I 1 30-May-2006 Job Performance Measure Exam Page:

-- -I. I JFM NO JR015.004 Perform a Plant Calorimetric per 0-6.3 Revision #: 4 Review Date: 5/30/2006 Location: In Plant Estimated Time (minutes): 20.00 Candidate:

Evaluator:

. d Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

30-MUY-2006 Page: 2 Job Performance Measure Exam -- ~

L/

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

The PPCS calorimetric calculation is not operable and the LEFM is not being used.

Initiating Cues :

The Control Room Foreman has directed you to perform a maximum unit power calculation per 0-6.3. For this JPM an Auxiliary Operator will collect field data collect and provide it to you.

Although the PPCS calorimetric calculation function is not operable, the PPCS is operable and may be used as necessary.

W

30-May-2006 Page:

Job Perfurmanee Measure Exam --

Description:

Perform a Plant Calorimetric per 0-6.3 (JR015.004)

JPM Tasks Task ID: 193-001-01-01B Task Standards :

In accordance with the procedure Tools :

Calculator Safety Glasses Hard Hat Hearing Protection Terminating Cues

--. Task Completion References :

-ID Description Review Date Ref Flag PRO 0-6.3 MAXIMUM UNIT POWER PRO 0-6.3.1 STEAM GENERATOR BLOWDOWN CORRECTION FACTOR Safety Considerations Consequences of Inadequate Performance:

Thermal design limit challenge General Comments :

Provide a copy of 0-6.3 and 0-6.3.1

3 0-May-2 006 Page: 4 Job Performance Measure Exam _- . -

Performance Checklist Element : Conditions : Standards :

Obtain current 0-6.3 and 0-6.3.1. NOTE: It is permissible to only Same as element.

obtain Attachment I and I1 of 0-6.3 and Attachment I of 0-6.3.1.

Comments :

Satisfactory Unsatisfactory Element : CRITICAL Conditions : Standards :

Properly collect and record data NOTE: If either RTD is unreliable Obtains data from:

required by 0-6.3 Attachments I (S/G RTD feedwater temperature -PPCS if available and 11. deviation high alarm on PPCS) do -MCB not use RTD data, instead use the -NIS average T/C feedwater temperature and apply for both loops.

Note: Provide Barton Data obtained by the A 0 to the examinee Comments :

Satisfactory n Unsatisfactory 0 Element : CRITICAL Conditions : Standards :

Properly collect and record data CUE: When Data Properly Obtain the S/G blowdown for Blowdown Correction Factor Collected the hand out per flow, temperature and per 0-6.3.1, Attachment I. collected data for calculations. pressure +/- 20 psig for each S/G from the blowdown panel.

Comments :

Satisfactory Unsatisfactory [7 Element : CRITICAL Conditions : Standards :

Properly perform calculations per 1) Same as element.

0-6.3.1, Attachment I. 2) If interpolate any value between selected rows.

3) Fq +/- .05.

Comments :

Satisfactory Unsatisfactory 0

I 1 30-May-2006 Job Performance Measure Exam Page:

- . -5. I w Element: CRITICAL Conditions : Standards :

Properly perform calculations per NOTE: If action is required per Same as element.

0-6.3, Attachment I and 11. step 5.3.2, DO NOT take action.

Advise the Shift Supervisor or +/- 0.5% of calculated CRF of any problems noted. answer.

Comments :

Satisfactory n Unsatisfactory 0 6 Element : Conditions : Standards :

Recommends appropriate action if Same as element.

100% power.

Comments :

Satisfactory 0 Unsatisfactory 0 7 Element : Conditions : Standards :

Compares calorimetric to NIS, TERMINATING CUE: No further Same as element.

recommends action if action.

disagreement exists.

NOTE: Attach completed 0-6.3 and 0-6.3.1 to this JPM.

Comments :

Satisfactory 0 Unsatisfactory 0 JPM Questions Question Answer References Reference Type Reference ID Description Ref Flag

I 25-May-2006 Job Performance Measure Exam Page:

1

- JPMNO JR341.002 0-6.13 Daily Performance Log Attachment I Revision #: 0 Review Date: 4/28/2006 Location: Simulator Estimated Time (minutes): 15.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

2 5-M~ry-2 006 Page: - 2 I

Performame Measure Exam -- ~

I

'.d NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE MAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

Normal plant monitoring in progress.

