ML040270203

From kanterella
Jump to navigation Jump to search
Special Team Inspection Report 05000445-02-009 - Preliminary White Finding
ML040270203
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 01/27/2004
From: Chamberlain D
Division of Reactor Safety I
To: Blevins M
TXU Energy
References
EA-04-009, IR-02-009
Download: ML040270203 (9)


See also: IR 05000445/2002009

Text

January 27, 2004

EA-04-009

Mr. M. R. Blevins, Senior Vice President

and Principal Nuclear Officer

TXU Energy

ATTN: Regulatory Affairs

Comanche Peak Steam Electric Station

P.O. Box 1002

Glen Rose, Texas 76043

SUBJECT: COMANCHE PEAK STEAM ELECTRIC STATION - SPECIAL TEAM INSPECTION

REPORT 05000445/2002-09 - PRELIMINARY WHITE FINDING

Dear Mr. Blevins:

This letter discusses a finding that appears to have low to moderate safety significance. As

described in the subject inspection report issued on January 9, 2003, the finding involved the

failure to identify and correct an indicated flaw in a steam generator tube during Refueling

Outage 1RF08. Failure to remove the tube from service resulted in a steam generator tube

leak. The finding was characterized as an Apparent Violation pending the determination of its

safety significance. As noted in the inspection report, since your staff removed the leaking tube

from service, it did not present an immediate safety concern. This finding was assessed based

on the best available information, including influential assumptions, using the applicable

Significance Determination Process (SDP) and was preliminarily determined to be a White

finding. The finding was preliminarily determined to have a low to moderate safety significance

because of the inability of the degraded tube to meet its required safety margins, as indicated

by the in-situ testing failures and the associated inability to withstand some severe accident

conditions, resulting in an increase in the large early release frequency ( LERF) for this

performance deficiency. We have provided a summary of the Phase 3 Significance

Determination as an enclosure to this report.

There were some differences between your safety assessment, as documented in your letters

to the NRC dated March 5 and April 9, 2003, and the significance determination performed by

the NRC. These differences included your use of thermal-hydraulic models that predicted much

lower steam generator tube temperatures during severe accidents than the NRC models

predict. This results in much lower tube failure probabilities than in the NRCs analysis. The

agencys models are not designed to be overly-conservative, given the current state of

knowledge. The staff considers its model results to be the best currently available basis for

risk-informing inspection efforts in this technical area. In addition, your analysis treats the flaw

as being smaller and stronger than we believe your data actually indicates. We believe that the

-2-

NRC model uses your data in a more objective manner. Finally, in the last of the models you

offered for consideration (the fully linked Level 1 and 2 logic model treatment) there appears to

be a problem with the truncation level used in the analysis. If corrected, we believe that your

model may well support a risk conclusion similar to the conclusion of the NRCs risk analysis.

The finding is also an apparent violation of NRC requirements, as discussed in Section 02.02 of

the inspection report, and is being considered for escalated enforcement action in accordance

with the "General Statement of Policy and Procedure for NRC Enforcement Actions"

(Enforcement Policy), NUREG-1600. The current Enforcement Policy is included on the NRCs

website at: http://www.nrc.gov/what-we-do/regulatory/enforcement.html

Before we make a final decision on this matter, we are providing you an opportunity (1) to

present to the NRC your perspectives on the facts and assumptions used by the NRC to arrive

at the finding and its significance at a Regulatory Conference or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of the receipt of this letter, and we encourage you to submit supporting documentation

at least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation. If you

decide to submit only a written response, such submittal should be sent to the NRC within

30 days of the receipt of this letter.

Please contact Charles Marschall at 817-860-8185 within 10 business days of the date of the

receipt of this letter to notify the NRC of your intentions. If we have not heard from you

within 10 days, we will continue with our significance determination and enforcement

decision, and you will be advised by separate correspondence of the results of our

deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for these inspection findings at this time. In addition, please be advised that the number

and characterization of apparent violations in the inspection report, referenced in the subject

line of this letter, may change as a result of further NRC review.

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and

its enclosures will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Dwight D. Chamberlain, Director

Division of Reactor Safety

Docket: 50-445

License: NPF-87

-3-

Enclosure: SDP Phase 3 Summary

cc w/enclosure:

Roger D. Walker

Regulatory Affairs Manager

TXU Generation Company LP

P.O. Box 1002

Glen Rose, TX 76043

George L. Edgar, Esq.

