HBL-09-009, Post-Shutdown Decommissioning Activities Report, Revision 3

From kanterella
(Redirected from ML091880320)
Jump to navigation Jump to search
Post-Shutdown Decommissioning Activities Report, Revision 3
ML091880320
Person / Time
Site: Humboldt Bay
Issue date: 06/30/2009
From: Roller P
Pacific Gas & Electric Co
To:
Document Control Desk, NRC/FSME
References
HBL-09-009, OL-DPR-07
Download: ML091880320 (29)


Text

Pacific Gas and Electric Company 1000 King Salmon Avenue Humboldt Bay PowerPlant Eureka, CA 95503 PaulJ. Roller 707/444-0700 Directorand PlantManagerHumboldt Bay Nuclear June 30, 2009 PG&E Letter HBL-09-009 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Docket No. 50-133, OL-DPR-7 Humboldt Bay Power Plant, Unit 3 Post-Shutdown Decommissioning Activities Report, Revision 3

Dear Commissioners and Staff:

Pursuant to 10 CFR 50.82(a)(7), Pacific Gas and Electric Company (PG&E) is submitting the enclosed Revision 3 to the Post-Shutdown Decommissioning Activities Report (PSDAR) for Humboldt Bay Power Plant, Unit 3. PSDAR Revision 3 reflects a change in decommissioning activity status since PSDAR Revision 2 was submitted to the NRC on March 31', 2008. The PSDAR has been revised to (1) provide a detailed schedule of decommissioning activities, (2) reflect the use of NUREG-0586, Supplement 1, "Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities," dated November 2002, that supersedes the original issuance of NUREG-0586 dated August 1988, and (3) discuss a site-specific issue not previously described in the PSDAR, including PG&E's method for ensuring this site-specific issue remains bounded by previously issued environmental impact statements. These changes are pervasive throughout the PSDAR and are, therefore, not identified with revision bars.

In accordance with 10 CFR 50.82(a)(4)(i), the enclosed PSDAR continues to describe planned Unit 3 decommissioning activities and associated schedule, provide an estimate of expected costs, and discuss reasons for concluding that the environmental impacts associated with site-specific decommissioning activities are bounded by appropriate, previously issued, environmental impact statements.

Sincerely, Paul J. Ro ller Directorand Plant ManagerHumboldt Bay Nuclear Enclosure

Document Control Desk PG&E Letter HBL-09-009 June 30, 2009 Page 2 cc/enc:- Gary W. Butner, DHS Elmo E. Collins, Jr.

Robert Evans John B. Hickman Humboldt Distribution

Enclosure PG&E Letter No. HBL-09-009 POST-SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT HUMBOLDT BAY POWER PLANT, UNIT 3 Revision 3 May 2009

Enclosure PG&E Letter No. HBL-09-009 TABLE OF CONTENTS Section Title Page No.

1.0 INTRODUCTION

1

2.0 BACKGROUND

2

3.0 DESCRIPTION

AND SCHEDULE OF PLANNED DECOMMISSIONING ACTIVITIES 3 4.0 ESTIMATE OF EXPECTED DECOMMISSIONING COSTS 4 5.0 ENVIRONMENTAL IMPACTS 5

6.0 REFERENCES

7 ATTACHMENT A - DECOMMISSIONING SCHEDULE 8 i

Enclosure PG&E Letter No. HBL-09-009

1.0 INTRODUCTION

Pacific Gas and Electric Company (PG&E) submitted the initial Humboldt Bay Power Plant (HBPP), Unit 3, Post-Shutdown Decommissioning Activities Report (PSDAR) to the Nuclear Regulatory Commission (NRC) on February 27, 1998, in accordance with 10 CFR 50.82 (a)(4)(i). PG&E is submitting Revision 3 to the PSDAR in accordance with 10 CFR 50.82 (a)(7) to provide the NRC with a detailed decommissioning activity schedule, to use a more recent NRC guidance document as a reference, and to inform the NRC of a site-specific issue not previously described in the PSDAR.

On December 11, 2008, PG&E completed the transfer of spent fuel from the HBPP Unit 3 spent fuel pool (SFP) into the Humboldt Bay Independent Spent Fuel Storage Installation (ISFSI). As a result, PG&E is ready to begin decontamination and dismantlement of Unit 3. PSDAR Section 3.0 describes planned decommissioning activities, and Attachment A provides a detailed decommissioning schedule.

Previous revisions of the PSDAR discussed reasons for concluding that the environmental impacts associated with site-specific decommissioning activities are bounded by appropriate, previously issued, environmental impact statements; specifically, NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities" (FGEIS)

(Reference 1) and NUREG-1166, "Final Environmental Statement for Decommissioning Humboldt Bay Power Plant, Unit No. 3" (Reference 2). In November 2002, the FGEIS was superseded by NUREG-0586, Supplement 1, "Generic Environmental Impact Statement oh Decommissioning of Nuclear Facilities," (GELS) (Reference 3). PG&E has reviewed the GElS and continues to conclude that the environmental impacts associated with site-specific decommissioning activities are bounded by appropriate, previously issued, environmental impact statements.

Revision 3 of the PSDAR addresses the potential environmental impacts of decommissioning activities that are affected by a HBPP site-specific issue not previously described in the PSDAR. This site-specific issue pertains to plant systems contaminated with alpha emitting radionuclides resulting from fuel clad failures that occurred during reactor operation. PG&E will apply the guidance and techniques in the GElS to ensure that the environmental impacts associated with the site-specific issue remain bounded by the GELS.

Section 5.0 discusses the alpha issue in more detail.

In accordance with 10 CFR 50.82 (a)(4)(i), this PSDAR describes the planned decommissioning activities and associated schedule for Unit 3, and provides an estimate of expected costs.

I

Enclosure PG&E Letter No. HBL-09-009

2.0 BACKGROUND

Unit 3 was operated by PG&E as a 65 MWe natural circulation boiling water reactor (BWR). In addition to Unit 3, two oil and/or natural gas fueled units, Units 1 and 2, exist on the plant site and continue to be operated by PG&E.

Unit 1 is rated at 52 MWe, and Unit 2 is rated at 53 MWe. Two diesel-fueled gas turbine Mobile Emergency Power Plants, each rated at 15 MWe, are also currently located at the plant and are operated by PG&E.

Unit 3 was granted a construction permit by the Atomic Energy Commission (AEC) on October 17, 1960, and construction began in November 1960. The AEC issued Provisional Operating License No. DPR-7 for Unit 3 in August 1962. Unit 3 achieved initial criticality on February 16, 1963, and began commercial operation in August 1963.

On July 2, 1976, PG&E shutdown Unit 3 for an annual refueling and to conduct seismic-studies and implement seismic modifications. Unit 3 remained in a shutdown condition pending completion of ongoing seismic and geologic studies. In December 1980, it became apparent to PG&E that the cost of completing required backfits would likely make it uneconomical to restart the unit. Work was suspended at that time awaiting further guidance regarding backfitting requirements. In 1983, updated economic analyses confirmed that restarting Unit 3 would not be economical. Therefore, in June 1983, PG&E announced its intention to decommission Unit 3.

The NRC issued License Amendment 19 for Unit 3 on July 16, 1985, that modified the plant status to a possess-but-not-operate status. The NRC's Decommissioning Safety Evaluation Report was issued on April 29, 1987 (Reference 4). The Unit 3 License expires in 2015.

During the 13 years of Unit 3 commercial operation, 11 core cycles of operation were completed. Unit 3 operated a total of 7.85 effective full power years. The fuel was removed from the reactor in January and February 1984, and placed in the SFP. The spent nuclear fuel was transferred to the Humboldt Bay ISFSI in 2008 and will remain stored in the ISFSI until a high-level waste repository has been built, and the Department of Energy assumes control of the fuel. The ISFSI license, issued by the NRC on November 17, 2005, expires in 2025.

2

Enclosure PG&E Letter No. HBL-09-009

3.0 DESCRIPTION

AND SCHEDULE OF PLANNED DECOMMISSIONING ACTIVITIES Several major inter-related activities are either currently ongoing or planned for the near future at the HBPP site.

  • Unit 3 decommissioning has started.
  • Units 1 and 2 will be replaced by a new generation facility, called the Humboldt Bay Generating Station (HBGS), currently under construction.
  • Units 1 and 2 will be decommissioned after HBGS begins commercial operation.
  • Unit 3 decommissioning will be completed following completion of Units 1 and 2 decommissioning.

Coordinating and scheduling these activities requires a great deal of planning, and the sequence is dependent upon successful completion of HBGS construction and operation, as well as successful decommissioning of Units 1 and 2.

Because spent fuel has been removed from the Unit 3 SFP and loaded into the ISFSI, decommissioning of Unit 3 has begun. Attachment A provides a schedule of planned decommissioning activities. This schedule incorporates cost and schedule assumptions for planned activities that are reflected in the latest decommissioning cost estimate (Reference 5). Studies for some of these activities are continuing, and, therefore, the schedule and methods identified in Attachment A may change. For example, the reactor vessel is assumed to be segmented; however, studies may show that disposing the vessel in one piece is feasible and advantageous. PG&E will continue to inform the NRC of significant schedule changes.

As shown on the-Attachment A schedule, PG&E started decommissioning Unit 3 in May 2009 by dismantling the main transformers, to be followed by decontaminating and dismantling the generator, turbine, condenser, pipe tunnel, and feed pump room that will provide space for future radwaste processing. PG&E plans to construct the HBGS during 2009 and 2010, and commence operation in mid-2010. Once the HBGS begins commercial operation, PG&E plans to dismantle and decommission Units 1 and 2. (Units 1 and 2 must remain operational until HBGS begins commercial operation to provide continued electrical services to the local area.) After Units 1 and 2 are decommissioned, the space previously occupied by Units 1 and 2 can be used as a lay-down area for the completion of Unit 3 decommissioning.

3

Enclosure PG&E Letter No. HBL-09-009 The schedule depicted in Attachment A is contingent upon HBGS beginning commercial operation in 2010. If construction and operation of HBGS is significantly delayed, PG&E may adjust the dismantlement priorities and schedule. PG&E will inform the NRC of significant schedule changes.

4.0 ESTIMATE OF EXPECTED DECOMMISSIONING COSTS PG&E submits annual decommissioning funding assurance reports to the NRC in accordance with the requirements of 10 CFR 50.75(f). Updates to decommissioning cost estimates and decommissioning trust fund balances are documented in these reports, the latest of which was submitted on March 31, 2009 (Reference 6).

The March 31, 2009 Decommissioning Funding Report for HBPP Unit 3 stated that at the end of calendar year 2008, the market value of the HBPP Unit 3 decommissioning trust funds was $331.1 million. PG&E estimated an additional $35.745 million (future nominal dollars) will need to be collected beginning in 2007 to coincide with decommissioning of HBPP Unit 3 beginning in 2009 based on a site-specific decommissioning cost estimate prepared by TLG Services, Inc. and adjusted per the Nuclear Decommissioning Cost Triennial Proceeding (NDCTP) Decision 07-01-003 from the California Public Utilities Commission (CPUC).

The March 31, 2009 Decommissioning Funding Report for HBPP Unit 3 further stated that, based on the site-specific cost estimate prepared by TLG Services, Inc. and adjustments as a result of the NDCTP Decision 07-01-003, PG&E has estimated that the decommissioning costs are approximately

$395.5 million ($37.1 million disbursed from the Trust(s) through December 2008 and $358.4 million future radiological removal costs) for HBPP Unit 3 in 2009 dollars. These costs do not include site restoration of the facilities ($6.5 million), nor spent fuel management until 2015 ($83.8 million).

On April 3, 2009, PG&E submitted to the CPUC an updated the site-specific cost estimate for HBPP Unit 3. PG&E will provide an update of the 2009 site-specific decommissioning cost estimate to the NRC in a future Decommissioning Funding Report when approved by the CPUC. Revised information pertaining to estimated decommissioning costs and the status of the trust fund will be documented in future Decommissioning Funding Reports sent to the NRC annually in accordance with 10 CFR 50.75(f).

4

Enclosure PG&E Letter No. HBL-09-009 5.0 ENVIRONMENTAL IMPACTS 10 CFR 50.82 (a)(4)(i) requires the PSDAR to include, "a discussion that provides the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be bounded by appropriate previously issued environmental impact statements." PG&E originally assessed the environmental impact of Unit 3 decommissioning in the Unit 3 Environmental Report, dated July 30, 1984 (Reference 7). The NRC response to the Environmental Report is documented in NUREG-1 166, dated April 1987.

Later, PG&E assessed the environmental impact of Unit 3 decommissioning based on NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities" (FGEIS) dated August 1988. More recently, the NRC evaluated the environmental impacts of decommissioning nuclear facilities, including HBPP, in NUREG-0586, GELS, Supplement 1, dated November 2002. The Supplement updates information from the 1988 FGEIS regarding technological advances in decommissioning activities and changes in NRC regulations. The environmental impacts described in the Supplement supersede those described in the 1988 FGEIS. As a result, PG&E has re-assessed the environmental impact of Unit 3 decommissioning based on NUREG-0586, Supplement 1.

The occupational dose for complete decommissioning of Unit 3, following 23 years of SAFSTOR, considers: (1) occupational dose received from placing Unit 3 in SAFSTOR and maintaining Unit 3 in SAFSTOR through 2008, (2) dose from all occupational activities required for the actual decommissioning of Unit 3 through 2015, and (3) occupational dose due to truck shipments.

The occupational dose for Unit 3 decommissioning will meet the regulatory standards in 10 CFR 20 and is, therefore, bounded by the criteria in the GELS.

Public dose from decommissioning Unit 3, following 23 years of SAFSTOR, considers direct exposure and gaseous and liquid effluents. Direct exposure and effluents in gaseous and liquid discharges are not expected to exceed the design objectives of 10 CFR 50, Appendix I, nor the dose and effluent concentration limits in 10 CFR 20 and 40 CFR 190. Therefore, the public dose from Unit 3 decommissioning is bounded by the criteria in the GELS.

At the time that HBPP Unit 3 entered commercial service in 1963, the nuclear fuel assemblies utilized stainless steel as the fuel rod cladding. The stainless steel-clad fuel experienced gross cladding failures during operation. These failures were severe enough that radioactive fuel was released from the cladding and dispersed throughout numerous plant systems, contaminating these systems with alpha emitting radionuclides, i.e., transuranic elements.

5

Enclosure PG&E Letter No. HBL-09-009 HBPP completed the transition from stainless steel to zircaloy assemblies in 1969.

Over the SAFSTOR period, as beta and gamma emitting radionuclides have decayed, alpha has become a more dominant factor in dose contribution.

Because alpha causes more severe biological damage when internal exposure occurs, the potential radiological dose consequences are likewise more severe. This issue leads to a unique, plant-specific concern that exists for HBPP decommissioning and is not discussed in the GELS.

The alpha issue was not discussed in previous revisions of the PSDAR.

However, it was described in two previous PG&E decommissioning funding assurance report submittals to the NRC: (1) PG&E Letter HBL-03-002, dated March 27, 2003, Enclosure 5 (Reference 8), and (2) PG&E Letter HBL 002, dated March 30, 2007, Enclosure 3 (Reference 9). These enclosures contain cost studies developed by TLG Services, Inc. and state "The extent of the alpha contamination will require additional radiological controls and will reduce the efficiency of component removal activities." HBPP will implement appropriate best management practices and mitigating measures so that the alpha issue will not invalidate NRC expectations nor the conclusions on radiological environmental impacts contained in the GELS.

Based on the above discussions, PG&E continues to conclude that Unit 3 decommissioning will be accomplished with no significant adverse environmental impacts, and because:

  • By implementing appropriate best management practices and mitigating measures to minimize the impacts of decommissioning activities, there are no unique aspects of the plant or decommissioning techniques that would invalidate or alter the conclusions of the GELS.
  • Delaying the dismantlement of Unit 3 following 23 years of SAFSTOR has resulted in considerable radioactivity decay with resultant reduced external dose rates and lower occupational deep dose equivalent exposure.
  • Public and occupational doses are bounded by the GElS criteria.
  • Radiation dose to the public will be minimal.
  • Decommissioning does not constitute an imminent health or safety problem and will generally have a positive environmental impact.

6

Enclosure PG&E Letter No.,HBL-09-009

6.0 REFERENCES

1. NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities," dated August 1988. \
2. NUREG-1 166, "Final Environmental Statement for Decommissioning Humboldt Bay Power Plant, Unit No. 3," dated April 1987.
3. NUREG-0586, "Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities," Supplement 1, dated November 2002.
4. NRC Safety Evaluation Report, Humboldt Bay Power Plant, Unit No. 3 Decommissioning, dated April 29, 1987.
5. TLG Services, Inc. Document P01-1604-002, Rev. 0, "Decommissioning Cost Study Report for the Humboldt Bay Power Plant, Unit 3, 2010 SAFSTOR," dated March, 2009.
6. PG&E Letter HBL-09-004, "Decommissioning Funding Report for Humboldt Bay Power Plant Unit 3," submitted to the NRC, dated March 31,2009.
7. Environmental Report, Attachment 6 to PG&E's application to decommission HBPP, dated July 30, 1984.

8 PG&E Letter HBL-03-002, "Decommissioning Funding Reports for Diablo Canyon Power Plants Units 1 and 2 and Humboldt Bay Power Plant Unit 3," submitted to the NRC, dated March 27, 2003.

9 PG&E Letter HBL-07-002,, "Decommissioning Funding Report for Humboldt Bay Power Plant Unit 3," submitted to the NRC, dated March 30, 2007.

7

Enclosure PG&E Letter No. HBL-09-009 ATTACHMENT A HUMBOLDT BAY POWER PLANT UNIT 3 DECOMMISSIONING SCHEDULE 8

Humboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 I Durat 2 2010 2011 20 2013 1 2014 '

Ara-Hmbld.

HBU3-1000 we.Pan Decommissioning Start 100% 04-May-09 A 0 0,-May"9*t9A, Area 0 Hum*tooldtPower Plant Milestone 0 .-  : .. .. . .........-p i t,:g a o.. Weste Prb ess ng . . . . . . . . . .

Area 1 Reconliguration of Turbine Building for Waste Processing HBU3-YDt-1 Main Transformers - Remove 95% 04-May-09 A 02-Jun-09 18 u Equip yni- ug-09 ! i Il 09n

  • P1'- i  !  ! 'i i ! ! i i! i*0 -y i.. i. !. : . ; . .  ?. i  : i: . i . i . ! . . . i . . . .. I HBU3-TB1 -2 Main Generator/Exciter House - 0% 03-Jun-09 21-Aug-09 46 i C
  • 9 " 11~. 9, Remove Equip Jul 0? Reo-09 i i i~ i i i ii ~ i i l ~ i  !! ~ ~ ii i i ii i i i HBU3-TB3-1 Reactor Feed Pump/Lube Oil - 0% 15-Jun-09 02-Dec-09 97 Remove Equip III*

i ii i  !  ! I 01 A i! i i i~ i i ii i iirrtl! i ii i~ i i HBU3-TB2-1 Main Condenser and associated 0% 14-Jul-09 01-Apr-11 356 piping removal HBU3-TBl-1 Main Turbine and Associated 0% 24-Aug-09 04-Jan-11 282 ?4-piping removal HBU3-TB2-2 Seal Oil Unit/Exciter Swgr - 0% 24-Aug-09 17-Dec-09 66 ?4- 17, Q ic-ý09 Remove Equip I

Are 2Turin Pie u nnueLl/pipe Galle/ryp 12 Nov 1iii ii Dy :1QArea? Tartairk.Pipe TurlneVPipeQaI~ery ENNER-ICflu-l .sm

-9vlwmmmm Tunnel - Remove Equip HBU3-TB4-2 Pipe Gallery - Remove Equip 0% 02-Dec-09 11-Nov-10 196

;.t 29, 24-Novi;

)beTOý ArO I Outside Atilaty:Equit meint I Area 3 Outside Ancillary Equipment 1'-Nov-1U 29-Nov-1I b ovni 0 lyorogen Yarn S2§ 0% 24-Nov-10 29-Nov-it0 4 Iv :to HBU3-T83-3 2400/480v Transformers -

Remove Equip Page 1 of 17 ASK tilter: HSPP Execution Activities 5-28-09.

H= Actual Work rn-r Critical Remaining Work V 1 Summary

== Remaining Work +

  • Milestone (c) Primavera Systems, In(

Humboldt Bay Power Plant Execution Activities Rev. I HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 Ae*ItD Durationns 2M00 2010 2011[i.1 2012 I 2013 1 2014 I1 2 l1 I HBU3-TB3-2 Propane Engine Generator 0% 30-Nov-10 02-Dec-10 3 04J-N11-0 )a M -

o-Fe,-l?.2 Area 4 Turtrinie Ancillary rob6s:ni Area 4 Turbine Ancillary Rooms HBU3-TB5-1 AnionlCatiori/Resin Tanks - 0% 04-Jan-lI 17-Mar-11 43 Remove HBU3-TB5-2 Condensate Demineralizers - 0% 18-Mar-11 02-May-l1 26

  • 0*-May,-I 1 i',

Remove Equip HBU3-TB6-2 Vacuum Pump/Condensate 0% 03-May-11 05-Jul- 1 36 1 05 uii-ý Pump - Remove Equip HBU3-TB6-1 Air Ejector/Gland Seal 0% 06-Jul- 1 30-Aug-11 32 ul 11 30-Aug Condenser - Remove Equip HBU3-TB5-1-D Anion/Cation Resin Tank Area - 0% 31-Aug-t1 14-Sep- 1 9 Decon

. .. . . . . .- . . I HBU3-TB5-2-D Condensate Demineralizer Area 0% 15-Sep-11 17-Nov-li 38 -Sep lI 7li4e*11i I

.. 0.

- Decon Vacuum Pump/Condensate 0% 22-Nov-1 1 29-Dec-i 1 23 ýý-N ii 0i* ec-i11l HBU3-TB6-2-D Demin Area - Decon HBU3-TB6-1-D Air Ejector/Gland Seal 0% 30-Dec-i1 02-Feb-12 20 Sec-li to, -,eb-2:2 Condenser Area - Decon W. f,5.04p-09, Area Spent Foe ooWsiMan g6eczthn 1 Area-

5. Spn-ulPoWseMngmn HBU3-RB1-4a Remove Spent Fuel Racks 0% 01-Sep-09 15-Sep-09 8 0~ p-Qi S PI S I I  ??-J~u~lý3, i Area 6 Rejuieling Oiitdtnb Adceqs Shail Area euln 6 uligAcs hf 3d-cr ~I I

Re ve Remove Equip on OOl tEoo U*/o U1-UC[-Ub* -:)U-I*IOV-U* - S sZ TASK filter: HBPP Execution Activities 5-28-09.

rN-M Actual Work rn-r Critcal Remaining Work *' Summary Page 2 of 17 E Remaining Work * + Milestone (c) Prmavera Systems, Inc]

Humboldt Bay Power Plant Execution Activities Rev. I HBPP Execution Activities Rev. 5/28/09 I 12-Jun-09 09:48 to ODuatlon 209 2010 2011 2012 2013 1 2 4 1 I ........

. ; . L - -

Mir HBU3-HtiB-b :lev,-54, -RuTrip U0% u1-uec-u0 uyr-Jun-0u 104 c-u DI-Junil[)

Accumulators - Remove Equip HBU3-RB2-5 Elev.-44, CRD Piping - Remove 0% 02-Jun-10 19-Oct-10 02,,Jun-I l9 -

Equip Elev.-34, Suppression Pool 0% 20-Oct-I10 12-Nov-10 oc,1 HBU3-RB2-4 Access Hatch - Remove Equip 1*-0 HBU3-RB2-3 Elev.-24, CRD Hydraulic Filters 0% 15-Nov-10 23-Feb-11 ii

- Remove Equip HBU3-RB2-2 Elev. - 14, Manlift - Remove 0% 24-Feb- 11 27-Apr-11 24 ebi i ~pr-il Equip HBU3-RB2-1-D EL-3 Suppression Pool Cooler 0% 11-Dec-12 24-Jan-13 Area - Decon HBU3-RB2-2-D Elev. -14, Manlift Area - Decon 0% 29-Jan-13 16-Apr-13 .2nJ 1 6Apr- 3:

HBU3-RB2-3-D Elev.. 24, CRD Hydraulic Filter 0% 17-Apr-1 3 22-May-13 -Apr-! 22-May4i Area - Decon HBU3-RB2-4-0 Elev.-34, Suppression Pool 0% 23-May-13 13-Jun-13 3LMay j :1:3Ju6n13:

Access Shaft Area - Decon HBU3-RB2-5-D Elev.-44, CRD Piping Area - 0% 18-Jun-13 05-Jul-1 3 Decon iýJu 1 0 -Juli  !,

HBU3-RB2-6-D Elev.-54, CRD Trip Accumulator 0% 08-Jul-13 22-Jul-13 Area - Decon t&: ay- 2, Area 7 Heat Eschangers:

Arr Ha E - I7 44Jun-i I Remove Equip rN-M Actualmorr 0-0 CnricalRemaining Worir .- Summary Page 3 of 17 [ASK tilter HBP Execuiton Actrvities5-28-09.

== Remaining Work +

  • Milestone I(c) Prnmavera Systems. Inc

Humboldt Bay Power Plant Execution Activities Rev. l HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 I CopeeDurMon 09W 1 2010 I 2011 201 2013 I 2014 201 J

.... . I -- * " I ~I I -. ... ,,, *4, ,q HBU3-RI34-1 Shutdown Heat 0% 15-Jun-ti 17-Aug-11 36 Exchangers/Pumps - Remove Equip

. . . . . . . . . . .. . . . . . . . . . . I1

  • l . . .MA HBU3-RB3-i-D Cleanup Heat Exchangers - 0% 03-Feb-12 21-Mar-12 28 Decon 16;ar-a HBU3-RB4-1-D Shutdown Heat 0% 22-Mar-12 16-May-12 32 Exchangers!Pumps - Decon L EU m-m I Area 8 Reactor Veseal Removal 1~l I

Ht3UO-HAV-M Reactor Vessel - Mobilize 0% U1-Jun-1U v1-Apr-11 125 Reactor Vessel Team 'Aii a'6  ! i i i ]  !  : *  ::  :  :  :  :

HRtU3-RXV Reactor Vessel - 0% 04-Apr-11 28-Sep-12 312 internals/Segment Remove/Load GTCC into Cask 6

I -Ae Spi H13U3-RH2-8 Suppression Pool - North -

Remove Equip 0% 18-Aug-1t 12-Jan-i 2 vs i~  : i: -Avgii:X 0 1 0 1~

,Or ?$-Mayl:3,: Ajai r $upfppresiibr Ch.*imbrs HBU3-R82-9 Suppression Pool - South - 0% 17-Jan-12 19-Jun-12 89 Remove Equip Suppression Pool - North - 20-Jun-12 06-Dec-12 98 -- i Oi- rX HBU3-RB2-8-D 0%

Deeon 310-Aug-Il0 2 HBU3-RB2-9-D Suppression Pool - South - 0% 07-Dec-12 28-May-13 98 Decon Oeviciia rojc

-HBU3-SPiO-i Area 10 Special Projects 5% 9X6 - ri.

04-May-09 A 01-Apr-it1 397

! *08-.An 4dl "ar 11 Renhuat df L quid Rai qn2 HBU3-RWl-1 RWM Concentrator Pumps & 0% 31-Aug-11 06-Jan-12 75 Filters - Remove Equip

. II ActualWork Critcal Remaining Work _ Sa

_ii _ _m TASK filter: HBPP Execution Activites 5-28-09.

=- Remaining Work *

  • Milestone (c) Primavera Systems, Inc

Humboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 I 1 2

  • j~jf~JIJAj.

ACWAW W ACMW 12013 MM lJq]APIJ

-1=7_ j , - l 2014-l02021 a . I- mljw4, NI*JI P 4414 alQJIli 114 II*JIAJI~i~lq JI!IP4alP4JiJ(l**,q4tI VIqqAl;=y HBU3-RW1-2 RWB - Waste Receiver & Hold 0% 09-Jan-12 22-May-12 77 ray,1Z Tanks - Remove Equip 03 ManSi HBU3-RW1-3 Radwaste Demineralizer - 0% 23-May-12 23-May-12 Remove Equip HBU3-RW1-4 Concentrated Waste Tanks - 0% 24-May-1 2 23-Jul-12 t

Remove Equip 245t HBU3-RW1-5 Resin Disposal Tank - Remove 0% 24-Jul-12 14-Sep-12 4-, ep-t1 Equip iep-.

06-Oct-i HBU3-RWI-6 Upper Elevation - RWB - 0% 17-Sep-12 09-Oct- 12 A7 Remove Equip HBU3-RWP Rad Waste Embedded Piping 0% 10-Oct-1 2 06-Dec-1 2 HBU3-RWI-1-D RWM Concentrator Pumps & 0% 07-Dec-12 24-Jan-13 ) !-2t Filters - Decon HBU3-RWt-2-D RWB - Waste Receiver & Hold 0% 29-Jan-13 11-Apr-13 ii 1:3Jrn-13 :

Tanks - Decon HBU3-RW1-3-D Radwaste Demineralizer - 0% 12-Apr-13 18-Apr-13 Decon

-Apri 09 Ju*!li1]iii HBU3-RWI-4-D Concentrated Waste Tanks - 0% 23-Apr-13 22-May-13 Decon 3*-Mayi'*

HBU3-RWI-5-D Resin Disposal Tank - Decon 0% 23-May-13 13-Jun-13 I8-un- 220ct

!! i~i i~

HBU3-RWl-6-D Upper Elevation - RWB - Decon 0% 18-Jun-13 09-Jul-13 HBU3-YD2-4 Condensate/Demin Water 0% 26-Sep-13 22-Oct-13 14 Storage Tank - Remove Equip M Cntical Remaining Work mlSummary Page 5 of 17 TASK filter; HBPP Execution Actiities 5-2M9.

F-M Actual Work .m C 3 Remaining Work *

  • Milestone I(c) Pimavera Systems. Inc

Humboldt Bay Power Plant Execution Activities Rev../ HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48

.vr Name / i% ltasth Orginal HB3YD--Condensate/Demin444! Water complete Duartien 209 1 2010 1 2011 1 01 2013 1 014 1 21

- 1 I

HBU3-YD2-4-D Condensate/Demin Water 0% 22-Oct-1 3 24-Oct-13 2  !-oct.

Storage Tank - Decon HBU3-UC1230 LLRW processing equipment 0% 01-Jan-14* 06-Jan-14 4 tsob as ýSump Area12 p asso Su I 1111111111 I

HBU3-Rf32-7 Elev.-66, Uassion 6uump, HcI:LI 0% 1-Omay-12 1t'-UCT-1 z 32 . .. . .17,Maý

- Remove Equip l Oct-1 1-6'-

Elev.-66, Cassion Sump Area - 0% 16-Oct-12 10-Dec-12 32 10 D.t HBU3-RB2-7-D Decon

~'i atci-Area 13, -e olr Veisisl tiavity ARe I.-fRR13 R ReReatt Vessel r Cavt 0 01-Oct-12 05-Feb-13 73 I

Concrete - Remove Equip HBU3-RB1-6-D Reactor Vessel Cavity - Decon 0% 06-Feb-13 06-Feb-13 4ukj1$:Atrea;14 Cinrir44.Roorý Oqdc1Ne~rOY5uO~ol Are 14Cnto....adNery potRom ..

£H UII3-TB7-1 10-00t12 Main Control Room - Remove 0% 10-Oct-1 2 08-Nov-12 18 Equip 08'-NOv HBU3-TB7-5 Demin Control PaneVRFB 0% 09-Nov-12 21-Nov-12 7 12 Access - Remove Equip HBU3-T87-2 Instr Repair/Counting 0% 23-Nov-12 27-Nov-12 3 12!

Room/Vent Equip - Remove Equip 21 No0lýP' HBU3-T87-3 Locker Room/Personnel Decon 0% 28-Nov-12 03-Dec-12 3 Area - Remove Equip ,1 *07-O HBU3-TB7-4 Hot Lab - Remove Equip 0% 04-Dec-12 07-Dec-12 4 :04-De HmCritical Remaining Work Summary Page 6 of 17 TASK filter: HBPP Executon Activities 5-28-09.

H Actual Work .

=D Remaining Work *

  • Milestone (c) Primavera Systems, Inc

Humboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48

.. . Name ty% Ib .tyl A11V1 g. ,

ComPlete Oamton 20 1 2010 2011 1 2012 2013 04 61 HBU3-TB7-6 Hot Lab Attic - Remove Equip 0% 10-Dec-12 26-Dec-12 1t RP Office/Count Room - 0% 27-Dec-12 03-Jan-1 3 4 2t E in HBU3-TB7-7 Remove Equip HBU3-TB7 Control Room/Demin Hall - 0% 04-Jan-13 15-Jan-13 6 art 13 Decon HBU3-TB7-1-D Main Control Room - Decon 0% 01-Apr-13* 10-Apr-13 6 ý3:

)1:-A r-1l<

HBU3-TB7-2-D Instr Repair/Counting 0% 11-Apr-13 16-Apr-13 4 16~A~

Room/Vent Equip - Decon HBU3-TB7-3-D Locker Room/Personnel Decon 0% 17-Apr-13 28-May-13 24 I AOr-*1 ~

Area - Decon 0% 29-May-13 12-Jun-13 9 12 HBU3-TB7-4-D Hot Lab - Decon HBU3-TB7-5-D Demin Control Panel/RFB 0% 13-Jun-13 21-Jun-13 5 13Jun-1 un-1 Access - Decon 24 Jun 1aJ,*

HBU3-TB7-6-D Hot Lab Attic - Decon 0% 24-Jun-13 24-Jun-13 2i Juii in 0% 25-Jun-t3 25-Jun-13 2 HBU3-TB7-7-D RP Office/Count Room - Decon I

I,-- 16-pp .q JGI4Jn-i4' Area 15, Reafilor Fuelird duild I

MOU6-tiO 1-40 up P'ool 0mm, Fuel row I 0-oep-Uit Spent rue, open, clean up u1- a- v 0-t- 1:-

activities 0% 01-Oct-12 15-Jan-t3 60 15-~

HBU3-RB1-i Emergency Conrdensor -

Remove Equip I. . . . Il l . . . . . . . . . . . . . . I . . . . . . . . . . . .

[ASK tiller: HBPP Execution Activities 5-28-09.

in-0 Actual Work N Critical Remaining Work . Summary Page 7 of 17 0 Remaining Work *

  • Milestone (c) Primavera Systems, In(

Humboldt Bay Power Plant Execution Activities Rev. I HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 I o I I IDuration 209 2010 1 ..

Of 2012 2UM MlI I 1

ýiflý 2015 pifos N~m 4IJ I IAA:43 .A: : ý . ************************************************-i-.i-i-'~-i-i-i'.

ý. ý or HBU3-RB1-4 SFP Pumps/Filters - Remove i 0%o U1-uct-12 2/-Nov-1I 33 Equip ... ,0 O t- .. No.. 12...

16-Jan- 13 30-Jan-13 c HBU3-RB1-2 Spent Fuel Pool - Remove Equip HBU3-RB1-5 LaydownlCask Washdown General Area (Decon Facility) -

Remove Equip 31-Jan-13 02-Apr-13

~I I]1

~.

!iiii O2April i 2Aiii HBU3-RBP Refuel Building Embedded 01-Apr-13* 22-May- 13 01 -Apr13 b Piping HBU3-RB1-3 Cask Shipping Area - Remove 02-Apr- 13 12-Apr-13 Equip HBU3-RB3-2 New Fuel Storage/Fuel Pool 12-Apr-13 02-May-13 13 Coolers - Remove Equip HBU3-RB4-2 TBDT/Floor Drain Pumps - 02-May-13 1i-Jun-i3 in* -3 Remove Equip HBU3-RB1 RFB + 12 Decon 22-May-13 14-Aug-13 14+Aug-13 HBU3-RBI-I-D Emergency Condensor - Decon 29-May-13 20-Jun-13 i A M!i

-' : 1 HBU3-RB3-2-D New Fuel Storage/Fuel Pool 04-Jun-13* 20-Jun-13 liunl3 Coolers - Decon i lii iilii i [ iJ (32Augi HBU3-RB1-2-D Spent Fuel Pool - Decon 21-Jun-13 21-Aug-13 HBU3-RB4-2-D TBDT/Floor Drain Pumps - 21-Jun-13 23-Jul-13 tun1413 Decon HBU3-RB1-3-D Cask Shipping Area - Decon 0% 22-Aug-13 02-Oct-13 I ,,_,.~ . _,_r _ _ _ _ _. _ __,_,_ _

rN-01 Actual Work 01- Critical Remaining Work V Summary Page 8 of 17 BASK filter: HBPP Execution Actvities 5-28-09.

=- Remaining Work *

  • Milestone r (c) Primavera Systems, Inc

Humboldt Ba Power Plant Execution Activities Rev.:.HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 Complete Duation 2009 1 2010 2011 1 2012 1 2013 1 2014 I

HBU3-RB1-4-D SFP Pumps/Filters- Decon 0% 03-Oct-13" 29-Oct-13 15 u~n-ucT-:v5 HBU3-RB1-5-D LaydownlCask Washdown 0% 30-Oct-13" 09-Jan-14 40 General Area (Decon Facility) -

Decon -

h t

&1bec-1i3j Area 16Rembval of turbine gul

- - II . -: 1117 0.Ar1 9 19 ,,I 19 - (

HBU3-TB4-1-D Pipe Tunnel Area - Decon 0% 17-Jul-12 04-Oct-12 48 HBU3-TBP Turbine Building Embedded 0% 02-Jan-tX* 04-Dec-13 192 Piping 0-Nov, 13:Area 17:Hot Machinie Shiip &Calii 17- Hot Area5. Mahn Shi & airtonFclt HI U13-IM*'.1-1 Ht Machine chon Equlipment 0% 02-Sep-13' 14-Oct-13 2b Q2' ep-1?ý' 14-Qct 13 Removal HBU3-HMS1-2 HMS Calibration Facility 0% 14-Oct-13 31-Oct-13 10 I44-ot-1 Equipment Removal

-ct-

?n HBU3-HMSP Hot Machine Shop Embedded 0% 31-Oct-13* 05-Nov-13 1 l- *05-Nohj-13 Piping HMU3-Hm1-7 I ra 8PckgdRWSoagLW vacKaged Hauwaste Storage Building - Remove Equip tr, WVulRco i AS 0% ul-JUl-]4- T'JU 4V 1q

.1:4-Jimq5, Area 15 HBU3-RW1-8 Low-Level Waste Storage 0% 22-Jul-14 30-Jul-14 4 22-Jul 4 30-Jul-i4 Building - Remove Equip HBU3-RW1-9 Solid Waste Vault - Remove 0% 29-Jul-14 01-Aug-14 3 29-JUIjI14 01-Aqg 14:

Equip 11 E-= Crtical Renmaining Workw i-W Summary Page 9 of 17 TASK filter; HBPP Execution Activities 5-28-09.

Actual Work Remaining Work * # Milestone (c) Primavera Systems. Inc I

Humboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 AiI At" IID 22 202 HBU3--W1-f-u Packaged -adwaste Storage 0% U4-AUg-14 2t-NOV-14 67 i04-Au- 26-Novw1 Building - Decon HBU3-RWi-8-D Low-Level Waste Storage 0% 02-Dec-14 30-Dec-14 16 Building - Decon HBU3-RW1-9-D Solid Waste Vault - Decon 0% 31-Dec-14 14-Jan-1 5 9 t:;;b ;j:[ z l i: :1:4; 1: l

,___0 -Dk-c13 Area 19 FIFORoof HVAI( staci Area 19 RFS Roof HVAC, Stock, Plant Exhaust Fans HBU3-YD2-i Stack - Elev. 0'0" - Remove 0% 24-Jul-13 19-Aug-13 Equip HBU3-RB5-1 RFB Roof/HVAC only - Remove 0% 01-Aug-13* 10-Sep-13 Equip HBU3-YD2-2 Stack - Elev. 12'0" - Remove 0% 19-Aug-13 05-Sep-13 19q-Aug-'

Equip 10-Sep*l~l HBU3-YD2-1 -D Stack - Elev. 0'0"- Decon 0% 19-Aug-13 04-Sep-13 10-Sep I

i0-Siip i 5 epilli ! ~ i !i i i i i l HBU3-YD2-3 Stack - Elev.26'0" - Remove Equip 0% 10-Sep-13 26-Sep-13 7° P* '

04 0- -i Sep-1:3 ii!i!i i HBU3-YD2-2-D Stack - Elev. 120" - Decon 0% 10-Sep-13 30-Sep-13 10Se i0 2iii i ii3 i i i i~ i i~

HBU3-RB5-1-D RFB Roof/HVAC only - Decon 0% 10-Sep-13 25-Sep-13 31 0 Se-3 HBU3-YD2-5 Plant Exhaust Fans - Remove 0% 10-Sep-13 04-Dec-13 Equip i!!26-Se HBU3-YD2-3-D Stack - Elev.26'0" - Decon 0% 26-Sep-13 10-Oct- 13 ActualWork 01-M Critcal Remaining Work Summary Page10of17 HR---WExecution Actvities 5-28-09.

TASK filter:HBPP

ý Remaining Work *

  • Milestone (c) Primavera Systems, In

I Humboldt Bay Power IA ~MAi Plant ExecutionI Activities A*.Ifr* l Sta.t Rev. I 1*t~ l HBPP O~dorn t Execution Activities Rev. 5/28/09 ...

12-Jun-09; ,

09:48 wq w - Mma Activity% San t1if"411 Original *1111 *"fll '1 C6m'ete DUMN on zu] I I lpl J-U."j, W.-Iij.. '. FIMAIII.- d-m. vij..Uacijn-ýX.ý 'm IIIJJJAIIqqiAjI FI`ILj p(ttisrudim 4 1 . . .

31

0-Dec 13:

HBU3-YD2-5-D Plant Exhaust Fans - Decon 0% 04-Dec-13* 06-Dec-13 2 loe ml-. iMaLJf'M .a 7. S ep f-i p-I14, Area td OCW ufli 1vn 2, Mw H-1 .,,t rsPu s AO% fl2.Iul-13 2 Iud.. 14 ui-13:

- Remove Equip HBU3-YD1-3 CCP Discharge Piping - 0% 24-Jul-13 1 -Oct- 13 45 Remove Equip HBU3-YD1-2-D CCW Heat Exchangers/Pumps 0% 24-Jul-13 30-Jul-13 2

- Decon 0% 11-Oct-13 29-Oct-13 10 ii 4 Ju~l 1 HBU3-YD1-3-D CCP Discharge Piping - Decon 11 Oct11 HBU3-YD2-6a Gaseous Radwaste Holdup 0% 22-Oct-13 04-Dec-13 24 Tunnel - North of RB iIi Od-HBU3-YD2-6b Gaseous Radwaste Holdup 0% 01-Aug-14* 11 -Sep-14 24 Tunnel - Under RB and South 1 Oct 18-Ara2- Un~

icag caal Can---al South Yar Deon NothYrdDe HBU3-YD1 -5 Intake Structure 0% 11-Oct-13 31-Oct-13 13 HBU3-YD1-4 Discharge Canal - Remove 0% 05-Nov-13 18-Mar-15 282 17- 00-14 Equip HBU3-YD1 South Yard Area Decon 0% 03-Jan-14 17-Jan-14 8 t%3-,J~r-HBU3-YD2 North Yard Area Decon 0% 03-Jan-14 28-Jan-14 13 HBU3-YDI-4-D Discharge Canal - Decon 0% 18-Mar-15 26-Mar-15 4 18'Mqrl -SM4r-15 mm Actual Work - Critcal Remaining Work *.-11' Summary Page 11 of 17 TASK filter: HBPP Execution Activities 5-28-09.

== Remaining Work *

  • Milestone (c) Primavera Systems, Inc

iumboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 I 6vit-.Iar jFinish I dW

ýE vIrU) OA  %

Copeejrdo 2009 2 010 1 2011 1 H12 1 . 2014D.~ ~

Jý AprLl:lý 100 08 iitk 1 1 HBU3-YDD Drains and Catch Basin 0% 15-Apr- 11 08-.Jul-1 1 48 Installations 15-Apr-11 I 31-Jul-12 270 HBU3-YDS Contaminated Soil Removal 0% :5 ....... fill ,

HBU3-YDP Yard Embedded Piping 0% 03-Dec-13' 06-Jan-14 19

~-Jn 1 ~ 8-atvl:4i 0%

17Jni S.i HBU3-YDPa Circ Water Discharge Pipe 02-Jan-14* 28-Jan-14 14 02Wah-S ' 0-: ... .a. . .

(after HMS Bldg removal) ivy !y!ei I Area 23 Demolition and Sockfill of Structures ij*iiii'::,

HBU3-A23-1-1(TB Building Demolition 0% 03-Dec-13" 05-Mar-14 54 HBU3-A23-1-1"TB Soil Removal 0% 06-Mar-14 08-May-14 36 Ot-ia-Ma 4 :09-Maj-1 4


1o-14, fe J1C 0% 09-May-14 09-Jun-14 18 I

(vay 09 Jun i4 HBU3-A23-1-1:TB Survey following soil removal HBU3-A23-1-1: TB Remediation Survey 0% 10-Jun-14 12-Aug-14 36 i'3,uAu -iS HBU3-A23-1-1, TB Final Site Survey 0% 13-Aug-14 13-Oct-14 36 HBU3-A23-1-1! TB Back fill area 0% 14-Oct-14 12-Nov-14 18 i4O0ct1 1ý2 4 jo-L 1, HBU3-A23-2-1(RB excluding SFP Building 0% 01-May-14* 04-Aug-14 54 ... ......... 01.ay-4' 04-Atutq4 Demolition HN-rCritical Remaining Work Summary Page 12 of 17 ASK filter: HBPP Execution Activities 5-28-09.

  • H Actual Work .-

== Remaining Work *

  • Milestone (c) Pnmavera Systems, Inc

Humboldt Bay Power Plant Execution Activities Rev. I HBPP Execution Activities Rev. 5/28/09 i 12-Jun-09 09:48 I .. .... A NaDum

,t m10% rC ,i 2011 1 1'01201 2014 1 20 . .

, 111lEPAMIJI-944 JIFI Ij iJIJIN'1i l- 40 IpIll q4 INj iJjljjp*IqNUIM I *411IMV241111""A"I HBU3-A23-2-1 -RB excluding SFP Soil Removal 0% 05-Aug-14 07-Oct-14 36 :05Aug- 0 tbv 14::  :: : :

HBU3-A23-2-1. RB excluding SFP Survey 0% 08-Oct-14 06-Nov-14 18 following soil removal 3J-i S

+I HBU3-A23-2-1i RB excluding SFP Remediation 0% 07-Nov-14 13-Jan-15 36 Survey HBU3-A23-2-1, RB excluding SFP Final Site 0% 14-Jan-15 16-Mar-i5 36 Survey HBU3-A23-2-1f RB excluding SFP Back fillarea 0% 17-Mar-15 19-May-15 36 i... . -.. ...

.... i . - 9'ay-i

" 6 M

HBU3-A23-3-1 (Stack and Recombiner Building 0% 05-Nov-13* 05-Dec-13 18 Demolition HBU3-A23-3-1"Stack and Recombiner Soil 0% 07-Oct-14 08-Dec-14 36 -066-14 1l~~ki :3p,

-15 Removal HBU3-A23-3-1; Stack and Recombiner Survey 0% 09-Dec-14 08-Jan-15 18 :09DDec following soil removal HBU3-A23-3-1: Stack and Recombiner 0% 13-Jan-15 13-Mar-15 36 $3'Mar1-l5 Remediation Survey 0% 16-Mar-15 14-May-15 36 16-Mar-IS 4 MIay1 HBU3-A23-3-1, Stack and Recombiner Final Site Survey 0% 19-May-15 17-Jun-15 18 19 MVl 17ýJUrv-i 5 HBU3-A23-3-1 fStack and Recombiner Back fill area 7-W: 10 May 13 Area 23-4 Deiio!itioh ari I:pac lfl -S:;Oit FL HBU3-A23-4-1( Spent Fuel Pool (SFP) Building 0% 01-Apr-13° 04-Apr-13 4 Of, Ari j -Apr-iiT:

Demolition I,

Page 13of 17 TASK filter-HBPP Execution AcSvities5-28-09.

rn-r Actual Work ED-= Remaining Work rtical .. Summary 3 Remaining Work *

  • Mitestone (c) Pnmauera Systems. Inc

12-Jun-09 09:48 Humboldt Bay Power Plant Execution Activities Rev.

IP= 1 completevll I

iHBPP Execution Activities Durtio DZ 1 moo09 1IRev. 5/28/09 2010 1 OD1 2012 1

.. 2013 1~~

20I15 HBU3-A23-4-1 Spent Fuel Pool (SFP) Soil 0% 09-Apr-13 12-Apr-13 4 9 -Apr- 128Apr-13i Removal HBU3-A23-4-1; Spent Fuel Pool (SFP) Survey 0% 15-Apr-13 18-Apr-13 4 following soil removal HBU3-A23-4-1 Spent Fuel Pool (SFP) 0% 23-Apr-13 26-Apr-13 4 2 Ar i 26 A i i i iJ Remediation Survey HBU3-A23-4-1i Spent Fuel Pool (SFP) Final 0% 29-Apr-13 02-May-13 4 ý29Apri O-Mify-1:3:

Site Survey HBU3-A23-4-1. Spent Fuel Pool (SFP) Back fill 0% 07-May-13 10-May-13 4 area

'i i i '~~~~~~ . . ~~~.

' i ,ii...' . i . '.'..

-- 16n137 0% 01-Aug-14* 01-Sep-14 18 01-Aqfugý14*. I 0 i-sep- 14:

HBU3-A23-5-1(RW Storage, Low Level RW storage, and Kelly Building Demolition HBU3-A23-5-1" RW Storage, Low Level RW 0% 02-Sep-i14 01-Oct-14 18 storage, and Kelly Bldg Soil Removal 0414-HBU3-A23-5-1; RW Storage, Low Level RW 0% 02-Oct-14 04-Nov-14 18 02,0c14: 04 P storage, and Kelly Bldg Survey following soil removal HBU3-A23-5-1: RW Storage, Low Level RW 0% 05-Nov-14 10-Feb-15 54 storage, and Kelly Bldg Remediation Survey i::i i:i ii i! 03 ii:il Mar 14 SiIoi i!May-54

_4 i HBU3-A23-5-1, RW Storage, Low Level RW 0% 11-Feb-15 13-May-15 54 7 .. . . .. .. . 1F ii05-NOV 13 M~ay15ý storage, and Kelly Bldg Final Site Survey 0% 14-May-15 16-Jun-15 18 0 i Wtiii riii1"4-i i 16-Jun15I HBU3-A23-5-1! RW Storage, Low Level RW storage, and Kelly Bldg Back fill area 14ý4-l.iiS Area 23 HBU3-A23-6-1( RW Bldg and High Level Vault 0% 03-Mar-14* 01-May-14 36 Building Demolition Critical Remaining Work Summary Page 14 ot17 [ASK filter: HBPP Execution Activities 5-28-09.

11-41 Actual Work - ..

== Remaining Work *

  • Milestone (c) Primavera Systems, In(

Humboldt Bay Power Plant Execution Activities Rev. l HBPP Execution Activities Rev. 5/28/09 12-Jun-09 09:48 Coe te Duraton 2009 201 1 20 2013 14 HBU3-A23-6-1" RW Bldg and High Level Vault 0% 06-May-14 04-Jul-14 1

36 ljjjjvljjI~qj ~ j~t jpq l l -May-l i ý4 uel"

-uur-tq4j!