Initiating Cues :

Perform 0-6.13 Attachment I Channel Checks and Instrument Verification

25-May-2006 Job Performance Measure Exam Page:

-3. I

Description:

0-6.13 Daily Performance Logs Attachment (JR341.002)

JPM Tasks Task ID: 119-009-03-01B Task Standards :

Identify switch, meter or component out of required position or band.

Tools :

Terminating Cues Task Completion References :

-ID Description Review Date Ref Flag PRO 0-6.13 DAILY SURVEILLANCE LOG 0 Safetv Considerations Consequences of Inadequate Performance:

Tech Spec Violation General Comments :

1) Setup the Simulator at any 100% power IC
2) Insert MALF PZR3A, 43%
3) Verify >5% deviation between LT-426 and the other channels
4) Fill out 0-6.13 Attachment I for the last RWST visual check 7/16/06 92%

I 1 25-May-20 06 Job Performance Measure Exam Page:

-- PI Performance Checklist 1 Element : Conditions : Standards :

Review 0-6.13 Attachment I CUE: give attachment to examinee Same as element Comments :

Satisfactory 0 Unsatisfactory 0 2 Element : Conditions : Standards :

Perform Attachment I per Locates meters verify procedure parameters are within operability bands and complete Attachment I signoffs Comments :

Satisfactory 0 Unsatisfactory Element : CRITICAL Conditions : Standards :

Recognize that LT-426 is outside Locates LT-426. Determines the acceptance band that the instrument is inoperable per 0-6.13 and SR3.3.1.1 Comments :

