MONTHYEARRA23-018, Post-Outage Inservice Inspection (ISI) Summary Report2023-06-27027 June 2023 Post-Outage Inservice Inspection (ISI) Summary Report RA22-051, Submittal of the Snubber Program Plan for the Fourth 10-Year Interval2022-11-16016 November 2022 Submittal of the Snubber Program Plan for the Fourth 10-Year Interval RA22-021, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2022-06-0808 June 2022 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report ML21196A5022021-07-15015 July 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA21-017, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2021-04-0909 April 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report NMP2L2711, Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-8792019-10-16016 October 2019 Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-879 RA19-034, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2019-06-0707 June 2019 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report NMP2L2700, Co. - Submittal of Proposed Alternative to Utilize Code Case N-879 for Plants2019-04-30030 April 2019 Co. - Submittal of Proposed Alternative to Utilize Code Case N-879 for Plants ML18200A0802018-07-18018 July 2018 Submittal of Fourth 10-Year Interval Inservice Testing (IST) Program Plan RA18-059, Inservice Testing Program Plan, Technical Position TP-052018-07-18018 July 2018 Inservice Testing Program Plan, Technical Position TP-05 ML17314A0082017-11-10010 November 2017 Submittal of Program Plan Associated with the Fourth Lnservice Inspection (ISI) Interval and the Third Containment Lnservice Inspection (Cisi) Interval RA17-055, Post-Outage 90-Day Lnservice Inspection (ISI) Summary Report2017-06-0707 June 2017 Post-Outage 90-Day Lnservice Inspection (ISI) Summary Report RA16-020, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2016-06-0808 June 2016 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA16-021, Cycle 17 Startup Test Report Summary2016-05-12012 May 2016 Cycle 17 Startup Test Report Summary RA15-028, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2015-06-26026 June 2015 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA15-035, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2015-05-28028 May 2015 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RS-15-011, Proposed Alternative to the Examination Requirements for Nozzle-to-Vessel Welds and Inner Radii Sections in Accordance with 10 CFR 50.55a(z)(1)2015-01-29029 January 2015 Proposed Alternative to the Examination Requirements for Nozzle-to-Vessel Welds and Inner Radii Sections in Accordance with 10 CFR 50.55a(z)(1) RA14-018, Post-Outage 90-Day Inservice (ISI) Summary Report2014-05-29029 May 2014 Post-Outage 90-Day Inservice (ISI) Summary Report ML14149A2732014-05-29029 May 2014 LaSalle County Station, Unit 1 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA13-023, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2013-05-31031 May 2013 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA12-052, Amended Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2012-10-26026 October 2012 Amended Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA12-018, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2012-06-0505 June 2012 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA11-024, Unit 2 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2011-06-0303 June 2011 Unit 2 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA10-023, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2010-06-0404 June 2010 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA09-041, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2009-05-0808 May 2009 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA08-070, Submittal of Third 10-Year Inservice Testing (IST) Interval Program Plan2008-12-17017 December 2008 Submittal of Third 10-Year Inservice Testing (IST) Interval Program Plan RA07-045, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2007-06-0101 June 2007 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA07-036, Submittal of Relief Requests Associated with the Third Inservice Inspection (ISI) Interval and the Second Containment Inservice Inspection (Cisi) Interval2007-04-30030 April 2007 Submittal of Relief Requests Associated with the Third Inservice Inspection (ISI) Interval and the Second Containment Inservice Inspection (Cisi) Interval RS-07-058, Amergen/Exelon Nuclear - Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements2007-04-19019 April 2007 Amergen/Exelon Nuclear - Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements RA06-063, Proposed Third Ten-Year Interval Inservice Testing Program2006-10-16016 October 2006 Proposed Third Ten-Year Interval Inservice Testing Program ML0629704302006-09-29029 September 2006 Proposed Third Ten-Year Interval Inservice Testing Relief Request RA06-038, Post-Outage 90-Day Inservice Inspection Summary Report2006-06-16016 June 2006 Post-Outage 90-Day Inservice Inspection Summary Report ML0518004412005-06-10010 June 2005 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report ML0429405252004-10-15015 October 2004 Amended 90-Day Post Outage ISI Summary Reports ML0414201292004-05-0707 May 2004 Post-Outage 90-Day Inservice Inspection Summary Report ML0314900182003-05-21021 May 2003 Post-Outage 90-Day Inservice Inspection Summary Report ML0213307432002-05-0606 May 2002 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report 2023-06-27
