August 15, 2006 Tennessee Valley Authority ATTN: Mr. K. W. Singer Chief Nuclear Officer and Executive Vice President 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
MEETING SUMMARIES: 1.) CATEGORY 1 PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) RE. BROWNS FERRY UNIT 1 RECOVERY STATUS; 2.) MEETING OF THE NRC RESTART PANEL FOR THE BROWNS FERRY UNIT 1 RECOVERY; 3.) PERFORMANCE ASSESSMENT OF BROWNS FERRY UNIT 1 - DOCKET NO. 50-259
Dear Mr. Singer:
This refers to the public meeting conducted at Calhoun Community College located near Decatur, Alabama on August 3, 2006. The purpose of the meeting was to discuss the Browns Ferry Unit 1 (BF1) Restart Project Status. Discussions during this meeting included the following topics: Unit 1 schedule, returning systems to service, emerging issues, regulatory status, and operational readiness. Enclosure 1 contains a list of attendees. Enclosure 2 contains the NRC Browns Ferry Unit 1 Recovery Issues List which represents the NRCs understanding of the issues requiring NRC review prior to restart of Unit 1. Enclosure 3 contains the presentation material used by your staff to discuss the status of the Browns Ferry Unit 1 Restart Project. The list is current as of August 3, 2006, the date of the meeting.
The meeting was informative and a beneficial exchange of information. As a result of the meeting the NRC will continue to work with your staff in understanding which procedures applicable to fire protection operator manual actions will be completed prior the NRCs Triennial Fire Inspection of BF1. In addition the NRC informed TVA that any change in BF1 restart scheduling could potentially impact NRCs resources and schedule for inspections of system readiness and start up assessment inspections. During the meeting the NRC noted that your staff presentation emphasized continued safe operation of Units 2 and 3 while maintaining a focus on the Unit 1 scheduled restart date. The NRC stated that we will continue to maintain and ensure public health and safety as its overriding priority of the operating Unit 2 and 3 and throughout the Unit 1 recovery process.
In addition, on August 3, 2006, the Nuclear Regulatory Commission (NRC) held an internal meeting of the NRC Browns Ferry 1 (BF1) Restart Oversight Panel at the Browns Ferry site.
The purpose of this panel meeting was to discuss NRC perspectives on the BF1 restart project status, results from recent NRC inspections of BF1, status of notable licensing actions, and recent issues important to NRC oversight and inspections. The panel was established in accordance with NRC Inspection Manual Chapter (IMC), IMC 2509, Browns Ferry Unit 1 Restart Project Inspection Program. The purpose of IMC 2509 is to provide the policies and requirements for the restart inspection program, to establish a BF1 Restart Oversight Panel, and to document the major regulatory and licensee actions associated with the restart.
2 TVA MC 2509 Browns Ferry Unit 1 Restart Project Inspection Program Section 05.10.b specifically states that the Restart Oversight Panel will provide licensee performance assessment periodically prior to restart. The Restart Oversight Panel has determined that guidance contained in sections of MC 0305 "Operating Reactor Assessment Program," referring to performance assessments are not fully applicable to BF1. The assessment program for BF1 recovery process will only collect information from inspections until a full transition into the Reactor Oversight Process (ROP) has been completed. Currently four (4) cornerstones are under the ROP (MC 305): Occupational Radiation Safety, Public Radiation, Emergency Preparedness, and Physical Protection. All other cornerstones are being monitored through the inspection findings and corrective action process. The Panel uses the inspection findings to determine the adequacy of the licensees performance.
Because TVAs recovery effort is intended to ensure full compliance and because BF1 has no discernable risk in its present defueled state, neither MC 2515 nor the present guidance for performance indicators (PIs) are fully applicable. However, using this program documentation as a guide, inspection findings for the past six months would be classified as having very low safety significance and would require no additional NRC oversight. The NRC identified several weakness, deficiencies and non-cited violations throughout the assessment period which are captured and addressed in the licensees corrective action program (CAP) and all are dispositioned using traditional enforcement. The Panel assessment of the recovery effort to date indicates that TVA has performed work in a safe manner that promotes maintaining and protecting public health and safety.
The NRC plans to continue to conduct non-ROP inspections including system readiness inspections, operational readiness assessment inspections and ongoing BF1 recovery and restart inspections through a standard assessment cycle which would cover through March 31, 2007.
Documents associated with the NRC oversight of the BF1 Recovery can be found at on the NRCs website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/bf1-recovery.html.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning these meetings, please contact me at (404) 562-4501.
Sincerely,
/RA/
Joseph W. Shea, Deputy Director Division of Reactor Projects, Region II Docket No.: 50-259 License No.: DPR-33
Enclosures:
- 1. List of Attendees
- 2. NRC Browns Ferry Unit 1 Recovery Issues List (August 9, 2006)
- 3. TVA Presentation Handout - Browns Ferry Nuclear Plant - Unit 1 Restart cc w/encls: (See page 3)
OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE MTW for MSL1 MTW NAME TNazario MLesser MWidmann DATE 08/15/2006 08/15/2006 08/15/2006 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
3 TVA cc w/encls.:
Ashok S. Bhatnagar Senior Vice President Nuclear Operations Tennessee Valley Authority Electronic Mail Distribution Larry S. Bryant, Vice President Nuclear Engineering & Technical Services Tennessee Valley Authority Electronic Mail Distribution Brian O'Grady Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution Preston D. Swafford Senior Vice President Nuclear Support Tennessee Valley Authority Electronic Mail Distribution General Counsel Tennessee Valley Authority Electronic Mail Distribution John C. Fornicola, Manager Nuclear Assurance and Licensing Tennessee Valley Authority Electronic Mail Distribution Bruce M. Aukland, Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution Glenn W. Morris, Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority Electronic Mail Distribution William D. Crouch, Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P. O. Box 303017 Montgomery, AL 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611 Masoud Bajestani, Vice President Browns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P. O. Box 2000 Decatur, AL 35609 Robert G. Jones, General Manager Browns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P. O. Box 2000 Decatur, AL 35609 Distribution w/encl: (See page 4)