Morgan Lewis

1111 Pennsylvania Avenue, NW

Washington, DC 20004

Terry Parks, Chief Inspector

Texas Department of Licensing

and Regulation

Boiler Program

P.O. Box 12157

Austin, TX 78711

The Honorable Walter Maynard

Somervell County Judge

P.O. Box 851

Glen Rose, TX 76043

Chief, Bureau of Radiation Control

Texas Department of Health

1100 West 49th Street

Austin, TX 78756-3189

Environmental and Natural

Resources Policy Director

Office of the Governor

P.O. Box 12428

Austin, TX 78711-3189

Brian Almon

Public Utility Commission

William B. Travis Building

P.O. Box 13326

1701 North Congress Avenue

Austin, TX 78711-3326

Susan M. Jablonski

Office of Permitting, Remediation and Registration

Texas Commission on Environmental Quality

MC-122

P.O. Box 13087

Austin, TX 78711-3087

-4-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (DBA)

Branch Chief, DRP/A (WDJ)

Senior Project Engineer, DRP/A (TRF)

Senior Reactor Analyst (DPL)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

ACES Director (GFS)

Senior Reliability and Risk Analyst (SML)

JDixon-Herrity, OE (JLD)

RFranovich, NRR (RLF2)

DOCUMENT: R:\_CPSES\CP2002-09 CHOICE WHITE LETTER.WPD

RIV:DRS/EB RIV:DRS NRR:DSSA/SPSB C:DRS/EB C:DRP/A

WCSifre DPLoveless SMLong CSMarschall WDJohnson

CSM = E CSM = T CSM = E /RA/ /RA/

01/27/04 01/26/04 01/26/04 01/22/04 01/26/04

D:ACES D:DRS

GFSanborn DDChamberlain

/RA/ /RA/

01/26/04 01/27/04

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

Significance Determination Process

Phase 3 Summary

A. Overview of Issue

A failure to identify and correct a clearly detectable steam generator tube flaw indication

during eddy current examinations in the 2001 refueling outage (1RF08) resulted in the

tube remaining in service until it leaked in September of 2002. The tube subsequently

failed in-situ testing, indicating that it would not have met design basis accident

requirements.

B. Significance Determination Basis

1. Reactor Inspection for IE, MS, B cornerstones

a. Phase 1 screening logic, results and assumptions

The team determined that a Significance Determination Process Phase 2 analysis

was required because the issue resulted in the failure of a reactor coolant system

barrier, specifically a steam generator tube leak.

b. Phase 2 Risk Evaluation

In accordance with Inspection Manual Chapter 0609, Appendix A, the inspectors

conducted a Phase 2 estimation using the Risk-Informed Inspection Notebook for

Comanche Peak Steam Electric Station, Unit 1, Revision 1. The dominant affected

accident sequences are provided in Table b-1. This finding increases the likelihood

of an initiating event, specifically, the Steam Generator Tube Rupture; therefore, the

initiating event likelyhood was increased by one order of magnitude in accordance

with Manual Chapter 0609, Appendix A, Attachment 2.

The Phase 2 estimation resulted in a preliminary WHITE finding. Therefore, the

analyst determined that the finding should be evaluated using the Phase 3 process.

TABLE b-1

PHASE 2 DOMINANT ACCIDENT SEQUENCES

Initiating Event Sequence Contribution

Steam Generator Tube Rupture SGTR-EQ1/ISO-SDC 8

(SGTR)

SGTR-EIHP-EQ2/ISO 7

SGTR-AFW-MKRWST 6

SGTR-AFW-FB 6

SGTR-AFW-EIHP 7

Enclosure -2-

c. Phase 3 Analysis

The analysts conducted an assessment of the Comanche Peak steam generator

tube degradation that was as independent as was feasible while using the licensees

information to make the assessment specific to Comanche Peak. By reviewing the

differences in the analysts and licensees underlying assumptions of the physical

phenomena involved in this analysis, the licensee identified some appropriate

sensitivity studies to perform on both analyses. Upon consideration of all results, the

analysts concluded that the best estimate point value of the change in large early

release frequency ( LERF) for this performance deficiency was 5.5 x 10-7/year. This

frequency range corresponds to a white finding in the significance determination

process.

The assessment of risk for this degraded tube was evaluated for the following three

types of severe accident sequences:

(1) Core Damage Sequences Initiated by Spontaneous Tube Rupture:

In this case, the in-situ test demonstrated that the tube was capable of

withstanding pressure differentials in the range encountered during normal

operation; therefore, the analysts concluded that there was no increase in risk

associated with spontaneous tube rupture sequences.

(2) Core Damage Sequences Initiated by Secondary Depressurization Events that

Induce Tube Rupture:

Because the in-situ test was not capable of reaching the pressure difference that

would be created by a design-basis secondary depressurization event, it was

necessary to use information from the eddy current inspections to estimate the

burst pressure for the flawed tube. The predicted burst pressure was greater

than the differential pressure that would be experienced during a design-basis

depressurization event. However, the predicted burst pressure also had a

significant amount of uncertainty, leaving some probability that the tube would

actually have burst if exposed to the elevated pressure differential.

A probability distribution for the burst pressure was developed based on the

in-situ test results and the predicted uncertainty in the model. The analysts

estimated the induced rupture probability as the fraction of this probability

distribution that was below the pressure difference created by the accident

sequence. The analysts increased estimated induced rupture probability as a

function of time to account for crack growth during the last operating cycle. The

analysts used a series of burst probabilities for specific time periods during the

last year of operation with the flawed tube.

