Letter Sequence Other |
---|
|
|
MONTHYEARML0419702212004-06-28028 June 2004 RAI, Security Plan Sections 1-9 (TAC MC2892, MC2893, MC2894, MC2988, MC2972, and MC2973) Project stage: RAI ML0426705332004-06-28028 June 2004 RAI Security Plan Sections 1 - 9 Project stage: RAI ML0419701042004-06-28028 June 2004 Request for Additional Information Security Plan Sections 1 - 9 (TAC Nos. MC2972 and MC2973) Project stage: RAI ML0421804742004-07-23023 July 2004 RAI Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan Project stage: RAI ML0421003752004-07-26026 July 2004 RA, Training and Qualification Plan Project stage: Other ML0421500022004-07-28028 July 2004 Physical Security Plan - Response to Request for Additional Information - NRC Order EA-03-086 Training and Qualification Plan Project stage: Response to RAI ML0421903082004-08-0404 August 2004 Units 1 and 2 - Physical Security Plan - Response to Request for Additional Information - NRC Order EA-03-086 - Training and Qualification Plan Project stage: Response to RAI ML0422903722004-08-12012 August 2004 Physical Security Plan, Response to Request for Additional Information, NRC Order EA-03-086, Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan Project stage: Response to RAI ML0422903762004-08-12012 August 2004 Physical Security Plans, Response to Request for Additional Information, NRC Order EA-03-086, Security Contingency Plan Project stage: Response to RAI ML0425905272004-09-0909 September 2004 Supplemental Response to the Design Basis Threat Order Physical Security Plans - NRC Order EA-03-086 (TAC No. Mc 2988) Project stage: Supplement ML0425701382004-09-0909 September 2004 Supplemental Response to the Design Basis Threat Order Physical Security Plans - NRC Order EA-03-086 Project stage: Supplement ML0425701422004-09-10010 September 2004 Units 1 and 2 - Supplemental Response to the Design Basis Threat Order Physical Security Plans - NRC Order EA-03-086 Project stage: Supplement ML0425900612004-09-10010 September 2004 Units 1 and 2 - Supplemental Response to the Design Basis Threat Order Physical Security Plans - NRC Order EA-03-086 (TAC Nos. MC2972 and MC2973) Project stage: Supplement ML0429200552004-10-14014 October 2004 Supplemental Response to the Design Basis Threat Order Physical Security Plants (PSP) - NRC Order EA-03-086 Project stage: Supplement ML0431200132004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-003-086 Regarding Revised Design Basis Threat... Project stage: Other ML0431200222004-10-28028 October 2004 Administrative Change to Facility Operation License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat... Project stage: Other ML0431200252004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat... Project stage: Other ML0433702232004-11-24024 November 2004 Response to NRC Request for Information Regarding Relaxation of Section Iii.A of Order EA-03-086 Project stage: Response to RAI 2004-07-26
[Table View] |
|
---|
Category:Letter
MONTHYEARCNL-24-080, Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011)2024-11-20020 November 2024 Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011) IR 05000390/20240032024-11-13013 November 2024 Integrated Inspection Report 05000390/2024003, 05000391/2024003 & 07201048/2024001 CNL-24-021, Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020)2024-11-12012 November 2024 Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020) IR 05000259/20240102024-11-12012 November 2024 Design Basis Assurance Inspection Program Inspection Report 05000259/2024010 and 05000260/2024010 and 05000296/2024010 IR 05000327/20240032024-11-0606 November 2024 Integrated Inspection Report 05000327/2024003 and 05000328/2024003 ML24312A1552024-11-0606 November 2024 Cycle 27 Core Operating Limits Report, Revision 1 IR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 IR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-014, License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22)2024-11-0404 November 2024 License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22) CNL-24-064, Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R52024-11-0404 November 2024 Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R5 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision ML24304A8492024-10-31031 October 2024 December 2024 Requalification Inspection Notification Letter IR 05000327/20250102024-10-29029 October 2024 Notification of Sequoyah, Units 1 and 2 - Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000327/2025010 and 05000328/2025010 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry ML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter 2024-09-08