4 TVA Meeting Summary to Karl W. Singer from Joseph W. Shea dated August 15, 2006.
SUBJECT:
MEETING SUMMARIES: 1.) CATEGORY 1 PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) RE. BROWNS FERRY UNIT 1 RECOVERY STATUS; 2.) MEETING OF THE NRC RESTART PANEL FOR THE BROWNS FERRY UNIT 1 RECOVERY; 3.) PERFORMANCE ASSESSMENT OF BROWNS FERRY UNIT 1 - DOCKET NO. 50-259 Distribution w/encl:
C. Holden, NRR L. Raghavan, NRR J. Boska, NRR M. Widmann, DRP L. Mellen, DRP T. Nazario, DRP K. Clark, RII M. Lesser, DRS W. Bearden, DRP C. Casto, DRP J. Shea. DRP L. Plisco, RII B. Wetzel, OEDO L. Slack, RII EICS RIDSRIDSNRRDIPMLIPB PUBLIC List of Attendees NRC/TVA Unit 1 Restart Management Meeting Nuclear Regulatory Commission J. Shea, Deputy Director, Division of Reactor Projects (DRP)
C. Holden, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR M. Widmann, Chief, Branch 6, DRP L. Raghavan, Branch Chief, DORL, NRR M. Lesser, Chief, Engineering Branch 3, Division of Reactor Safety (DRS)
W. Bearden, Senior Resident Inspector Unit 1, Branch 6, DRP C. Stancil, Resident Inspector, Branch 6, DRP T. Ross, Senior Resident Inspector Units 2 and 3, Branch 6, DRP T. Nazario, Project Engineer, Branch 6, DRP J. Boska, Project Manager, DORL, NRR K. Clark, Public Affairs, RII Browns Ferry (TVA)
B. OGrady, Site Vice President M. Bajestani, Vice President Unit 1, Restart T. McGrath, Senior Project Manager, Operational Readiness W. Crouch, Site Licensing & Industry Affairs Manager R. Baron, Unit 1 Nuclear Assurance Manager J. McCarthy, Unit 1 Licensing G. Little, Unit 1 Restart Manager J. Valente, Engineering Restart Manager C. Beasley, TVA Communications and Government Relations J. Schlessel, Unit 1 Maintenance and Modifications Manager Public K. Middleton, News Corner C. Pascheulco, Decatur Daily J. Tipper, Shoals Environmental Alliance J. North M. Robbins M. Wingo B. Lawson, Huntsville Times NRC REGION II - BROWNS FERRY UNIT 1 RECOVERY ISSUES LIST Issue Status as of August 10, 2006 Reconciled with last TVA Quarterly Update Last BF1 Public Restart Meeting: May 3, 2006 at Browns Ferry Summary TVA Special Programs - There are 27 TVA Special Programs identified in the TVA Regulatory Framework Letter (dated 12/13/2002) regarding Unit 1 recovery. Prior to the Unit 1 recovery, additional Special Programs existed which were closed and/or combined with the remaining 27. This matrix identifies all 30 Special Program areas in order to clarify how several programs have been consolidated into the inspection process based on how the issues were reviewed for the Unit 2 and 3 recoveries. TVA is providing Special Program closures for the 27 they identified via a comprehensive quarterly issue update letter.
14 Open 10 Expected to be closed during the next inspection report period 16 Inspections complete - (based on the reviews performed, no further NRC inspections are anticipated in this area)
Initial inspections have been performed for most Special Programs. Inspections are complete for: Cable Tray Supports, Conduit Supports, Configuration Management (including Design Calc. Review subpart), IGSCC, Drywell Platforms, Platform Thermal Growth and Seismic II/I as of 01/06.
Generic Communications Open Items - Includes all items from TVA Regulatory Framework correspondence and other NRC reviews to identify issues for Unit 1. These include NRC Generic Letters, Bulletins, Multi-plant Actions (MPA), Three Mile Island (TMI) Items, Temporary Instructions (TI), etc.
11 Open 9
Expected to be closed during the next inspection report period 55 Closed/Complete (Items adequately resolved for restart in accordance with NRC Inspection Manual Chapter (MC) 2509.
Other Miscellaneous Issues - Item to be Dispositioned Prior to Restart 5
Not Dispositioned 7
Dispositioned Open Items (LERs, URIs, and IFIs) - Includes items identified as open for Unit 1 based on historical docket review. This was the primary inspection area in 2004. Also includes any recently identified issues pending resolution.
3 Open Listed below.
53 Closed Adequately resolved for restart per MC 2509 and closed in an IR since BF1 Recovery inspections began in 2003.
Remaining Unit 1 LERs, URIs, and IFIs LER 88-37 Inadequate Design Results for HVAC (Seismic Issue) - Vias reviewed 9/05, field work not complete, to be rescheduled, 07/06. Anticipated closure in 2006-08 URI 06-12-01 Use of Local Manual Operator Actions to Achieve Safe Shutdown during a fire (see Special Program #12).
URI 06-06-01 Adequacy of RHRSW SRTS Activities NOTES:
An extensive review of inspection reports (IR) back to 1985 was done for all open inspection items against Unit 1.