Satisfactory Unsatisfactory

~~~

4 Element : Conditions : Standards :

Notify the CRS or SM CUE: No Further Actions Same as Element Comments :

Satisfactory Unsatisfactory 0

I I

I 25-May-2006 Job Performance Measure Exum Page: 5

..-l)M Ouestions Question Answer References Reference Type Reference ID Description Ref Flag

I 1 25-May-2006 Job Performance Measure Exam Page:

-l. I

.-..../

JPM NO JR343.005 Control of LCOs for Equipment Out of Service Revision #: 0 Review Date: 4/28/2006 Location: Simulator Estimated Time (minutes): 10.00 Candidate:

Evaluator:

-4 Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

I I

25-May-2006 Job Performame Measure Exam Page:

-- PI 1

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

Plant is at 55% power, Mini-Purge is not in service, no other equipment has an A-52.4 submitted on it.

Initiating Cues :

Shift Supervisor requests MOV-852A be deemed inoperable and asks you to fill out an A-52.4 to declare the component inoperable. The equipment will be inoperable due to the breaker being found tripped and cannot be reset. Required testing for operability will be determined after investigation of the problem. Use present date and time for when the component is to be deemed

- inoperable.

25-M~~~-2006 Job Performance Measure Exam Page:

-- 3I

Description:

Complete a A-52.4 Limiting Conditions for Operablity Evaluation (JR343.005)

JPM Tasks Task ID: 300-003-01-01A Task Standards :

Correctly determine the allowable time out of service for a single component.

Tools :

Terminating Cues Task Completion Trainee Says Task is Completed References :

-ID DescriDtion Review Date Ref Flag I

PRA A-52.4 CONTROL OF LIMITING CONDITIONS OF 0 OPERATIONS TECHSP ITS 3.5.2 ECCS - MODES 1,2, and 3 Safetv Considerations Consequences of Inadequate Performance:

Tech Spec Violation General Comments :

Component Inoperable is the B train of ECCS Tech Spec. 3.5.2

I I 25-May-2006 Job Performance Measure Exam Page:

-- 4I v

Performance Checklist 1 Element : Conditions : Standards :

Obtain a controlled copy of CUE: Give Examinee copy of the Same as Element A-52.4 procedure Comments :

Satisfactory 0 Unsatisfactory 0 2 Element : Conditions : Standards :

Fill in EIN, Date, and Time Same as element complete step 3.2.1 Comments :

Satisfactory Unsatisfactory 0 3 Element : Conditions : Standards :

Determine Plant mode and Plant Mode is Mode 1 complete step 3.2.2

- Comments:

Satisfactory Unsatisfactory u

  • 4 Element: CRITICAL Conditions : Standards :

Determine Tech Spec Section and Enter corect T.S. in 3.2.3.

fill in step 3.2.3 Tech Spec Section 3.5.2 ECCS Modes 1-3 Comments :

Satisfactory u Unsatisfactory 5 Element : Conditions : Standards :

Perform Loss of Safety Function Determines that no loss of Screening per Attachment I1 fill in safety function exists step 3.2.4 Comments :

Satisfactory Unsatisfactory 0 u - Element : Conditions : Standards :

Records EOOS PFS and System CUE: Colors are both Green Records Colors Colors complete step 3.2.5

25-May-2 006 Job Performance Measure Exam Page:

- 5.- I u-Comments :

Satisfactory 0 Unsatisfactory 0

  • 7 Element: CRITICAL Conditions : Standards :

Determines Required Action time Go To T.S. 3.5.2 from T.S. 3.5.2 complete step Determine that A Train is 3.2.6 operable (Table 3.5.2-1)

Determine Reqired action time from 3.5.2A 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore Record in step 3.2.6 Comments :

Satisfactory 0 Unsatisfactory

  • 8 Element: CRITICAL Conditions : Standards :

Determines Required Action time CUE: No further actions Go to 3.5.2B record time in not met from T.S. 3.5.2 complete step 3.2.13 step 3.2.13 Mode 3 in 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Mode 4 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Comments :

Satisfactory 0 Unsatisfactory 0 JPM Questions Question Answer References Reference Type Reference ID Description Ref Flag

I 1 I

25-May-2006 Job Performance Measure Exam Page:

I

-l. 1 v

JPM NO JC119.001 Complete EPIP 1-5 Status Report (PPCS no avalible)

Revision #: 0 Review Date: 5/22/2006 Location: Simulator Estimated Time (minutes): 10.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

25-May-2006 Page: 2 Job Performance Measure Exam -- ~

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

The Plant was at 100% power when a LOCA occured. An Alert was declared and the Initial notification has been made per EPIP 1-5. The PPCS has failed and the TSC is unable to complete status reports for transmittal. The communicator is currently busy making followup notifications.

Initiating Cues :

The Shift Manager directs you to complete and transmit the plant status report per EPIP 1-5 Attachment 3e.

r 1 25-May-2006 Page:

Job Performance Measure Exam -- - -3.1 L-

Description:

Complete EPIP 1-5 Status Report (PPCS 00s) (JC119.001)

JPM Tasks Task ID: 119-007-03-01A Task Standards :

Correctly complete EPIP 1-5 Attachment 3e data sheet.

