other definitions of steady state in other plant procedures and Tech Specs. Use of the incorrect steady state definition would result in determining that the reactor is at steady state.

COMMENTS:

STEP 2 IF in Mode 1 during non steady state conditions OR Rx Power 15%- 90% power, verify Rx Power within applicable limits:

SAT

  • Refer to Limits and Precautions of OP/i fAll 102/004 (Operation At Power) for applicable limits.

UNSAT STANDARD: Candidate refers to Limits and Precautions of OP/i/Ni 102/004 (Operation At Power)

COMMENTS:

Admin-238 Page 6 of 9 CRITICAL STEP STEP 3: Determine the magnitude of NI offset.

STANDARD: Candidate refers to the power history provided and determines SAT that CTP = 91.737% and Ni-7 = 89.67% therefore Ni-7 is out of calibration by 2.067%

UNSAT COMMENTS:

CRITICAL STEP STEP 4: Determine if Nis are conservative or non-conservative.

STANDARD: Candidate refers to the Note for limit and precaution step 2.2.5 SAT and determines that NIs are non-conservative since Core Thermal Power is> Nis.

U NSAT COMMENTS:

STEP 5: Determine which Limit and Precaution contains guidance needed.

SAT STANDARD: Based on power history, 2.2.6 C applies since it is for use During operation with Reactor > 90% CTP (power maneuvering OR steady state) UNSAT COMMENTS:

Adm in-238 Page 7 of 9 CRITICAL STEP STEP 6: Determine actions required by Limit and Precaution 2.2.6 C.

SAT STANDARD: Determine that the following are required:

UNSAT

  • Stop the power increase
  • Perform an NI calibration to restore Nis to allowable range Note: Since NIs have not been out by 2% for > 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, the actions of 2.2.6.C.2 are NOT required.

COMMENTS:

END TASK TIME STOP:

Admin 238 Page 8 of 9 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 3 Determining the magnitude of NI error is required to determine the correct NI tolerance allowed for the current plant conditions.

4 Determining that Nis are non-conservative is required to determine the correct NI tolerance allowed for the current plant conditions.

6 These actions are required based on current status of NIs to ensure Safety Analysis assumptions are met.

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Power escalation to 100% RTP is in progress.

Current Time is 0730 Reactor Power = 91.7%

Power history is attached INITIATING CUES:

Using the attached power history, you are to perform the Day Shift RPS Instrumentation Heat Balance Check Power Range Amplifiers Surveillance (SR 3.3.1.2) on Page 8 of 27 of PT/1/A10600/001 (Periodic Instrument Surveillance) Enclosure 13.1 (Mode 1&2) and determine the minimum actions required (if any).

000000 C

%j%J*%JØØ).

L0.)()

0n 00100 -

0 CD CDDCDCOO LL00O)

Cl)

O)-O)OL F3-0 0 CD CD Cl)

Cl) 0 CD CD CD 0 PDDm C0-CD%). U)

L01()1L0 00CDrn CD4

-&0 cooozoooco9 CD CD CD CD 4(DO0.O CD CD CD CD L00CDCD 010Ci)C3 0

CDCD-)00

Admin-239 Page 1 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-239 Perform NI Surveillance and Determine Any Required Actions SRO Only CANDIDATE EXAMINER

Admin-239 Page 2 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Perform NI Surveillance and Determine Any Required Actions Alternate Path:

WA Facility JPM #:

NEW K/A Rating(s):

System: Gen K/A: 2.2.12 Rating: 3.7/4.1 Task Standard:

Perform SR 3.3.1.2 in accordance with PT/1/A/0600/0O1 (Periodic Instrument Surveillance) and determine that the power increase must be stopped and actions taken to correct NI calibration.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

PT/i /A/0600/0Oi (Periodic Instrument Surveillance)

OP/i/Ni 102/004 (Operation at Power)

Validation Time: 14 minutes Time Critical: NO Candidate: Time Start:

NAME Time Finish:_______

Performance Rating: SAT UNSAT Performance Time Examiner: /

NAME SIGNATURE DATE COMMENTS

Admin-239 Page 3 of 8 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

Adm in-239 Page 4 of 8 Tools/Equipment/Procedures Needed:

PT/i /A/0600/OOi (Periodic Instrument Surveillance)

OP/i/Ni 102/004 (Operation at Power)

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Power escalation to 100% RTP is in progress.

Current Time is 0730 Reactor Power = 91.7%

RPS channel 1 D is in Manual Bypass for I&E Power history is attached INITIATING CUES:

Using the attached power history, you are to perform the Day Shift RPS Instrumentation Heat Balance Check Power Range Amplifiers Surveillance (SR 3.3.1.2) on Page 8 of 27 of PT/i/N0600/001 (Periodic Instrument Surveillance) Enclosure 13.1 (Mode 1&2) and determine the minimum actions required (if any).

Admin-239 Page 5 of 8 START TIME:

STEP 1: Determine if the unit is at Steady State NOTE: Steady State is defined as being +/-2% of a steady power SAT level for > 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> STANDARD: Using the NOTE above and the attached power history, UNSAT determine that the unit is NOT at Steady State as defined by this surveillance. 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 15 minutes ago power was 89.462%.

Current power level is 91 .737%. Power has changed by more than 2% within the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

Note: there are several other definitions of steady state in other plant procedures and Tech Specs. Use of the incorrect steady state definition would result in determining that the reactor is at steady state.

COMMENTS:

STEP 2 IF in Mode 1 during non steady state conditions OR Rx Power 15%- 90% power, verify Rx Power within applicable limits:

SAT

  • Refer to Limits and Precautions of OP/1/A/1102/004 (Operation At Power) for applicable limits.

UNSAT STANDARD: Candidate refers to Limits and Precautions of OP/1/A/1102/004 (Operation At Power)

COMMENTS:

Admin-239 Page 6 of 8 CRITICAL STEP STEP 3: Determine the magnitude of NI offset.

STANDARD: Candidate refers to the power history provided and determines SAT that CTP = 91.737% and NI-7 = 89.67% therefore Ni-7 is out of calibration by 2.067%

UNSAT COMMENTS:

CRITICAL STEP STEP 4: Determine if Nis are conservative or non-conservative.

STANDARD: Candidate refers to the Note for limit and precaution step 2.2.5 SAT and determines that Nis are non-conservative since Core Thermal Power is> NIs.

UNSAT COMMENTS:

STEP 5: Determine which Limit and Precaution contains guidance needed.

SAT STANDARD: Based on power history, 2.2.6 C applies since it is for use During operation with Reactor > 90% CTP (power maneuvering OR UNSAT steady state)

COMMENTS:

Admin-239 Page 7 of 8 CRITICAL STEP STEP 6: Determine actions required by Limit and Precaution 2.2.6 C.

SAT STANDARD: Determine that the following are required:

  • Stop the power increase UNSAT
  • Perform an NI calibration to restore Nis to allowable range Note: Since Nis have not been out by 2% for > 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, the actions of 2.2.6.C.2 are NOT required.

CUE: inform candidate that while attempting to calibrate the Nis, 1 Ni-7 failed low and Rx Engineering has determined that 1 Nl-7 is NOT operable. Instruct the candidate to determine ALL Tech Spec Conditions and Required Actions that apply.

COMMENTS:

  • CRITICAL STEP STEP 7: Determine all Tech Spec Conditions and Required Actions that apply.

SAT STANDARD: Determine the following:

UNSAT

  • Since 1 D RPS channel is in Manual Bypass, all functions in 10 RPS channel are required.
  • *Tech Spec 3.3.1 (RPS Instrumentation) Condition A will be entered for the following functions:

o Nuclear Overpower o Nuclear Overpower Flux/Flow Imbalance o Reactor Coolant Pump to Power

  • *10 RPS channel must be placed in Trip within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> COMMENTS:

TIME STOP:

Admin-239 Page 8 of 8 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 3 Determining the magnitude of NI error is required to determine the correct NI tolerance allowed for the current plant conditions.

4 Determining that Nis are non-conservative is required to determine the correct NI tolerance allowed for the current plant conditions.

6 These actions are required based on current status of Nis to ensure Safety Analysis assumptions are met.

7 These actions are required to determine the correct Tech Spec Condition and Required Action.

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Power escalation to 100% RTP is in progress.