Many of these were resolved but never formally closed on the Unit 1 docket. Most of these items have now been formally closed in a Unit 1 IR and recorded in NRCs RPS tracking program. Open allegations, OI investigations, and emerging/draft issues are not contained in this list. Open Licensing Actions with NRR are maintained on a separate list, but will be evaluated for addition to this list by the Restart Panel.
Sources for all the above issues include: Historical RPS, SIMS, NUREG 1435 (Status of Safety Issues at Licensed Power Plants), SECY 95-264 (final Unit 3 Restart Matrix)
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 1
Cable Ampacity 3.11.3 DRS-C.
Smith 04-07 Open 9/27/06 Yes NUREG-1232 No Inspection scheduled 10/16/06.
2 Cable Installation/
Cable Separations Issues 3.11.4,.5 DRS-Staples 04-07 04-09 05-08 05-09 06-07 Expected Closure 06-08 Open 9/27/06
- Yes, tracked as 9 sub issues SER 4/08/92 SER 7/1/94 on bend radius No Related closure item LER 88-32. Ref. 1/28/93 closure letter. U2 closed in IR 90-
- 25. U3 closed in IR 95-25.
Scheduled for 9/18/06 3
Cable Splices 3.13 DRS-Merriweather Rodriguez 04-08 05-08 06-07C Open 9/27/06 Yes SER 4/08/92 1/23/91 No Thermal overload issues identified in IR 05 will need to address extent of condition reviews once completed by TVA.
4 Cable Tray Supports 2.2.2.7; SE 12/17/91 DRS-Vias, Nazario 03-10 04-06 05-08C Closed 2/18/05 Yes SER 12/17/91 11/19/92 3/19/93 No TVA 10/7/04 letter on SQUG [GL 87-02]
summarized resolution.
U3 closed in IRs 90-22,95-14, 95-20, 95-52.
5 Component and Piece Part Qualification 3.3 DRS-Merriweather Expected Closure 06-08 Open 6/26/06 Yes 12/07/93 NRC letter No Initial program review completed during EQ inspection - Next Inspections scheduled 10/16/06.
U3 closed in IR 95-60.
Related to Item #11.
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 6
Conduit Supports 2.2.2.3 DRS-Vias, Nazario 04-06 05-08C Closed 2/18/05 Yes SER 10/24/89 3/20/92 11/19/92 3/19/93 No TVA 10/7/04 letter on SQUG [GL 87-02]
summarized resolution U3 closed in IRs 95-15 &
95-57.
7 Configuration Mgmt/ Design Baseline 2.1 DRS-Mellen, SSDPC Team 05-08C Closed 5/19/05 Yes NRC 11/21/91 approval letter on U1 docket No Utilized baseline SSDPC inspection procedure for review.
Related to Item #10.
8 Containment Coatings 3.7 DRS-Lenahan 04-07 04-08 05-06 Expected Closure 06-08 Open 8/14/06 Yes NUREG 1232 covered U2.
No U3 closed in IRs 94-01, 94-09, 94-18, 94-27.
Scheduled for weeks of 8/28 and 9/1 9
Control Rod Drive insert
/withdrawal piping 2.2.3.2 DRS-
- Lenahan, Vargas 04-07 04-08 05-08 05-09 06-06C Open 5/08/06 Yes NUREG 1232 covered U2.
No U3 closed in IR 95-52.
10 Design calc review 2.1 DRS-Mellen, SSDPC type team inspection 05-08C Closed 5/19/05 No -
See Note NRC 11/21/91 approval letter on U1 docket No Utilized baseline SSDPC inspection procedure for review. Note :this item incorporated into Item #7.
11 Environmental Qualification 3.2 DRS-Merriweather Mas-Penaranda 03-10 04-08 05-08 Expected Closure 06-08 Open 7/31/06 Yes NUREG 1232 covered U2 No U3 closed in IRs 95-43, 95-
- 56. Inspection Scheduled 10/30/06
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 12 Fire Protection/10 CFR 50, Appendix R 3.1 DRS-Fillion,
- Wiseman, Rodriguez 04-09 05-16 06-12 Open 8/7/06 Yes SER 12/08/88 11/03/89 3/31/93 11/02/95 No.
Previous SERs addressed overall approach, no Unit 1 specific exemptions considered required. Next triennial inspection sched.
8/06 for U 1, 2, & 3. Team to determine if any impact from OMA or hot short generic resolutions.
U3 was closed in IRs 94-27, 95-04, 95-07, 95-37.
Scheduled for 9/30/06 13 Flexible Conduits 3.12 DRS-
- Staples, 04-07 04-09 06-06C Open 7/31/06 Yes SER 3/19/93 SER 10/3/95 No Related to GL 87-02 resolution.
14 Fuses 3.11 DRS-Merriweather Christnot assist in sampling verification 04-08 05-08 06-07C Open 9/20/06 Yes NUREG 1232 covered U2 SER.
4/14/89 No Program reviewed in 04-08.
Next inspection 6/06.
U3 closed in IRs 93-02, 93-08, 95-02, 95-45.
15 HVAC Duct Supports 2.2.2.4 DRS-Vias Expected Closure 06-08 Open 5/25/06 Yes NUREG 1232 covered U2 SER.
10/24/89 8/22/90 No Also address LER/88-37 during next inspection.
U3 closed in IRs93-201 &
95-52.
16 Instrument Sensing Lines 3.4 DRS-Lenahan 06-07 Expected Closure 06-08 Open 7/13/06 Yes SER 12/10/91 No U3 closed IRs 94-24, 95-
- 56. Scheduled for weeks of 8/28 and 9/1
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 17 Instrument Tubing 2.2.3.4 DRS-
- Lenahan, Nazario 05-08 06-07 Expected Closure 06-08 Open Yes See Note Yes See Note No Note: Program combined with small bore piping (Item
- 29) in original regulatory framework letter.