Tools :

Terminating Cues The Data sheet is correctly completed References :

-ID Description Review Date Ref Flag PREPIP EPIP 1-5 NOTIFICATIONS CI Safety Considerations Consequences of Inadequate Performance:

Failure to correctly complete the required data sheet will result in the TSC & EOF being unable to assess plant conditions. This results in an inability of those organization to provide the need support the the Control Room and to protect the public.

General Comments :

Setup the Simulator to any at Power IC. Insert a 5000 gpm LOCA and complete E-0. Freeze simulator and record EPIP 1-5 Attachment 3e data for the key.

25-May-2006 Page:

Job Performance Measure Exam -- . -4 1 u.

Performance Checklist 1 Element : Conditions : Standards :

Obtain EPIP 1-5 Procedure and Obtain Procedure review attachment 3e Determine that Attachment 3e must be performed Comments :

Satisfactory 0 Unsatisfactory 0

~

  • 2 Element: CRITICAL Conditions : Standards :

Obtain Data for Attachment 3e Locates MCB indicators and from the Control Room records Data on the indications. attachment Comments :

Satisfactory Unsatisfactory

    • Element: CRITICAL Conditions : Standards :

Transmitts the attachment to the CUE: No further actions Transmits to the TSC via Fax L

TSC or telephone Comments :

Satisfactory 0 Unsatisfactory c]

JPM Questions Question Answer References Reference Type Reference ID Description Ref Flag

I I 25-May-2006 Job Performance Measure Exam Page:

-- -l. I

\-

JPM NO JS345.001 Respond to a Hazardous Chemical Spill Revision #: 0 Review Date: 5/22/2006 Location: In Plant Estimated Time (minutes): 15.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

I I 25-iMry-2006 Page:

I Performance Measure Exam --

J d'

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES, ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

The plant is operating durring normal conditions 100% power. Dayshift Midweek. You are the Shift ,Manager.

Initiating Cues :

The Stockroom notifies you that they were transporting 2 barrels of Hydrazine from the Warehouse to the Turbine Building. While decending the hill near the Outside Condensate Storage tank one of the barrels fell off the pallet and is leaking.

I I 25-May-2006 Job Performance Measure Exam Page:

-3. I

'y

Description:

Respond to a Hazardous Chemical spill JPM Tasks Task ID: 345-001-05-03A Task Standards :

Implement IP-ENV-3 to contain the spill and notify appropriate responders.

Tools :

TerminatinE Cues Task Completion References :

-ID Descrbtion Review Date Ref Flag PRIP IP-ENV-3 RESPONSE TO A SPILL OF HAZARDOUS L-MATERIAL/WASTE Safetv Considerations Consequences of Inadequate Performance:

Failure to mitigate the effects of a Chemical Spill result in an increase in risk to plant personnel and the public.

General Comments :

25-May-2006 Page: 4 Job Performance Measure Exam -- ~

W-Performance Checklist 1 Element : Conditions : Standards :

Obtain Copy of IP-ENV-3. Go to Same as Element the spill response section Comments :

Satisfactory Unsatisfactory Iz]

  • 2 Element : CRITICAL Conditions : Standards :

Announce spill over PA system CUE: Announcement is made. Makes the announcement or direct operator to make the annoucement Comments :

Satisfactory 0 Unsatisfactory 0

  • 3 Element : CRITICAL Conditions : Standards :

Dispatches Personnel to evaluate CUE: Personnel Contacted Contacts one of the following the spill. to evaluate the spill:

-NLO Note: Give the following Cue to -Chemical Control the SM after the evaluator has been Coordinator dispatched. -Safety Group

-Chemistry Group CUE: The spill evaluator reports the following;

1. The barrel split open spilling 112 its 35 gal contents.
2. Some of the contents ran into the storm drain located North of the outside CST.
3. The Forklift operator breathed in fumes from the chemical and is feeling ill, he is now in the TSC.
4. The material involed is SCAVOX 35% Hydrazine.
5. The HazMat Coordinator is on scene attempting to contain the spill.

Comments :

Satisfactory Unsatisfactory 0

25-May-2006 Job Performance Memure Exam Page:

-- - -51

-/ Element: CRITICAL Conditions : Standards :

Announces a Medical Emergency Note: When the Medical Make or Direct annoucement Announcement is made give the for Medical Response team to following cue. report to the TSC CUE: The CRS is refering to A-7 "Handling Injuries and Medical Emergencies and the associated notifications Comments :

Satisfactory 0 Unsatisfactory [7

  • 5 Element: CRITICAL Conditions : Standards :

Determines that the spill is major Determine that per attachment 1 and step 3.3.3 A. 2. that the spill is major.

Comments :

Satisfactory 0 Unsatisfactory

~ ~

Element : CRITICAL Conditions : Standards :

Perform Major spill action (not CUE: When notification made to Obtains MSDS sheet for the previously done) the Response coordinator- chemical MaryEllen Dangler has been Completes Attachment 2 notified and is acting as Notifies the Response Coordinator and Enviromental coordinator and Enviromental response team leader. staff Comments :