Current Time is 0730 Reactor Power = 91.7%

RPS channel 1 D is in Manual Bypass for I&E Power history is attached INITIATING CUES:

Using the attached power history, you are to perform the Day Shift RPS Instrumentation Heat Balance Check Power Range Amplifiers Surveillance (SR 3.3.1.2) on Page 8 of 27 of PT/1/A10600/001 (Periodic Instrument Surveillance) Enclosure 13.1 (Mode 1&2) and determine the minimum actions required (if any).

000000 C

%J%JØ 0C) 0cJl0c5100 0

CD

-I CDDDOO LO0O)C

-o Cl,

-.3V%)- 0 (0

(0 Co 0)

Cl)

-h 0

O(DOOZOL 0 P°°°m O0-(0F) Cl)

C)1UL0 00(D

° 0 m CDL(0 2

caocx 0(0(0CDO Lb1 OLO (0 CD (0L.LOp( CO

(

0 (0 ØL 0C3i C0(D-1%)000

Admin-305 Page 1 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-305 Determine RP Requirements for an Assigned Task CANDIDATE EXAMINER

Admin-305 Page 2 of 8 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Determine the RP requirements for entering the MWHUT room to verify valve positions Alternate Path:

N/A Facility JPM #:

NEW .

K/A Rating(s):

System: Gen K/A: 2.3.7 Rating: 3.5/3.6 Task Standard:

Determines the correct RWP number, Task number, Dose and Dose Rate alarm setpoints, and dress category for the assigned task.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X Simulate

References:

Various RWPs MWHUT room plan view Validation Time: 14 minutes Time Critical: NO Candidate: Time Start:

NAME Time Finish:_______

Performance Rating: SAT UNSAT Performance Time Examiner:

NAME SIGNATURE DATE COMMENTS SIMULATOR OPERATOR INSTRUCTIONS:

Admin-305 Page 3 of 8 NONE

Admin-305 Page 4 of 8 Tools/Equipment/Procedures Needed:

Various RWPs MWHUT room plan view READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Over the last several days there has been a slow unexplained decrease in MWHUT level and a corresponding slow increase in HAWT level.

The Unit 1 CRS has directed you to go to the Unit 1&2 MWHUT room and verify the following valves (located in a congested area underneath the MWHUT) are CLOSED:

  • LWD-970 (1 A MWHUT Drain Block to HAWT)
  • LWD-971 (1A MWHUT Tell Tale)
  • LWD-972 (1 B MWHUT Drain Block to HAWT)
  • LWD-973 (1 B MWHUT Tell Tale)

INITIATING CUES Determine the following requirements for entry into the MWHUT room to check the above listed valves CLOSED:

  • RWPTasknumber
  • Dose Alarm setpoint
  • Dose Rate Alarm setpoint
  • Dress Category Indicate your answers below.

Admin-305 Page 5 of 8 START TIME:

STEP 1: Determine the RWP to be used.

STANDARD: Candidate reviews the RWPs provided and determines that RWP SAT 23 is correct for this job.

U NSAT COMMENTS:

CRITICAL TASK STEP 2: Determine the RWP Task to be used.

STANDARD: Candidate reviews RWP 23 tasks and the provided plan view of SAT the MWHUT room and determines that the work will require entry into a High Radiation Area and therefore determines that Task 2 is correct. UNSAT COMMENTS:

CRITICAL TASK STEP 3: Determine the Dose and Dose Rate ED setpoints.

STANDARD: Candidate reviews RWP 23 Task 2 and determines that the SAT setpoints are as follows:

  • Dose Alarm: 25 mrem UNSAT
  • Dose Rate Alarm : 500 mrem/hr COMMENTS:

Admin-305 Page 6 of 8 CRITICAL TASK STEP 4 Determine the Dress Category for protective clothing requirements STANDARD: The candidate will review the plan view provided and determine SAT that the work will require entry into a High Radiation Area and a Contaminated Area. Based on the Plan View assessment the candidate should determine that Dress Category H applies UNSAT COMMENTS:

END OF TASK TIME STOP:

Admin-305 Page 7 of 8 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 2 Critical since some of the RP requirements for Task 2 (other than Dose and Dose Alarm setpoints) are different 3 Critical since proper ED setpoints provide personnel protection 4 Critical to prevent personnel contamination protections as well as preventing the spread of contamination

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Over the last several days there has been a slow unexplained decrease in MWHUT level and a corresponding slow increase in HAWT level.

