Letter Sequence RAI |
---|
|
|
MONTHYEARML0719800252007-08-0101 August 2007 University of Missouri-Rolla: Request for Additional Information Regarding: Technical Specifications Amendments Project stage: RAI ML0724004062007-08-23023 August 2007 University of Missouri - Rolla Reactor, Response to Request for Additional Information Regarding Changes to Technical Specification 6.3, Operating Procedures Project stage: Response to RAI ML0724001582007-08-23023 August 2007 Univ of Missouri - Rolla Reactor Facility Response to Request for Additional Information Re Changes to Technical Specification 6.3, Operating Procedures. Project stage: Response to RAI ML0725302972007-10-19019 October 2007 University of Missouri - Rolla Research Reactor (Umrr) Facility - Issuance of Amendment No. 19 to Facility Operating License R-79 Project stage: Approval 2007-08-01
[Table View] |
|
---|
Category:Letter
MONTHYEARML24281A0622024-10-0808 October 2024 Examination Confirmation Letter No. 50-123/Ol-25-01 Missouri University of Science and Technology ML24221A2882024-08-0808 August 2024 Follow-Up Report on EN-57239, Deviation from 10 CFR 50.54(k) and Missouri S&T Reactor (R-79) Technical Specification 6.1.3.1.a) IR 05000123/20242012024-07-0101 July 2024 Board of Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report 05000123/2024201 ML24151A6642024-05-30030 May 2024 Submittal of 2023-2024 Annual Progress Report for Missouri University of Science and Technology Reactor ML24018A1112024-01-19019 January 2024 Board of the Curators of the University of Missouri – Change of Facility Backup Project Manager ML24017A1662024-01-18018 January 2024 Examination Confirmation Letter No. 50-123/Ol-24-02, Missouri University of Science and Technology (Must) ML23349A2062023-12-15015 December 2023 Missouri University of Science and Technology Reactor (Mstr), Follow-Up Report on EN-56878, Reportable Occurrence ML23311A0722023-12-12012 December 2023 Examination Report Letter No. 50-123/OL-24-01, Missouri University of Science and Technology ML23222A2202023-08-10010 August 2023 Examination Confirmation Letter No. 50-123/OL-24-01, Missouri University of Science and Technology IR 05000123/20232012023-08-0202 August 2023 Board of Curators of the University of Missouri - Us Nuclear Regulatory Commission Safety Inspection Report No. 05000123/2023201 ML23145A2542023-05-23023 May 2023 2022-2023 Annual Progress Report for Missouri University of Science and Technology Reactor ML23114A0772023-04-24024 April 2023 Examination Result Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML23114A0762023-04-24024 April 2023 Examination Report No. 50-123/OL-23-01, Missouri University of Science and Technology ML23040A3902023-03-13013 March 2023 Examination Confirmation Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML22280A1742022-10-31031 October 2022 Examination Confirmation Letter No. 50-123/OL-23-01, Missouri University of Science and Technology ML22298A3032022-10-17017 October 2022 Level 1 Personnel Change at the Missouri University of Science and Technology Reactor ML22235A7872022-08-23023 August 2022 Missouri & T Reactor, Response to Notification of Violation and Inspection Report 05000123/2022002 IR 05000123/20222022022-07-25025 July 2022 Board of Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000123/2022202 and Notice of Violation ML22150A0072022-05-30030 May 2022 Submittal of 2021-2022 Annual Progress Report for the Missouri University of Science and Technology Reactor ML22098A2232022-05-0505 May 2022 Board of Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Security Inspection Report (Cover Letter) ML22018A3062022-02-0101 February 2022 Examination Confirmation Letter No. 50-123/OL-22-02, Missouri University of Science and Technology ML21330A0462022-01-21021 January 2022 Board of Curators of the University of Missouri Issuance of Amendment No 23 to Renewed Facility Operating License No R-79 ML21292A3342021-10-18018 October 2021 Missouri & T Reactor, Follow-Up Report on and Retraction of EN-55509, Reported Violation of Technical Specification (Limiting Condition of Operation) 3.3.2 ML21257A1192021-09-23023 September 2021 Board of the Curators of the University of Missouri - Change of Facility Project Manager ML21203A0762021-07-28028 July 2021 Examination Confirmation Letter No. 50-123/OL-22-01, Missouri University of Science and Technology IR 05000123/20210012021-06-28028 June 2021 Missouri University of Science and Technology (Ms&T) Routine Safety Inspection 50-123/2021-01 ML21153A4322021-06-0202 June 2021 Missouri & T Reactor - Follow-Up Report on Violation of Technical Specification (Surveillance Requirement) 4.6.2(1), EN-55266 ML21134A2452021-05-14014 