Satisfactory Unsatisfactory 0 7 Element : Conditions : Standards :

Evaluate the spill for EPIP 1-0 CUE: No Further Actions Detemine that no classifiction reporti bility critera was exceeded Comments :

Satisfactory Unsatisfactory 0

I 25-May-2006 Job Performance Measure Exam Page:

-- ~

1 JPM NO JS343.006 Loss Of Safety Function Determination Revision #: 0 Review Date: 5/22/2006 Location: Classroom Estimated Time (minutes): 10.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

25-MUY-2006 Page: 2 Pmformance Measure Exam -- ~

V '

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

100% Power normal operations. The following equipment is 00s "D"SW pump "B"CNMT Recirc Fan MOV 852A Initiating Cues :

The MCC 1D Supply Breaker trips and cannot be reset. MCC 1D is deenergized. What action must be taken per Tech Specs?

1 25-May-2 006 Job Performance Measure Exam Page:

-- -- I

Description:

Loss of Safety Function Determination JPM Tasks Task ID: 300-003-03-02C Task Standards :

Correctly Identify that a loss of Safety Function Exists Tools :

Terminating Cues Task Completion Trainee Says Task is Completed References :

-ID Description Review Date Ref Flag PRA A-52.4 CONTROL OF LIMITING CONDITIONS OF OPERATIONS TECHSP ITS 3.5.2 ECCS - MODES 1,2, and 3 TECHSP ITS 3.6.6 Containmen Spray (CS), Contaiment Recirculation Fan Cooler (CRFC), NaOH, and Containment Post-Accident Charcoal Systems TECHSP ITS 3.7.8 Service Water System CI TECHSP ITS 3.8.9 Distribution Systems - MODES 1,2,3, and 4 0 Safety Considerations Consequences of Inadequate Performance:

Tech Spec Violation General Comments :

I I 25-May-2006 Job Performance Measure Exam Page:

-- 4 I Performance Checklist 1 Element : Conditions : Standards :

Obtain Copy of Tech Specs and Same As Element A-53.4 Comments :

Satisfactory Unsatisfactory 0

  • 2 Element: CRITICAL Conditions : Standards :

Per TS 3.8.9 determine that "B" Same as Element train of AC power Dist is inoperable Comments :

Satisfactory Unsatisfactory c]

3 Element : Conditions : Standards :

Fill out A52.4 steps3.2.1-3.2.3 Same as Element Comments :

Satisfactory Unsatisfactory c]

  • 4 Element: CRITICAL Conditions : Standards :

Perform Saferty Function Evaluate 00s equipment evaluation (per Attachment 11) 1) SW pump D- Not in SW spec. therefore 3.8.9 gives guidence

2) "B" Recirc Fan All other fans have normal power supplies therefore do not have a loss of safety function.

3 ) MOV 852A, MCC 1D supplies MOV 852B therefore both trains of RHR are incapable of injection and inoperable.

Comments :

Satisfactory Unsatisfactory c]

25-May-2006 Page: 5 Job Performance Measure Exam - . -

.-. Element: CRITICAL Conditions : Standards :

Determine both trains of SI Cue: No further actions Same as Element iooperable enter TS 3.5.2B which directs to TS 3.0.3 Comments :

Satisfactory Unsatisfactory JPM Questions Question Answer References Reference Type Reference ID Description Ref Flag

1 I 22-Mi~y-2006 Job Performance Measure Exam Page:

-l. I JPM NO JS119.0Oi Verify Equipment Tagout Boundary Revision#: 0 Review Date: 4/28/2006 Location: Classroom Estimated Time (minutes): 10.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

22-May-2006 Job Performance Measure Exam Page:

-- 2. I 1,.

NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAh4INEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

Condensate transfer pump (PCD04) requires pump bearing replacement.

Initiating Cues :

The SM has requested you review the completed Isolated Work Area Request (A- 1401, Figure

1) for isolating the Condensate Transfer Pump (PCD04) to veri@ work area boundaries.

22-May-2006 Job Performance Measure Exam Page:

--  :.I b..

Description:

Review Isolated Work Area Request(JS 1 19.001)

JPM Tasks Task ID: 342-004-03-02A Task Standards :

1) Determine adequate boundary exists
2) Determine inadequate boundary exists Tools :

P&ID 33013-1234 P-12 Terminating Cues Trainee Says Task is Completed Task Completion v

References :

-ID Description Review Date Ref Flag PROPSA A-1401 STATION HOLDING RULES 0 PRP P-12 ELECTRICAL SYSTEMS PRECAUTIONS, 0 LIMITATIONS, AND SETPOINTS Safety Considerations Consequences of Inadequate Performance:

Personal Injury Equipment Damage General Comments :

Provide P&ID and A-1401 Figure 1 to student. Incorporate errors on A-1401 Figure 1 if it is desired to exercise Option 2.

d'

22-May-2006 Page: 4 Job Performance Measure Exam

~~

v Performance Checklist 1 Element : Conditions : Standards :

Review Isolated Work Boundary. Same as element.

Comments :

Satisfactory 0 Unsatisfactory 0

  • 2 Element: CRITICAL Conditions : Standards :

Option 1 - Boundary is adequate. CUE: No further actions Option 1 - Determines no Option 2 - Boundary is not errors in boundary.