Scheduled for weeks of 8/28 and 9/1 18 Intergranular Stress Corrosion Cracking (IGSCC) 3.6 DRS-Fuller 03-09 03-10 04-06 04-07 04-09 05-08C Open Yes SER 12/21/89 U2 SER 12/03/93 U3 SER 4/25/05 NRR to issue SE.
NRC letter to TVA RAI Program submitted for review 7/21/04. Scope of U1 different than U2 and 3.
Reviews have included recirc and RBCCW piping, Mechanical Stress Improvement Process (MSIP).
U3 closed in IRs 92-31 &
93-05.
19 Large Bore Piping Supports 2.2.3.1 DRS-Chou, Rivera 03-09 05-06 05-08 05-09 06-07 Expected Closure 06-08 Open Yes see note NUREG 1232 No Note: TVA tracks as Bul 79-02 and 79-14, not as a special program.
Scheduled for weeks of 8/28 and 9/18
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 20 Long Term Torus Integrity Program 2.2.4.3; SE 8/20/80 DRS-Chou 03-09 03-10 04-11 04-07 04-09 Expected Closure 06-08 Open 7/5/06 Yes SER 5/06/85 2/10/92 No Complete in conjunction with large bore pipe program. Internal torus complete.
U3 closed in IRs 94-15,95-03, 95-52. Scheduled for weeks of 8/28 and 9/18 21 Drywell Steel Platforms and Upper drywell platforms 2.2.2.5 DRS-Lenahan 03-09 04-07 05-08C Open 4/20/06 Yes SER 12/7/93 No Inspection complete, no further action planned.
22 Misc Steel Frames 2.2.2.6 SE 10/24/89 DRS-
- Lenahan, Carrion 03-09 06-06C Open No No No Drywell steel is complete.
-TVA to NRC 12/13/02 letter combined Misc Steel Frames into Lower Drywell Platforms and Miscellaneous Steel.
23 Moderate Energy Line Break (MELB) 3.8 NRR/DRP Mellen 06-07C Complete 6/4/05 Yes NUREG 1232 Letter dated June 7, 2006 No TVA to NRC 6/25/04 letter completed TVA actions.
Reviewed for U3 in IR 95-
24 Platform Thermal Growth 2.4 DRS-Lenahan 03-09 04-04 05-08 06-06 C Open No No No Inspection complete, no further action planned.
TVA to NRC 12/13/02 letter combined Platform Thermal Growth into Lower Drywell Platforms and Miscellaneous Steel
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 25 Probabilistic Safety Assessment (PSA) 3.9 NRR -
Chernoff DRS -
Bernhard Possible closure 9/06 Complete 2/18/05 No No SER for any unit (PSA).
NRC staff evaluation 9/28/94 for U2 (88-20) 5/20/98, 5/04/99 for U3 (88-20)
Yes See Note.
Historical: TVA to NRC 12/13/02 letter closed PSA with BFN Multi-Unit PSA (April 14, 1995). NRC request ltr 6/21/04.
NRR to review TVAs 8/17/04 Resp to GL 88-20.
NRR response letter to close.U3 closed in IR 95-
- 49.
Note: Issuance of MC1895 and MC5729 will close this action. Expected 1/14/07 26 Q List 3.15 DRP-Bearden 06-07C Open Yes No No Inspection planned 7/06.
The BF1 Senior Resident Inspector is following this item.
27 Restart test program (RTP) 4.6 NRR/DRP Open 9/12/06 Yes NUREG 1232 SER 8/30/94 Yes NRR Ltr to TVA 6/15/05 requesting details of RTP.
TVA submitted RTP 8/15/05. Currently under tech staff review. Specific licensee system turnover reviews to be done on key systems by experienced inspectors familiar with BWR mitigating systems.
U3 closed in IRs 95-07, 08, 26, 51, 60. This is being tracked on the Master Inspection List.
TVA SPECIAL PROGRAMS (Endorsed per 8/14/03 Reg Framework ltr from NRR/Marsh)
Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports (C-Inspection Completed)
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 28 Seismic Class II Over I/Spacial Systems Interactions and Water Spray 2.2.4.2 DRS-Vias, Nazario 05-08C Open Yes SER 11/19/92 No Inspection complete, no further actions planned.
Include DCN 51192, as referenced in IR 04-06, Section E1.3. Related to GL 87-02.
29 Small Bore Piping
/Supports 2.2.3.3 DRS-
- Lenahan, Nazario Alternate -
Vias 05-08 Expected Closure 06-08 Open Yes SER 10/24/89 2/4/92 No Inspect in conjunction with Instrument Tubing. (Item
- 17) U3 closed in IRs 95-03, 95-57. Scheduled for weeks of 8/28 and 9/1 30 Thermal Overload 3.11 DRS-Merriweather 04-08 05-08 06-07C Open 9/20/06 Yes NUREG 1232 No Next inspection 6/06. NCV identified in IR 05-08 regarding TOL design implementation problems -
will need to address extent of condition reviews once completed by TVA.
U3 closed in IR 95-25.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 1
BU 79-02 Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts SER 2/8/90 DRS-Chou Expected Closure 06-08 Open Yes No NUREG 1232 Associated with large bore piping Special Program reviews. Scheduled for weeks of 8/28 and 9/18 2
BU 79-12 Short Period Scrams At BWR Facilities DRS-MacDonald 06-07C Open Yes No No U3 item closed in IR 95-51, TVA action due 6/06.
3 BU 79-14 Seismic Analysis for As-Built Safety Related Piping Systems DRS-Chou Expected Closure 06-08 Open Yes SER 10/24/89 NUREG 1232 Associated with large bore piping Special Program reviews.
U3 closed IRs 94-15, 94-29, 95-03, 95-52. Scheduled for weeks of 8/28 and 9/18 4
BU 80-06 Engineered Safety Feature Reset Controls DRS-Mas-Penaranda Expected Closure 06-08 Open Yes No SER No Inspection scheduled 10/29.
U3 item closed in IR 95-22, 5
BU 84-02 Failure of GE Type HFA Relays in Use in Class 1E Safety Systems DRP 04-09C Closed 2/18/05 Yes No SER No U3 item closed in IR 95-43 6
BU 86-02 Static O Ring Differential Pressure Switches DRP 05-06C Closed 5/19/05 Yes No SER 94-31 U3 item closed in IR 94-31, see also IFI 93-04-01..
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 7
BU 88-03 Inadequate Latch Engagement in HFA Type Relays Manufactured by GE SER 8/2/90 NRR/DRP 04-09C Closed 2/18/05 Yes No SER TVA submittal required upon completion NRR determined issue is closed for Unit 2-3.
8 BU 88-04 Potential Safety Related Pump Loss DRP Bearden 04-09C Closed 2/18/05 Yes No SER Yes TI 2515/105 (orig.
did not require BF to do insp.).
TVA response submitted 5/04, U1 item addressed in IR 95-31. TVA to NRC 5/7/04 letter completed TVA actions.
9 BU 88-07 Power Oscillation in Boiling Water Reactors DRS-MacDonald 06-07C Complete Yes SER 5/31/94 No Reference TI 2515/099.
-NRC to TVA 5/31/1994 letter, TVA considers complete with issuance of TS 300.
10 BU 88-10 Nonconforming Molded-Case Circuit Breakers DRP-S.
Walker IR 05-09C Closed 2/21/06 Yes No SER.
NRC to TVA letter 3/10/92 Reference NRC to TVA letter 3/10/92 closed Bulletin for U1.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 11 BU 90-01 Loss of Fill Oil in Rosemount Transmitters DRS-Moore/
Peabody IR 05-09C Closed 2/21/06 Yes SER 4/04/95 NRR closeout letter / SE 2/7/05 TI 2515/122 -
reference only.
MC change notice 95-08 deleted TI for BF1. TVA ltr 6/7/04.
12 BU 93-02 Debris Plugging of Emergency Core Cooling Suction Strainers DRP-Patterson Inspection complete.
06-06 Complete 5/19/05 Yes 6/28/93 ltr 7/19/94 ltr SER pending per NRR No original SER for U2/3. TVA response 5/6/04.
U3 closed in IR 95-60.
13 BU 93-03 Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs SER 4/20/94 DRP-Walker Expected Closure 06-08 Open Yes SER 4/20/94 TVA closure ltr See GL 92-04. Use TI 2515/128 reference. Verify installation to close. U3 closed IRs 95-31 and 95-56,93-201.
14 BU 95-02 Unexpected Clogging of a RHR Pump Strainer While Operating in Suppression Pool Cooling Mode DRP-Patterson 06-06C Complete 5/19/05 Yes SER 3/14/96 BU 93-02 No SER Was to be addressed for Unit 3 around startup.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 15 BU 96-03 Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling Water Reactors DRP-Patterson Inspection complete.
06-06 Complete 5/19/05 Yes No SER SER pending per NRR 11/15/99 NRC letter completed review for U 2,3.
TVA committed to actions for U2/3.
Credit for containment over-pressure issue not yet approved for U1. Reg Guide under review.
NRR to determine U1 impact.
16 GL 82-33 Instrumentation to Follow the Course of an Accident - R.G.
1.97 SER 2/8/90 DRS-Mellen, Peabody 05-07C Closed 8/19/05 Yes SER 2/8/90 5/10/91 5/3/94 11/19/04 update letter for neutron monitoring U3 closed IRs 90-32,93-201, 95-39..
Ref.TI 2515/87.
NRR reviewing an amendment involving a proposed upgrade to the neutron monitoring system.
17 GL 83-08 Modification of Vacuum Breakers on Mark 1 Containments DRP-Bearden 05-06C Closed 5/19/05 Yes TVA submittal required upon completion Ref. TI 2515/096, NRC letter 11/25/86 for all three units.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 18 GL 83-28 Salem ATWS
-Item 1.2 Trip Review
-Item 4.5.2 Periodic On-Line Testing
-Item 4.5.3 Intervals for On-Line Testing DRP-DiPaolo 06-07C Open Yes Multiple SERs 8/17/90 9/2/86 10/27/86 3/23/88 6/1/89 5/1/89 9/2/86 6/12/85 6/17/85 TI 2515/064 & TI 2500/020 A-9 (this is a TI requiring inspection).
Item 1.2 Trip review remains open.
19 GL 87-02 Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors DRS-Vias 04-06 06-06 Inspection Complete Open Yes SER 3/21/00 SER pending per NRR Related to USI A-
- 46. Status in, E1.3. Program submittal 10/7/2004. No U2,3 ref. Related to Special Program Seismic II/I 20 GL 88-01 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping SER 12/3/93 DRS-Fuller 05-08.
Inspection Complete 06-06 06-07C Open Yes No SER Issued 6/6 IR 95-44. See Special program IGSCC closed in 05-08.
SER Issued
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 21 GL 88-11 Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations SER 6/29/89 NRR/Mellen, NRR to review TS 293 to determine U1 impact, any RAI.06-07C Closed 5/19/05 Yes 6/29/89 No Ref. USI A-26.
