ML11189A126

From kanterella
Jump to navigation Jump to search
Notification of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000482/2011006 and Request for Information
ML11189A126
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 07/08/2011
From: O'Keefe N
NRC Region 4
To: Matthew Sunseri
Wolf Creek
References
Download: ML11189A126 (9)


See also: IR 05000482/2011006

Text

UNITED STATES

NUC LE AR RE G UL AT O RY C O M M I S S I O N

R E GI ON I V

612 EAST LAMAR BLVD , SU I TE 400

AR LI N GTON , TEXAS 76011-4125

July 8, 2011

Matthew W. Sunseri, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, KS 66839

SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF NRC TRIENNIAL

FIRE PROTECTION BASELINE INSPECTION (NRC INSPECTION

REPORT 05000482/2011006 AND REQUEST FOR INFORMATION

Dear Mr. Sunseri:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),

Region IV staff will conduct a triennial fire protection baseline inspection at your Wolf Creek

facility beginning in September 2011. The inspection team will be comprised of reactor

inspectors from the NRC Region IV office. The team will conduct the inspection in accordance

with the baseline Inspection Procedure 71111.05T, Fire Protection- (Triennial)

dated August 1, 2011.

The schedule for the inspection is as follows:

  • Information gathering visit: September 20-22, 2011
  • Onsite inspection: October 17 - 21, 2011

October 31 to November 4, 2011

The purpose of the information gathering visit is to obtain information and documentation

needed to support the inspection, to become familiar with the fire protection programs, fire

protection features, post-fire safe shutdown capabilities, plant layout, and mitigating strategies

to address Section B.5.b of the Interim Compensatory Measures Order, EA-02-026, of

February 25, 2002/10 CFR 50.54(hh)(2). Four inspectors and a senior reactor analyst will

participate in the information gathering visit to select the fire areas for evaluation, identify

additional documents needed to support the inspection, obtain unescorted access, and meet

with the key personnel who will support the inspection. The fire area selection will require a

walkdown of candidate fire areas accompanied by key personnel from your staff. The enclosure

to this letter provides an initial list of the documents the team will need for their review. We

request that your staff transmit copies of the documents listed in the enclosure to the NRC

Region IV office for team use in preparation for the inspection. Please send this information so

that it will arrive in our office in Arlington, Texas, by the dates listed in the enclosure.

During the information gathering visit, the team will also discuss the following inspection support

administrative details: office space size and location; specific documents requested to be made

available to the team in their office spaces; arrangements for reactor site access; and the

Wolf Creek Nuclear Operating Company -2-

availability of knowledgeable plant engineering, operations and licensing organization personnel

to serve as points of contact during the inspection.

We request that during the onsite inspection weeks, you ensure that copies of analyses,

evaluations, or documentation regarding the implementation and maintenance of the fire

protection program, including post-fire safe shutdown capability, be readily accessible to the

team for their review. Of specific interest for the fire protection portion of the inspection are

those documents that establish that your fire protection program satisfies the NRC regulatory

requirements and conforms to applicable NRC and industry fire protection guidance. For

the B.5.b portion of the inspection, those documents implementing your mitigating strategies

and demonstrating the management of your commitments for the strategies are of specific

interest. Also, please ensure the availability of appropriate personnel knowledgeable of:

(1) plant systems required to achieve and maintain safe shutdown conditions from inside and

outside the control room, (2) the electrical aspects of the post-fire safe shutdown analyses,

(3) reactor plant fire protection systems, and (4) the fire protection program and its

implementation.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection or the inspection team's information or logistical needs, please

contact Greg Pick, the lead inspector, in the Region IV office at (817) 860-8270, or by email,

greg.pick@nrc.gov.

Sincerely,

/RA/

N. OKeefe, Chief

Engineering Branch 2

Division of Reactor Safety

Docket: 50-482

License: NPF-42

Wolf Creek Nuclear Operating Company -3-

Enclosure: Triennial Fire Protection

Inspection Documentation Request List

cc: Distribution via ListServ for Wolf Creek

Wolf Creek Nuclear Operating Company -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Jeff.Clark@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Bob.Caldwell@nrc.gov)

Senior Resident Inspector (Chris.Long@nrc.gov)

Resident Inspector (Charles.Peabody@nrc.gov)

WC Administrative Assistant (Shirley.Allen@nrc.gov)

Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov)

Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov)

Project Engineer, DRP/B (Greg.Tutak@nrc.gov)

Project Engineer, DRP/B (Nestor.Makris@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Balwant.Singal@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

RIV/ETA: OEDO (Jack.McHale@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

S:\DRS\Reports\Reports Draft\WC\WC TFP RFI_GAP.Docx ADAMS ML11189A126

ADAMS: No Yes SUNSI Review Complete GAP Reviewer Initials: GAP

Publicly Available Non-Sensitive

Non-publicly Available Sensitive

SRI/DRS/EB2 C:DRS/EB2

GPick NOKeefe

/RA/ /RA/

07/7/2011 07/ 8 /2011

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

Triennial Fire Protection Inspection Documentation Request

Please provide the following documents (items 1 - 8) prior to the onsite information-gathering

visit, preferably no later than September 9, 2011. Where practical, please provide copies

electronically unless specified otherwise with folders indexed by request number. If documents

are provided as stored in your electronic records system without titles, please provide

titles/descriptions in the electronic file name or, as a minimum, an index by number with the

appropriate title/description.

