Safety Evaluation Input for Watts Bar, Unit 2, FSAR 9.1 and 9.5
ML100880477
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 01/21/2010
From: Steve Jones
NRC/NRR/DSS/SNPB
To: Joel Wiebe
Watts Bar Special Projects Branch
Wiebe, Joel NRR/DORL/WBSP, 415-6606
References
Download: ML100880477 (1)


Text

From: Jones, Steve Sent: Thursday, January 21, 2010 3:15 PM To: Epperson, Dan; Wiebe, Joel Cc: WBN2HearingFile Resource; Smith, Edward

Subject:

RE: Watts Bar 2 Task Status - Section 9.1 and 9.5 Follow Up Flag: Follow up Flag Status: Flagged Dan and Joel, I completed the initial product review for Sections 9.1.1, 9.5.4, 9.5.5, and 9.5.6. With the exception of the page containing the beginning of of Section 9.5.4, the pages are all identical to Amendment 92. The page containing the beginning of Section 9.5.4 has no change bars indicating a change within that Section, either. Consequently, there is no review/SE input necessary for these Sections. Please update the task list accordingly.

Dan, I attempted to add notes/comments in EPM, but that function did not work for me. Should I be able to do that?

Steve From: Epperson, Dan Sent: Thursday, January 21, 2010 12:28 PM To: Jones, Steve Cc: Rice, Ayanna

Subject:

Watts Bar 2 Task Status - Section 9.1 and 9.5

Steve, You have new tasks on the Watts Bar 2 project. Please check your task assignments in EPM under "My Tasks" and update the "% Work Complete" for "Conduct Product Review" for 9.1.1, 9.5.4, 9.5.5, and 9.5.6 with task start date of 1/4/10.

In addition, you have new tasks for "Complete Draft SE section w/ Open Items and Forward to PM" for 9.5.7 and 9.5.8 with task start date of 1/4/10. Are there going to be RAIs for these sections? If so, then we will need to revise the schedule to add the appropriate RAI review tasks.

Let me know.

Dan E-mail Properties

Mail Envelope Properties (BBC4D3C29CD0E64E9FD6CE1AF26D84D51FA6757AED)

Subject:

RE: Watts Bar 2 Task Status - Section 9.1 and 9.5 Sent Date: 1/21/2010 4:43:26 PM Received Date: 1/21/2010 3:17:32 PM From: Jones, Steve Created By: Steve.Jones@nrc.gov Recipients:

Dan.Epperson@nrc.gov (Epperson, Dan)

Tracking Status: None Joel.Wiebe@nrc.gov (Wiebe, Joel)

Tracking Status: None WBN2HearingFile.Resource@nrc.gov (WBN2HearingFile Resource)

Tracking Status: None Edward.Smith@nrc.gov (Smith, Edward)

Tracking Status: None Post Office:

HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 10740 1/21/2010 Options Expiration Date: