Letter Sequence RAI |
---|
|
|
MONTHYEARML0723405142007-11-16016 November 2007 University of Missouri - Rolla Research Reactor Facility - Request for Additional Information Regarding License Renewal Project stage: RAI ML0732409672007-12-19019 December 2007 Determination of Acceptability and Sufficiency for Docketing and Opportunity for a Hearing Regarding the Application from the University of Missouri-Rolla for Renewal of the Facility License for the University of Missouri-Rolla Reactor Project stage: Other ML0812007022008-04-30030 April 2008 Missouri University of Science and Technology Draft Request for Additional Information Regarding Application for License Renewal Project stage: Draft RAI ML0812700242008-05-12012 May 2008 Missouri University of Science and Technology Research Reactor (Mstr) Facility - Request for Additional Information (Rais) Regarding License Renewal Project stage: RAI ML0818204102008-06-26026 June 2008 Response to Request for Additional Information from the Missouri University of Science & Technology University of Missouri-Rolla Reactor Facility, Part VII Project stage: Response to RAI ML0824605612008-09-0808 September 2008 Missouri University of Science and Technology Reactor (Mstr), Request for Additional Information (Rai), August 27, 2008 Project stage: RAI ML0826305652008-09-16016 September 2008 Response to Request for Additional Information Letter Dated September 8, 2008 for the Missouri University of Science and Technology Reactor (Mstr) Facility Project stage: Response to RAI ML0831905292008-11-0707 November 2008 Missouri University of Science and Technology Reactor - Intent to Support Decommissioning Activities Project stage: Request ML0802901562009-03-19019 March 2009 Missouri Univ. of Science and Technology - Environmental Assessment Regarding License Renewal of Facility Operating License No. R-79 Project stage: Other ML0901405202009-03-24024 March 2009 Missouri University of Science and Technology Research Facility Technical Specifications Project stage: Request ML0901405112009-03-30030 March 2009 Issuance of Renewed Facility License No. R-79 for the Missouri University of Science and Technology Research Reactor (TAC No. Mc 5737) Project stage: Approval 2008-06-26
[Table View] |
|
---|
Category:Letter
MONTHYEARML24281A0622024-10-0808 October 2024 Examination Confirmation Letter No. 50-123/Ol-25-01 Missouri University of Science and Technology ML24221A2882024-08-0808 August 2024 Follow-Up Report on EN-57239, Deviation from 10 CFR 50.54(k) and Missouri S&T Reactor (R-79) Technical Specification 6.1.3.1.a) IR 05000123/20242012024-07-0101 July 2024 Board of Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report 05000123/2024201 ML24151A6642024-05-30030 May 2024 Submittal of 2023-2024 Annual Progress Report for Missouri University of Science and Technology Reactor ML24018A1112024-01-19019 January 2024 Board of the Curators of the University of Missouri – Change of Facility Backup Project Manager ML24017A1662024-01-18018 January 2024 Examination Confirmation Letter No. 50-123/Ol-24-02, Missouri University of Science and Technology (Must) ML23349A2062023-12-15015 December 2023 Missouri University of Science and Technology Reactor (Mstr), Follow-Up Report on EN-56878, Reportable Occurrence ML23311A0722023-12-12012 December 2023 Examination Report Letter No. 50-123/OL-24-01, Missouri University of Science and Technology ML23222A2202023-08-10010 August 2023 Examination Confirmation Letter No. 50-123/OL-24-01, Missouri University of Science and Technology IR 05000123/20232012023-08-0202 August 2023 Board of Curators of the University of Missouri - Us Nuclear Regulatory Commission Safety Inspection Report No. 05000123/2023201 ML23145A2542023-05-23023 May 2023 2022-2023 Annual Progress Report for Missouri University of Science and Technology Reactor ML23114A0772023-04-24024 April 2023 Examination Result Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML23114A0762023-04-24024 April 2023 Examination Report No. 50-123/OL-23-01, Missouri University of Science and Technology ML23040A3902023-03-13013 March 2023 Examination Confirmation Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML22280A1742022-10-31031 October 2022 Examination Confirmation Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML22298A3032022-10-17017 October 2022 Level 1 Personnel Change at the Missouri University of Science and Technology Reactor ML22235A7872022-08-23023 August 2022 Missouri & T Reactor, Response to Notification of Violation and Inspection Report 05000123/2022002 IR 05000123/20222022022-07-25025 July 2022 Board of Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000123/2022202 and Notice of Violation ML22150A0072022-05-30030 May 2022 Submittal of 2021-2022 Annual Progress Report for the Missouri University of Science and Technology Reactor ML22098A2232022-05-0505 May 2022 Board of Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Security Inspection Report (Cover Letter) ML22018A3062022-02-0101 February 2022 Examination Confirmation Letter No. 50-123/OL-22-02, Missouri University of Science and Technology ML21330A0462022-01-21021 January 2022 Board of Curators of the University of Missouri Issuance of Amendment No 23 to Renewed Facility Operating License No R-79 ML21292A3342021-10-18018 October 2021 Missouri & T Reactor, Follow-Up Report on and Retraction of EN-55509, Reported Violation of Technical Specification (Limiting Condition of Operation) 3.3.2 ML21257A1192021-09-23023 September 2021 Board of the Curators of the University of Missouri - Change of Facility Project Manager ML21203A0762021-07-28028 July 2021 Examination Confirmation Letter No. 50-123/OL-22-01, Missouri University of Science and Technology IR 05000123/20210012021-06-28028 June 2021 Missouri University of Science and Technology (Ms&T) Routine Safety Inspection 50-123/2021-01 ML21153A4322021-06-0202 June 2021 Missouri & T Reactor - Follow-Up Report on Violation of Technical Specification (Surveillance Requirement) 4.6.2(1), EN-55266 ML21134A2452021-05-14014 May 2021 Missouri Univ. of Science & Technology, Self-Identified Violation of Operator Requalification Program 2.2 ML21039A3422021-02-0808 February 2021 Examination Confirmation Letter No.50-123/OL-21-01, Missouri University of Science and Technology ML21005A0272021-01-25025 January 2021 Must Amendment No 23 Acceptance Review - Application Accepted 12-28-2020 (6) ML20337A1622020-12-0202 December 2020 Proposed License Amendment Request for Missouri University of Science and Technology Reactor (License R-79, Docket 50-123) ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20314A3622020-11-12012 November 2020 Board of the Curators of the University of Missouri - Issuance of Amendment No. 22 to Renewed Facility Operating License No. R-79 to Extend the Period to Perform Visual Inspections of the Shim/Safety Rods ML20309A6762020-11-0404 November 2020 Missouri University of Science and Technology - Written Communication as Specified by 10 CFR 50.4 Requesting Approval of an Exigent Amendment to the Technical Specifications Appended to Facility Operating License R-79 IR 05000123/20202012020-09-28028 September 2020 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000123/2020201 ML20150A6062020-05-29029 May 2020 Missouri Univ. of Science & Technology - Submittal of 2019-2020 Annual Progress Report for Missouri University of Science and Technology Reactor ML20006C9282019-12-23023 December 2019 Examination Confirmation Letter No. 50-123/OL-20-02, Missouri University of Science and Technology ML19347B2142019-12-23023 December 2019 Examination Report No. 50-123/OL-20-01, Missouri University of Science and Technology ML19304B7332019-11-0505 November 2019 Examination Confirmation Letter No. 50-123/OL-20-01, Missouri University of Science and Technology ML19206A3642019-07-25025 July 2019 Examination Confirmation Letter No. 50-123/OL-19-02, Missouri University of Science and Technology IR 05000123/20192012019-07-0303 July 2019 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Inspection Report No. 50 123/2019-201 ML19182A3592019-07-0101 July 2019 Level 1 Personnel Change at the Missouri University of Science and Technology Reactor ML19149A6242019-05-29029 May 2019 Missouri s & T Reactor - 2018-2019 Annual Progress Report for Missouri University of Science and Technology Reactor ML19010A0822019-01-17017 January 2019 Washington State University - Change of Facility Project Manager ML19028A2942019-01-17017 January 2019 Level III Personnel Change at the Missouri University of Science and Technology Reactor Facility, License R-79, Docket 50-123 ML18365A3532019-01-0808 January 2019 Missouri University of Science and Technology - Change of Facility Project Manager IR 05000123/20182022018-12-26026 December 2018 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Security Inspection Report 05000123/2018202 (Cover Letter) ML18276A2842018-09-28028 September 2018 Missouri S&T Reactor - Submittal of Updated Operator Requalification Program ML18257A1372018-09-14014 September 2018 Missouri University of Science and Technology Reactor (S&T Reactor) - Reply to a Notice of Violation ML18233A4012018-07-0202 July 2018 Requesting Approval for Reviewing Official at Mstr 2024-08-08
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML19042A0182019-02-0707 February 2019 Level 3 Personnel Change ML0824605612008-09-0808 September 2008 Missouri University of Science and Technology Reactor (Mstr), Request for Additional Information (Rai), August 27, 2008 ML0812700242008-05-12012 May 2008 Missouri University of Science and Technology Research Reactor (Mstr) Facility - Request for Additional Information (Rais) Regarding License Renewal ML0723405142007-11-16016 November 2007 University of Missouri - Rolla Research Reactor Facility - Request for Additional Information Regarding License Renewal ML0719800252007-08-0101 August 2007 University of Missouri-Rolla: Request for Additional Information Regarding: Technical Specifications Amendments ML0527103872005-09-26026 September 2005 RAI Letter - Security Measures - Bonzer 2019-02-07
[Table view] |
Text
September 8, 2008 Mr. William Bonzer, Reactor Manager Missouri University of Science and Technology 226 Fulton Hall Rolla, MO 65409-0170
SUBJECT:
MISSOURI UNIVERSITY OF SCIENCE AND TECHNOLOGY RESEARCH REACTOR (MSTR) FACILITY B REQUEST FOR ADDITIONAL INFORMATION (RAIs) REGARDING LICENSE RENEWAL (TAC NO. MC5737)
Dear Mr. Bonzer:
We are continuing our review of your August 30, 2004 application, and your responses to RAI submissions dated November 16, November 27, December 26, 2007; January 17, March 6, and June 26, 2008, and associated supplements, for license renewal of the MSTR. After reviewing your submissions, questions have arisen for which we require additional information and clarification. During a discussion with you on August 25, 2008, you agreed to provide a response to the enclosed Request for Additional Information (RAI) no later than September 17, 2008. Your timely response is needed to support completion of the review. In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation.
Should you have any questions, please contact me at 301-415-4007.
Sincerely,
/RA/
John Nguyen, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-123 License No. R-79
Enclosures:
As stated cc w/enclosure: See next page
September 8, 2008 Mr. William Bonzer, Reactor Manager Missouri University of Science and Technology 226 Fulton Hall Rolla, MO 65409-0170
SUBJECT:
MISSOURI UNIVERSITY OF SCIENCE AND TECHNOLOGY RESEARCH REACTOR (MSTR) FACILITY B REQUEST FOR ADDITIONAL INFORMATION (RAIs) REGARDING LICENSE RENEWAL (TAC NO. MC5737)
Dear Mr. Bonzer:
We are continuing our review of your August 30, 2004 application, and your responses to RAI submissions dated November 16, November 27, December 26, 2007; January 17, March 6, and June 26, 2008, and associated supplements, for license renewal of the MSTR. After reviewing your submissions, questions have arisen for which we require additional information and clarification. During a discussion with you on August 21, 2008, you agreed to provide a response to the enclosed Request for Additional Information (RAI) no later than September 17, 2008. Your timely response is needed to support completion of the review. In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation.
Should you have any questions, please contact me at 301-415-4007.
Sincerely,
/RA/
John Nguyen, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-123 License No. R-79
Enclosures:
As stated cc w/enclosure: See next page DISTRIBUTION:
PUBLIC RidsNrrDprPrta RidsNrrDprPrtb RTR R/F ACCESSION NO.: ML082460561 Template No.: NRR-106 OFFICE PRTA:PM PRTA:LA DRIP/RPRP: PRTA:BC NAME J Nguyen jtn EBarnhill eeb CPittigilo cp DCollins dsc DATE 9/8/08 9/8/08 9/8/08 9/8/08 OFFICIAL RECORD COPY
Missouri University of Science and Technology Docket No. 50-123 cc:
Dr. Samuel Frimpong, Chair School of Mines and Nuclear Engineering 305 McNutt Hall Missouri University of Science and Technology Rolla, MO 65409-0630 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health 930 Wildwood Drive, P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809 State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
REQUEST FOR ADDITIONAL INFORMATION MISSOURI UNIVERSITY OF SCIENCE AND TECHNOLOGY DOCKET NO. 50 -123
- 1. Provide the purpose, frequency, and duration of operating the reactor at power levels ranging from 200 kW to 300 kW. Discuss reactor design, safety function, and procedures that prevent the reactor from exceeding the fuel cladding temperature and an uncontrolled reactor transient.
- 2. Section 14.3.2.2. Section 7.2.2.4 of the MSTR SAR specifies two channels: High Voltage (HV) Safety Channel No.1 and HV Safety Channel No. 2 for scram functions. However, these channels are missing in TS 14.3.2.2. Provide justification why these channels are not included in TS 14.3.2.2.
- 3. Section 14.3.4. The specification in this section states: The reactor shall not be operated unless the reactor truck door is closed and the ventilation intake and exhaust duct louvers are operable or secured in a closed position. Discuss whether any work is allowed involving core fuel loading, or installed control rods when the confinement is not operable.
- 4. Section 14.3.6.1. The specification in this section states: The reactor shall not be operated unless the Continuous Air Monitor (CAM) is operable and the Radiation Area Monitors (RAMs) located at the reactor bridge, at the demineralizer, and in the basement experimental area are operable. Discuss the CAM design (associated alarms, set points, and warning circuitry), surveillance, and reactor procedure that ensure the CAM can perform its intended function including preventing an undetected release of airborne radioactivity to the health and safety of the public, MSTR personnel, or the environment.
- 5. Section 6.2.1 of the current TS specifies that the Committee shall be composed of at least five members. However, Section 14.6.2.1 of the proposed TS specifies that the Committee shall be composed of at least three members. Provide justification why the Committee specified in the proposed TS is composed of at least three members. Also provide discussion on how the quorum requirement in TS 14.6.2.2 (1) will be met if two of the minimum three members have reactor operation responsibilities.
- 6. Section 9.2, Handling and Storage of Reactor Fuel. Provide dimensions of the wall that separates the main pool and the fuel storage pit.
- 7. Under 10 CFR 50.33(d), Contents of applications; general information, certain information is required by the applicant, Missouri University of Science and Technology Reactor (MSTR),
as applicable. To comply with this regulation, please update the application to include a statement of the organizational form of MSTR (e.g., corporation, etc.), the state where it is incorporated or organized and the principal location where MSTR does business, and the names, addresses and citizenship of directors and principal officers. Also, please state whether the MSTR is owned, controlled, or dominated by an alien, foreign corporation, or foreign government, and if so, give details.
Enclosure
- 8. Under 10 CFR 50.33(f)(2), The applicant shall submit estimates for total annual operating costs for each of the first five years of operation of the facility. Provide the projected operating costs of the MSTR for each of the years FY2009 to FY2013 (the first five year period after the projected license renewal) as well as MSTRs primary source(s) of funding that covers the operating costs for the above fiscal years.
- 9. The supplement to the application indicates that that cost to decommission the MSTR ranges from $ 1.9 million to $ 5.8 million depending on the disposal option selected. The staff needs the following additional information to complete its review:
- a. Selected disposal option and the basis for the disposal option selected.
- b. MSTRs plans to adjust the level of funds in the escrow account periodically over the life of the MSTR to meet changes in the decommissioning cost estimate.
- c. Copy of the financial mechanism that reflects the updated decommissioning costs.