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24318A8602024-10-29029 October 2024 NRR E-mail Capture - Draft Request for Additional Information -Tennessee Valley Authority (TVA) License Amendment Request (LAR) to Revise Watts Bar TS 3.7.11 for Main Control Room Chiller Extension of Completion Time ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24255A5822024-09-10010 September 2024 SLRA - Requests for Additional Information - Set 1 ML24255A5802024-09-10010 September 2024 SLRA - Requests for Additional Information - Set 1 - Email from Jessica Hammock to James Barstow ML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24045A0272024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23332A0042023-11-27027 November 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Revised Alternative 0-ISI-47 ML23307A0832023-11-0808 November 2023 Enclosure - Request for Additional Information HDI-Sequoyah NDE Exemption Request 10-30-2023 ML23307A0822023-11-0808 November 2023 Request for Additional Information – August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML23243A9892023-08-29029 August 2023 Inspection Information Request ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23124A0082023-05-0303 May 2023 NRR E-mail Capture - Request for Additional Information Related to Proposed Alternative Requests for the 5th 10-Year Inservice Testing Interval for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to TVAs 12/19/2022 Response of the Staffs Rsi Regarding 08/04/2022 SQN Exemption Request ML23062A5942023-02-27027 February 2023 Enclosure - NRC SQN Exemption Rsi Response Staff Follow Up Questions ML23041A0022023-02-0909 February 2023 NRR E-mail Capture - Request for Additional Information Related to TVA Alternative Request BFN-0-ISI-32 (CNL-22-025) ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22299A0292022-10-26026 October 2022 NRR E-mail Capture - Request for Additional Information for Relief Request BFN-2-ISI-003 Re Weld Examination Coverage ML22292A2722022-10-19019 October 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Adopt TSTF-505 and TSTF-439 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22257A0622022-09-14014 September 2022 Requalification Program Inspection - Sequoyah Nuclear Plant ML22255A0842022-09-0909 September 2022 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-04 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22208A2172022-07-15015 July 2022 NRR E-mail Capture - Request for Additional Information Related to TVA Relief Request BFN-21-ISI-02 (CNL-21-081) ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22168A0802022-06-17017 June 2022 NRR E-mail Capture - Request for Confirmation of Information and Additional Information Related to TVAs Request to Use Control Bay Chiller Cross-Tie ML22160A4742022-06-0303 June 2022 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Re LAR to Use Advanced Framatome Methodologies in Support of Atrium 11 Fuel ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plants LAR to Adopt TSTF-505 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22168A0392022-05-13013 May 2022 NRR E-mail Capture - Draft Request for Confirmation of Information and Additional Information Related to TVAs Request to Use Control Bay Chiller Cross-Tie ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to TVAs Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML22047A1612022-02-16016 February 2022 NRR E-mail Capture - Request for Additional Information Regarding TVAs Request to Expand the SFP Criticality Safety Analysis for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21237A4952021-08-25025 August 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-04 ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21173A1042021-06-21021 June 2021 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Request to TS 3.8.6 2024-09-10
[Table view] |
Text
SAFEGUARDS INFORMATION July 26, 2004 Mr. Karl W. Singer, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 c/o Mr. Ashok S. Bhatnagar c/o Ms. Joan E. McCullum c/o Mr. James Traister
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2 AND 3, WATTS BAR NUCLEAR PLANT, UNIT 1, AND SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NOS. MC2892, MC2893, MC2894, MC2988, MC2972, AND MC2973)
Dear Mr. Scalice:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguard contingency plan, and training and qualification (T&Q) plan, including an implementation schedule, for Browns Ferry Nuclear Plant, Units 1, 2 and 3, Watts Bar Nuclear Plant, Unit 1, and Sequoyah Nuclear Plant, Units 1 and 2.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.
Please disregard the July 9, 2004, letter regarding the RAIs on your T&Q Plan. While the questions enclosed with that letter are correct, there were errors in the cover letter that required correction. Your response is requested within 10 working days of the date of receipt of this letter.
Sincerely, Deirdre W. Spaulding, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-390, 50-327, and 50-328
Enclosure:
As stated cc w/o encl: See next page WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards NOTICE: The Enclosure contains Safeguards Information is subject to Civil and Criminal Information. Upon separation from the Enclosure, this Penalties letter is DECONTROLLED.
SAFEGUARDS INFORMATION
July 26, 2004 Mr. Karl W. Singer, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 c/o Mr. Ashok S. Bhatnagar c/o Ms. Joan E. McCullum c/o Mr. James Traister
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2 AND 3, WATTS BAR NUCLEAR PLANT, UNIT 1, AND SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NOS. MC2892, MC2893, MC2894, MC2988, MC2972, AND MC2973)
Dear Mr. Scalice:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguard contingency plan, and training and qualification (T&Q) plan, including an implementation schedule, for Browns Ferry Nuclear Plant, Units 1, 2 and 3, Watts Bar Nuclear Plant, Unit 1, and Sequoyah Nuclear Plant, Units 1 and 2.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.
