RAI, Security Plan Sections 1-9 (TAC MC2892, MC2893, MC2894, MC2988, MC2972, and MC2973)
ML041970221
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/28/2004
From: Spaulding D
NRC/NRR/DLPM/LPD2
To: Scalice J
Tennessee Valley Authority
Spalding D, NRR/DLPM/LPD3-1, 415-2928
References
TAC MC2892, TAC MC2893, TAC MC2894, TAC MC2972, TAC MC2973, TAC MC2988
Download: ML041970221 (3)


Text

SAFEGUARDS INFORMATION June 28, 2004 Mr. J. A. Scalice Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 c/o Mr. Ashok S. Bhatnagar c/o Ms. Joan E. McCullum c/o Mr. James Traister

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TACMC2892, MC2893, MC2894, MC2988, MC2972, AND MC2973)

Dear Mr. Scalice:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Browns Ferry Nuclear Plant, Units 1, 2 and 3.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.

Sincerely,

/RA/

Deirdre W. Spaulding, ,

Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296,

Enclosure:

As stated cc w/o encl: See next page WARNING: Violation of Section 147 NOTICE: The enclosed information contains Safeguards of the Atomic Energy Act, Information. Upon separation from the enclosure, this Safeguards Information is subject to letter is DECONTROLLED.

Civil and Criminal Penalties SAFEGUARDS INFORMATION

June 28, 2004 Mr. J. A. Scalice Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 c/o Mr. Ashok S. Bhatnagar c/o Ms. Joan E. McCullum c/o Mr. James Traister

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TACMC2892, MC2893, MC2894, MC2988, MC2972, AND MC2973)

Dear Mr. Scalice:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Browns Ferry Nuclear Plant, Units 1, 2 and 3.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.

Sincerely,

/RA/

Deirdre W. Spaulding, Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296,

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION: PUBLIC SPRT R/F OGC ACRS ADAMS Accession Number: ML041970221 E\Team C\ML041970221.wpd OFFICE SPRT/NRR/PM SPRT/NSIR SPRT/NRR/SC NAME DSpaulding JPeralta JNakoski DATE 6/26/04 6/28/04 6/28/04 OFFICIAL RECORD COPY

Tennessee Valley Authority BROWNS FERRY NUCLEAR PLANT cc:

Mr. J. A. Scalice Mr. Jon R. Rupert, Vice President Chief Nuclear Officer and Browns Ferry Unit 1 Restart Executive Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place P.O. Box 2000 1101 Market Street Decatur, AL 35609 Chattanooga, Tennessee 37402-2801 Mr. Robert G. Jones Mr. Karl W. Singer, Senior Vice President Browns Ferry Unit 1 Plant Restart Manager Nuclear Operations Browns Ferry Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority 6A Lookout Place P.O. Box 2000 1101 Market Street Decatur, AL 35609 Chattanooga, TN 37402-2801 Mr. Mark J. Burzynski, Manager Mr. James E. Maddox, Vice President Nuclear Licensing Engineering & Technical Services Tennessee Valley Authority Tennessee Valley Authority 4X Blue Ridge 6A Lookout Place 1101 Market Street 1101 Market Street Chattanooga, TN 37402-2801 Chattanooga, TN 37402-2801 Mr. Timothy E. Abney, Manager Mr. Ashok S. Bhatnagar, Site Vice President Licensing and Industry Affairs Browns Ferry Nuclear Plant Browns Ferry Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 P.O. Box 2000 Decatur, AL 35609 Decatur, AL 35609 General Counsel Senior Resident Inspector Tennessee Valley Authority U.S. Nuclear Regulatory Commission ET 11A Browns Ferry Nuclear Plant 400 West Summit Hill Drive 10833 Shaw Road Knoxville, TN 37902 Athens, AL 35611 Mr. T. J. Niessen, Acting General Manager State Health Officer Nuclear Assurance Alabama Dept. of Public Health Tennessee Valley Authority RSA Tower - Administration 6A Lookout Place Suite 1552 1101 Market Street P.O. Box 303017 Chattanooga, TN 37402-2801 Montgomery, AL 36130-3017 Mr. Michael D. Skaggs Plant Manager Chairman Browns Ferry Nuclear Plant Limestone County Commission Tennessee Valley Authority 310 West Washington Street P.O. Box 2000 Athens, AL 35611 Decatur, AL 35609