1. The current version of your fire protection program and fire hazards analysis.

2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate

acceptable plant response.

3. Copies of the licensing basis documents for fire protection (safety evaluation reports,

pertinent sections of the final safety analysis report, exemptions, deviations, letters

to/from the NRC regarding fire protection/fire safe shutdown, etc.).

4. The fire probabilistic risk assessment or portions of the plants individual plant

examination for external events report addressing fire events. Also, include the results

of any post-IPEEE reviews, and listings of actions taken/plant modifications conducted in

response to IPEEE information.

5. A copy of the documents that support your multiple spurious operation evaluations (i.e.,

expert panel reports, evaluation packages, et cetera).

6. Information related to the design change for power-operated relief valves.

7. The thermal-hydraulic analysis and other evaluations that support the recent power-

operated relief valve control circuit modification and any analyses that supported the

recently retracted license amendment request.

8. Information that supports closure of Licensee Event Reports 2009-003-00, 2010-007-00,

and 2010-013-00. This should include corrective action program documents and design

change packages.

Please provide the following documentation (items 9 - 50) during the information-gathering visit

in order to support inspection preparation. Whenever practical, please provide copies

electronically, except for drawings. Drawings should be provided as paper copies of sufficient

size (Size D) such that all details are legible. If documents are provided as stored in your

electronic records system without titles, please provide titles in the electronic file name or, as a

minimum, a listing by number with the appropriate title/description.

9. Plant layout and equipment drawings (include drawing titles or descriptions) for fire

areas that identify: (a) the physical plant locations of major hot standby and cold

shutdown equipment; (b) plant fire area and/or fire zone delineation; and (c) the

-1- Enclosure

locations of fire protection equipment, such as detection, suppression, and post-fire

emergency lighting units; and (d) fire area boundaries. The specific documents needed

to support inspection preparation will be discussed during the site visit.

10. Fire protection program implementing procedures (e.g., administrative controls, operator

response procedures for fires, fire fighting procedures, etc.).

11. Operating procedures used for achieving and maintaining hot and cold shutdown

conditions from the control room in the event of a fire outside the control room (III.G.2

areas).

12. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)

capability with or without control room evacuation.

13. A list of equipment used to achieve and maintain hot standby and cold shutdown in the

event of a fire (safe shutdown equipment lists).

14. Piping and instrumentation (flow) diagrams showing the components used to achieve

and maintain hot standby and cold shutdown for normal and alternate shutdown. Please

provide one copy of the piping and instrumentation (flow) diagrams for these systems of

a size sufficient to read all details. These should include the systems used for reactor

coolant system (RCS) makeup, RCS pressure control, decay heat removal, and

reactivity control, including the essential support systems.

15. A listing, with descriptions, of design change packages which were determined to impact

fire protection and post-fire safe shutdowns, performed since October 1, 2008.

16. A listing of open and closed corrective action documents initiated since

December 1, 2008, which relate to the fire protection program or equipment, including

corrective actions for fire-induced circuit failures, both single and multiple spurious

actuations (for the selected fire areas). Include Corrective Action Process document

number, date, and subject.

17. A listing of the applicable codes and standards (with the versions/dates) related to the

design of plant fire protection features and evaluations of any code deviations. Copies

of these codes should be available for review.

18. A listing of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps and suppression systems. Also, include a

list of maintenance and surveillance testing procedures used to verify fuse and breaker

coordination in accordance with the post-fire safe shutdown coordination analysis.

19. Drawings of the portions of the emergency lighting system that support fire response.

20. Drawings of communication systems credited in the license basis for firefighting and

plant operations during fires where control room is occupied and/or evacuated.

21. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.

-2- Enclosure

22. Procedures used to remove smoke from safety-related areas and the engineering

studies or calculations that support the design basis.

23. Copies of fire protection program change evaluations (Generic Letter 86-10 evaluations)

performed since October 1, 2008.

24. Maintenance rule performance criteria and a summary of the performance history for

systems or functions monitored within the maintenance rule program that support the fire

protection program or involve safe shutdown equipment, over the period since

October 1, 2008.