As shown in Table c-1, the analyst used a frequency of 1 x 10!3 per reactor-year

for the frequency of a secondary depressurization event, a probability of 0.25

(1 out of 4) that the depressurization event affects the steam generator with the

flawed tube, and a conditional probability of 1 x 10!2 that the combined

secondary depressurization event and tube rupture will result in core damage.

The time periods in Table c-1 are based on the licensees estimated crack

Enclosure -3-

growth rate. Summing the risk contributions for all time periods in the year

produces a result of 2.35 x 10!8 per reactor-year for the increase in core damage

frequency.

The analysts adjusted these values to reflect a slower crack growth rate than

was estimated by the licensee. The analysts used the 95th percentile crack

growth rate (15% of the wall thickness per year) from a Westinghouse database,

instead of the licensees estimate of 27% per year. The slower crack growth rate

increased the risk estimate by predicting that the crack had been in a condition

susceptible to rupture for a longer period of time before it was discovered. The

adjustment in the growth rate resulted in a frequency of 4.2 x 10-8/year. Because

the tube rupture and secondary pressure boundary failure create a direct path to

the atmosphere, this result is also the LERF.

TABLE c-1

RESULTS OF STAFFS ANALYSIS FOR SECONDARY

DEPRESSURIZATION SEQUENCES

Initiating Event Core Damage

Frequency Time Period Probability Burst Frequency

(per year) (fraction of last year) SG 2 Affected Probability CCDP (per year)

1 x 10-3 3/12 1/4 0 1 x 10-2 0

1 x 10-3 4.5/12 1/4 0.004 1 x 10-2 3.75 x 10-9

1 x 10-3 1.5/12 1/4 0.009 1 x 10-2 2.81 x 10-9

1 x 10-3 1/12 1/4 0.015 1 x 10-2 3.13 x 10-9

1 x 10-3 1/12 1/4 0.024 1 x 10-2 5.00 x 10-9

1 x 10-3 0.9/12 1/4 0.039 1 x 10-2 7.31 x 10-9

1 x 10-3 0.1/12 1/4 0.072 1 x 10-2 1.50 x 10-9

TOTAL 2.35 x 10-8

(3) Core Damage Sequences Initiated by Other Phenomena that Induce

Tube Rupture by Creating Abnormally High Temperatures in the Tube

Material:

The burst pressure predicted in the previous section for the flawed tube is

based on its strength at normal operating temperatures. If a core

damage accident occurs in a manner that does not depressurize the

reactor coolant system before the reactor core melts, physical testing has

demonstrated that the hot gases from the core will reach and overheat

the steam generator tubes. The increase in temperature substantially

reduces the burst pressure of the tube. The pressure difference across

the tubes in a steam generator with a depressurized secondary side

would be sufficient to rupture this cracked tube at the higher

temperatures. Consequently, the portion of the plants baseline core

Enclosure -4-

damage frequency that produces the conditions necessary to rupture the

cracked tube becomes an additional contribution to the large early

release frequency because of the crack.

The staffs analysis for this contribution starts with the frequency of the

plant damage states (PDSs) in the licensees PRA that have the

characteristics necessary to heat the tubes with the reactor coolant

system at high pressure. This is multiplied by the probability that the

reactor coolant system will not become depressurized before the tube

ruptures and by the probability that the secondary side of the steam

generator does become depressurized. The product is further reduced

by a factor of 0.5 to account for the probability that the tube is in the part

of the steam generator tube bundle that heats up most rapidly. The next

reduction factor is the fraction of the last year of operation during which

the degradation of the tube made it susceptible to failure under these

severe conditions. Finally, the licensees baseline contribution to the

large early release frequency is subtracted from the result to produce the

incremental change caused by the flaw. An outline of the calculation is

presented in Table c-2.

The analysts total risk estimate for the subject finding is the sum of the

estimated change in risk for the three types of severe accident

sequences documented in the preceding sections. This summation is

provided in Table c-3. The result falls into the white range for the

LERF.

TABLE c-2

ANALYSIS FOR SEVERE ACCIDENT SEQUENCES

THAT INDUCE TUBE RUPTURE

Data Used: Frequency (per year)

or Probability:

Sum of Relevant PDS Frequencies: 4.0x10!5

Probability of RCS Depressurization during Core Damage Progression: x 0.5

Probability that Steam Generator Containing the Flaw is Depressurized: x 0.1

Probability that the Flaw is in Hottest Part of the Tube Bundle: x 0.5

Fraction of Last Year that the Flaw was Vulnerable to Rupture: x 0.57

Total Estimated LERF with Flaw: 5.7x10!7

IPE Baseline LERF from Severe Accident Induced Tube Rupture: - 5.6x10!8

TOTAL ESTIMATED LERF: 5.1x10!7

Enclosure -5-

TABLE c-3

STAFFS TOTAL RISK ESTIMATE

Type of Tube Rupture: LERF (per year)

Spontaneous 0

Induced by Secondary Depressurization Events + 4.2 x 10-8

Induced by Core Damage Accidents + 5.1 x 10-7

TOTAL LERF 5.5 x 10-7