adequate. Option 2 - Determines and reports errors in boundary.

V-4046 needs to be closed.

Comments :

Satisfactory 0 Unsatisfactory 0 M Questions Question Answer References Reference Type Reference ID Description Ref Flag

25-May-2006 Job Performance Measure Exam Page:

-- -:I U

JPM NO JS341.002 Approve Liquid Release per CH-RETS-LIQ-REL (JS341.002)

Revision #: 1 Review Date: 5/22/2006 Location: Classroom Estimated Time (minutes): 10.00 Candidate:

Evaluator:

I Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

25-May-2006 Job Performance Measure Exam Page:

-:I NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE 'IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WRITTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF P M REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

The operating crew is preparing to release a Monitor Tank.

Initiating Cues :

You are the Shift Manager and are required to review a release form prior to making a Liquid Release of the Monitor Tank per CH-RETS-LIQ-REL "Liquid Waste Release" Figure V

I 1 25-May-2006 Job Performance Measure Exam Page:

-- -:I L

Description:

Approve Liquid Release per CH-RETS-LIQ-REL (JS341.002)

JPM Tasks Task ID: 341-012-03-03A Task Standards :

Detects errors in the permit and does not approve the permit until corrected.

Tools :

Terminating; Cues Task Completion References :

ID Descrbtion Review Date Ref Flag PRCH CH-RETS-LIQ-REL LIQUID WASTE RELEASE CI Safetv Considerations Consequences of Inadequate Performance:

Exceeding Release rate for a Liquid Release General Comments :

Complete a CH-RETS-LIQ-REL Attachment V for pre release condition. (May obtain RP assistance) compete pre release parts correctly except @r the sample time being >12 hour prior to the start of the release.

I 25-May-2006 Page: 4 Job Performance Measure Exam - -

Performance Checklist 1 Element : Conditions : Standards :

Reviews CH-RETS-LIQ-REL Same as element form.

Comments :

Satisfactory 0 Unsatisfactory 0

  • 2 Element: CRTTICAL Conditions : Standards :

Evaluate Attacment V for correct Determines the form is Data incorrect in that the release time is outside the allowable time permited. (> 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> since the sample time)

Comments :

Satisfactory Unsatisfactory [7 Element : Conditions : Standards :

--/ Determine that sample must be Cue No further actions Same as element.

redone Comments :

Satisfactory Unsatisfactory JPM Ouestions Question Answer References Reference Type Reference ID Description Ref Flag

2 5-May-2 006 Page:

Job Performance Measure Exam --

JPM NO JS340.021 Event Classification Revision #: 0 Review Date: 5/4/2006 Lo cation: Simulator Estimated Time (minutes): 15.00 Candidate:

Evaluator:

Actual Time:

Trainee Performance: Satisfactory Unsatisfactory Trainee:

Instructor:

Submitted By Date Reviewed By Date

I I 25-May-2006 Job Performance Measure Exam Page:

_- . -21 NOTE THE EVALUATOR WILL EXPLAIN THE JPM INITIAL CONDITIONS AND PROVIDE CLARIFICATION AS REQUIRED. THE EXAMINEE MAY USE ANY CONTROLLED COPY REFERENCES THAT ARE NORMALLY AVAILABLE IN THE CONTROL ROOM, INCLUDING LOGS. MAKE ALL WIUTTEN REPORTS, ORAL REPORTS, AND LOG ENTRIES AS IF THE EVOLUTION WAS ACTUALLY BEING PERFORMED. THE EVALUATOR WILL BE TAKING NOTES. ASK FOR CLARIFICATION OF JPM REQUIREMENTS PRIOR TO THE BEGINNING OF JPM PERFORMANCE.

Initial Conditions:

The plant experienced the events of the just concluded scenario.

Initiating Cues :

Classify this event at the highest required classification per EPIP 1-0.

25-May-2006 Page: 3 Job Performance Measure Exam -- -

u

Description:

Event Classification for the 2006 Initial License exam (JS340.02 1)

JPM Tasks Task ID: 340-001-05-02N Task Standards :

Classify per the Nuclear Emergency Response Plan Tools :

Terminating; Cues Task Completion Trainee Says Task is Completed References :

- -ID PREPIP EPIP 1-0 Description GINNA STATION EVENT EVALUATION Review Date Ref Flag AND CLASSIFICATION Safetv Considerations Consequences of Inadequate Performance:

Failure to correctly Classify the event leads to the Failure to correct implement the Emergency plan, resulting in a unnecessary threat to the health and safety of the public.

General Comments :

The JPM is designed to be used with the 2006 Initial NRC License Exam.

1 I 25-May-2006 Job Performance Measure Exam Page:

. -41 d'

Performance Checklist 1 Element : Conditions : Standards :

Obtain copy of EPIP 1-0 May use Procedure or Wall Chart Comments :

Satisfactory Unsatisfactory 0

~~

  • 2 Element: CRITICAL Conditions : Standards :

Correctly determine Classification CUE: No futher actions Scenario 06 1 Alert based on RCS Leakage

>46 gpm EAL 3.1.2 Scenario 06- 1-2 SAE based on Faulted Ruputed S/G EAL 4.2.1 Scenario 06-1-3 Alert Based on RCS Leakage

> 46 gpm EAL 3.1.2 Comments :

Satisfactory Unsatisfactory 0 JPM Questions Question Answer References Reference Type Reference ID Description Ref Flag