[Table view] Category:Letter type:RA
MONTHYEARRA23-072, Regulatory Commitment Change Summary Report2023-12-15015 December 2023 Regulatory Commitment Change Summary Report RA23-057, Registration of Use of Cask to Store Spent Fuel2023-08-11011 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-055, Registration of Use of Cask to Store Spent Fuel2023-08-11011 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-052, Registration of Use of Cask to Store Spent Fuel2023-08-0404 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-051, Registration of Use of Cask to Store Spent Fuel2023-07-21021 July 2023 Registration of Use of Cask to Store Spent Fuel RA23-048, Registration of Use of Cask to Store Spent Fuel2023-07-14014 July 2023 Registration of Use of Cask to Store Spent Fuel RA23-045, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2023-06-30030 June 2023 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation RA23-047, Registration of Use of Cask to Store Spent Fuel2023-06-30030 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-018, Post-Outage Inservice Inspection (ISI) Summary Report2023-06-27027 June 2023 Post-Outage Inservice Inspection (ISI) Summary Report RA23-046, Registration of Use of Cask to Store Spent Fuel2023-06-23023 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-042, Registration of Use of Cask to Store Spent Fuel2023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-029, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 2022 Annual Radiological Environmental Operating Report RA23-028, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report RA23-027, Annual Dose Report for 20222023-04-21021 April 2023 Annual Dose Report for 2022 RA23-025, Post Accident Monitoring Report2023-04-0707 April 2023 Post Accident Monitoring Report RA23-013, Submittal of Triennial Chlorine Survey Report2023-03-30030 March 2023 Submittal of Triennial Chlorine Survey Report RA23-019, Cycle 20 Core Operating Limits Reports2023-03-21021 March 2023 Cycle 20 Core Operating Limits Reports RA22-066, 150 Day Submittal Cover Letter2022-12-0202 December 2022 150 Day Submittal Cover Letter RA22-060, Regulatory Commitment Change Summary Report2022-11-30030 November 2022 Regulatory Commitment Change Summary Report RA22-051, Submittal of the Snubber Program Plan for the Fourth 10-Year Interval2022-11-16016 November 2022 Submittal of the Snubber Program Plan for the Fourth 10-Year Interval RA22-041, Unit 2 Cycle 19 Core Operating Limits Report Revision2022-10-0505 October 2022 Unit 2 Cycle 19 Core Operating Limits Report Revision RA22-029, Cycle 20 Startup Test Report Summary2022-06-10010 June 2022 Cycle 20 Startup Test Report Summary RA22-021, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2022-06-0808 June 2022 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA22-020, Annual Radiological Environmental Operating Report2022-05-13013 May 2022 Annual Radiological Environmental Operating Report RA22-018, Annual Dose Report for 20212022-04-22022 April 2022 Annual Dose Report for 2021 RA22-010, Cycle 20 Core Operating Limits Reports2022-03-21021 March 2022 Cycle 20 Core Operating Limits Reports RA21-059, Regulatory Commitment Change Summary Report2021-11-30030 November 2021 Regulatory Commitment Change Summary Report RA21-050, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2021-11-0909 November 2021 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation RA21-051, County Station Physical Security Plan (Revision 18)2021-09-29029 September 2021 County Station Physical Security Plan (Revision 18) RA21-052, Registration of Use of Cask Store Spent Fuel2021-09-17017 September 2021 Registration of Use of Cask Store Spent Fuel RA21-046, Registration of Use of Cask to Store Spent Fuel2021-08-0505 August 2021 Registration of Use of Cask to Store Spent Fuel RA21-043, Cycle 19 Startup Test Report Summary2021-07-15015 July 2021 Cycle 19 Startup Test Report Summary RA21-031, 2020 Annual Radiological Environmental Operating Report2021-05-13013 May 2021 2020 Annual Radiological Environmental Operating Report RA21-029, Unit 2 - 2020 Annual Radioactive Effluent Release Report2021-04-29029 April 2021 Unit 2 - 2020 Annual Radioactive Effluent Release Report RA21-026, Annual Dose Report for 20202021-04-22022 April 2021 Annual Dose Report for 2020 RA21-016, Netco Rack Insert 10-year Surveillance Report2021-04-15015 April 2021 Netco Rack Insert 10-year Surveillance Report RA21-017, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2021-04-0909 April 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA21-019, Unit 