NRR considers issue closed.
NRC to TVA 1/8/93 letter regarding PT curve change, 22 GL 88-14 Instrument Air Supply System Problems Affecting Safety Related Equipment SER 5/9/89 DRP-Mellen 05-08C Closed 11/21/05 Yes 5/9/89 ltr No IRs 95-38, 95-56.
23 GL 88-20 Individual Plant Examination of External Events for Severe Accident Vulnerabilities NRR-Chernoff DRS-Bernhard Planned closure 9/06 Closed 2/21/06 Yes No Yes, NRR to issue letter to licensee to close See note NRR reviews required, HQ audit conducted 01/06.
See Special Program - PSA.
Initial IPE was U2, then multi-plant was U2/3. TVA letter 1/14/05 indicating complete. Note:
Expected closure date 1/14/07 24 GL 89-06 Safety Parameter Display System SER 2/5/92 DRS-MacDonald 06-07C Open Yes Yes No See TMI item 1D.2
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 25 GL 89-08 Erosion/Corrosi on - Induced Pipe Wall Thinning DRP-Bearden 05-09C Closed 2/21/06 Yes 8/21/89 ltr U3 closed IR 95-
- 41. Insp.
26 GL 89-10 Safety-Related Motor-Operated Valve Testing and Surveillance NRR/
DRP-Mellen 04-09 Open Yes No SER Waiting on NRR Review TI 2515/109.
Propose NRR onsite review by Scarborough.
Acceptable to closeout via inspection. The Senior Project Engineer is following the progress on this item.
27 GL 89-13 Service Water System Problems Affecting Safety Related Equipment DRS-Maymi 05-09 06-07C Closed 2/21/06 Yes SER 4/23/90 TVA submittal -
notification of action completion TI 2515/118, and TI 2515/159 as ref.
U3 closed in IR 95-
- 23. Adequate resources to complete in combination with heat sink.
28 GL 89-16 Installation of a Hardened Wetwell Vent SER 8/16/91 DRP-Shaeffer 05-06C Closed 2/21/06 Yes SER 8/16/91 No Reference TI 2515/121. U3 closed in IR 95-38, 95-56.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 29 GL 92-01 Reactor Vessel Structural Integrity NRR DRP/Mellen 06-07C Complete Yes No SER NRR to issue closure ltr.
TVA to NRC 5/23/94 letter, TVA will inform NRC of the applicability of NEDO 32205 within 90 days of the final surveillance capsules analysis report. 7/07/99 letter closed for U 2,3.
30 GL 92-04 Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs SER 3/25/93 DRP-Walker Expected Closure 06-08 Complete Yes SER 3/25/93 No IR 93-16, see IEB 93-03,
-Long term actions were addressed as part of the resolution of Bulletin 93-03. TI 2515/119 ref. U2 93-16. NRC 3/25/93 letter found acceptable for all three units - verify.
31 GL 94-02 Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in BWRs DRS-MacDonald 06-07C Open Yes No SER Yes U3 closed in IR 94-11, 95-62. Ref TI 2515/119
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 32 GL 94-03 Intergranular Stress Corrosion Cracking of Core Shrouds in BWRs DRS-Fuller 05-08C Closed 11/21/05 Yes SER 1/13/95 No U3 closed in IRs 94-16 & 95-44 See SP #18.
33 GL 95-07 Pressure Locking and Thermal Binding of Safety-Related and Power-Operated Gate Valves DRP-Beardon 06-06 C Open Yes SER 6/23/99 No TVA action due 06/06 Lic. Response 5/11/04, 7/29/04.
NRC HQ Ltr/SE 1/28/05 closed.
34 GL 96-01 Testing of Safety-Related Logic Circuits DRS - S.
Walker Expected Closure 06-08 Open Yes No SER No U2,3 - closed in 6/28/99 completion letter; IRs 98-03, 98-05, 98-07, & 98-
- 09. Scheduled for 10/23/6 35 GL 96-05 Periodic Verification of Design Basis Capability of Motor Operated Valves DRP-Moore 05-09C Closed 2/21/06 Yes No SER No
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 36 GL 96-06 Assurance of Equipment Operability and Containment Integrity During Design Basis Accident Conditions DRS-Vias05-08C Closed 11/21/05 Yes No SER No NRC ltr 2/15/00 closed for all three units, however stated U1 would be revisited. TVA submitted response 5/12/04.
NRR letter 2/7/05 said TVA provided acceptable resolution.
37 GL 97-04 Assurance of Sufficient Net Positive Suction for Emergency Core Cooling and Containment Heat Removal Pumps DRP-Patterson Inspection complete 06-06 Closed Yes BU 93-02 SER issued 6/27/06 6/11/98 Ltr closed for U 2,3. TVA response for U1 5/6/04-TVA considers complete based on Unit 1 EPU application, dtd 6/28/04.
38 GL 98-01 Readiness of Computer Systems at Nuclear Power Plants DRP-Shaeffer 05-06C Closed Yes No SER No NRC to TVA 10/18/99 letter completed.
GENERIC COMMUNICATIONS: Bulletins {BU} and Generic Letters {GL}
Issue Description Resolved on U2-3 (Nureg 1232 Vol.