Please disregard the July 9, 2004, letter regarding the RAIs on your T&Q Plan. While the questions enclosed with that letter are correct, there were errors in the cover letter that required correction. Your response is requested within 10 working days of the date of receipt of this letter.
Sincerely, Deirdre W. Spaulding, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-390, 50-327, and 50-328
Enclosure:
As stated cc w/o encl: See next page DISTRIBUTION:
SPRT R/F RidsNsirDns RidsNrrDlpm OGC ACRS E. Brown K. Jabbour M. Comar M. Mashall (A) E. Hackett V. McCree, RII ADAMS Accession Number: ML *See previous concurrence OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR* SPRT/NRR/SC*
NAME DSpaulding CHawes JPeralta JNakoski DATE 7/8/04 7/9/04 OFFICIAL RECORD COPY
BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority SEQUOYAH NUCLEAR PLANT WATTS BAR NUCLEAR PLANT cc:
Mr. Karl W. Singer Mr. Mark J. Burzynski, Manager Chief Nuclear Officer and Nuclear Licensing Executive Vice President Tennessee Valley Authority Tennessee Valley Authority 4X Blue Ridge 6A Lookout Place 1101 Market Street 1101 Market Street Chattanooga, TN 37402-2801 Chattanooga, Tennessee 37402-2801 General Counsel Mr. Ashok S. Bhatnagar, Senior Vice President Tennessee Valley Authority Nuclear Operations ET 11A Tennessee Valley Authority 400 West Summit Hill Drive 6A Lookout Place Knoxville, TN 37902 Chattanooga, TN 37402-2801 Chairman Mr. James E. Maddox, Vice President Limestone County Commission Engineering & Technical Services 310 West Washington Street Tennessee Valley Authority Athens, AL 35611 6A Lookout Place 1101 Market Street State Health Officer Chattanooga, TN 37402-2801 Alabama Dept. of Public Health RSA Tower - Administration Mr. Pedro Salas, Manager Suite 1552 Licensing and Industry Affairs P.O. Box 303017 Sequoyah Nuclear Plant Montgomery, AL 36130-3017 Tennessee Valley Authority P.O. Box 2000 Mr. Michael D. Skaggs, Plant Manager Soddy Daisy, TN 37379 Browns Ferry Nuclear Plant Tennessee Valley Authority Mr. Lawrence E. Nanney, Director P.O. Box 2000 Division of Radiological Health Decatur, AL 35609 Dept. of Environment & Conservation Third Floor, L and C Annex Mr. Timothy E. Abney, Manager 401 Church Street Licensing and Industry Affairs Nashville, TN 37243-1532 Browns Ferry Nuclear Plant Tennessee Valley Authority Senior Resident Inspector P.O. Box 2000 Sequoyah Nuclear Plant Decatur, AL 35609 U.S. Nuclear Regulatory Commission 2600 Igou Ferry Road Senior Resident Inspector Soddy Daisy, TN 37379 Browns Ferry Nuclear Plant U.S. Nuclear Regulatory Commission Mr. T. J. Niessen, Acting General Manager 10833 Shaw Road Nuclear Assurance Athens, AL 35611 Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority SEQUOYAH NUCLEAR PLANT WATTS BAR NUCLEAR PLANT cc:
Mr. Jon R. Rupert, Vice President Mr. Paul L. Pace, Manager Browns Ferry Licensing and Industry Affairs Browns Ferry Nuclear Plant Watts Bar Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 P.O. Box 2000 Decatur, AL 35609 Spring City, TN 37381 Mr. Robert G. Jones Mr. Larry S. Bryant Manager Browns Ferry Watts Bar Nuclear Plant Browns Ferry Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 P.O. Box 2000 Spring City, TN 37381 Decatur, AL 35609 Senior Resident Inspector Site Vice President Watts Bar Nuclear Plant Browns Ferry Nuclear Plant U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road P.O. Box 2000 Spring City, TN 37381 Decatur, AL 35609 County Executive Mr. David A. Kulisek, Plant Manager Rhea County Courthouse Sequoyah Nuclear Plant 375 Church Street Tennessee Valley Authority Suite 215 P.O. Box 2000 Dayton, TN 37321 Soddy Daisy, TN 37379 County Mayor County Mayor P. O. Box 156 Hamilton County Courthouse Decatur, TN 37322 Chattanooga, TN 37402-2801 Ms. Ann P. Harris Mr. Randy Douet 341 Swing Loop Road Site Vice President Rockwood, Tennessee 37854 Sequoyah Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Soddy Daisy, TN 37379 Mr. William R. Lagergren Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381