May 2021 Missouri Univ. of Science & Technology, Self-Identified Violation of Operator Requalification Program 2.2 ML21039A3422021-02-0808 February 2021 Examination Confirmation Letter No.50-123/OL-21-01, Missouri University of Science and Technology ML21005A0272021-01-25025 January 2021 Must Amendment No 23 Acceptance Review - Application Accepted 12-28-2020 (6) ML20337A1622020-12-0202 December 2020 Proposed License Amendment Request for Missouri University of Science and Technology Reactor (License R-79, Docket 50-123) ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20314A3622020-11-12012 November 2020 Board of the Curators of the University of Missouri - Issuance of Amendment No. 22 to Renewed Facility Operating License No. R-79 to Extend the Period to Perform Visual Inspections of the Shim/Safety Rods ML20309A6762020-11-0404 November 2020 Missouri University of Science and Technology - Written Communication as Specified by 10 CFR 50.4 Requesting Approval of an Exigent Amendment to the Technical Specifications Appended to Facility Operating License R-79 IR 05000123/20202012020-09-28028 September 2020 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000123/2020201 ML20150A6062020-05-29029 May 2020 Missouri Univ. of Science & Technology - Submittal of 2019-2020 Annual Progress Report for Missouri University of Science and Technology Reactor ML20006C9282019-12-23023 December 2019 Examination Confirmation Letter No. 50-123/OL-20-02, Missouri University of Science and Technology ML19347B2142019-12-23023 December 2019 Examination Report No. 50-123/OL-20-01, Missouri University of Science and Technology ML19304B7332019-11-0505 November 2019 Examination Confirmation Letter No. 50-123/OL-20-01, Missouri University of Science and Technology ML19206A3642019-07-25025 July 2019 Examination Confirmation Letter No. 50-123/OL-19-02, Missouri University of Science and Technology IR 05000123/20192012019-07-0303 July 2019 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Inspection Report No. 50 123/2019-201 ML19182A3592019-07-0101 July 2019 Level 1 Personnel Change at the Missouri University of Science and Technology Reactor ML19149A6242019-05-29029 May 2019 Missouri s & T Reactor - 2018-2019 Annual Progress Report for Missouri University of Science and Technology Reactor ML19010A0822019-01-17017 January 2019 Washington State University - Change of Facility Project Manager ML19028A2942019-01-17017 January 2019 Level III Personnel Change at the Missouri University of Science and Technology Reactor Facility, License R-79, Docket 50-123 ML18365A3532019-01-0808 January 2019 Missouri University of Science and Technology - Change of Facility Project Manager IR 05000123/20182022018-12-26026 December 2018 Missouri University of Science and Technology - U.S. Nuclear Regulatory Commission Security Inspection Report 05000123/2018202 (Cover Letter) ML18276A2842018-09-28028 September 2018 Missouri S&T Reactor - Submittal of Updated Operator Requalification Program ML18257A1372018-09-14014 September 2018 Missouri University of Science and Technology Reactor (S&T Reactor) - Reply to a Notice of Violation ML18233A4012018-07-0202 July 2018 Requesting Approval for Reviewing Official at Mstr 2024-08-08
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML19042A0182019-02-0707 February 2019 Level 3 Personnel Change ML0824605612008-09-0808 September 2008 Missouri University of Science and Technology Reactor (Mstr), Request for Additional Information (Rai), August 27, 2008 ML0812700242008-05-12012 May 2008 Missouri University of Science and Technology Research Reactor (Mstr) Facility - Request for Additional Information (Rais) Regarding License Renewal ML0723405142007-11-16016 November 2007 University of Missouri - Rolla Research Reactor Facility - Request for Additional Information Regarding License Renewal ML0719800252007-08-0101 August 2007 University of Missouri-Rolla: Request for Additional Information Regarding: Technical Specifications Amendments ML0527103872005-09-26026 September 2005 RAI Letter - Security Measures - Bonzer 2019-02-07
[Table view] |
Text
August 1, 2007 Mr. William Bonzer, Reactor Manager University of Missouri-Rolla 226 Fulton Hall Rolla, MO 65409-0170
SUBJECT:
UNIVERSITY OF MISSOURI - ROLLA RESEARCH REACTOR FACILITY -
REQUEST FOR ADDITIONAL INFORMATION REGARDING CHANGES TO TECHNICAL SPECIFICATIONS (TAC NO. MD5976)
By letter dated April 9, 2007, you requested changes to the University of Missouri, Rolla, Research Reactor Technical Specifications. The Nuclear Regulatory Commission (NRC) staff has reviewed the information provided and has determined that additional information is needed to complete its review.