2 Cycle 19 Core Operating Limits Reports2021-04-0707 April 2021 Unit 2 Cycle 19 Core Operating Limits Reports RA20-058, Licensee Post Exam Submittal Letter2020-12-0202 December 2020 Licensee Post Exam Submittal Letter RA20-044, Unit 2 - Unit 1 Cycle 19 Core Operating Limits Report2020-09-10010 September 2020 Unit 2 - Unit 1 Cycle 19 Core Operating Limits Report RA20-026, 2019 Annual Radiological Environmental Operating Report2020-05-13013 May 2020 2019 Annual Radiological Environmental Operating Report RA20-023, Annual Dose Report for 20192020-04-28028 April 2020 Annual Dose Report for 2019 RA20-016, Corrected Drawing for One-Line Electrical Power Supply for Containment Vent System Final Integrated Plan2020-03-24024 March 2020 Corrected Drawing for One-Line Electrical Power Supply for Containment Vent System Final Integrated Plan RA20-015, Triennial Chlorine Survey Report2020-03-20020 March 2020 Triennial Chlorine Survey Report RA20-014, Cycle 19 and Cycle 18 Core Operating Limits Reports2020-03-12012 March 2020 Cycle 19 and Cycle 18 Core Operating Limits Reports RA19-048, Registration of Use of Cask to Store Spent Fuel2019-09-0606 September 2019 Registration of Use of Cask to Store Spent Fuel RA19-045, Registration of Use of Cask to Store Spent Fuel2019-08-0909 August 2019 Registration of Use of Cask to Store Spent Fuel RA19-041, Registration of Use of Cask to Store Spent Fuel2019-07-0303 July 2019 Registration of Use of Cask to Store Spent Fuel RA19-039, Registration of Use of Cask to Store Spent Fuel2019-06-25025 June 2019 Registration of Use of Cask to Store Spent Fuel RA19-034, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2019-06-0707 June 2019 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report 2023-08-04
[Table view] |
Text
..... Exeltmn Exelon Generation Company, LLC www.exeloncorp.com NuClear LaSalle County Station 2601 North 21"Road Marseilles, IL 61341-9757 RA06-063 10 CFR 50.55a(f)
October 16, 2006 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-1 1 and NPF-1 8 NRC Docket Nos. 50-373 and 50-374
SUBJECT:
Proposed Third Ten-Year Interval Inservice Testing Program The purpose of this letter is to inform the NRC that Exelon Generation Company, LLC (EGC) intends to synchronize the Ten-Year In-Service Inspection intervals between LaSalle County Station (LSCS) Units 1 and 2 in accordance with 10 CFR 50.55a, "Codes and standards,"
paragraph (f), "Inservice testing requirements."
The LSCS Unit 1 second IST Interval is scheduled to end on October 11, 2006. The LSCS Unit 2 second IST Interval will end on May 07, 2007.
To effect the synchronization and alignment between the Unit 1 and Unit 2 IST intervals, the following shall be implemented based on the provisions of ASME Code Section Xl paragraph IWA-2430 "Inspection Intervals". In accordance with "Program B" of sub-paragraph IWA-2430(d), each inspection interval may be reduced or extended up to one year, however, adjustments shall not cause successive intervals to be altered by more than one year from the original pattern of intervals.
These changes will assure that the IST Program implemented on both Units 1 and 2 use the same Code Edition and Addenda for the next and successive intervals and will therefore establish common implementing procedures for both units. The common code of record for the third interval IST program will be the American Society of Mechanical Engineers (ASME) OM Code 2001 Edition through 2003 Addenda.
The current end date of the Unit 1 IST interval reflects a 690 day extension allowed by IWA-2430(e) for a Unit 1 forced outage Li F35. The current end date of the Unit 2 IST interval reflects a 932 day extension allowed by IWA-2430(e) for a Unit 2 refueling outage L2R07.
ASME Code Section XI paragraph IWA-2430(d) allows applying the IST extension to the interval in addition to extending the IST interval due to a power unit that is out of service for greater than 6 months.
October 16, 2006 U. S. Nuclear Regulatory Commission Page 2 As a result of these extensions of the current IST intervals as shown in the table below, the new date to start both LSCS Unit 1 and Unit 2 IST Third Ten-Year Interval will be October 11, 2007.
The extensions are all within the required maximum of one year in accordance with IWA-2430(d).
Table - Extension of Current LSCS IST Intervals I
Unit No. Inclusive Dates Time Extended Unit 1 October 11, 2006 to October 11, 2007 1 year Unit 2 Mav 07. 2007 to October 11. 2007 < 1 year Since the provisions of ASME Code Section Xl paragraph IWA-2430(d) are met, a relief request in accordance with 10 CFR 50.55a, "Codes and standards," paragraph (a)(3)(i) is not required and therefore this letter is provided for information only.
If you have any questions or require additional information, please contact Mr. Terrance Simpkin, Regulatory Assurance Manager, at 815-415-2800.
Respectfully, e kSusan Landahl Site Vice President LaSalle County Station cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - LaSalle County Station