ML042590527

From kanterella
Jump to navigation Jump to search

Supplemental Response to the Design Basis Threat Order Physical Security Plans - NRC Order EA-03-086 (TAC No. Mc 2988)
ML042590527
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 09/09/2004
From: Pace P
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Security and Incident Response
References
EA-03-086, TAC MC2988
Download: ML042590527 (2)


Text

SAFEGUARDS INFORMATION Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 EA-03-086 SEP o 9 2004 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D. C. 20555 Gentlemen:

In the Matter of

)

Docket No.50-390 Tennessee Valley Authority

)

WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 -

SUPPLEMENTAL RESPONSE TO THE DESIGN BASIS THREAT ORDER PHYSICAL SECURITY PLANS -

NRC ORDER EA-03-086 (TAC NO. MC 2988)

The purpose of this letter is to provide the Physical Security Plan which also includes the Training and Qualification Plan and the Safeguards Contingency Plan.

This plan supercedes TVA's proposed Physical Security Plan dated April 29, 2004, pursuant to the subject Order and includes proposed changes in response to NRC's requests for additional information dated July 7, July 14, July 28, August 12, and September 1, 2004.

In TVA's letter to NRC dated September 1, 2004, TVA stated that the force-on-force exercises shall follow the guidance of NEI 03-09 (Revision 1) January 2004.

As stated in the supplemental Physical Security Plans TVA will follow the guidance of NEI 03-09 (Revision 2) April 2004.

This response contains Safeguards Information as defined in 10 CFR 73.21.

TVA therefore, requests that the Enclosure be withheld from public disclosure.

There are no Regulatory commitments identified in this submittal.

If you have any questions about these responses, please contact me at (423) 365-1824.

MThen separated from the attached I

I Safeguards, the page is decontrolled. I SAFEGUARDS INFORM4AT ION

SAFEGUARDS INFORMATION U.S. Nuclear Regulatory Commission Page 2 04 SEP 0 9200 I declare under penalty of perjury that the foregoing is true and correct.

Executed on the 9th day of September 2004.

Sincerely, P

. Pace Manager, Site Licensing and Industry Affairs Enclosure cc (without Enclosure):

NRC Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 Ms. Margaret H. Chernoff, Project Manager U.S. Nuclear Regulatory Commission MS 08G9 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Mr. R. J. Pascarelli, Project Manager U.S. Nuclear Regulatory Commission MS 08G9 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 U.S. Nuclear Regulatory Commission (w/Enclosure)

Region II Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 When separated from the attached Safeguards, the page is decontrolled.

SAFEGUARDS INFORMATION