The Unit 1 CRS has directed you to go to the Unit 1 &2 MWHUT room and verify the following valves (located in a congested area underneath the MWHUT) are CLOSED:

  • LWD-970 (1A MWHUT Drain Block to HAWT)
  • LWD-971 (1A MWHUT Tell Tale)
  • LWD-972 (1 B MWHUT Drain Block to HAWT)
  • LWD-973 (1 B MWHUT Tell Tale)

INITIATING CUES Determine the following requirements for entry into the MWHUT room to check the above listed valves CLOSED:

  • RWP Task number
  • Dose Alarm setpoint
  • Dose Rate Alarm setpoint
  • Dress Category Indicate your answers below.

ADM-407 Page 1 of 10 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Admin-407 Determine Emergency Classification and Complete Emergency Notification Form SRO Only CAN DI DATE EXAMINER

ADM-407 Page 2 of 10 REGION II INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task:

Determine Emergency Classification and Protective Action Recommendations Alternate Path:

N/A Facility JPM #:

ADM-407 K/A Rating(s):

System: G K/A: 2.4.38 Rating: 2.4/4.4 Task Standard:

Appropriate classification is determined within 15 minutes and associated Emergency Notification Form is completed within an additional 15 minutes.

Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant Classroom X Perform X_ Simulate

References:

RP/0/B/1 000/01 RP/0/B/1 000/02 BASIS Document (Volume A, Section D of the Emergency Plan)

Validation Time: 20 mm. Time Critical: Yes Candidate: Time Start:

NAME Time Finish:

Performance Rating: SAT UNSAT Performance Time:

Examiner: /

NAME SIGNATURE DATE Comments

ADM-407 Page 3 of 10 SIMULATOR OPERATOR INSTRUCTIONS:

NONE

ADM-407 Page 4 of 10 Tools/Equipment/Procedures Needed:

P P10/B/i 000/00 1 P PlO/B/i 000/002 Emergency Notification Forms READ TO OPERATOR DIRECTIONS TO STUDENT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

08:00:00 Unit 1 experiences a SG Tube Leak of 35 gpm in the lA SG.

08:05:00 ERO activated by the OSM due to the SG Tube Leak.

08:15:00 Message sheet 1 provided to offsite agencies.

While performing the Unit 1 shutdown the following event/time line occurs; 08:28:20 With Reactor power = 39% decreasing, a spurious Turbine/Generator trip occurs. An automatic Reactor trip did not occur. The Reactor was manually tripped.

08:31:28 CT-i Lockout occurs. The Unit 1 BOP dispatched to activate the SSF using AP/0/A11700/025. TDEFWP feeding Steam Generators 08:32:50 Control Room reports to the OSM that MFBs have failed to automatically re-energize and efforts are underway to energize MFBs manually from CT-4 in accordance with the EOP ENCL 5.38.

08:42:00 SSF operator reports that per AP/i/A11700/025 flow has been established to Unit ls RCP Seals 08:44:00 MFBs energized from CT-4 (continued on next page)

ADM-407 Page 5 of 10 INITIATING CUE:

You are to perform the required actions of the Emergency Coordinator by referring to RP/0/B/1 000/01, Emergency Classification:

1. Determine Emergency Classification at 08:45:00.
2. Complete appropriate Emergency Notification Form for the current conditions.

THIS IS A TIME CRITICAL JPM Note: Do not use Emergency Coordinators judgment while classifying the event. When required, an operator will maintain the Emergency Coordinators Log and assume the duties of the Control Room Offsite Communicator.

ADM-407 Page 6 of 10 START TIME:

STEP 1: Classify the Event at 0845 CRITICAL STEP STANDARD: Refer to RP/0/B/1000/01 (Emergency Classification) Enclosure 4.4 (Loss of Shutdown Function). SAT Classify the event as an Alerf due to the following:

Valid reactor trip signal received or reguired WITHOUT automatic UNSAT scram AND DSS has inserted Control Rods OR Manual trip from the Control Room is successful and reactor power is less than 5% and decreasing Time for Classification COMMENTS:

STEP 2: Refer to RP/0/B/1 000/02 (Control Room Emergency Coordinator Procedure)

Step 2.1.