3 Section /
Prev. Ser)
NRC Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by Prev U2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 39 GL 98-04 Potential for Degradation of the ECCS and Containment Spray System After a LOCA Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment DRS-Lenahan Inspection Complete 06-06 Closed Yes No Wating on NRR review TVA to NRC 5/11/04 letter provided response NRC 11/24/99 Ltr closed for all TVA sites.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 40 I.D.1 Control Room Design Review DRS-MacDonald 06-07C Open 3/28/06 Yes SER 10/29/91 No 41 I.D.2 Safety Parameter Display Console DRS-MacDonald 06-07C Open 7/24/06 Yes SER 2/05/92 No 42 II.B.3 Post-Accident Sampling System DRS-Hamilton 06-06 C Open 6/28/06 Yes SER 5/27/87 No 43 II.E.4.2.
1-4 Containment Isolation Dependability -
Implement Diverse Isolation, containment purge valves DRP-Bearden Expected Closure 06-08 Open Yes SER 1/6/95 10/3/95 6/24/04 ltr Yes SER pending SE or Ltr required.
NRR review required.
The BF1 Senior Resident Inspection is following this item 44 II.F.1.2.
C Accident -
Monitoring -
Containment High Range Radiation DRS-Hamilton 06-06 C Open 5/9/06 Yes SER 1/8/82 No 45 II.F.1.2.
D Accident -
Monitoring -
Containment Pressure DRP-Bearden 05-06C Closed Yes SER 6/16/83
-NRC to TVA 11/8/90 letter closed issue.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 46 II.F.1.2.
E Accident -
Monitoring -
Containment Water Level DRP-Bearden 05-06C Closed Yes SER 6/16/83 No
-NRC to TVA 12/12/83 letter, TS Amendment 92 closed issue.
47 II.F.2.4 (Generic Letter 84-23)
Instrumentation for Detection of Inadequate Core Cooling DRP-Patterson 05-07C Closed 8/19/05 Yes No SER No 48 II.K.3.13 HPCI/RCIC Initiation Levels DRP-Bearden 05-07C Closed 8/19/05 Yes SER 9/19/83 TVA will notify upon completion 49 II.K.3.18 ADS Actuation Modifications DRP-Bearden 05-07C Closed 8/19/05 Yes SER 5/29/90 No 50 II.K.3.27 Common reference level for BWR DRP-Bearden 05-08C Open TVA tracking closure via TMI I.D.1.
No SER 9/19/83 No Not on TVA letter, added during Shaeffer's review. See IRs 91-03, 91-10, U3 item closed in IR 95-16, NRR ltr dtd 12/30/82 agreed w/integration into I.D.1 and considered item closed for U1,2,3.
51 II.K.3.28 Qualification of ADS Accumulators DRP-Bearden 05-07C Closed 8/19/05 Yes SER 5/29/90 No
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 52 MPA-B011 Flood of equipment important to safety DRP-Monk Closed See Comment No Letter Dated 6/7/6 No The aspects of this item associated with restart are covered by existing special program 23, Moderate Energy Line Break.
This item is redundant and is considered administratively closed.
53 MPA-B041 Fire protection -
Final TS (including SER Sup)
DRS-Fillion 05-16 Closed See Comment See Comment No No No The aspects of this item associated with restart are covered by existing special program 12, Fire Protection 10CFR 50 Appendix R. This item is redundant and is considered administratively closed.
54 MPA-C002 BWR recirc pump trip (ATWS)
DRP-DiPaolo Closed See Comment See Comment No No No The aspects of this item associated with restart are covered by the review of Generic Letter 83-28. This item is redundant and is considered administratively closed.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 55 TI 2500
/20 Inspection to determine compliance with ATWS Rule 10 CFR 50.62 DRP-DiPaolo Closed See Comment See Comment Yes No No The aspects of this item associated with restart were closed in the review of GL 83-28.
56 TI 2515
/111 EDSFI Followup Unit 1 Followup for previously performed electrical distribution inspection DRS-Fillion Expected Closure 06-08 No N/A N/A Review selected EDG/Bus loading calcs similar to U3 closure in 95-60.
Request calcs in advance. Scheduled for 9/11/06 57 TI 2515
/154 Spent fuel Material Control and Accountability DRP Bearden 04-08C No No No 58 TI 2515
/156 Offsite Power System Readiness DRP Bearden 04-08C No No USI A-44 Station Blackout.
59 TI 2515
/157 Mark I and II Containment Operations DRP/
Bearden See Note No No Note:This TI has been classified as Safeguards.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 60 USI A-7 Mark 1 Long-Term Program, NuReg-0661, Supp 1 DRS-Chou Closed See Comment See Comment No No The aspects of this item associated with restart are covered by the review of Special Program 20, Long Term Torus Integrity Program. This item is redundant and is considered administratively closed.
61 USI A-9 ATWS DRP-DiPaolo Closed See Comment See Comment No No The aspects of this item associated with restart were closed in the review of GL 83-28.
62 USI A-24 Qualification of Class 1E Safety-Related Equipment DRS-Merriweather Closed See Comment See Comment No No The aspects of this item associated with restart are covered by the review of Special Programs 11, Environmental Qualification and Special Program 05, Component and Piece Parts Qualification.
This item is redundant and is considered administratively closed.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 63 USI A-26 Reactor Vessel Pressure Transient Protection NRR/
Chernoff
/Mellen Closed See Comment Closed 2/21/06 No No No The aspects of this item associated with restart are covered by the review of Generic Letter 88-11. This item is redundant and is considered administratively closed.
64 USI A-44 Station Blackout DRS-Schin Open No N/A N/A TVA to implement DC power mods.
Previously closed for U3 IRs 95-16, 95-34, 95-60. Include Battery Performance Scheduled for 10/10/06 65 USI A-46 Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors DRS-Vias Inspection complete.
06-06 See Comment No SER pending per NRR Ref. GL 87-02.The aspects of this item associated with restart are covered by the review of Generic Letter 87-02.
