Summary of Telephone Conference Call Held on March 30, 2010, Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc. Regarding Progress on National Fire Protection Association (NFPA) Standard 805 Transition Activities
ML101440247
Person / Time
Site: Palisades Entergy icon.png
Issue date: 06/08/2010
From: Mahesh Chawla
Plant Licensing Branch III
To:
Division of Operating Reactor Licensing
Chawla M, NRR/DORL, 415-8371
References
TAC ME0072
Download: ML101440247 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 Jillle 8, 2010 LICENSEE: Entergy Operations. Inc.

FACILITIES: Palisades Nuclear Plant

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MARCH 30, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The enclosure provides the status of each task and shows several of the tasks as complete. The licensee reported that all the tasks were on track and there were no other concerns with respect to meeting the final LAR issuance date of December 31, 2010. Enclosure 2 provides the list of all attendees.

Background

On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML083260577). NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

~??!ML Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ

3/30/10 Palisades NFPA 805 Project Milestones NEI Task Milestone Start Title Status' No. Date' Date 3 Transition of Nuclear Safety Performance Criteria Task 1:

INEI 04-02 Table B-2\

09/24/10 On Track -

Fundamental Fire Protection Program & Design Elements Task 2:

IINEI 04-02 Table B-1 \

09/23/10 On Track -

Task 3: Radioactive Release Transition (NEI 04-02 Table G-1) 09/23/10 On Track -

Task 4: Nuclear Safety Analysis Transition (NEI 04-02 Table B-3) 11/01/10 On Track -

ST 4.1.1 Off-Site Power Cable Selection and Analysis 11/01/10 On Track -

ST 4.1.2 Other Power Cable Selection and Analysis - Complete -

ST 4.1.3 Subsequent Cable/Instrument Identification & Analysis 06/18/10 On Track -

Non-Power Operational Modes Transition Task 5:

IINEI 04-02 Table F-1\

09/23/10 On Track -

Task 6: Intemal Events PRA 11/12/10 On Track -

ST 6.2.1 Prepare LERF Model - Complete -

ST 6.2.2 Update Flooding Analysis - Complete -

ST6.3 Thermal Hydraulic Analysis for MSO/HRA - Complete -

ST6.4 Intemal Events PRA Peer Review - Complete -

Task 7: Fire PRA 10/12110 On Track -

ST 7.6.4 R3 Internal Events Model - Complete -

ST7.7 Quantification Risk Screening - Complete -

ST7.8 Scoping for Fire Modeling - Complete -

ST 7.9/10 Circuit Failure Mode Likelihood Analysis - Complete -

ST7.12 Post Fire HRA 08/27/10 On Track -

ST7.13 Seismic Fire Interaction Assessment - Complete -

ST 7.14 Fire Risk Quantification 08/06/10 On Track -

ST 7.15 Uncertainty and Sensitivity Analysis 08/06/10 On Track -

ST 7.17.4 In-Process Fire PRA Peer Review - Complete -

ST7.17.5 Final Fire PRA Peer Review 06/25/10 On Track -

Task 8: NFPA 805 Fire Risk / Change Evaluations 09/23/10 On Track -

ST 8.1 Fire Risk / Change Evaluations 09/23/10 On Track -

ST 8.2 Non-Compliance Risk Evaluations 09/23/10 On Track OS/24/10 Task 10: Transition Report 11/15/10 On Track -

Task 11: License Amendment Request (LAR) 12/31/10 On Track -

Notes:

1 The currentschedule(805 T2-2N 22MAR10) dates were validated to be on or before these dates unlessotherwisenoted.

2 "On Track" means that the task currentpercentage completed ill the expected completion percent and the expected completion date for the task is projectedto be met.

3 Start dates providedare estimates and may vary contingentupon predecessorcompletion and available resourcesat that time. Even if this start date is adjusted. the completion date is slill expected to be met unless indicated otherwise.

Comments:

None.

Enclosure 1 E:IPalisadeslPLPIEnforcement Extension\NRC Conf callslMilestone Itrs\NRC Milestones 03-30-10.xls

TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.

LIST OF PARTICIPANTS MARCH 30, 2010 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Mahesh Chawla Proiect Manaaer HEADQUARTERS Harrv Barrett Senior Fire Protection Enaineer ENTERGY Paula Anderson Licensina Manaaer Jim Kuemin Licensing Engineer Tom Swiecicki Fire Protection Lead Chad Main Project Manager Brian Bogan PRA Lead Roger Stobert Contract Project Manager NFPA 805 Alan Blind Engineering Director Frank Yanik PRA Engineer Enclosure 2

ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.

Mahesh Chawla, Project Manager IRA!

Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosures:

1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:

PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett, NRR RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEllegood, Rill SBagJey, EDO R-1I1 CSteger, NRR ADAMS Accession No""" ML101440247 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC NAME MChawia BTully AKlein RPascarelli DATE OS/27/10 06/08/10 06/01/10 06/08/10