IF No EAL exists, AND ERO activation is desired, SAT THEN GO TO Enclosure 4.4, (ERO Pager Activation)

STANDARD: Determine step 2.1 does not apply UNSAT COMMENTS:

ADM-407 Page 7 of 10 TIME STEP 3: Step 2.2 CRITICAL STEP Declare the appropriate Emergency Classification level.

Classification ALERT (UE, ALERT, SAE, GE)

Time Declared: SAT STANDARD: Declare an ALERT as described in Step 1:

UNSAT STOP TIME #1: Time ALERT Declared (Should be the time classified as recorded in step 1)

(SAT is < Start Time + 15 minutes)

COMMENTS:

STEP 4: Step 2.3 IF a Security event is in progress THEN GO TO Step 2.5 SAT STANDARD: Determine Steps 2.3 does not apply COMMENTS: UNSAT STEP 5: Step 2.4 IF assistance from ERO personnel is desired/required:

THEN activate ERO pagers from the ERO Pager Activation Panel STANDARD:

Determine that ERO activation is required and activate pagers. SAT CUE: Inform the candidate the ERO pagers have been activated.

UNSAT COMMENTS:

STEP 6: Step 2.5 Appoint Control Room Offsite Communicator(s) and notify him to be prepared to transmit messages.

SAT STANDARD: Control Room Offsite Communicator has already been appointed COMMENTS: UNSAT

ADM-407 Page 8 of 10 STEP 7: Step 2.6 IAAT Changing plant conditions require an emergency classification upgrade, SAT STANDARD: Another Upgrade is not expected.

COMMENTS:

UN SAT CRITICAL STEP STEP 8: Step 2.7 Obtain the appropriate Offsite Notification form from the Emergency Plan SAT cart.

STANDARD: Initial ALERT form # 4.4.A.1 is selected and candidate continues to fill- UNSAT out form per substeps of Step 2.7.

COMMENTS:

STEP 9: Step 1.7 CRITICAL STEP Complete the Emergency Notification Form.

SAT STANDARD: Correctly tills out Emergency Notification Form for 0845 In Accordance With Key provided:

U NSAT Form complete within 15 minutes of classification in step 1.

COMMENTS:

END OF TASK TIME STOP:

ADM-407 Page 9 of 10 CRITICAL STEP EXPLANATIONS:

STEP # Explanation 1 The candidate needs to be able to utilize the procedure and determine that an Alert has occurred.

3 Required to ensure commitments are met and offsite agencies notified as required 8 Required to successfully notify otfsite agencies 9 The candidate must be able to complete the emergency notification form to provide accurate information.

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

08:00:00 Unit 1 experiences a SG Tube Leak of 35 gpm in the lA SG.

08:05:00 ERO activated by the OSM due to the SG Tube Leak.

08:15:00 Message sheet 1 provided to offsite agencies.

While performing the Unit 1 shutdown the following event/time line occurs; 08:28:20 With Reactor power = 39% decreasing, a spurious Turbine/Generator trip occurs. An automatic Reactor trip did not occur. The Reactor was manually tripped.

08:31 :28 CT-i Lockout occurs. The Unit 1 BOP dispatched to activate the SSF using AP/0/A11700/025. TDEFWP feeding Steam Generators 08:32:50 Control Room reports to the OSM that MFBs have failed to automatically re-energize and efforts are underway to energize MFBs manually from CT-4 in accordance with the EOP ENCL 5.38.

08:42:00 SSF operator reports that per AP/i/A11700/025 flow has been established to Unit ls RCP Seals 08:44:00 MFBs energized from CT-4 INITIATING CUE:

You are to perform the required actions of the Emergency Coordinator by referring to RP/0/B/i 000/01, Emergency Classification:

1. Determine Emergency Classification at 08:45:00.
2. Complete appropriate Emergency Notification Form for the current conditions.

THIS IS A TIME CRITICAL JPM Note: Do not use Emergency Coordinators judgment while classifying the event. When required, an operator will maintain the Emergency Coordinators Log and assume the duties of the Control Room Offsite Communicator.