Soil Removal T T HBU3-A23-6-1: RW Bldg and High Level Vault 0% 07-Jul-14 05-Aug-14 18 Survey following soil removal T6Augi: 0 HBU3-A23-6-1, RW Bldg and High Level Vault 0% 06-Aug-14 08-Oct-14 36  ;:

~~~~~ , :f-al ~~

N : : !D,ý J-i-4 Remediation Survey HBU3-A23-6-1' RW Bldg and High Level Vault 0% 09-Oct-14 10-Dec-14 36 0-9Oct14 ýii :4.

Final Site Survey HBU3-A23-6-1! RW Bldg and High Level Vault 0% 11-Dec-14 14-Jan-15 18 Back fillarea illi- 124a 14 Ar,,i a M~-1 teioitioh 0% 30-Oct-1 3 18 i I T i i  ; 01-Odt-13 , 30-Oct13  :

HBU3-A23-7-1 ( Transformer and Hot Machine 01-Oct-13" Shop Building Demolition HBU3-A23-7-1"Transformer and Hot Machine 0% 31-Oct-13 04-Dec-13 18 3vC3 fý1!t-t3M 04-DOd-1:3.

Shop Soil Removal HBU3-A23-7-1; Transformer and Hot Machine 0% 05-Dec-13 06-Jan-14 18 Shop Survey following soil removal HBU3-A23-7-1" Transformer and Hot Machine 0% 07-Jan-14 05-Feb-14 18 Shop Remediation Survey 0% 06-Feb-14 10-Apr-14 36 0- Feb-14, iAr 14 HBU3-A23-7-1, Transformer and Hot Machine Shop Final Site Survey 0% 11-Apr-14 12-May-14 18 1 pii 1 1APt 12,'MaV-14 HBU3-A23-7-1! Transformer and Hot Machine Shop Back fillarea 16ý ae 14, ýAtoa238D0 Pn P!-Noivls1V' 'I 0,7-rjjnL14:

HBU3-A23-8-itBMisc Yard Foundations - 0% 05-lNov-1 3* 07-Jan-14 36 Building Demolition

@D-0 Crlical Remaining Work V Summary Page 15 o117 TASK filter: HBPP Execution Activities 5-28-09.

N- Actual Work .

Remaining Work *

  • Milestone (c) Primavera Systems, Inc

Humboldt Bay Power Plant Execution Activities Rev. HBPP Execution Activities Rev. 5/28/0 1 12-Jun-09 09:48 I N. I I*i*=Excuio tAc ivitie Re .5/80 ..... ... 1 1 2-u -9494 9:4 " I I Wý14ý 1 ILU:3=3 1=94=11:34:3=4 ...

O8Jan-. . 4*.. *  ;;2*Mar-4*  !!!ii!i!

HBU3-A23-8-1 Misc Yard Foundations - Soil 0% 08-Jan-14 12-Mar-14 36 Removal HBU3-A23-8-1; Misc Yard Foundations - Survey 0% 13-Mar-14 11-Apr-14 18 OMair-i ii1 -14:

following soil removal HBU3-A23-8-1 Misc Yard Foundations - 0% 14-Apr-14 12-Jun-14 36 Remediation Survey HBU3-A23-8-1, Misc Yard Foundations - Final 0% 17-Jun-14 15-Aug-14 36 Site Survey

  • i l pai 12-un1 HBU3-A23-8-1 I Misc Yard Foundations - Back 0% 18-Aug-14 16-Sep-14 18 fillarea

-0May-,5 HBU3-A23-9-1 I Intake/Discharge Structures & 0% 26-Mar-1 5 01-Apr-i5 4 2q*M4r41t5 01A-Ar55 Canals Building Demolition

.. . . . . . . . . . . . . . Se 14 . . . . .

i i 77 i i 7 T HBU3-A23-9-1 "Intake/Discharge Structures & 0% 01-Apr-15 09-Apr-15 4 01Ar1 09 Apr .15:

Canals Soil Removal HBU3-A23-9-1, Intake/Discharge Structures & 0% 09-Apr-15 15-Apr-15 4 OS'Aprt 1:5Apr!15 Canals Survey following soil removal HBU3-A23-9-1" Intake/Discharge Structures & 0% 15-Apr-15 23-Apr-15 4 Canals Remediation Survey HBU3-A23-9-1, Intake/Discharge Structures & 0% 23-Apr- 15 29-Apr-15 4 O3pt 29'Apr-15 Canals Final Site Survey HBU3-A23-9-1 I Intake/Discharge Structures & 0% 29-Apr-i 5 07-May-15 4 29-Apr; 1 07-tuly 15 Canals Back fillarea 04-[NSep-14 5 Area 24 RCRA:

Area 24 RCRA Cleanup - Soils, Hazmat Removal HBU3-A24--1000 RCRA Cleanup- Soils, Hazmat 0% 01-Sep-14° 04-Sep-14 4 Removal  : 0i:::

e:: 4: I:04-Sep-14  ::

Citical Remaining Work Summary Page 16 of 17 TASK filter: HBPP Execution Activities 5-28-09.

111-4 Actual Work 1 .

== Remaining Work *

  • Milestone (c) Primavera Systems. Inc

Humboldt Bay Power Plant Execution Activities Rev. l HBPP Execution Activities Rev. 5/28/09 112-Jun-09 09:48

. . . . . . . . . 2015

. .. t...IL) ..... .. . . . .

Na.. . . I Ac iv t J11121 00 1 if ~ 2~ ~ 01 1

~

A5ia~

_Aiuve N I&

2012

~

1ý ! ý4I~

1

~

201 NIIjjlj1`JqPVJ~ *0~aL4 Are 2014 Area325TFina StatustSurveyn&tReguluroey Closure 1* 06Ja-1  :::: ýi I Report Y 0O-Jan 14ýArea ý56 aISite Pestourarey HBU3-SCA-1000 Backfill Site 0% 01-Jan-14* 06-Jan-14 4 0% 01-Jan-t4* 06-Jan-14 4 V06-nJ: 4ýArea ý6:7tW~ste Stip~n:

HBU3-SCA-t 010 Grade and Landscape Site 01-,Jab 14' P 06-Jan: 14

. .. .. . . . . . . . . . . . . . . . . . . . . . . . . . WIO0-*1&n~l-4 ,: t :6~ :~t:i :n 1re  ! :

0% 01-Jan-14* 06-Jan-1 4 4 YA-:1 0.6-')4n1:4~rS2 rll~&nich HBU3-UC1 180 Disposal of DAW generated  ! i01i 0 1:Jah414 I 06-Ja n n1*

4 . . .. . . .

HBU3-A28-1000 Training for the masses 0% 01-Jan-14* 06-Jan-14 4 Pi Apr`il iFoss Un iil i &i HBU3-FU1-1 Fossil Units Shutdown/New 0% 01-Sep-1i0 0

  • Fossil Unlits8huicown/Newv 0eniComplete Gen Complete HBU3-FU1-2 Fossil Units 1&2 Abatement 0% 01-Sep-10* 0 +:Fossil Unit 62ýAbaterment HBU3-FU1-3 Fossil Units 1&2 Tanks and 0% 01-Apr-t 1 0 4:1Fossil Units 1&21:anks and 8thnicuresý (demoich)

Structures (demolish) 4-:-.ý44 HBU3-StRes - Site Restoration 0% 02-Jun-15* 04-Jan-16 124 W1-Jurt-l 5* 0000 1000 HBU3-LT-1000 NRC Termination of License 0% 02-Jun-15* 04-Jan-16 124 TASK filter: HBPP Execution Activities 5-28-09.

u Actual Work 1 CriticalRemaining Work . 1 Summary Page 17 of 17 Remaining Work *

  • Milestone (c) Primavera Systems, Inc