Draft Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate
ML071840997
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 08/15/2007
From: Richard Guzman
NRC/NRR/ADRO/DORL/LPLI-1
To: Mckinney B
Susquehanna
Guzman R, NRR/DORL, 415-1030
References
TAC MD3309, TAC MD3310
Download: ML071840997 (5)


Text

August 15, 2007 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (SSES 1 AND 2) - DRAFT ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RELATED TO PROPOSED EXTENDED POWER UPRATE (TAC NOS. MD3309 AND MD3310)

Dear Mr. McKinney:

Enclosed is a copy of the Draft Environmental Assessment and Finding of No Significant Impact related to your application dated October 11, 2006, as supplemented by letters dated October 25, December 4 and 26, 2006, February 13, March 14 and 22, April 13, 17, 23, 26, and 27, May 3, 14, 9, and 21, and June 1, 4, 8,14, 20, and 27, July 6, 12, 13, 30, 31, and August 3, 2007, for SSES 1 and 2. The proposed amendment would authorize increasing the maximum steady-state reactor core power level from 3489 megawatts thermal (MWt) to 3952 MWt, which is an increase of approximately 13 percent thermal power. The proposed increase in power level is considered an extended power uprate.

The assessment is being forwarded to the Office of the Federal Register for publication. In this regard, the comment period will expire on September 20, 2007.

Sincerely,

/RA/

Richard V. Guzman, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

Draft Environmental Assessment cc w/encl: See next page

August 15, 2007 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (SSES 1 AND 2) - DRAFT ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RELATED TO PROPOSED EXTENDED POWER UPRATE (TAC NOS. MD3309 AND MD3310)

Dear Mr. McKinney:

Enclosed is a copy of the Draft Environmental Assessment and Finding of No Significant Impact related to your application dated October 11, 2006, as supplemented by letters dated October 25, December 4 and 26, 2006, February 13, March 14 and 22, April 13, 17, 23, 26, and 27, May 3, 14, 9, and 21, and June 1, 4, 8,14, 20, and 27, July 6, 12, 13, 30, 31, and August 3, 2007, for SSES 1 and 2. The proposed amendment would authorize increasing the maximum steady-state reactor core power level from 3489 megawatts thermal (MWt) to 3952 MWt, which is an increase of approximately 13 percent thermal power. The proposed increase in power level is considered an extended power uprate.

The assessment is being forwarded to the Office of the Federal Register for publication. In this regard, the comment period will expire on September 20, 2007.

Sincerely,

/RA/

Richard V. Guzman, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

Draft Environmental Assessment cc w/encl: See next page

  • EA input provided by memo. No substantive changes made.

Accession Number: ML071840997 Draft EA: ML071841085 Package: ML071841027 OFFICE LPLI-1\PM LPLI-1\LA REBA\BC OGC LPLI-1\BC NAME RGuzman SLittle EBenner* LSubin MKowal DATE 8/13/07 8/14/07 5/11/07 EA DTD 8/13/07 8/15/07 OFFICIAL RECORD COPY

DISTRIBUTION:

PUBLIC LPLI-1 Reading File C. Haney RidsNrrDorl J. Lubinski RidsNrrDorl M. Kowal RidsNrrDorlLpIi-1 R. Guzman RidsNrrPMRGuzman E. Benner RidsNrrDlrReba T. Alexion RidsNrrPMTAlexion ACRS RidsAcrsAcnwMailCenter RidsOgcRp RidsRgn1MailCenter cc: Plant Mailing List

Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:

Robert A. Saccone Bryan A. Snapp, Esq General Manager - Nuclear Operations Assoc. General Counsel PPL Susquehanna, LLC PPL Services Corporation 769 Salem Blvd., NUCSB3 Two North Ninth Street, GENTW3 Berwick, PA 18603-0467 Allentown, PA 18101-1179 Terry L. Harpster Supervisor - Document Control Services General Manager - Plant Support PPL Susquehanna, LLC PPL Susquehanna, LLC Two North Ninth Street, GENPL4 769 Salem Blvd., NUCSA4 Allentown, PA 18101-1179 Berwick, PA 18603-0467 Richard W. Osborne Rocco R. Sgarro Allegheny Electric Cooperative, Inc.

Manager - Nuclear Regulatory Affairs 212 Locust Street PPL Susquehanna, LLC P.O. Box 1266 Two North Ninth Street, GENPL4 Harrisburg, PA 17108-1266 Allentown, PA 18101-1179 Director - Bureau of Radiation Protection Supervisor - Pennsylvania Department of Nuclear Regulatory Affairs Environmental Protection PPL Susquehanna, LLC P.O. Box 8469 769 Salem Blvd., NUCSA4 Harrisburg, PA 17105-8469 Berwick, PA 18603-0467 Senior Resident Inspector Michael H. Crowthers U.S. Nuclear Regulatory Commission Supervising Engineer P.O. Box 35, NUCSA4 Nuclear Regulatory Affairs Berwick, PA 18603-0035 PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Regional Administrator, Region 1 Allentown, PA 18101-1179 U.S. Nuclear Regulatory Commission 475 Allendale Road Steven M. Cook King of Prussia, PA 19406 Manager - Quality Assurance PPL Susquehanna, LLC Board of Supervisors 769 Salem Blvd., NUCSB2 Salem Township Berwick, PA 18603-0467 P.O. Box 405 Berwick, PA 18603-0035 Luis A. Ramos Community Relations Manager, Dr. Judith Johnsrud Susquehanna National Energy Committee PPL Susquehanna, LLC Sierra Club 634 Salem Blvd., SSO 443 Orlando Avenue Berwick, PA 18603-0467 State College, PA 16803