THREE MILE ISLAND ACTION ITEMS Issue Description Resolved on U2-3 (Nureg 1232 Vol. 3 Section /
Prev. SER)
Nrc Insp Lead/
Alternate Insp Reports
[C-closed]
TVA Closure Status (Planned)
Tracked in TVA Restart Issues Letter NRR Unit 1 Covered by 2-3 SER or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments 66 USI A-75 MPA-B085, Required Actions on Generic Implications of Salem ATWS
- Events, Section 1.2, Post Trip Review DRP-DiPaolo Closed See Comment See Comment No The aspects of this item associated with restart were closed in the review of GL 83-28.
OTHER MISC ISSUES (Item to be Dispositioned Prior to Restart)
Issue Description NRC Insp Lead/
Alternate Closure IR NRR Unit 1 Covered by U2-3 Ser or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments A
New simulator qualification/
Fidelity and Operator staffing Review licensees new simulator to support 3 unit operations.
Review Licensed Operator staffing plans.
DRS-OLHPB -
J. Moorman N/A No. TVA will submit ltr when testing complete.
Letter submitted 7/28/05.
Construction complete. RII OLB discussed with HQs OLB in May 05 - no requirement to inspect; however, will assess performance during Requal. insp. & review any outstanding fidelity issues.
B Lay up inspections DRP-Bearden 04-06C Final layup inspection completed in 2004, or further actions required.
C In-vessel inspections, core spray UT Full RPV internals/
weld inspection complete 2005 for 10 year ISI DRS - Bearden (Fuller, Crowley, Blake) 05-08 05-09 06-06C N/A N/A Observed activities and reviewed final report.
Verified all items completed.
D ORAT Determine scope of unit start-up oversight reviews (likely reduced scope Operational Readiness Assessment Team
[ORAT]) and assemble & schedule team.
Restart Panel to review inspection scope.
N/A - See Comment N/A N/A This item was placed on the Browns Ferry Unit 1 Recovery Issues List as a placekeeper. The ORAT will be scheduled for early January 2007. This item is no longer needed on the Browns Ferry Unit 1 Recovery Issues List.
E Common Accident Signal DRP-Bearden 05-06 N/A - See Comment No.
Amendment approved 4/1/04.
There are no actions required on this issue prior to restart
OTHER MISC ISSUES (Item to be Dispositioned Prior to Restart)
Issue Description NRC Insp Lead/
Alternate Closure IR NRR Unit 1 Covered by U2-3 Ser or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments F
Extended Power Uprate Determine scope of needed inspection reviews to support licensing action.
NRR Project Manager New SE OPEN - pending SER G
Enhanced Restart Monitoring Restart Panel to determine duration.
Proposed 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> coverage.
DRP Coordinate.
N/A - See Comment This item was placed on the Browns Ferry Unit 1 Recovery Issues List as a placekeeper. The Enhanced Monitoring will be scheduled for February or March 2007. This item is no longer needed on the Browns Ferry Unit 1 Recovery Issues List.
H License Renewal Application Determine scope of needed inspection reviews to support licensing action.
& NRR Project Manager New SE issued 1/06.
Inspection TI to be completed by DRS.
NRR will review the final Renewal OL, renewal inspections, and SER for Items that impact U1 restart. Determine if any additional inspection required as followup to LR inspections or other requirements. Unit 1 Followup Inspection Related to License Renewal Application for the (BFN), Units 1, 2, and 3 I
Maintenance Rule U1 to comply with explicit scoping requirements of 50.65(b) for systems required to be operable or TS applicable.
NRR Project Manager/Region II inspection N/A - See Comment No No SE. Letter from TVA to confirm Unit 1 in compliance with 50.65(b).
There are no actions required on this issue prior to restart and is considered administratively closed.
OTHER MISC ISSUES (Item to be Dispositioned Prior to Restart)
Issue Description NRC Insp Lead/
Alternate Closure IR NRR Unit 1 Covered by U2-3 Ser or HQ Letter?
NRR New SE or TVA Submittal Req?
Comments J
License Amendment 234 Review Improved Standard Technical Specifications NRR Project Manager Yes NRC to confirm License condition ITS. TVA to review TS changes made by License Amendment 234 and any other subsequent TS changes prior to entering Mode that TS applies.
K Turbine Building Dynamic Seismic Analysis Confirm seismic demand accelerations for TB NRR Project Manager NRR to review.
License condition. NRC to confirm conclusions in TVA letter dated 9/17/04 for turbine building seismic loading.
L GL 2003-01 Control Room Habitability Bearden Inspection Requested by EDO. The BF1 Senior Resident Inspector is following this item.
E:\\Filenet\\ML062270449.wpd
LIST OF ACRONYMS USED C
Closed CA Corrective Action CFR Code of Federal Regulations EDG Emergency Diesel Generator EOC Extent of Condition Review EOP Emergency Operating Procedure FSAR Final Safety Analysis Report GL NRC Generic Letter IFI NRC Inspector Followup Item IFS Inspector Followup System ILRT Integrated Leak Rate Test (of the Reactor Building)
IR NRC Inspection Report LER Licensee Event Report MPA NRC Multi-Plant Action NRR Office of Nuclear Reactor Regulation OIL Open Item List OP Operating Procedure PM NRR Project Manager PER Problem EvaluationReport QA Quality Assurance RB Reactor Building RG Regulatory Guide RI Resident Inspector SER Safety Evaluation Report SFP Spent Fuel Pool SIMS Safety Issues Management System TIA NRC Task Interface Agreement (between NRC offices)
TS Technical Specifications UHS Ultimate Heat Sink URI NRC Unresolved Item VIO NRC Violation