9/26/05 Meeting Summary with Duke Energy Corp. on Oconee Units 1, 2 and 3, Re Rps/Esps
ML052770064
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 10/20/2005
From: Olshan L
NRC/NRR/DLPM/LPD2
To:
Duke Energy Corp
Olshan L N, NRR/DLPM, 415-1419
Shared Package
ML052770109 List:
References
TAC MC5895, TAC MC5896, TAC MC5897
Download: ML052770064 (5)


Text

October 20, 2005 LICENSEE:

DUKE ENERGY CORPORATION FACILITY:

OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3

SUBJECT:

SUMMARY

OF SEPTEMBER 26-27, 2005, MEETING TO DISCUSS THE LICENSE AMENDMENT REQUEST FOR A DIGITAL REACTOR PROTECTIVE SYSTEM AND ENGINEERED SAFEGUARDS PROTECTIVE SYSTEM (TAC NOS. MC5895, MC5896, AND MC5897)

On September 26-27, 2005, the Nuclear Regulatory Commission (NRC) met with Duke Energy Corporation (the licensee) to discuss the February 14, 2005, license amendment request for a digital Reactor Protective System (RPS) and Engineered Safeguards Protective System (ESPS). Enclosure 1 is a list of the attendees. Enclosure 2 is the slides presented by the licensee during the meeting.

The licensee presented its schedule for responding to the NRC staffs requests for additional information (RAI) and its schedule for implementation. The licensee stated that the design of the hardware and software is 90 percent complete and 100 completion is expected by the end of September 2005. The licensee is planning to install the digital RPS/ESPS on Oconee, Unit 1 during the Fall 2006 refueling outage.

The licensee stated that it is conducting simulator tests to justify the times assumed in the defense-in-depth and diversity analysis. The results of these tests will be discussed at a later time.

The licensee and the NRC held a detailed discussion on the two issues for which the NRC has concerns, the use of interchannel connections and the combining of RPS and ESPS into a single system. The licensee believes that the use of interchannel connections provides a safety benefit and that the combining of RPS and ESPS provides adequate safety. The licensee requested that the NRC staff provide its position on these two issues by the end of October 2005, so that the schedule for installing can be achieved.

CONTACT:

Leonard N. Olshan, NRR 301-415-1419 lno@nrc.gov The detailed discussion of the NRC staffs September 6, 2005, RAI will be held at a later time.

Please direct any inquiries to Leonard N. Olshan at 301-415-1419, or lno@nrc.gov.

/RA/

Leonard N. Olshan, Senior Project Manager, Section1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287

Enclosures:

1. List of Attendees
2. Slide Presentation cc w/encls: See next page

ML052770064

Enclosure:

ML052770316 NRC-001 OFFICE PDII-1/PM PDII-1/LA PDII-1/SC NAME LOlshan CHawes EMarinos DATE 10/ 19 /05 10/ 19 /05 10/ 20 /05

ENCLOSURE 1 LIST OF ATTENDEES MEETING TO DISCUSS THE OCONEE LICENSE AMENDMENT REQUEST FOR A DIGITAL RPS/ESPS SEPTEMBER 26 AND 27, 2005 NRC DUKE E. Marinos B. Shingleton A. Howe R. Gill M. Chiramal J. Calvo OTHER M. Waterman P. Loeser L. Heckle, Framatome W. Kemper P. Mangano, Framatome E. Thornsbury P. Berry, Framatome L. Olshan C. Hendrix, Jr., Framatome D. Muller T. Harris, Nuclear Energy Institute Y. Hsii J. Bongarra P. Rebstock C. Doutt D. Mas-Penaranda (by phone)

Oconee Nuclear Station, Units 1, 2, and 3 cc:

Ms. Lisa F. Vaughn Duke Energy Corporation 526 South Church Street P. O. Box 1006 Mail Code = EC07H Charlotte, North Carolina 28201-1006 Manager, LIS NUS Corporation 2650 McCormick Dr., 3rd Floor Clearwater, FL 34619-1035 Senior Resident Inspector U.S. Nuclear Regulatory Commission 7812B Rochester Highway Seneca, SC 29672 Mr. Henry Porter, Director Division of Radioactive Waste Management Bureau of Land and Waste Management Dept. of Health and Env. Control 2600 Bull St.

Columbia, SC 29201-1708 Mr. Michael A. Schoppman Framatome ANP 1911 North Ft. Myer Dr.

Suite 705 Rosslyn, VA 22209 Ms. Karen E. Long Assistant Attorney General NC Department of Justice P.O. Box 629 Raleigh, NC 27602 Mr. R. L. Gill, Jr.

Manager - Nuclear Regulatory Issues and Industry Affairs Duke Energy Corporation 526 S. Church St.

Mail Stop EC05P Charlotte, NC 28202 Division of Radiation Protection NC Dept of Environment, Health, & Natural Resources 3825 Barrett Dr.

Raleigh, NC 27609-7721 Mr. Peter R. Harden, IV VP-Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road 12th Floor Charlotte, NC 28210 Mr. Henry Barron Group Vice President, Nuclear Generation and Chief Nuclear Officer P.O. Box 1006-EC07H Charlotte, NC 28201-1006 Mr. B. G. Davenport Regulatory Compliance Manager Oconee Nuclear Site Duke Energy Corporation ON03RC 7800 Rochester Highway Seneca, SC 29672