American Nuclear Society Standard 15.1, Development of Technical Specifications for Research Reactors, Section 6.4, Procedures, states [s]ubstantive changes to the previous procedures shall be made effective only after documented review by the review group and approval by Level 2 or designated alternates. Minor modifications to the original procedures which do not change their original intent may be made by Level 3 or higher but the modifications must be approved by Level 2 or designated alternates within 14 days. Your proposed amendment states [c]hanges that do not change the original intent of the procedures may be made with the approval of the Facility Manager. Please clarify whether the minor modifications need to be approved by Level 2 (Reactor Facility Director) and time to be approved after they are modified by the Facility Manager.
In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation. Following receipt of the additional information, we will continue our evaluation of your license amendment request. As discussed with you, we understand that you intend to respond to this request for additional information within 30 days of receipt of this letter.
Should you have any questions, please contact me at 301-415-1128 or John Nguyen at 301-415-4007.
Sincerely,
/RA/
Marvin Mendonca, Senior Project Manager Research and Test Reactors Branch B Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-123 License No. R-79
August 1, 2007 Mr. William Bonzer, Reactor Manager University of Missouri-Rolla 226 Fulton Hall Rolla, MO 65409-0170
SUBJECT:
UNIVERSITY OF MISSOURI - ROLLA RESEARCH REACTOR FACILITY -
REQUEST FOR ADDITIONAL INFORMATION REGARDING CHANGES TO TECHNICAL SPECIFICATIONS (TAC NO. MD5976)
By letter dated April 9, 2007, you requested changes to the University of Missouri, Rolla, Research Reactor Technical Specifications. The Nuclear Regulatory Commission (NRC) staff has reviewed the information provided and has determined that additional information is needed to complete its review.
American Nuclear Society Standard 15.1, Development of Technical Specifications for Research Reactors, Section 6.4, Procedures, states [s]ubstantive changes to the previous procedures shall be made effective only after documented review by the review group and approval by Level 2 or designated alternates. Minor modifications to the original procedures which do not change their original intent may be made by Level 3 or higher but the modifications must be approved by Level 2 or designated alternates within 14 days. Your proposed amendment states [c]hanges that do not change the original intent of the procedures may be made with the approval of the Facility Manager. Please clarify whether the minor modifications need to be approved by Level 2 (Reactor Facility Director) and time to be approved after they are modified by the Facility Manager.
In accordance with 10 CFR 50.30(b), your response must be executed in a signed original under oath or affirmation. Following receipt of the additional information, we will continue our evaluation of your license amendment request. As discussed with you, we understand that you intend to respond to this request for additional information within 30 days of receipt of this letter.
Should you have any questions, please contact me at 301-415-1128 or John Nguyen at 301-415-4007.
Sincerely,
/RA/
Marvin Mendonca, Senior Project Manager Research and Test Reactors Branch B Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-123 License No. R-79 DISTRIBUTION:
PUBLIC RidsNrrDprPrta RidsNrrDprPrtb RTR Reading ACCESSION NO.: ML071980025 TEMPLATE No.: NRR-106 OFFICE PRTA PRTA:LA PRTB:PM PRTA:BC NAME J Nguyen EHylton egh MMendonca mm DCollins dsc DATE 7/16/07 8/1/07 8/1/07 8/1/07
University of Missouri - Rolla Docket No. 50-123 cc:
Dr. Mariesa Crow, Dean School of Mines and Metallurgy 305 McNutt Hall University of Missouri-Rolla Rolla, MO 65401 Dan Estel University of Missouri-Rolla Nuclear Reactor Facility 1870 Miner Circle Rolla, MO 65409-0630 Mr. Michael Chapman Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health 930 Wildwood Drive, P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809 State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611