UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 18, 2010 LICENSEE:
Entergy Operations, Inc. (ENO)
FACILITIES:
Palisades Nuclear Plant (PNP)
SUB.IECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 23,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The enclosure provides the status of each task and shows several of the tasks as complete. The licensee reported that all the tasks were on track and there were no other concerns with respect to meeting the final license amendment request issuance date of December 31, 2010. In accordance with the schedule submitted by the licensee, the final fire probabilistic risk assessment peer review has been scheduled for the week of August 22, 2010. NRC staff expressed the desire to participate in this review.
However, NRC participation in the peer review has not been finalized with the licensee.
Background
On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155),
made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
- 1. Table - Palisades NFPA 805 Project Milestones
- 2. Table - List of Attendees cc w/encls: Distribution via ListServ
6/23/10 Palisades NFPA 805 Project Milestones NEI Task No.
Title Milestone Date' Status' Start Date' Task 1:
Transition of Nuclear Safety Performance Criteria INEI 04-02 Table B-2\\
09/24/10 On Track Task 2:
Fundamental Fire Protection Program & Design Elements INEI 04-02 Table B-1\\
09/23/10 On Track Task 3:
Radioactive Release Transition NEI 04-02 Table G-1 \\
09/23/10 On Track Task 4:
Nuclear Safety Analysis Transition
'NEI 04-02 Table B-3\\
11/01/10 On Track ST4.1.1 Off-Site Power Cable Selection and Analysis 11/01/10 On Track ST 4.1.2 Other Power Cable Selection and Analysis Complete ST 4.1.3 Subsequent Cable/Instrument Identification &
Analvsis Complete Task 5:
Non-Power Operational Modes Transition
'NEI 04-02 Table F-1\\
09/23/10 On Track Task 6:
Internal Events PRA 11/12110 On Track ST 6.2.1 Prepare LERF Model Complete ST 6.2.2 Update Flooding Analysis Complete ST6.3 Thermal Hydraulic Analysis for MSO/HRA Complete ST6.4 Internal Events PRA Peer Review Complete Task 7:
Fire PRA 10/12110 On Track ST 7.6.4 R3 Internal Events Model Complete ST7.7 Quantification Risk Screening Complete ST7.8 Scoping for Fire Modeling Complete ST 7.9/10 Circuit Failure Mode Likelihood Analysis Complete ST 7.12 Post Fire HRA 08/27/10 On Track ST 7.13 Seismic Fire Interaction Assessment Complete ST 7.14 Fire Risk Quantification 08/10/10 See Comments ST 7.15 Uncertainty and Sensitivity Analysis 08/06/10 On Track ST 7.17.4 In-Process Fire PRA Peer Review Complete ST 7.17.5 Final Fire PRA Peer Review 08/27/10 See Comments 08/22110 Task 8:
NFPA 805 Fire Risk / Change Evaluations 09/23/10 On Track ST8.1 Fire Risk / Change Evaluations 09/23/10 On Track ST 8.2 Non-Compliance Risk Evaluations 09/23/10 On Track 07/13/10 Task 10:
Transition Report 11/15/10 On Track Task 11:
License Amendment Request (LAR) 12131/10 On Track Noles:
1 The current schedule (805 T3-4D 14JUN10) dales were validated to be on or before these dates unless otherwise noted.
2 *On Track-means that the task current percentage completed ~ the expected completion percent and the expected completion date for the task is projected to be met.
3 Start dates provided are estimates and may vary contingent upon predecessor completion and available resources at that time. Even if this start date is adjusted, the completion dale is still expecled to be met unless indicated otherwise.
Comments:
7.14 - Current scheduled milestone date is 4 days after previous reported milestone date. Within the schedule tolerance.
7.17.5 - The Final Fire PRA Peer Review has been moved to August to accommodate model completion and vendor alignment issues.
Page 1 of 1
TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.
LIST OF PARTICIPANTS JUNE 23, 2010 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer Alan Dahbur Electrical Engineer REGION ENTERGY Tom Swiecicki Fire Protection Lead Chad Main Project Manager Jim Miksa Engineering Program Manager Jim Kuemin Licensing Engineer Roger Stobert Contract Project Manager NFPA 805
Au[;Ust 18, 2010 LICENSEE:
Entergy Operations, Inc. (ENO)
FACILITIES: Palisades Nuclear Plant (PNP)
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 23,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The enclosure provides the status of each task and shows several of the tasks as complete. The licensee reported that all the tasks were on track and there were no other concerns with respect to meeting the final license amendment request issuance date of December 31, 2010. In accordance with the schedule submitted by the licensee, the final fire probabilistic risk assessment peer review has been scheduled for the week of August 22, 2010. NRC staff expressed the desire to participate in this review.
However, NRC participation in the peer review has not been finalized with the licensee.
Background
On December 9,2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155),
made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
Mahesh Chawla, Project Manager IRA!
Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
- 1. Table - Palisades NFPA 805 Project Milestones
- 2. Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:
PUBLIC LPL3-1 rtf RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR naylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrell RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEliegood, Rill SBagley, EDO R-III CTucci, NRR ADAMS Accession No' ML102080623 OFFICE LPL3-1/PM LPL3-1/LA DRAlAFPB/BC LPL3-1/BC NAME MChawla BTuily /THarris for AKlein RPascarelli DATE 08/19/10 07/30/10 08/17/10 08/18/10 OFFICIAL RECORD COpy