ML102980312

From kanterella
Jump to navigation Jump to search
Email from Cline, Leonard to Lew, David, Et Al, Salem Unit 1 AFW Piping Update.
ML102980312
Person / Time
Site: Salem PSEG icon.png
Issue date: 04/15/2010
From: Leonard Cline
Reactor Projects Branch 3
To: Clifford J, David Lew
Division Reactor Projects I
References
FOIA/PA-2010-0334
Download: ML102980312 (1)


Text

Ziev, Tracey From: Cline, Leonard Sent: Thursday, April 15, 2010 4:31 PM To: Lew, David; Clifford, James Cc: Burritt, Arthur; Schroeder, Daniel; Welling, Blake; OHara, Timothy; Conte, Richard; Ennis, Rick

Subject:

RE: Salem Unit 1 AFW piping Update No significant update on either the Unit 1 AFW or the Unit 1 containment liner issues as of 1600 today (4/15).

With respect to the containment liner there was not a lot of progress on the UT measurements through the day. They have spent most of the day cleaning and prepping the surfaces for the UTs and expect to have results tomorrow. With regard to the AFW piping the only new information is that the completion of the FEA has been pushed to Monday (4/19).

From: Cline, Leonard Sent: Tuesday, April 13, 2010 3:50 PM To: Lew, David Cc: Burritt, Arthur; Schroeder, Daniel; Welling, Blake; Cline, Leonard; OHara, Timothy; Conte, Richard; Ennis, Rick

Subject:

Salem Unit 1 AFW piping Update Progress on the UTs of the Salem Unit 1 AFW piping has been slowed by the rain. They will probably not complete the UTs until tomorrow, but may still be able to complete the FEA before the end of the day tomorrow (4/14). At the latest PSEG expects to complete the FEA for the Unit 1 piping by Thursday (4/15).

There are no other significant updates for this issue at this time.