25. A copy of fire protection program requirements (e.g., limiting conditions for operation,

surveillance test requirements) covered by Technical Specifications, Technical

Requirements Manual, Updated Final Safety Analysis Report, or similar documents.

26. Copies of internal and external self-assessments, audits, peer-assessments or similar

reviews related to post-fire safe shutdown capability or the fire protection program

completed since October 1, 2008.

27. A list of manual actions taken outside the control room which are credited to mitigate the

consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should

group actions by the initiating fire area or zone and indicate where the action must take

place.

28. Electronic copies of operator study guides (i.e., lesson plan text and graphics) or design

basis documents that describe the purpose/function/operating characteristics of the safe

shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and

reactivity control, including the essential support systems).

29. Two copies of one-line diagrams of the AC and vital DC electrical distribution systems.

These should depict how power gets from the switchyard to the engineered safety

feature loads (480V and 4160V).

30. A list of automatic and manually initiated gaseous fire suppression systems in the plant,

giving location and the key equipment being protected.

31. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or

maintain hot shutdown and b) reach and/or maintain cold shutdown.

32. A list of high to low pressure interface valves.

33. A copy of procedures governing the training and operation of the fire brigade.

34. Organization charts of site personnel down to the level of fire protection staff personnel.

35. A contact list of key site personnel who will be supporting this inspection, giving location

of their office and phone number onsite.

-3- Enclosure

36. The team would like to observe an unannounced fire brigade drill in the plant, if possible,

during the week of October 31, 2011. Please put us in contact, during the onsite

information gathering trip, with the appropriate personnel for planning drills.

37. The team would like to perform a walkthrough of the procedure for control room

evacuation due to fire with qualified operators in the plant during the week of October 17,

2011. Please put us in contact, during the onsite information gathering trip, with the

appropriate personnel for planning the walkthrough.

The following documents (items 38 - 50) involve B.5.b mitigating strategies.

38. A copy of the license condition that incorporated the requirements issued to address the

requirements of Section B.5.b of the ICM Order, EA-02-026, dated February 25, 2002,

and 10 CFR 50.54(hh)(2).

39. A list of all modifications to regulatory commitments made to meet the requirements of

Section B.5.b of the ICM Order, EA-02-026, dated February 25, 2002, the subsequently

imposed license conditions, and 10 CFR 50.54(hh)(2).

40. A list of procedures/guidelines which were revised or generated to implement the

mitigation strategies. These could be extensive damage mitigation guidelines (EDMGs),

severe accident management guidelines (SAMGs), emergency operating procedures

(EOPs), abnormal operating procedures (AOPs), etc.

41. A matrix that shows the correlation between the mitigation strategies identified in

Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that are

used to implement each strategy.

42. A list of engineering evaluations/calculations that were used to verify engineering bases

for the mitigation strategies.

43. Copies of piping and instrumentation diagrams (P&ID) or simplified flow diagrams for

systems relied upon in the mitigation strategies. These could be the type used for

training.

44. A list of modification packages and simplified drawings/descriptions of modifications that

were made to plant systems to implement the mitigation strategies.

45. Copies of procedure(s) used to inventory equipment (hoses, fittings, pumps, etc.)

required to be used to implement the mitigation strategies.

46. A list of B.5.b strategies, if any, which have implementing details that differ from that

documented in the submittals to the NRC and the safety evaluation report.

47. A copy of site general arrangement drawing(s) that show the majority of buildings/areas

referenced in B.5.b documents.

48. Training records/ training matrix/ lesson plans related to B.5.b.

-4- Enclosure

49. Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)

required to implement any mitigating strategies.

50. The team would like to perform a walkthrough of the procedure implementing a sample

mitigating strategy (to be selected by the inspector during the information gathering visit)

and the inventory equipment (hoses, fittings, pumps, etc.) required to be used to

implement the mitigation strategies during the week of October 31, 2011. Please put us

in contact with the appropriate personnel for planning the walkthrough during the onsite

information gathering trip.

The following documentation needs (items 51 - 53) will be dependent upon sample selections,

and will be finalized during discussions with your staff. Please provide the required documents

by October 3, 2011. Whenever practical, please provide copies electronically. Drawings should

be provided as paper copies of sufficient size such that all details are legible.

51. Pre-fire plans for the selected fire areas (areas to be selected by the team during the

information-gathering trip).

52. List of identified fire induced circuit failure configurations (for the selected fire areas) that

could prevent operation or cause maloperation of equipment credited for safe shutdown

in the event of a fire. Include failure configurations associated with hot shorts, open

circuits, or shorts to ground identified as potentially causing spurious or multiple spurious

actuations or maloperations of this equipment.

53. Cable routing information for components and equipment, credited for safe shutdown in

the selected fire areas. This information request item will be discussed and finalized

with your staff during the information gathering visit.

-5- Enclosure