MONTHYEARML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemp'S Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemp'S Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23129A7892023-05-0909 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Trip and Standby Auto-Start Logic Associated with Safety Related HVAC Trains ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22285A1562022-10-12012 October 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Atlantic Sturgeon 10/11/2022 (Bottom Trawl) ML22280A1302022-10-0707 October 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report - Sturgeon 10/06/2022 ML22269A4822022-09-26026 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/23/2022 ML22269A0352022-09-23023 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/22/2022 ML22265A1512022-09-22022 September 2022 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Relocate TS Requirements for Reactor Head Vents to TRM ML22286A2062022-09-14014 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/13/2022 ML22244A0422022-09-0101 September 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Revise and Relocate Reactor Coolant System PT Limits and Pops Limits to PTLR ML22244A1192022-09-0101 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 08/31/2022 ML22206A0262022-07-25025 July 2022 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22206A1032022-07-22022 July 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 07/21/2022 ML22194A0522022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review - Hope Creek, Salem 1 and 2 - Relocate Staff Qualification Requirements to Licensee Quality Assurance Topical Report ML22188A0762022-07-0707 July 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 07/06/2022 ML22187A1482022-07-0606 July 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection - Sturgeon 07/05/2022 ML22199A2432022-06-29029 June 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 06/28/2022 ML22129A0682022-05-0505 May 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report - 2 Sturgeon 05/04/2022 2024-01-10
[Table view] |
Text
/)~. /1 Pham, Bo From: Pham, Bo Sent: Friday, November 12, 2010 9:16 AM To: Perkins, Leslie
Subject:
RE: Draft Slides for Salem/Hope Creek Public Mtg Leslie, here are my changes to the script for your DSEIS presentation. Let me know if you don't agree or need clarification. Thanks.
Slide 7: Environmental Issues of Continued Operation This slide lists the environmental issues NRC staff reviewed for Hope Creek Generating Station and Salem Nuclear Generating Station during the proposed license renewal period.
Overall, the direct and indirect impact from license renewal on all of these issues were found to be SMALL, which means there were some noticeable impacts, but not enough to cause any permanent alteration to the ecology or environment.
Slide 8: Cumulative Impacts As part of its NEPA review, the staff also looked at the potential cumulative impacts associated with Salem &
Hope Creek. These impacts include the effects on the environment from other past, present, and reasonably foreseeable future human actions. It's important to note that these impacts may not even be related to the relicensing of Salem & Hope Creek. Nevertheless, the intent of NEPA is that an agency be cognizant of and ready to be able to disclose ALL the environmental impacts activities within the proximity of its action.
This slide provides a summary of our findings with respect to cumulative impacts. Overall, the one reasonably foreseeable action in the near future is the potential for PSEG to proceed with its request to construct additional reactors on the site, which as you can see, expands the range of potential impact for Socioeconomics, Aquatic Resources, and Terrestrial resources. We did note in the SEIS, however, that the specific impacts of that future activity is also being reviewed and captured in a separate environmental impact statement by the NRC. Our staff has been working closely with the Office of New Reactors to make we coordinate and capture the relevant information within scope.
Slide 9: Alternatives [change last bullet to say "No Action Alternative"l A major step in determining whether license renewal is reasonable or not is comparing the likely impacts of license renewal with the alternatives including other methods of power generation and not renewing the HCGS and Salem operating licenses.
In the draft environmental impact statement, NRC staff considered supercritical coal-fired generation, natural gas combined-cycle generation, new nuclear generation and, as part of the combination alternative, conservation/efficiency, natural gas combined-cycle generation, and solar power.
Finally, as required by NEPA, the NRC staff also considered the case of the No Action Alternative, which equates to no license renewal of Salem and Hope Creek at the end of their licenses.
The staff found that impacts from energy alternatives would vary widely based on the characteristics of the alternatives. In most cases, construction of new facilities created significant impacts. Overall, NRC staff concludes that continued operation of the existing HCGS and Salem is the environmentally-preferred alternative.
Bo Pham 15
Chief, Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-8450 From: Perkins, Leslie Sent: Wednesday, November 10, 2010 9:04 AM To: Sheehan, Neil; Welling, Blake; Pham, Bo; Rodriguez, Michael; Burton, William; Fells, Carmen; Schroeder, Daniel; Screnci, Diane; Burritt, Arthur; Brady, Bennett; McKenna, Philip; Wentzel, Michael; Harris, Brian Cc: McNamara, Nancy; Tifft, Doug; Galloway, Melanie; Dacus, Eugene; Holian, Brian
Subject:
Draft Slides for Salem/Hope Creek Public Mtg
- All, Attached are the draft slides for the Salem/Hope Creek Nov. 1 7 th Meeting.
Leslie Perkins Project Manager Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-2375 16