December 16, 2010, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc. Regarding Progress on National Fire Protection Association (NFPA) Standard 805 Transition Activities
ML110110647
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/13/2011
From: Mahesh Chawla
Plant Licensing Branch III
To:
Chawla M, NRR/DORL, 415-8371
References
TAC ME0072
Download: ML110110647 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 January 13, 2011 LICENSEE:

Entergy Operations, Inc. (ENO)

FACILITIES:

Palisades Nuclear Plant (PNP)

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON DECEMBER 16, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The enclosure provides the status of each task and shows several tasks as complete. The licensee reported that Palisades NFPA 805 project is delayed and the new completion date is May 27,2011. The licensee is bringing additional resources to support this date and will also incorporate comments from independent Probabilistic Risk Assessment reviews and any lessons learned from Oconee Safety Evaluation Report.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155).

made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

iil 1\\

/jlVJd)&1 f1;L Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via ListServ

12/16/10 Palisades NFPA 805 Project Milestones NEI Task No.

Title Milestone Date Status Start Date Task 1:

Transition of Nuclear Safety Performance Criteria (NEI 04-02 Table B-2\\

12117110 See Comments Task 2:

Fundamental Fire Protection Program & Design Elements INEI 04-02 Table B-1\\

03/04/11 See Comments Task 3:

Radioactive Release Transition IINEI 04-02 Table G-1 \\

Complete Task 4:

Nuclear Safety Analysis Transition NEI 04-02 Table B-3\\

03129111 See Comments ST 4.1.1 Off-Site Power Cable Selection and Analysis 02111/11 On Track ST 4.1.2 Other Power Cable Selection and Analysis Complete ST4.1.3 Subsequent Cablellnstrument Identification & Analysis Complete ST4.1.4 App. R Cable Issues from the FPRA Peer Review 03/29/11 See Comments Task 5:

Non-Power Operational Modes Transition NEI 04-02 Table F-1) 02102111 See Comments Task 6:

Intemal Events PRA Complete ST 6.2.1 Prepare LERF Model Complete ST 6.2.2 Update Flooding Analysis Complete ST 6.3 Thermal Hydraulic Analysis for MSOIHRA Complete ST 6.4 Intemal Events PRA Peer Review Complete Task 7:

Fire PRA 04/01/11 See Comments ST 7.6.4 R3 Intemal Events Model Complete ST 7.7 Quantification Risk Screening Complete ST 7.8 Scoping for Fire Modeling Complete ST 7.9/10 Circuit Failure Mode Likelihood Analysis Complete ST 7.12 Post Fire HRA 02103/11 See Comments ST 7.13 Seismic Fire Interaction Assessment Complete ST 7.14 Fire Risk Quantification 03/15/11 See Comments ST 7.15 Uncertainty and Sensitivity Analysis 03/21/11 See Comments ST 7.17.4 In-Process Fire PRA Peer Review Complete ST 7.17.5 Final Fire PRA Peer Review 04/01/01 See Comments Task 8:

NFPA 805 Fire Risk 1Change Evaluations 03/28/11 See Comments ST 8.1 Fire Risk 1Change Evaluations 03116111 See Comments ST 8.2 Non-Compliance Risk Evaluations 03/23/11 See Comments 01119111 Task 10:

Transition Report 04/13/11 See Comments Task 11:

License Amendment Request (LAR) 05/27/11 On Track Comments:

Task 1 - essentially complete awaiting Oconee RAI closures and the Oconee SER to acquire any possible lessons learned.

Task 2 - in final comment resolution and is also awaiting Oconee RAI closures and is being held open pending the Oconee SER to acquire any possible lessons learned.

Task 4 - Completion extended due to incorporation of comments from independent PRA review associated with cable circuit analysis, fire risk evaluations, and evaluation of variances from deterministic requirements.

Task 5 - essentiallycompletependinglessonslearnedfrom the OconeeSER submittal.

Task 7 - Completion extendeddue to extensionof Subtasks7.14& 7.15 basedon alignmentwith Task4 extension.

Tasks8 & 10- Task 7 is pushingout Task 8 & 10 as the Fire Risk Evaluations (FRE's)& TransitionReport(TR)can not be completed until the Deterministic Fire PRA is complete.

Task11 - The new Palisades' NFPA805 LAR submittaldate is 5/27/11 Additionalresourceshave been obtainedto support this date.

E:\\Palisades\\PLP\\Enforcement Extension\\NRC Canf calls\\Mileslone Itrs\\NRC Milestones 12-16-10.xls

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS DECEMBER 16, 2010 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer John Elleaood Senior Resident Insoector REGION ENTERGY Jim Kuemin Licensing Engineer Jim Miksa Engineering Programs Manager Tom Swiecicki Fire Protection Lead Engineer Chad Main Project Manager Roger Stobert Contract Project Manager Brian Bogan PRA Lead Amy Hazelhoff Contract Engineer

ML083370155),

made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

Mahesh Chawla, Project Manager IRAJ Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1. Table - Palisades NFPA 805 Project Milestones
2. Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:

PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGiessner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEllegood. Rill SBagley, EDO R-III CTucci, NRR ADAMS Accession No' ML110110647 "via email OFFICE LPL3-1/PM LPL3-1/LA DRAlAFPB/BC LPL3-1/BC NAME MChawla BTuily /Triertis for AKlein*

RPascarelli DATE 01/13/11 01/12/11 01/11/11 01/13/11