SENS14;iE IN'0WR1-rf0ROFCAA U Y DAVIS-BESSE RESTA ATUS This information is current as of 5:30 pm (EST) on February 20, 2004.

The plant is in Mode 3 maintaining Normal Operating Pressure/Normal Operating Temperature.

(NOP/NOT - 5320 F/2155 psig). The licensee expects to maintain the plant in these conditions until restart.

LICENSEE ACTIVITIES PRIOR TO RESTART The licensee is currently tracking outstanding activities that need to be completed prior to restart [Mode 2/1]. There are approximately 24 restart items.

  • Corrective Actions: 8
  • Conditionr Reports:e
  • Field Work: 7
  • Post Maintenance Tests: 3
  • Surveillance Tests: 1 NRC ACTIVITIES PRIOR TO RESTART Below is a simplified time line that describes the significant NRC and licensee activities and milestones that are necessary for NRC to authorize restart.

These tentative dates are predicated upon the licensee successfully completing NRC pre-restart activities and demonstrating acceptable operating performance.

Key Agency decision points are annotated with asterisks (**) In the timeline below.

The outcome of each decision point could materially alter the timing and substance of the rest of the schedule.

The details of these activities are described Inthree Internal NRC documents: the Davis-Besse Oversight Panel Process Plan, the Davis-Besse Restart Communications Plan and the Davis-Besse Restart Punch Ust.

Final Panel deliberations on restart decision Panel briefing for Jim Caldwell, Jim Dyer, and Sam Collins on restart deliberations Panel Issues restart recommendation to Jim Caldwell Panel briefing for Commissioners' TAs Jim Caldwell Issues draft Order to licensee (for affirmation/hearing declination)

Licensee affirms conditions of Order and declines hearing Finalize restart authorization letter and Order (letter to be signed by Jim Caldwell; will authorize restart and transmit the Order - Order to be signed by Jim Dyer)

Implement Restart Communications Plan (1-day Enforcement Notification)

Issue restart authorization letter and Order .

Implement restart inspection plan

/\1)

Information in this record wa in accotnci3ri with the Freedom of Tn!ormatoflo Act, exe-pios _

FaO"IN11flS St !Z°f

SENSR~~MTO;i-d-bFCA S U4or CHALLENGES THAT THE LICENSEE RRENTLY A None at this time.

LICENSEE ACTIVITIES FOLLOWING RESTART AUTHORIZATION The following sequence of events were taken from a licensee Level 1 schedule.

NRC approval for restart Enter operational Mode 2 (reactor startup)

Reactor critical - Zero power physics testing Enter Mode I (greater than 5% power)

Readiness and effectiveness review prior to synch to the grid Synch to the grid Readiness and effectiveness review prior to exceeding 50% power Reactor at 100% power SENFOIV ORIOF